preliminary design program - wellesley, ma
TRANSCRIPT
Preliminary Design Program
Ernest F. Upham
Elementary School
35 Wynnewood Road, Wellesley, MA
December 18, 2019
SMMA No. 19106.00
Symmes Maini & McKeeAssociates
Table of Contents
1. INTRODUCTION
1.1 Statement of Interest Summary
1.2 Invitation to Feasibility Study
1.3 Design Enrollment
1.4 Capital Budget Statement District
1.5 Project Directory
1.6 Project Schedule
1.7 Section Appendices
2. EDUCATIONAL PROGRAM
Table of Contents within Section
3. INITIAL SPACE SUMMARY
3.1 Summary
3.2 Narrative Description of the Variances Between the Districts Proposed
Program and the MSBA Guidelines
3.3 Scaled Floor Plans of the Existing Facility
3.4 Section Appendices
4a. EVALUATION OF EXISTING CONDITIONS
Ernest F. Upham
4a.1 Determination of Property Title
4a.2 Determination of Historic Regulations
4a.3 Existing Building Conditions
4a.4 Existing Structural System
4a.5 Existing Fire Protection Systems
4a.6 Existing Plumbing Systems
PRELIMINARY DESIGN
PROGRAM
Ernest F. Upham
Elementary School
35 Wynnewood Rd, Wellesley, MA
SMMA
1000 Massachusetts Avenue
Cambridge, MA 02138
www.smma.com
of Design Narrative
4a.7 Existing Mechanical Systems
4a.8 Existing Electrical Systems
4a.9 Existing Technology Systems
4a.10 Existing Video Surveillance, Access Control and Intrusion Detection
Systems
4a.11 Existing Public Address (PA0 System and Clock System
4a.12 Existing Audiovisual Systems and Teaching/Learning Tools
4a.13 Existing Food Service Conditions
4a.14 Preliminary Hazardous Materials Report (Electronic Submission Only)
4a.15 Section Appendices
4b. EVALUATION OF EXISTING CONDITIONS
John D. Hardy
4b.1 Determination of Property Title
4b.2 Determination of Historic Regulations
4b.3 Existing Building Conditions
4b.4 Existing Structural System
4b.5 Existing Fire Protection Systems
4b.6 Existing Plumbing Systems
4b.7 Existing Mechanical Systems
4b.8 Existing Electrical Systems
4a.9 Existing Technology Systems
4a.10 Existing Video Surveillance, Access Control and Intrusion Detection
Systems
4a.11 Existing Public Address (PA0 System and Clock System
4a.12 Existing Audiovisual Systems and Teaching/Learning Tools
4b.13 Existing Food Service Conditions
4b.14 Preliminary Hazardous Materials Report (Electronic Submission Only)
4b.15 Section Appendices
of Design Narrative
5a. SITE DEVELOPMENT REQUIREMENTS
Earnest F. Upham
5a.1 Summary
5a.2 Site Existing Conditions and Development Requirements
5a.3 Site Development Requirements
5a.4 Site Investigation
5a.4a Preliminary Topographical Report
5a.4b Preliminary Geotechnical Report
5a.4c Preliminary Geo-Environmental Report
(Electronic Submission Only)
5a.4d Preliminary Traffic Report
5a.5 Section Appendices
5b. SITE DEVELOPMENT REQUIREMENTS
John D. Hardy
5b.1 Summary
5b.2 Site Existing Conditions and Development Requirements
5b.3 Site Development Requirements
5b.4 Site Investigation
5b.4a Preliminary Topographical Report
5b.4b Preliminary Geotechnical Report
5b.4c Preliminary Geo-Environmental Report
(Electronic Submission Only)
5b.4d Preliminary Traffic Report
5b.5 Section Appendices
of Design Narrative
6 PRELIMINARY EVALUATION OF ALTERNATIVES
6.1 School Assignment Practices and Available Space
6.2 Tuition Agreements with Adjacent School Districts
6.3 Renting, Acquisition of Existing Buildings for School Use
6.4 Available Sites Analysis
6.5 Construction Alternates including Cost Estimate & Schedules
• Code Upgrade Options
i. Base repair of Upham
(Seven schools; K-5, 240 student enrollment)
• Renovations and/or Additions to Existing Buildings
i. Add/Reno of Upham
(Seven schools; K-5, 240 student enrollment)
ii. Add/Reno of Upham
(Six schools with equalized enrollments; K-5, 365
student enrollment)
iii. Add/Reno of Hardy
(Six schools with equalized enrollments; K-5, 365
student enrollment)
• New Building Construction and evaluation of potential locations
i. New Construction on Upham site
(Seven schools; K-5, 240 student enrollment)
ii. New Construction on Upham site
(Six schools with equalized enrollments; K-5, 365
student enrollment)
iii. New Construction on Hardy site
(Six schools with equalized enrollments; K-5, 365
student enrollment)
• Overall Conclusions
6.6 Section Appendices
of Design Narrative
7 LOCAL ACTIONS AND APPROVAL CERTIFICATION
7.1 Local Action and Approval Certification
7.2 Certified Meeting Minutes (Electronic Submission Only)
7.3 Meeting Agendas
7.4 Section Appendices
8 APPENDICES
8.1 Statement of Interest
8.2 Programming Meeting Minutes
8.3 Visioning Session Notes
2 3 41
Introduction
Acknowledgements
Preliminary Design Program | p. 1
Acknowledgements
Anthony Proia, Project Manager
Jennifer Flynn, Project Coordinator
Sharon Gray, (Chair), School Committee Ryan Hutchins, Community/Construction
Thomas Ulfelder (Vice Chair),
Board of Selectmen
Meghan Jop, Executive Director
Virginia Ferko, Community/Town
Government
Matt King, Permanent Building Committee
Marjorie Freiman, Board of Selectmen David Lussier, Superintendent of Schools
Steve Gagosian, FMD Designee Melissa Martin, School Committee
Mary Gard, Advisory Committee Heather Sawitsky, Community/Town Government
Joubin Hassanein,
Community/Construction
Jose Arias Soliva, Community/Architecture
Charlene Cook, Hardy Principal Cynthia Mahr, Asst. Superintendent of Schools
Jeffery Dees, Upham Principal
David Lussier, Superintendent of Schools
Ellen Quirk, Hunnewell Principal
Compass Project Management
2 3 41
Introduction
Design Team
Preliminary Design Program | p. 1
Design Team
Project Manager Architecture Educational
Programming Consultant
Civil Engineering /
Environmental Permitting
SMMA SMMA New Vista Design SMMA
Landscape Architecture Structural Engineering Fire Protection /
Plumbing Engineering
Hazardous Materials
SMMA Steere Engineering Inc SMMA Nobis, Inc.
Electrical Engineering /
Lighting Consultant
Data / Communications Geotechnical
Engineering
Geo-environmental
Engineering
SMMA ART Engineering Nobis, Inc. Nobis, Inc.
Cost Estimating Kitchen/Food Service
Consultant
Acoustical Consultant Library/Media Consultant
A.M. Fogarty Lisa May Acentech, Inc. SMMA
Technology / Audio
Visual Consultant
Theatrical Consultant Sustainable / Design Code Consultant
Acentech, Inc. Lorelli Associates SMMA Building, Fire & Access,
Inc.
Site Survey Furniture, Fixtures, &
Equipment Consultant
Traffic Consultant Security Consultant
Nitsch Engineering Stefura Associates BETA Good Harbor Techmark
2 3 41
Introduction
Introduction
Preliminary Design Program 1 | p. 1
1 Introduction
1.1 Statement of Interest Summary
The Ernest F. Upham School is a public elementary school located at 35 Wynnewood Road in Wellesley
Massachusetts and currently supports grades K-5 with a current enrollment of approximately 225 students. This
brick masonry school building was constructed in 1957 with an addition in 1967 and modular classrooms added
in 1993. It is the vision of the District to replace three of their aging elementary schools with two new elementary
schools of equal enrollment with the remaining four elementary schools in the District. One of those two 365-
student schools, the Hunnewell Elementary School, is underway as a fully Town-funded separate project. The
Ernest F. Upham Elementary School project, through this Feasibility Study intends to serve as the second 365-
student school located at either the existing school site or the Hardy Elementary School site.
In April 2017, Wellesley Public Schools submitted a Statement of Interest (SOI) to the Massachusetts School
Building Authority (MSBA) for the Ernest F. Upham school. Some of the major physical and educational
constraints are described here:
The Ernest F. Upham site measures approximately twelve (12) acres. There is a softball field and a relatively new
playground but the remainder of the site is rocky and wooded. The site is bordered by residential properties on
all four sides. Site access and bus queuing are very poor, parking and queuing overflow into the neighborhood
on a regular basis. The administrative suite has no visual control over arrival, dismissal or recess areas. The
exterior enclosure is minimally insulated and failing due to water intrusion. Minimal roof insulation is present.
Classrooms are heated and ventilated through unit ventilators; plumbing fixtures are antiquated. Panels, feeders
and branch wiring are older than 30 years and need replacement. The toilets and drinking fountains in the
building are minimally accessible. The finishes, though well maintained, are beyond their useful life. The SKILLS
program has grown over the years and necessitated the conversion of academic spaces to support the program.
Because every space is currently fully utilized at Upham, there are no spaces to offer additional supplementary
programs and support programs for students. The multi-purpose room is currently used as a gymnasium,
cafetorium and for OT/PT.
As part of the feasibility study, the District has an agreement with the MSBA to consider the following grade
configurations:
• 240 students – for grades K-5 (one of seven elementary schools)
• 365 students – for grades K-5 (one of six elementary schools)
The complete Statement of Interest is Included in Appendix 8.1.
1.2 Invitation to Feasibility Study
At the October 31, 2018 Board of Directors meeting, the MSBA board voted to issue an invitation to the Town of
Wellesley to partner with the MSBA in conducting a feasibility study for the Ernest F. Upham Elementary School
to identify and study possible solutions and, through a collaborative process with the MSBA, reach a mutually-
agreed upon solution.
The Invitation is included in Appendix 1.7.
2 3 41
Introduction
1 | p. 2 Ernest F. Upham Elementary
1.3 Design Enrollment
As a result of a collaborative analysis of enrollment projections with the MSBA and space capacity needs for the
District’s K-12 enrollment, Wellesley Public Schools, on September 14, 2018 agreed that the design alternatives,
which may be evaluated as part of the feasibility study for the Ernest F. Upham Schools, shall be based on the
following design enrollment: 240 students for Grades K – 5 as one of seven grade K-5 schools, and 365
students as one of six grade K-5 schools with equalized enrollments.
The design enrollment letter is included in Appendix 1.7. The Design Enrollment Certification form will be
completed during the Preferred Schematic Report (PSR) phase and will be included in that submission.
1.4 Capital Budget Statement
The Upham Elementary School project feasibility phase is studying two design enrollments with different sized
buildings. Based on early budgeting, the project cost for the Upham Elementary School project could range
from $53 to $65 million exclusive of MSBA reimbursement. The Town of Wellesley maintains a healthy balance
sheet and its current debt loads are well within recommended levels. Currently, the Town has a Moody’s rating
of AAA. As financing for this project is based upon a successful debt override, the Town Treasurer is confident
that it can acquire bonded financing in excess of $65 million if it is approved by the citizens of Wellesley. The
Town’s 10-year capital plan has the following major capital building projects included, which total to
$129,946,500:
Other Town major project.
Middle School: Building Systems Replacement $ 12,981,000
Main Library: Renovation $ 4,090,000
Hunnewell School: New School $ 61,000,000
Town Hall: Renovation $ 20,041,000
Town Hall Annex: New Building $ 11,873,500
School Roof Replacements $ 6,984,000
DPW: Renovation Projects $ 12,977,000
The Capital Budget Statement is included in Appendix 1.7.
1.5 Project Directory
The project directory with contact information of the project’s key stakeholders is included in Appendix 1.7
2 3 41
Introduction
Introduction
Preliminary Design Program 1 | p. 3
1.6 Project Schedule
The project schedule anticipates MSBA Board of Director’s approval to proceed into Schematic Design at their
June 24, 2020 meeting and MSBA Board of Director’s approval of the Project Scope and Budget Agreement at
their February 10, 2021 meeting.
The Town of Wellesley approval and appropriation voting will occur in the month of March/April 2021. The
project schedule is included in Section 1.7, it will continue to be updated as the alternatives are evaluated, and a
preferred alternative is selected specifically with respect to the Schematic Design submission, design and
construction phase durations.
1.7 Section Appendices
PROJECTS OVER $1M INCLUDED IN 10-YEAR CAPITAL PLAN: SCHOOLS
PROJECT YEAR AMOUNT
MS: Building Systems FY21 $12,981,000
Hunnewell School FY22 $61,000,000
Hardy/Upham School FY22 $62,152,000
MS: Site Paving FY23 $2,000,000
Sprague & Bates Roofing FY25 $2,784,000
Sprague & Bates Paving FY26 $668,000
MS: Roofing Replacement FY26 $4,200,000
New Preschool FY27/28 $20,700,000
AC: MS, Schofield, Bates & Fiske FY26 (placeholder) $13,040,000
Total = $179,525,000
November 4th FMD Presentation
PROJECTS OVER $1M INCLUDED IN 10-YEAR CAPITAL PLAN: MUNICIPAL
PROJECT YEAR AMOUNT
Main Library: Renovation & Roof FY21 $4,090,000
Town Hall: “Annex” Building FY21/22 $11,873,500
Town Hall: Interior Restoration FY22/24 $20,041,000
DPW Renovations FY23/24 $12,977,000
New MOPO Bathhouse FY25 $1,000,000
Warren: HVAC System Replacement FY27 $1,352,000
Total = $51,333,500
November 4th FMD Presentation
Wellesley Hardy/Uphaml Elementary School ProjectProject Directory
Updated 12/02/19 DRAFT
Name Title Phone Fax Cell or Alt # Email
Client
Town of Wellesley Main #
Town Hall FMD office
525 Washington Street 888 Worcester Street
Wellesley, MA 02482 Wellesley, MA 02482
Meghan Jop Executive Director (781) 431-1019 ext. 2200 [email protected]
Marjorie Freiman BOS Chair (781) 237-6821 [email protected]
Thomas Ulfelder BOS Vice Chair (617) 875-2222 [email protected]
Jack Morgan BOS Secretary [email protected]
Lisa Olney BOS Secretary [email protected]
Beth Sullivan Woods BOS Member [email protected]
Joe McDonough FMD Director of Facilities (781) 489-4254 (781) 489-4266 [email protected]
Kevin Kennedy FMD Project Manager (781) 489-4290 (781) 489-4266 [email protected]
Dick Elliott FMD Project Manager (781) 489-4260 (781) 489-4266 [email protected]
Allen Hebert FMD Operations Manager (Energy Manager) (781) 489-4258 (781) 489-4266 [email protected]
Abbie LaFrancesca FMD Projects Assistant (781) 489-4291 (781) 489-4266 [email protected]
Stephanie Hawkinson Town Communications (781) 431-1019 ext. 2207 [email protected]
Michael T. Grant Inspector of Buildings/Commissioner (781) 431-1019 ext. 2221 (781) 283-5724 [email protected]
Michael Sweeney Electrical & Wiring Inspector (781) 431-1019 ext. 2222
Position Currently Vacant Plumbing Inspector (781) 431-1019 ext. 2224
Julie Meyer Wetlands Administrator (781) 431-1019 ext. 2292 [email protected]
Brandon Schmitt Natrual Resources Commission Director (781) 431-1019 ext. 2294 [email protected]
Cricket Vlass Tree Warden (DPW) (781) 235-7600 ext. 3335 [email protected]
Leonard Izzo Board of Health Director (781) 235-0135 (781) 235-4685 [email protected]
David Cohen DPW Director/Chief of Operations (781) 235-7600 ext. 3300 [email protected]
William Shaughnessy Water and Water Superintendent (781) 235-7600 ext. 3355 [email protected]
David Hickey Town Engineer (781) 235-7600 ext. 3315 [email protected]
Doug Stewart Assit. Town Engineer (781) 235-7600 ext.
Sheryl Strother Finance Director 781-431-1019 ext. 2214 (781) 239-1043 [email protected]
Jack Pilecki Police Chief 781-235-0062 (781) 235-3830 [email protected]
Richard DeLorie Fire Chief 781-235-1300 (781) 237-3161 [email protected]
Rachel Lopes Assistant Finance Director (781) 431-1019 ext 2211 [email protected]
Meghan Bond FMD Administrator (781) 489-4263 [email protected]
School Building Committee (includes members of the Permanent Building Committee, reps from the School Committee, BOS, FinCom, School officals,and community members.
Sharon Gray SBC Chair - SC rep. -Voting (781) 237-2502 (813) 992-5896 [email protected]
Thomas Ulfelder Vice Chair- BOS rep -Voting (617) 875-2222 [email protected]
Joubin Hassanein Community Rep-Voting (617) 594-4402 [email protected]
Ryan Hutchins Community Rep-Voting (617) 594-1082 [email protected]
Meghan Jop Executive Director - Voting (781) 431-1019, ext. 2205 [email protected]
Melissa Martin SC-Voting 617-461-4103 [email protected]
David Lussier Superintendent-Non Voting (781) 446-6200 [email protected]
Heather Sawitsky Community Rep-Voting (781) 235-2113 [email protected]
Jose Arias Soliva Community Rep-Voting (617) 548-5077 [email protected]
Virginia Ferko Community Rep-Voting (339) 225-1243 [email protected]
Marjorie Freiman, BOS BOS-Voting (781) 237-6821 [email protected]
Steve Gagosian FMD-Voting (781) 489-4256 [email protected]
Mary Gard Advisory rep. - Voting [email protected]
Charlene Cook Hardy Principal-Non Voting (781) 446-6270 [email protected]
Jeffery Dees Upham Principal-Non Voting (781) 446-6285 [email protected]
Cynthia Mahr Asst. Supt. (Operations)-Non Voting (781) 446-6200, ext. 5611 [email protected]
Ellen Quirk Hunnewell Principal-Non Voting (781) 446-6275 [email protected]
Matt King Community Rep- Voting [email protected]
Pemanent Building Committee
David Grissino Permanent Building Committee- Chair [email protected]
Mathew King Permanent Building Committee- Vice Chair [email protected]
Thomas Goemaat Permanent Building Committee [email protected]
Suzanne Littlefield Permanent Building Committee [email protected]
Michael Tauer Permanent Building Committee [email protected]
School Committee
Melissa Martin SC Chair [email protected]
Linda Chow SC Vice Chair [email protected]
Matt Kelley SC Secretary (508) 789-1259 [email protected]
Sharon Gray SC Member (781) 237-2502 (813) 992-5896 [email protected]
Jim Roberti SC Member [email protected]
Other Project Contacts
Fred Bunger Sustainability Energy Cmt Liaison [email protected]
Marybeth Martello Sustainable Energy Cmt staff [email protected]
Joshua Dorin Historical Commission liaison [email protected]
Grant Brown Historical Commission chair [email protected]
Ann-Mara Lanza Library Trustees liaison [email protected]
Marla Robinson Library Trustees chair [email protected]
Jamie Jurgensen Library Director (781) 235-1610 x1129 [email protected]
Tom Goemaat Permanent Bldg Committee [email protected]
1 of 2
Wellesley Hardy/Uphaml Elementary School ProjectProject Directory
Updated 12/02/19 DRAFT
Name Title Phone Fax Cell or Alt # Email
Owner's Project Manager
COMPASS Project Management, Inc. Main # 508-589-5061
One Edgewater Drive, Suite 204
Norwood, MA 02062
Tim Bonfatti Project Director - Principal 508-359-6111 508-589-6171 617-590-7765 [email protected]
Jeff D'Amico Senior Project Manager 508-359-6163 508-589-6171 617-943-4943 [email protected]
Dylan McIntosh Assistant Project Manager 617-480-5492 [email protected]
Mia Ayers Construction Site Manager 508-589-5061 781-956-3453 [email protected]
Mary Kuppens Accounting & IT Manager 617-943-1527 508-589-6171 [email protected]
Kim Lipsy Administrator & Website Manager 508-359-6033 508-589-6171 [email protected]
Cost Estimator (CPM Consultant)
PM & C Main # 781-740-8007
20 Downer Avenue, Suite 1C
Hingham, MA 02043
Peter Bradley Principal 781-740-8007 781-7401012 508-274-0394 [email protected]
Colin Dutton Cost Estimator, Project Manager 781-740-8007 781-740-1012 508-274-0394 [email protected]
Approval Authority MSBA
Massachusetts School Building Authority Main # 617-720-4466
40 Broad Street, Suite 500
Boston, MA 02109
Anthony Proia Project Manager 617-960-3059 [email protected]
Jennifer Flynn Project Coordinator 617-720-4466 617-720-5260 [email protected]
Architects and Engineers
Symmes Maini & McKee Associates 617.547.5400 800.648.4920
1000 Massachusetts Avenue
Cambridge, MA 02138
Alex Pitkin Principal-in-Charge 617-520-9220 617-233-5768 [email protected]
Kristen Olsen Project Manager / Project Architect 617-520-9242 857-999-5274 [email protected]
Anne Fontaine Architect 617-520-9481 [email protected]
Philip Poinelli Educational Programming 617-520-9219 617-721-0609 [email protected]
Anthony Iacovino Architect/ Accessibility 617-520-9434 617-417-9939 [email protected]
Erin Prestileo Civil Engineer 617-520-9214 [email protected]
Andrew Oldeman HVAC Engineer 617-520-9282 ext. 282 [email protected]
Rafael Gurevich Electrical/Lighting Engineer 617-520-9250 [email protected]
Paul Elliott Plumbing Engineer 401-519-0657 [email protected]
Peter Lukacic Landscape Architect 617-575-0314 [email protected]
Martine Dion Sustainable Design / Energy Model 617-520-9461 [email protected]
Paul Elliott Fire Protection/ Plumbing Engineering 401-519-0657 [email protected]
Kristin Norwood Specifications Consultant 617-575-0317 [email protected]
Jenifer Badershall Interior Design 617-520-9322 [email protected]
Designer Consultants
Educational Visioning
New Vista Design
David Stephen President 617.733.0847 [email protected]
Sustainability
Maclay Architects
Bill Maclay President (802) 496-4004 [email protected]
Haz Mat Consultant
Nobis Inc. (MBE)
Jeffery Brunelle 888-293-4888 [email protected]
Kitchen Consultant
Food Service Design LLC (WBE)
Lisa May, FCSI (781) 826-5522 [email protected]
Traffic Engineers
Beta Group Inc.
Kien Ho, PE (781) 255-1982
Geotechnical Engineers
Nobis Inc. (MBE)
Michael Ciance 978-683-0891
GeoEnvironmental Consultant
ADS Environmental Eng
Andrea Stiller
Data/Communications/Security Consultant
ART Engineering
Azim Rawji 508-797-0333
Acoustical Consulatnt/ Technology
Acentech Inc
Brian Masiello
Ioana Pieleanu 617-499-8069 [email protected]
Survey
Nitsch Engineering
Mark Violette 617-338-0063
Code Consultant
Building Fire & Access Inc
Robert Carasitti
FF&E
Stefura Associates
Lianne Vivilecchia 617-723-5164
Structural Engineering
Steere Engineering
2 of 2
ID Task Name Duration Start Finish Predecessors Successors
1 OPM / Designer Selection 157 days Mon 1/21/19 Tue 8/27/191516 Preliminary Design Program - Options Development 132 days Wed 7/24/19 Thu 1/23/2017 Develop Work Plan 10 days Wed 7/24/19 Tue 8/6/19 1218 Develop Existing Conditions Analysis 40 days Fri 7/26/19 Thu 9/19/1919 Designer Subconsultants on Board 20 days Fri 7/26/19 Thu 8/22/19 13 35,20,23,22,24,21,2520 Hazmat Survey of Hardy, Upham 20 days Fri 8/23/19 Thu 9/19/19 19 3521 Wetlands Delineation 15 days Fri 8/23/19 Thu 9/12/19 19 3522 Survey Topo & Utilities of Hardy, Upham 20 days Fri 8/23/19 Thu 9/19/19 19 3523 Designer Team Survey of Hardy, Upham 15 days Fri 8/23/19 Thu 9/12/19 19,13FS+5 days 3524 Geotechnical Investigation of Hardy, Upham 20 days Fri 8/23/19 Thu 9/19/19 19,13FS+5 days 3525 Develop Full List of Possible Options 54 days Fri 8/23/19 Wed 11/6/19 19 30,31FS+10 days26 Draft Education Plan 40 days Wed 8/14/19 Tue 10/8/19 14FS-10 days 27FS-11 days,34,29FS27 MSBA Educational Space Template 20 days Tue 9/24/19 Mon 10/21/19 13,26FS-11 days28 Ed Plan visioning -Week of October 1, 2019 1 day Thu 10/3/19 Thu 10/3/19 26FS-16 days29 1st Community Forum - Review Process,
schedule -Week October 14, 20191 day Tue 10/15/19 Tue 10/15/19 26FS+20 days
30 SBC Review Options 1 day Thu 11/7/19 Thu 11/7/19 25 3631 SBC Approval of Options 1 day Thu 11/21/19 Thu 11/21/19 25FS+10 days3233 Preliminary Design Program - Finalize Report 90 days Fri 9/20/19 Thu 1/23/2034 Finalize Educational Program and Template 13 days Wed 10/9/19 Fri 10/25/19 26 37FS+1 day35 Geotechnical Report, Survey & Utility Plans,
Phase 1 Site Assessment20 days Fri 9/20/19 Thu 10/17/19 20,19,23,22,24,21 36FS+5 days
36 Finalize Design Options Shortlist 19 days Fri 11/8/19 Wed 12/4/19 35FS+5 days,30 3837 WSC Approve Ed Plan 11 days Tue 10/29/19 Tue 11/12/19 34FS+1 day38 SBC Approve Submission of PDP 1 day Thu 12/5/19 Thu 12/5/19 36 39FS+8 days39 Submit Preliminary Design Plan (PDP) to MSBA 1 dayWed 12/18/19Wed 12/18/19 38FS+8 days 40FS+1 day,45,42FS+40 MSBA review of PDP 15 days Fri 12/20/19 Thu 1/9/20 39FS+1 day 4141 District Response to MSBA Review 10 days Fri 1/10/20 Thu 1/23/20 4042 2nd Community Forum - Review test fits
-Week of January 20, 20201 day Wed 1/22/20 Wed 1/22/20 39FS+103 days
4344 Preferred Schematic Report 135 days Thu 12/19/19 Wed 6/24/2045 Further Define / Analyze Shortlist Options 45 days Thu 12/19/19 Wed 2/19/20 39 47,49,50,48,46FS+15 da46 3rd Community Forum - Short list of Options -
Week March 20205 days Thu 3/12/20 Wed 3/18/20 45FS+15 days
47 Detailed Cost Estimate 15 days Thu 2/20/20 Wed 3/11/20 45 51,52FS+5 days48 District Operational/ Capital Budget Impacts 10 days Thu 2/20/20 Wed 3/4/20 4549 Permitting Plan 10 days Thu 2/20/20 Wed 3/4/20 4550 MA - CHPS Scorecard 10 days Thu 2/20/20 Wed 3/4/20 4551 Cash Flow - Schedule 1 day Thu 3/12/20 Thu 3/12/20 4752 School Committee / SBC Meeting Decision to
Recommend Preferred Schematic6 days Thu 3/19/20 Thu 3/26/20 47FS+5 days 53FS+1
day,54FS+16 days53 Project Update at Annual Town Meeting 10 days Mon 3/30/20 Fri 4/10/20 52FS+1 day,4554 School Committee / SBC / BOS Meeting Final
Approval Preferred Schematic5 days Mon 4/20/20 Fri 4/24/20 52FS+16 days 55FS+7 days
55 Submit Preferred Schematic Report to MSBA 1 day Wed 5/6/20 Wed 5/6/20 54FS+7 days 56FS+9 days,62FS+256 MSBA Facilities Assessment Subcommittee Meeting 1 day Wed 5/20/20 Wed 5/20/20 55FS+9 days 57FS+24 days,60FS+557 MSBA Board Approval 1 day Wed 6/24/20 Wed 6/24/20 56FS+24 days 61FS+15 days5859 Schematic Design - Preferred Solution 185 days Thu 5/28/20 Wed 2/10/2160 Prepare Final Design Program 22 days Thu 5/28/20 Fri 6/26/20 56FS+5 days61 File MHC PNF 23 days Thu 7/16/20 Mon 8/17/20 57FS+15 days62 Schematic Design - Pricing Set 106 days Thu 6/11/20 Thu 11/5/20 55FS+25 days 66,6363 Cost Estimates and Review Design 15 days Fri 11/6/20 Thu 11/26/20 62 6464 Design & Cost Refinement 2 days Fri 11/27/20 Mon 11/30/20 63 67,65FF65 Submit Email Confirmation of Budget and Schedule 1 day Mon 11/30/20 Mon 11/30/20 64FF66 Finalize SD - 100% 26 days Fri 11/6/20 Fri 12/11/20 62 67,68FS+5 days,94FS67 WPBC Approval SD and Budget 4 days Mon 12/14/20 Thu 12/17/20 66,6468 Submit Final SD report to MSBA 1 day Mon 12/21/20 Mon 12/21/20 66FS+5 days 69FS+15 days,72FS+69 MSBA Scope and Budget Mtg 1 day Tue 1/12/21 Tue 1/12/21 68FS+15 days 70,7570 MSBA Staff Review and Comments 5 days Wed 1/13/21 Tue 1/19/21 69 7171 District Incorporation of MSBA review 2 days Wed 1/20/21 Thu 1/21/21 7072 DESE Approval 1 day Tue 1/19/21 Tue 1/19/21 68FS+20 days73 MSBA Board Approval of Project Scope & Budget
Agreement1 day Wed 2/10/21 Wed 2/10/21 68FS+36 days 76FS+32 days
74 Town Approval Process 90 days Wed 1/13/21 Tue 5/18/21
8/22
11/711/21
3/26
4/24
5/65/20
6/24
12/211/12
1/192/10
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Augd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarte
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
Hardy/Upham Elementary SchoolWellesley, MAFeasibility Study Schedule
Preliminary Project Schedule12/10/19
DRAFT FOR DISCUSSION
Page 1
Project: Hardy Upham Project Schedule 191210 draft
ID Task Name Duration Start Finish Predecessors Successors
75 Public Forums and Information 51 days Wed 1/13/21 Wed 3/24/21 69 7676 Annual Town Meeting (place holder date) 10 days Mon 3/29/21 Fri 4/9/21 73FS+32 days,75 77FS+26 days77 Ballot Voting (place holder date) 1 day Tue 5/18/21 Tue 5/18/21 76FS+26 days 122FS-70 days,947879 Permitting and Regulatory Process 327 days Thu 6/17/21 Fri 9/16/2280 Town of Wellesley Approval Process 327 days Thu 6/17/21 Fri 9/16/2281 Planning Board Initial Review 1 day Thu 6/17/21 Thu 6/17/21 94FS+20 days82 Planning Board Meeting 1 1 day Thu 8/26/21 Thu 8/26/21 95 83FS+20 days83 Planning Board Meeting 2 1 day Fri 9/24/21 Fri 9/24/21 82FS+20 days84 PSI Approval - Planning Board 200 days Thu 9/2/21 Wed 6/8/22 95FS+5 days 131FS-40 days85 Conservation Commission Wetlands Approval 60 days Thu 8/26/21 Wed 11/17/21 9586 Water Service Approval - DPW 20 days Thu 1/6/22 Wed 2/2/22 10387 Sewage Disposal Approval - DPW & Board of Heal 20 days Thu 1/6/22 Wed 2/2/22 10388 Stormwater NPDES Permit 50 days Thu 5/19/22 Wed 7/27/22 13289 Site & Civil Permit 21 days Thu 5/19/22 Thu 6/16/22 13290 Building Permit 23 days Mon 6/13/22 Wed 7/13/22 11891 Town Execution of PFA Amendment 25 days Mon 8/15/22 Fri 9/16/22 133FS+25 days9293 Design Development 124 days Wed 5/19/21 Mon 11/8/2194 Commence Design Development 1 day Wed 5/19/21 Wed 5/19/21 66FS+20 days,77 95,81FS+20 days95 Design Development 70 days Thu 5/20/21 Wed 8/25/21 94 96,103FS+5 days,85,896 Cost Estimate and Review of DD 20 days Thu 8/26/21 Wed 9/22/21 95 9797 Submit DD to MSBA 5 days Thu 9/23/21 Wed 9/29/21 96 9898 MSBA Staff Review - DD Submission 15 days Thu 9/30/21 Wed 10/20/21 97 9999 District Incorporation of MSBA Review and Comment 10 days Thu 10/21/21 Wed 11/3/21 98 100100 WPBC Approval to Proceed 3 days Thu 11/4/21 Mon 11/8/21 99101102 Construction Documents 234 days Thu 9/2/21 Tue 7/26/22103 60% Construction Document Design 90 days Thu 9/2/21 Wed 1/5/22 95FS+5 days 104,86,87104 Cost Estimate and Review of 60% CD 20 days Thu 1/6/22 Wed 2/2/22 103 105,107105 WPBC Approval to Proceed 3 days Thu 2/3/22 Mon 2/7/22 104 111FS-10 days,106FS106 Prepare Ch 149 s 44M Life Cycle Analysis 10 days Tue 1/25/22 Mon 2/7/22 105FS-10 days107 60% CD Design Scope Adjustments 5 days Thu 2/3/22 Wed 2/9/22 104 108108 Submit 60% CD to MSBA 2 days Thu 2/10/22 Fri 2/11/22 107 109,131109 MSBA Review of 60% CD 15 days Mon 2/14/22 Fri 3/4/22 108 110110 District Incorporation of MSBA Review and Comment 10 days Mon 3/7/22 Fri 3/18/22 109111 90% Construction Document Design 40 days Tue 1/25/22 Mon 3/21/22 105FS-10 days 112,113112 Cost Estimate and Review of 90% CD 20 days Tue 3/22/22 Mon 4/18/22 111 114113 FMD & CPM Document Review 20 days Tue 3/22/22 Mon 4/18/22 111114 Submit 90% CD to MSBA 2 days Tue 4/19/22 Wed 4/20/22 112 115115 MSBA Review of 90% CD 15 days Thu 4/21/22 Wed 5/11/22 114 116116 District Incorporation of MSBA Review and Comment 10 days Thu 5/12/22 Wed 5/25/22 115 117117 WPBC Approval to Proceed 2 days Thu 5/26/22 Fri 5/27/22 116 118118 Issue Final Bid Packages 10 days Mon 5/30/22 Fri 6/10/22 117 119FS+30 days,133,90119 Submit 100% CD w/ Addenda to MSBA 2 days Mon 7/25/22 Tue 7/26/22 128,118FS+30 days120121 CM Procurement 110 days Wed 2/10/21 Tue 7/13/21122 Prepare Application to IG for CMR 10 days Wed 2/10/21 Tue 2/23/21 77FS-70 days 123123 IG Review an Approval of Application 40 days Wed 2/24/21 Tue 4/20/21 122 124124 RFQ for CMR 20 days Wed 4/21/21 Tue 5/18/21 123 125125 Review and Shortlist CM's 20 days Wed 5/19/21 Tue 6/15/21 124 126126 RFP for Shortlisted Firms 10 days Wed 6/16/21 Tue 6/29/21 125 127127 CM Proposals and Review 5 days Wed 6/30/21 Tue 7/6/21 126 128128 Interview and Select CM 5 days Wed 7/7/21 Tue 7/13/21 127 119,131129130 Bidding 62 days Thu 4/14/22 Fri 7/8/22131 Early Trade Package Bidding 20 days Thu 4/14/22 Wed 5/11/22 128,108,84FS-40 days132132 DRAFT GMP - Early Trade Packages 5 days Thu 5/12/22 Wed 5/18/22 131 136FS+30 days,88,89133 Filed Subcontractor Bidding 20 days Mon 6/13/22 Fri 7/8/22 118 91FS+25 days134135 Construction 505 days Thu 6/30/22 Wed 6/5/24136 Mobilize and Break Ground 1 day Thu 6/30/22 Thu 6/30/22 132FS+30 days 137137 Construction Phase 480 days Fri 7/1/22 Thu 5/2/24 136 138,139FS-17 days138 Substantial Completion 23 days Fri 5/3/24 Tue 6/4/24 137 140139 Install FFE & Tech Equipment 40 days Wed 4/10/24 Tue 6/4/24 137FS-17 days140 Move in Date (Building Available) 1 day Wed 6/5/24 Wed 6/5/24 138
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Augd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarte
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
Hardy/Upham Elementary SchoolWellesley, MAFeasibility Study Schedule
Preliminary Project Schedule12/10/19
DRAFT FOR DISCUSSION
Page 2
Project: Hardy Upham Project Schedule 191210 draft