precommissioning test for 220kv substation dajay

Upload: sherubd

Post on 14-Apr-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 Precommissioning Test for 220kv Substation Dajay

    1/12

    Tests carried out during the pre-commissioning test.

    Test date: 28/01/2013 - 03/02/2013

    Followings are present during the test:

    1. Voltech, office based in Tamil Nadu, India.

    2. CGL, office based in Kolkata.

    3. BPCL, office based in Tsirang.

    4. KECL, Site office based in Tsirang.

    Knee point voltage test: It is a minimum voltage test performed using the injection of voltage (for eg.

    HVN core) for PS- class, 1s1-1s2. While conducting the test, the tap position 1s1 & 1s2 is connected

    from the step up transformer applying the minimum of 1000V injection so as to get the output current

    of 150mA maximum. The test is further carried out with the application of 10% on the 1000Vapplication so as to get maximum current flowing across the secondary core terminals. However, the

    secondary CT current at the minimum knee point voltage is comparably less than that of the

    designated current of 150mA. If voltage exceeds minimum knee point voltage, the core goes into

    saturation no matter what the excitation current is being implied. At the point when the CT core

    reaches saturation point, Ixe increase by 50% of the normal current where it leads to detoriation in CT

    core and severe damages.

    Instruments used during the test: Variac (auto transformer), 5KV step-up transformer, multimeter (

    measures knee point voltage) & leakage current tester (tongue)- measures current corresponding to

    knee point voltage.

    Ratio test: Ratio test is conducted for both protection and metering class which covers every core

    terminals of U, V & W phases. The test is so conducted, where the two tap position of HVN (eg.

    1N1S1 & 1N1S2, 1N2S1 & 1N2S2) will be shorted. The current will be noted at the short guard wire

    with the gradual application of primary injection current from a loading transformer, where the

    conductor from the loading transformer will be passed through the core. Both the primary injection

    current in the primary cable and shorted core terminal wire measures current using leakage tester. The

    gradual increase in primary current up to300A should gives out 1A across the shorted secondary

    terminals.

    Instrument used: Variac (auto transformer), Loading transformer, Leakage current tester- 2nos.

    Winding resistance test: Winding resistance test is conducted for only PS class core, using resistance

    tester. The minimum of 1.5ohms should be obtained at the end of test. Tap to Tap (in a single core)- o

    ohm, Tap to tap (in a different core)- G ohm range, single core to earth- G ohm value should be

    shown in a galvanometer for a insulation resistance measurement check.

    Tan Delta test: Tan Delta test is so performed by the injection of voltage from the control transformer

    with the variation of voltage in three different ranges (i.e 2kV to 10kV), three readings are performed.

    The high voltage input is connected at the top of a bushing and another wire is tapped from the R-

    phase control unit to the tan delta point. With the application of voltage up to 10kV, the input current

    should be at the range of 100 of mA, which decreases with the rise in voltage and the capacitance is

    read in pico farad range (usually 350 to 500 PF range in case of 220kV transformer bushing). The tan

  • 7/29/2019 Precommissioning Test for 220kv Substation Dajay

    2/12

    delta, dissipation should be maintained within a range of 0.005 range to assure specified value which

    indicates that the insulation of a bushing is perfect. Value above 0.005 is unacceptable. The test so

    carried out is only UST (un-ground specimen test). GST (grounded specimen test) & GSTG(grounded

    specimen test with guard) will be performed after creation of transformer vacuum, oil infiltration and

    filling of oil. This latter two test shall be carried out after performing the above action before final

    commissioning.

    UST test is carried out only for bushings whereas GST & GSTG tests are carried out for windings of

    transformer.

    Polarization Index (PI): PI is the special test carried out to note resistance of transformer bushing on

    HV side after filling up insulating oil in main transformer tank and following an immersion of

    bushing into insulating transformer oil. The test is thus performed setting a range of time interval from

    1min to 10 min, automatically noting the value of bushing resistance in mega ohm. PI value is a ratio

    of resistance measured in 1min to 10 min where the value should be proportional to or more than 1.5.

    Higher the PI value, indicated high insulating oil and bushing dielectric strength.

    The test is so performed after shorting all three HV terminal bushing with HVN bushing using meger

    testing instrument. Positive terminal of megger is connected to the shorted bushing at HVN terminal

    and negative terminal is earthed.

    The above mentioned test details are all conducted for the transformer- T10024/1.

    Test date- 20/02/2013 - 22/02/2013

    Polarity test (CT): Polarity test is so performed to know the polarity of current transformer. The CT

    terminal P1 & P2 is connected with a probe. At the other spectrum, a galvanometer is connected

    across each and every tap position of individual core to see a correct deflection of galvanometertowards right. ( i.e 1S1-1S2, 1S1-1S3.....5S1-5S4). A 9V Pb battery is energized to the CT primary

    terminal P1 & P2 to read a deflection of galvanometer who's terminal is connected to respective tap

    position as stated above. If a galvanometer pointer deflects towards the right, the equipment polarity is

    correct and if deflected towards left equipment polarity is incorrect.

    IR test (CT): Insulation resistance (IR) test is so conducted to know the dielectric withstanding

    capacity of insulation of CT winding. The test is performed in different stages viz. Primary terminal

    (P1 or P2) to earth with 5kV DC meger input, Primary terminal (P1 or P2) to individual core

    (1S1....1S5) with 500V DC meger input, Core (1S1.....) to core (2S1.....) injecting 500V DC meger

    input. The IR value should be in the range of Giga Ohm, where primary to earth meger value is higher

    as compared to remaining connection as mentioned above.

    CT winding resistance test, Knee point voltage test and Ratio test is similar to the test as conducted in

    transformer CT for primary, secondary and Neutral CT inside respective turrets.

    The above test are conducted for ICT-1 CT.

    Test Date- 23/02/2013

    1. Megger test- Meger test is carried out for the transformer HV-Earth, LV-Earth & HV-LV. The test

    is conducted with the help of 5kV rated meger. The above test result is obtained in the range of 37G

    and above.

  • 7/29/2019 Precommissioning Test for 220kv Substation Dajay

    3/12

    2. Vector Group test- Vector group test is so conducted for the transformer having a vector group of

    Yyn0. Vector group test is conducted with the help of3 4 wire AC supply which is connected to a 4

    pole MCB, which is then connected to a HV bushings U, V, W. The U point terminals of the MCB is

    then connected to another U point terminal bushing of LV along with V & W. The voltages are

    measured so with respect to the terminals between each phases where the summation of two terminal

    result shall correspond to the terminal of the earlier measured. The test is conducted with the help of

    multimeter.

    3 Phase supply connected

    on HV side bushings

    U1-N2= U1-N1 + U1-N2

    W1-W2= V1+ V2

    4P MCB(for HV)

    R

    Y

    B

    N

    Transformer-10MVA

    U1 V1 W1 HVN

    U2 V2 W2 LVN

    4P MCB(for LV)

    R

    Y

    B

    N

    U1

    N1

    W1 V1

    N2

    W2V2

    U2

  • 7/29/2019 Precommissioning Test for 220kv Substation Dajay

    4/12

    SF6 Circuit Breaker-

    1. Difference between touch contact and fully closed contact- Wipe (in mm) (83-51)

    2. Difference between fully opened contact and fully closed contact- Pole stroke (in mm) (280-51)

    The test is performed along with the personnel specified from the CGL, Nashik, India. During the

    period, carried out slow closing and opening operation of breaker for all the breakers and thus

    conclusively obtained the above results. The above results correspond to the stipulated test

    requirement for the breakers generally. Hence the above test satisfied.

    24/02/2012

    Current Transformer

    Conducted tests for the fulfilment of CT application regarding Dagachhu incomer line bay. The test

    are conducted similar to the earlier test conducted for ICT-1 bay CT. All the tests are passed and

    concluded satisfactory.

    Transformer-10MVA

    Followed by the voltage ratio test for the 10MVA transformer. Test is so conducted starting from the

    OLTC tap no. 1 gradually increasing to tap no.17

    3-phase supply connected on HV side.

    The above test should witnessed as follows. While testing on tap no. 1, the voltage readings are

    conducted on each and every phase terminals across for both HV and LV side i.e R-B, B-Y, Y-R, R-

    N, Y-N & B-N by giving supply only in HV side regardless of LV side to satisfy the test. The voltage

    should show gradual increasing trend while increasing the tap position practically but the test result

    4P MCB(for HV)

    R

    YB

    N

    Transformer-10MVA

    U1 V1 W1 HVN

    Transformer Bushings

    positioned on HV & LV

    U2 V2 W2 LVN

    4P MCB(for LV)

    R

    Y

    B

    N

  • 7/29/2019 Precommissioning Test for 220kv Substation Dajay

    5/12

    was found unsatisfactory. It was agreed to carry out the test the next day to attain correct result. The

    test is further corrected whether the values obtained are correct or not by calculating from the standard

    value, for the rest of the tap position readings.

    HV-220000/ LV-66000= 3.33 (constant)

    Polarization index test- The test is conducted for the transformer ICT-1 after complete oil filtration

    and full filling of insulating oil in to transformer with the acquired BDV of 71kV.

    1minute- 31.7ohm

    10min- 115ohm

    PI value is calculated as 2.9

    Date- 25/02/2013

    SF6 CB- 1. Checked continuity test for inter-pole CB. The continuity is done for the control panellinking in between R, Y & B phase CB pole and Marshalling box. The test is carried out using digital

    multimeter.

    2. Carried out filling of SF6 gas for CB up to the ceiling requirement of normally 7.2 Kgf/mm.

    During the filling of gas, it is checked for gas locked out and gas alarm pressure as noted below.

    SF6 gas pressure Low Nominal SF6 gas pressure

    Gas locked out (GL) Gas alarm (GA)

    Gas alarm (GA) Gas locked out (GL)

    For R-phase- During the zero SF6 gas, the GL contact will be NO and GA contact will be NC. At the

    fully filled SF6 gas level, GL contact will be NC and GA contact shall be NO. Continuity is sound

    during NC contact which shall be checked in R-phase TB- XR1.

    Date- 26/02/2012

    Magnetization balance test and magnetizing current test. (f or ICT-1)

    The magnetizing balance and current test procedure are different for star and delta connected

    transformer. The test is conducted for star connected transformer, injecting supply on HV side and test

    read, then inject supply on LV side then test read where tapping out single phase supply (for e.g. R-

    phase) keeping other two phases open. Hence the voltage is measured across R-N, Y-N & B-N,

    whereas Vrn= Vyn + Vbn. Magnetizing current is measured using clamp meter on R-phase,

    approximately 1mA.

    The test is conducted for delta connected transformer, injecting supply on HV side and test read, then

    injecting supply on LV side and test read. The R-phase is connected to R-phase MCB and Y-phase is

    connected to MCB neutral, remaining B-phase is kept open. The voltage is measured across R-Y, Y-B& R-B whereas the Vry= Vyb + Vrb. Magnetizing current is measured in R-phase.

  • 7/29/2019 Precommissioning Test for 220kv Substation Dajay

    6/12

    Y(open)

    B(open)

    Vrn= Vyn + Vbn (hence the same test is conducted serially for other two opened phases and

    then the same test is adopted for LV side also)

    B-phase opened

    Vry= Vrb + Vyb (The same test is serially conducted for the remaining two opened phases

    and is adopted for LV side.

    SF6 Circuit Breaker

    1. Conducted CB closing and opening timing using CB operational analyzer kit giving DC

    supply. The closing time should be not more than 5ms and opening time should be not more than 3.3

    ms.

    2. DCRM(Dynamic contact resistance measurement) test.

    Conducted using DC battery kit and CB operational analyzer kit to check for contact

    resistance check. It is just tested to see the condition of breaker analyzing through graph denoting

    various parameters viz. closing coil current, tripping coil current, resistance and status of sharp shoot

    of tripping coil and closing coil current. If it is found sharp shoot, the test is not passed till the graph is

    normalized.

    3. CRM(Contact resistance measurement) test.

    The test measures the contact resistance during the time of arching operation. The contact

    resistance should be normally 90 micro ohms and below, shall indicate the contact is proper.

    04/03/2013

    Relay test- Carried out various test for distance relay, Restricted earth fault relay, differential

    over current relay. Simens relay uses Digsi manager software and PCM software for ABB relay.

    Omicron software is used during the testing of relay and generation of fault for relay, where this

    software is used along with omnicron kit which injects actuating quantities current and voltage tolearn about the correct operation and detecting of fault, time delay performed by relay.

    4P MCB(for HV)

    R

    Y

    B

    N

    Transformer-10MVA

    U1 V1 W1 HVN

    U1 V1 W1

    4P MCB(for HV)

    R

    Y

    B

    N

  • 7/29/2019 Precommissioning Test for 220kv Substation Dajay

    7/12

    REF relay- Uses metro cells which is connected in parallel and rheostat in series, where metro

    cells control and blocks the voltage and rheostat control and blocks the current. Thereby huge rush of

    short circuit current and high voltage is limited for the safety of relay.

    Distance relay- The relay operates based upon the ratio measurement (V/I) where the fault is

    detected in protected section of line length based on measuring impedance. The protection zone isalso divided into four namely Zone-1, 2, 3 and reversed zone.

    Zone-1: Operating time - 0sec. Zone-2: Operating time- 4 sec.

    Zone-3: Operating time- 8 sec. Reverse zone: Operating time- 1 sec.

    During the relay test, the fault is created by omicron kit through injection of current and voltage to see

    the correct sensing and operating of relay on time for the specified protected distance. Fault and

    operation of relay is displayed on the Resistance- reactance diagram for all four zones.

    PUTT- permissible under reach transfer trip relay shall energise and actuate the relay coil for the

    zone-1 operating time though the faults occur in zone-2.

    Time setting for Directional over current relay. (for normal inverse 67/67N )

    Time setting=[

    Where; =0.02 (Constant)

    I= Injected fault current

    Ip= Setted current (0.2Amps)

    0.15= Time multiplier setting(TMS)

    Rated full load current(Ifl)=

    For 300Amps-------CT sec. current= 1Amps

    For 26.243Amps= 0.087 Amps (CT sec. current, considering cos=1)

    0.087Amps for HV side of the transformer

    4370mA for LV side of the transformer considering the same calculation for the above HV side.

    Actual matching factor= 1.5

    (0.087x0.2x1.5)= 1 coil pick up current

    (0.087x0.2)= 3 coil pick up current

    Transformer 87T relay operates both the function for HVRef + SEF protection along with

    differential protection.

    14/03/2013

    Line Distance Protection 21.1(main 1) & 21.2 (main 2)

  • 7/29/2019 Precommissioning Test for 220kv Substation Dajay

    8/12

    SOTF(Switch on to fault) trip

    The SOFT trip occurs only during the time of breaker switching, whereas its considered to be a

    temporary fault and if the fault persist further the SOTF relay trips and SOTF LED glows.

    Settings.... Voltage----------60%

    Current---------20%

    .:. 0.6x 63.51= 38.106V

    0.2x 1= 0.2A

    As the voltage drops and the current rises in respect to the above values, the relay gives trip command

    to the breaker and breaker gets tripped.

    Directional Earth fault---for normal inverse status

    TMS (Tp) setted at 0.73sec

    Ip setting= 0.2 A

    Injecting current= 2x 0.2= 0.4A

    The above two operational settings are for the distance relay. If the above fault occurs then

    respectively the above LED blinks.

    87T Relay

    The LED glows w.r.t to the below operational settings.

    V/F setting

    V/F= 63.51/50= 1.27

    Setting= 1.4

    1.27x 1.4= 1.778

    1.778= V/F

    V=Fx 1.778= 50x 1.778= 88.9V

    F= 63.51/1.778= 35.71Hz

    The LED glows and relay trips if the above values varies so from the respective normal data. i.e

    V=63.51V & F=50Hz

    Harmonic inrush

    15% for 2nd harmonic and 30% for 5th harmonics.

    Where I2= Secondary current (LV)

    I1= Secondary current (HV)

  • 7/29/2019 Precommissioning Test for 220kv Substation Dajay

    9/12

    I2/I1= 15% or less and 30% or less for the respective harmonics settings. Relay gets tripped if the

    percentage gets exceed the above prescribed percentage and relay won't operate if the above

    percentage is below the above the setted percentage.

    Distance Protection relay

    PUTT- Following the eventual line fault detected in zone-2, the substation-1 does trip in the zone-1

    timing after receiving carrier signal from substation-2. Thereby in receiving the carrier from

    substation-2, LED in relay 21 does not glow unless the carrier is transmitted from substation-1. Due to

    the fact that the 20% of the line seen from S/s-1, the zone-1 protection falls for S/s-2, hence S/s-2

    transmit carrier signal for instantaneous tripping. Hence the tripping time shall be reduced for the

    cause of reliability of transmission line.

    Power Swing- It is so-called temporary power surges due to over loading of power transformer and

    rotor slip of generator due to fast reversing of rotor during the time of shutting down of a generator.

    The relay sense that the power swing cause due to ramping of voltage (dV/dt) and ramping of current

    (dI/dt)... which the summation of two ramping parameters gives rise to the ramping of impedance in

    the transmission line. There by relay sense it to be a temporary fault in the power system and it will

    just block the various setted zone, letting the power continuity through. Whereby the relay does not

    get tripped operated.

    Fuse Failure relay- The fuse failure relay gives annunciation and gets operated if the fuse inside CVT

    fails in one of the secondary phase till control panel, though the CT secondary phases are correctly

    operated the FFR gets operated. This is due to the drop in voltage or zero in voltage in one of the CVT

    secondary phase. The FFR gets operated if the actuating quantity particularly in voltage is so droped

    due to any wire/ fuse malfunction, though the line till bus is charged and in healthy status. The

    jurisdiction of FFR is from CVT secondary till the control panel.

    Directional Earth fault- The Directional earth fault relay do sense if any one or more of the phases in

    transmission gets earth fault. During the course of earth fault, say R- phase its voltage will be zero or

    too low which thereby it forms a path for neutral current. Hence the current will arise in R phase of aline and the remaining two Y & B phase will be having zero current. Thus due neutral current

    flowing, the current in the relay gets imbalance and relay gets trip operated.

    R-phase- 0V, Y-phase- 63.51V, B-phase- 63.51V

    IL(1)- 2A IL(2)- 0A IL(3)- 0A

    CVT Ratio test.

    Voltage at the secondary core (1a-1n)=

    80% 20%

    S/s-2S/s-1

  • 7/29/2019 Precommissioning Test for 220kv Substation Dajay

    10/12

    =

    (Let Primary injected voltage= 1100v)

    CT Ratio test.

    Current at the secondary core (1s1-1s2)=

    Transformer Differential stability test.

    DCRM Test for the SF6 Circuit Breaker.

    During the DCRM test, following important factors are to be noted:

    Contact travel timing. Contact travel distance. Dynamic and Static contact resistance. Pole mis-match.

    Contact travel distance for 220kV CB is specified at 130mm with the tolerance of +2mm and -5mm is

    accountable. Contact resistance should be below 100 is the acceptable limit as per the required

    standard. Dynamic contact resistance is more important to trace the contact resistance as compared to

    the static contact resistance, since dynamic resistance is measured at the first stable position of the

    contact for close-open operation, whereas static resistance is measured always at the time of stableposition of the contact after the contact is fully closed. Therefore dynamic resistance will be always

    more as compared to the static resistance.

    Pole mis-match should be considered important for maintaining equal voltage induced and current

    flowing through respective pole. Pole mis-match is considered 5ms or less for closing operation and

    3.3ms or less for opening operation. While conducting DCRM, first the contact travel signature

    should be conducted via single normal closing operation using transducer. The rated resistance of

    transducer is 6k but while testing should be setted at 3k between L-E terminals. In practical three

    terminals are connected L,N & E. The resistance between rest of the terminal shouldbe half of 3k.

    Note that the, DCRM test shall be operated only for C-O operation whereas timing test shall be

    operated for only O-C operation considering the importance of auto-reclose.

    Direction of power flow

    HVLV

    Relay

  • 7/29/2019 Precommissioning Test for 220kv Substation Dajay

    11/12

    The picture below shows the connection in the DCRM kit for testing the CB contact operation.

    Terminals to be connected on DCRM kit to the CB MB:

    1. Source 1- (CLS & TRP 1)--- X1-118 (in the same TB link)2. Source 2- (CLS & TRP 2)--- X1-119 (in the same TB link)3. Closing coil (C-)--- X1-24 (shorting not required for three phases, is shorted internally)4. Tripping coil 1 (C-)--- X1-40 (short at X1-40-41-42 externally)5. Tripping coil 2 (C-)--- X1-52 (short at X1-52-53-54 externally)6. C+ & CH1 C+, T1+ & CH2 C+ are shorted for Trip 1.7. C+ & CH1 C+, T2+ & CH3 C+ are shorted for Trip 2.

    Surge Monitor test on Lightning Arrester.

    Surge monitor test is so conducted using auto transformer and 5kV step-up transformer. The output

    voltage link of the step up transformer is connected to the surge monitor gauge meter giving input

    voltage of 40V to the surge gauge. while giving the voltage, the monitor meter should deflect towards

    the right of the scale and the counter should read in an increasing order. If the counter reads in an

    decreasing order the surge meter is found to be not working and ultimately the meter should be

    changed.

    Isolator Interlock operation for all bays.

    Page no: RB6

    For 89B close interlock coil (It pick only I/C, if u wish u can close 89B or u can keep it open)

    *** All bays 89C should be in open condition and TTX should not be operated.

    Page no: RB5

    For 89C Interlock

  • 7/29/2019 Precommissioning Test for 220kv Substation Dajay

    12/12

    ***All bays 89B should open and bay in normal mode and operate the TTX circuit. (NE1 for line).

    Then Interlock gets satisfied.