preliminary report on geotechnical impact on rail ... · preliminary report on geotechnical impact...

16
FS 604853 Douglas Partners Pty Ltd ABN 75 053 980 117 www.douglaspartners.com.au 96 Hermitage Road West Ryde NSW 2114 PO Box 472 West Ryde NSW 1685 Phone (02) 9809 0666 Brisbane • Cairns • Canberra • Central Coast Coffs Harbour • Darwin • Geelong Gold Coast • Macarthur • Melbourne Newcastle • North West Sydney • Perth • Port Macquarie • Sunshine Coast • Sydney • Townsville • Wollongong AMP Capital Shopping Centres Pty Limited Project 85160.08 50 Bridge Street 17 July 2020 Sydney NSW 2000 R.003.Rev0 LJH Attention: C/- Trevor Battle, TCB Project Management Email: [email protected] Preliminary Report on Geotechnical Impact on Rail Infrastructure Macquarie Town Centre - Corner Podium Development Waterloo Road, Macquarie Park 1. Introduction This letter sets out the likely impact that the proposed Macquarie Town Centre - Corner Podium Development may have on the adjacent rail infrastructure. The Macquarie Centre is located between the corners of Waterloo Road, Herring Road, and Talavera Road, Macquarie Park. The Sydney Metro railway tunnels run below Waterloo Road, adjacent to the southern site boundary. The Macquarie University railway station is located below Waterloo Road, near the south western corner of the site. In addition, the station east service shaft is located on the south- west boundary of the site. It is understood that the proposed redevelopment of the Corner Podium site will include demolition and the construction of a four-storey retail building “Station Plaza” with a partial basement retail level and underlying basement car park level. A new car park ramp is to be located on the southern boundary of the Podium Development. Some limited excavation and new foundations will be located within the rail second reserve. DP undertook 3D numerical modelling for a much more substantial development proposal in 2017 where the shopping centre was directly linking to the station concourse level. The previous development proposed included significant excavation in the first and second rail reserves. The current proposal includes no excavation or new footings in the first reserve, with only minor excavation (with some back filling) and a limited number of new footings in the second reserve. 2. References The following reports/drawings was used for this study: DP Report SSI/1-6266 (December 1978) Report on Excavation Conditions for the Proposed Macquarie Centre at North Ryde.

Upload: others

Post on 19-Oct-2020

5 views

Category:

Documents


1 download

TRANSCRIPT

  • FS 604853

    Douglas Partners Pty Ltd ABN 75 053 980 117

    www.douglaspartners.com.au

    96 Hermitage Road

    West Ryde NSW 2114

    PO Box 472

    West Ryde NSW 1685

    Phone (02) 9809 0666

    Brisbane • Cairns • Canberra • Central Coast • Coffs Harbour • Darwin • Geelong • Gold Coast • Macarthur • Melbourne Newcastle • North West Sydney • Perth • Port Macquarie • Sunshine Coast • Sydney • Townsville • Wollongong

    AMP Capital Shopping Centres Pty Limited Project 85160.08

    50 Bridge Street 17 July 2020

    Sydney NSW 2000 R.003.Rev0

    LJH

    Attention: C/- Trevor Battle, TCB Project Management

    Email: [email protected]

    Preliminary Report on Geotechnical Impact on Rail Infrastructure

    Macquarie Town Centre - Corner Podium Development

    Waterloo Road, Macquarie Park

    1. Introduction

    This letter sets out the likely impact that the proposed Macquarie Town Centre - Corner Podium

    Development may have on the adjacent rail infrastructure.

    The Macquarie Centre is located between the corners of Waterloo Road, Herring Road, and Talavera

    Road, Macquarie Park. The Sydney Metro railway tunnels run below Waterloo Road, adjacent to the

    southern site boundary. The Macquarie University railway station is located below Waterloo Road, near

    the south western corner of the site. In addition, the station east service shaft is located on the south-

    west boundary of the site.

    It is understood that the proposed redevelopment of the Corner Podium site will include demolition and

    the construction of a four-storey retail building “Station Plaza” with a partial basement retail level and

    underlying basement car park level. A new car park ramp is to be located on the southern boundary of

    the Podium Development. Some limited excavation and new foundations will be located within the rail

    second reserve.

    DP undertook 3D numerical modelling for a much more substantial development proposal in 2017 where

    the shopping centre was directly linking to the station concourse level. The previous development

    proposed included significant excavation in the first and second rail reserves. The current proposal

    includes no excavation or new footings in the first reserve, with only minor excavation (with some back

    filling) and a limited number of new footings in the second reserve.

    2. References

    The following reports/drawings was used for this study:

    • DP Report SSI/1-6266 (December 1978) – Report on Excavation Conditions for the Proposed

    Macquarie Centre at North Ryde.

  • Page 2 of 5

    Macquarie Town Centre - Corner Podium Development 85160.08.R.003.Rev0 Waterloo Road, Macquarie Park July 2020

    • DP Report SSI/1-6324 (April 1979) – Supplementary Report on Foundation Conditions for the

    Proposed Macquarie Centre at North Ryde .

    • DP Report 85160.08.R.001.Rev1 (July 2020) – Report on Geotechnical Assessment for the

    Macquarie Town Centre Corner Podium Development.

    • Structural Statement by BG&E for the Development Application Submission (draft, dated 23 June

    2020.

    • Structural Presentation to Sydney Metro by BG&E (includes plans and sections of proposed works

    near the rail infrastructure).

    3. Geology

    The geology at the site has been interpreted from the borehole information, detailed in DP’s

    Geotechnical Desktop Study Report 85160.08.R.001.Rev1, Geotechnical Investigation Report

    85160.03.R.001.Rev1 and the GHD boreholes SH110 and SH111. The interpreted geological profile is

    summarised in Table 1.

    Table 1: Ground Profile from Borehole 1 (DP Report 85160.03.R.001.Rev1)

    Stratum Description RL to Top of

    Stratum (m)

    Depth to Top

    of Stratum (m)

    1

    Filling: dark grey road base gravel to a depth of

    0.15 m, followed by brown medium to coarse grained

    sand with crushed sandstone gravel and a trace of

    clay.

    Ground Surface Ground Surface

    2 Sandstone: low to medium strength, moderately

    weathered, brown, medium grained sandstone. 50.5 2.5

    3

    Sandstone: medium strength, moderately weathered,

    fractured to slightly fractured, pale grey-brown

    medium to coarse grained sandstone with some

    extremely low strength bands.

    50.0 3.0

    4

    Sandstone: high strength, moderately weathered to

    fresh, fractured to slightly fractured, pale grey-brown

    medium to coarse grained sandstone with some

    extremely low strength bands.

    45.5 7.5

    No water table was considered as the permanent groundwater table is expected to be located below the

    invert levels of the station cavern.

  • Page 3 of 5

    Macquarie Town Centre - Corner Podium Development 85160.08.R.003.Rev0 Waterloo Road, Macquarie Park July 2020

    4. Proposed Structure

    It is understood that the proposed redevelopment of the Corner Podium site will include demolition and

    the construction of a four-storey retail building “Station Plaza” with a partial basement retail level and

    underlying basement car park level. A new car park ramp is to be located on the southern boundary of

    the Podium Development.

    The new structure for the podium and truck service tunnel will require foundations within the Rail Second

    Reserve. The footings are also expected to fall within the ‘zone of influence’ of the Service Shaft.

    The new four-storey retail structure will require foundations within the Rail Second Reserve and some

    excavation for a car park ramp (only slightly within the Second Reserve). The new footings will also will

    expected to fall within the ‘zone of influence’ of the Service Shaft.

    Refer to the drawings in the attached structural presentation to Sydney Metro for visualisations of the

    above.

    5. Likely Impact on Rail Infrastructure

    Based on the information available it is considered unlikely that the proposed development will adversely

    impact the Sydney Metro Station or Services Shaft. As some minor excavation is proposed in the

    Second Reserve with some new footings within the ‘zone of influence’ of the Station and Services Shaft,

    we expect that Sydney Metro will require geotechnical analysis (modelling)

    Our previous 3D modelling (2017), carried out for the much larger development, predicted

    displacements in the order of 5 – 10 mm in the Station Concourse. This displacement was assessed to

    be mainly due to the proposed excavation, which extended to the same RL as the Station Concourse.

    Rock stresses were found to be relatively low compared to the rock strength.

    The current proposed development, however, is far less obtrusive. We can therefore expect that the

    rock mass displacements and changes in stress will be significantly less than that predicted by the earlier

    modelling.

    6. Proposed Geotechnical Analysis

    In order to determine the potential impact of the new development on the shaft, service building, station

    and tunnels, a three dimensional numerical analysis can be carried out. We propose to use the FLAC3D

    program to analyse the problem. FLAC3D (Fast Lagrangian Analysis of Continua) is a three-dimensional

    explicit finite difference program for modelling of soil, rock and structural behaviour. FLAC3D is an

    analysis and design tool for geotechnical, civil and mining engineers that can be applied to a broad

    range of problems in engineering studies. Materials are represented by elements, or zones, which form

    a grid that is adjusted by the user to fit the shape of the object to be modelled. Each element behaves

  • Page 4 of 5

    Macquarie Town Centre - Corner Podium Development 85160.08.R.003.Rev0 Waterloo Road, Macquarie Park July 2020

    according to a prescribed linear or non-linear stress/strain law in response to the applied forces or

    boundary restraints. The material can yield and flow and the grid can deform (in large-strain mode) and

    move with the material that is represented. The explicit Lagrangian, calculation scheme and the mixed-

    discretization zoning technique used in FLAC3D ensure that plastic collapse and flow are modelled

    accurately. FLAC3D is ideally suited for modelling geomechanical problems that consist of several

    stages, such as sequential excavation, loading and de-stressing. The formulation can accommodate

    large displacements and strains and non-linear material behaviour, even if yield or failure occurs over a

    large area or if total collapse occurs.

    The 3D modelling objectives will be as follows:

    • Provide estimates of the change in maximum and minimum principal stresses in the rock mass

    surrounding the existing adjacent rail infrastructure due to the proposed redevelopment.

    • Provide estimates of displacement in the rock mass surrounding the existing adjacent rail

    infrastructure due to the proposed redevelopment.

    Note that the modelling is intended to determine the deformation and stress in the rock mass due to the

    relevant excavations. Although some concrete linings will be included in the model, it is not intended to

    model the structural elements in detail. The linings will be modelled as elastic elements (with no plastic

    yield). More detailed structural analysis may therefore be required if areas of concern are identified.

    7. Limitations

    Douglas Partners (DP) has prepared this report for this project at Macquarie Town Centre for AMP

    Capital Investors Limited in accordance with DP’s proposal SYD200571 dated 23 June 2020 and

    acceptance received from Mr. Trevor Battle of TCB Project Management on behalf of AMP.

    The work was carried out under a consultancy agreement between AMP and DP. This report is provided

    for the exclusive use of AMP for this specific project and purpose as described in the report. It should

    not be used by or relied upon for other projects or purposes on the same or other site or by a third party.

    DP has necessarily relied upon information provided by the client and/or their agents.

    The results provided in the report are indicative of the sub-surface conditions encountered in previous

    investigations and only at the specific sampling or testing locations, and then only to the depths

    investigated and at the time the work was carried out. Sub-surface conditions can change abruptly due

    to variable geological processes and also as a result of anthropogenic influences. Such changes have

    occurred on this site since the previous investigations were undertaken.

    DP’s advice is based upon the conditions encountered during previous investigations. The accuracy of

    the advice provided by DP in this report may be limited by undetected variations in ground conditions

    across the site between sampling or testing locations.

    This report must be read in conjunction with all of the attached and should be kept in its entirety without

    separation of individual pages or sections. DP cannot be held responsible for interpretations or

  • Page 5 of 5

    Macquarie Town Centre - Corner Podium Development 85160.08.R.003.Rev0 Waterloo Road, Macquarie Park July 2020

    conclusions made by others unless they are supported by an expressed statement, interpretation,

    outcome or conclusion stated in this report.

    This report, or sections from this report, should not be used as part of a specification for a project, without

    review and agreement by DP. This is because this report has been written as advice and opinion rather

    than instructions for construction.

    The contents of this report do not constitute formal design components such as are required, by the

    Health and Safety Legislation and Regulations, to be included in a Safety Report specifying the hazards

    likely to be encountered during construction and the controls required to mitigate risk. This design

    process requires risk assessment to be undertaken, with such assessment being dependent upon

    factors relating to likelihood of occurrence and consequences of damage to property and to life. This,

    in turn, requires project data and analysis presently beyond the knowledge and project role respectively

    of DP. DP may be able, however, to assist the client in carrying out a risk assessment of potential

    hazards contained in the Comments section of this report, as an extension to the current scope of works,

    if so requested, and provided that suitable additional information is made available to DP. Any such risk

    assessment would, however, be necessarily restricted to the geotechnical components set out in this

    report and to their application by the project designers to project design, construction, maintenance and

    demolition.

    Please contact the undersigned if you have any questions on this matter.

    Yours faithfully

    Douglas Partners Pty Ltd Reviewed by

    Luke James-Hall Charles Marais

    Associate Principal

    Attachments: About this Report

    BG&E Report (Ref. S19409, dated 23 June 2020)

    BG&E Structural Presentation to Sydney Metro

  • July 2010

    Introduction These notes have been provided to amplify DP's report in regard to classification methods, field procedures and the comments section. Not all are necessarily relevant to all reports. DP's reports are based on information gained from limited subsurface excavations and sampling, supplemented by knowledge of local geology and experience. For this reason, they must be regarded as interpretive rather than factual documents, limited to some extent by the scope of information on which they rely. Copyright This report is the property of Douglas Partners Pty Ltd. The report may only be used for the purpose for which it was commissioned and in accordance with the Conditions of Engagement for the commission supplied at the time of proposal. Unauthorised use of this report in any form whatsoever is prohibited. Borehole and Test Pit Logs The borehole and test pit logs presented in this report are an engineering and/or geological interpretation of the subsurface conditions, and their reliability will depend to some extent on frequency of sampling and the method of drilling or excavation. Ideally, continuous undisturbed sampling or core drilling will provide the most reliable assessment, but this is not always practicable or possible to justify on economic grounds. In any case the boreholes and test pits represent only a very small sample of the total subsurface profile. Interpretation of the information and its application to design and construction should therefore take into account the spacing of boreholes or pits, the frequency of sampling, and the possibility of other than 'straight line' variations between the test locations. Groundwater Where groundwater levels are measured in boreholes there are several potential problems, namely: • In low permeability soils groundwater may

    enter the hole very slowly or perhaps not at all during the time the hole is left open;

    • A localised, perched water table may lead to an erroneous indication of the true water table;

    • Water table levels will vary from time to time with seasons or recent weather changes. They may not be the same at the time of construction as are indicated in the report; and

    • The use of water or mud as a drilling fluid will mask any groundwater inflow. Water has to be blown out of the hole and drilling mud must first be washed out of the hole if water measurements are to be made.

    More reliable measurements can be made by installing standpipes which are read at intervals over several days, or perhaps weeks for low permeability soils. Piezometers, sealed in a particular stratum, may be advisable in low permeability soils or where there may be interference from a perched water table. Reports The report has been prepared by qualified personnel, is based on the information obtained from field and laboratory testing, and has been undertaken to current engineering standards of interpretation and analysis. Where the report has been prepared for a specific design proposal, the information and interpretation may not be relevant if the design proposal is changed. If this happens, DP will be pleased to review the report and the sufficiency of the investigation work. Every care is taken with the report as it relates to interpretation of subsurface conditions, discussion of geotechnical and environmental aspects, and recommendations or suggestions for design and construction. However, DP cannot always anticipate or assume responsibility for: • Unexpected variations in ground conditions.

    The potential for this will depend partly on borehole or pit spacing and sampling frequency;

    • Changes in policy or interpretations of policy by statutory authorities; or

    • The actions of contractors responding to commercial pressures.

    If these occur, DP will be pleased to assist with investigations or advice to resolve the matter.

  • July 2010

    Site Anomalies In the event that conditions encountered on site during construction appear to vary from those which were expected from the information contained in the report, DP requests that it be immediately notified. Most problems are much more readily resolved when conditions are exposed rather than at some later stage, well after the event. Information for Contractual Purposes Where information obtained from this report is provided for tendering purposes, it is recommended that all information, including the written report and discussion, be made available. In circumstances where the discussion or comments section is not relevant to the contractual situation, it may be appropriate to prepare a specially edited document. DP would be pleased to assist in this regard and/or to make additional report copies available for contract purposes at a nominal charge. Site Inspection The company will always be pleased to provide engineering inspection services for geotechnical and environmental aspects of work to which this report is related. This could range from a site visit to confirm that conditions exposed are as expected, to full time engineering presence on site.

  • Sydney Office—

    Level 2, 8 Windmill Street, Sydney NSW 2000

    P / +61 2 9770 3300 E / [email protected] BG&E Pty Limited

    bgeeng.com— ABN / 67 150 804 603

    Medium Sized Firm of the Year

    Consult Australia 2012 Awards for Excellence

    Project No: S19409

    23 June 2020

    AMP Capital

    ADRESS

    Attention: Mr Ben Mathews

    Dear Sir

    MACQUARIE TOWN CENTRE

    DEVELOPMENT APPLICATION SUBMISSION – STRUCTURAL STATEMENT

    1 INTRODUCTION

    BG&E Pty Ltd has been engaged by AMP Capital to review the Development Application architectural

    drawings for the proposed expansion works to Macquarie Town Centre and provide a structural

    statement. This statement is to be submitted as part of the documentation package for the

    Development Application.

    As part of this review, BG&E has been provided with the Hames Sharley architectural drawings.

    2 PROPOSED WORKS

    It is understood the proposed works as part of the development will primarily comprise structural

    works to the following areas:

    • Stage 1 - A vertical extension to the existing built form for the area further south along Waterloo Road between Herring Road and the internal Link Road.

    • Stage 2 - Demolition and new build works at the corner of Waterloo and Herrings Road that will extend over an area that is approximately the extent of the existing on grade carpark and ice

    rink

    The proposed structural works to each of these sites is described below.

    2.1 Stage 1 Works

    The architectural drawings outline that it is proposed to build an additional two levels above the

    existing built form that will extend over most of the existing Woolworths tenancy and external

    carparks. To enable this, the Level 3 Event Cinema tenancy will reduce in size.

    The structural works to each level will primarily comprising the following:

    • Level 0A – Existing Carpark

  • S19409-LTR-DA-BM-01.docx / Date 23/06/2020 / Page 2

    o Localised demolition and excavation work adjacent to the Macquarie University

    Station. No bulk excavation works are proposed.

    o Localised strengthening and alterations to the existing structure.

    o Structure for new substation.

    • Level 1A – Existing Retail o Localised strengthening and alterations to the existing structure.

    • Level 2A – Existing Carpark and Woolworths tenancy o Localised strengthening and alterations to the existing structure.

    • Level 3 – New Retail and Existing Cinema o Localised demolition of a portion of the exiting cinema tenancy.

    o Localised strengthening and alterations to the existing structure.

    o New floor structure that extends from the existing façade line to the Waterloo Road

    boundary.

    • Level 4A – New Ice Rink o Localised demolition of a portion of the exiting cinema tenancy.

    o Localised strengthening and alterations to the existing structure.

    o New floor structure that extends from the western edge of the proposed cinema

    tenancy to the Waterloo Road boundary.

    • Level 5 – Ice Rink Mezzanine o New localised floor structure around the perimeter of the ice rink and stadium seating.

    • Roof – No Trafficable o New long span lightweight steel roof that provides a column free space to the ice rink.

    Excavation Support

    As there is only detailed excavation with localised areas, there is expected to be little to no temporary

    excavation support required to achieve the proposed development layout. It is currently envisaged

    that no piled wall or ground anchors will be required in the Stage 1 works.

    The excavation is expected to be located within a small depth of overburden soil and low strengthen

    rock before self-supporting high strength rock is achieved. Careful detailing will be required where

    detailed excavation is occurring adjacent to the Macquarie University Station.

    New Structure

    The proposed development will also comprise new additional levels over the existing building

    structure, this includes both retail and ice rink levels. Careful considering will be required to assess the

    existing buildings structural capacity, particularly the foundations and columns, for the additional

    vertical and lateral loads. This will need to be checked in detail during the detailed design phase.

    During the detailed design phase of the project the composition and form of the structural materials

    will be assessed based on a number of factors including suitability with the architectural scheme,

    structural efficiency, integration with services, cost, buildability, construction program and fire

    protection. Consideration will also need to be given for the non-typical areas of the development

    which include column free spaces in the loading docks and structures adjacent to Macquarie University

    Station.

  • S19409-LTR-DA-BM-01.docx / Date 23/06/2020 / Page 3

    2.2 Stage 2 Works

    Demolition

    To achieve the proposed layout there will need to be the full demolition of the existing ice rink building

    together with a section of the vehicle tunnel adjacent to Herring Road.

    Excavation Support

    In most of the locations the basement excavation will not extend to the site boundary which will enable

    the use of temporary batters in the overburden soil rather than the use of a piled wall with anchors.

    Below the overburden will be permanent self-supporting vertical rock faces.

    The use of a piled perimeter retention wall for both the temporary and permanent conditions will be

    required along a limited section adjacent to Herring Road. Temporary ground anchors will be required

    to the retention wall and approval should be sought from Council and adjacent property owners where

    they extend over the boundary.

    No bulk excavation is proposed adjacent to Macquarie University Station.

    New Structure

    The proposed new building works will cover the whole of the site. The structural works to each level

    will primarily comprising the following:

    • Level 1A – New carpark • Level 2A – New retail • Level 3A – New retail • Level 4A – New retail • Level 5 – Plantroom mezzanines • Roof – Non-Trafficable skylights

    The new buildings will comprise between 4 suspended floors levels which includes one basement

    carpark level. There is also consideration for the building structure to be designed to accommodate a

    future tower development that will happened as part of a separate Development Application

    sometime in the future..

    As per the Stage 1 works, the composition and form of the structural materials will be assessed based

    on a number of factors including suitability with the architectural scheme, structural efficiency,

    integration with services, cost, buildability, construction program and fire protection.

    2.3 Interface with Sydney Metro

    Documentation received from Sydney Metro for the Macquarie University Station outline that the

    station access and services caverns are located adjacent to the development site along Waterloo Road.

    The project team is designing the new development based on the requirements of the Sydney Metro

    Underground Corridor Protection Technical Guidelines dated 16 October 2017.

  • S19409-LTR-DA-BM-01.docx / Date 23/06/2020 / Page 4

    During the Masterplan phase for the development, AMP has been in discussions with Sydney metro

    regarding the relationship between the proposed developments. It is expected that these discussions

    will be ongoing during the design development phase.

    An investigation study has been undertaken to gain and understanding of the relationship between

    the proposed development and station. The results indicate that the foundations locations for the

    proposed development will be outside the first reserve. Reference is made to the letter by BG&E Pty

    Limited titled “insert title” for further information relating to this part of the development.

    2.4 Geotechnical Conditions

    AMP has engaged Douglas Partners Pty Limited to undertake a comprehensive geotechnical

    assessment for the proposed developed.

    “The general subsurface profile encountered within the previous boreholes, in increasing depth order,

    may be summarised as follows:

    • Filling: Typically sand, clay and crushed sandstone filling to depths of 0.5 m to 3 m; over • Sandstone: The sandstone profile generally included extremely low to low strength rock about

    1 m to 2 m thick over low to medium strength rock grading to medium to high strength rock,

    typically below depths of 3 m to 5 m. High strength, mostly slightly fractured and unbroken

    sandstone was encountered at depths of about 6 m to 8 m. Bands of very high strength rock

    were encountered at some locations.”

    2.5 Code Compliance

    The design of the proposed works will need to be in accordance with the structural provisions of the

    Building Code of Australia, Australian Standards AS 1170.1, AS 1170.2, AS 3600, AS 3700 and AS4100

    together with accepted engineering principles and practice.

    Should you need anything further, or require any matters elaborated on, please contact the

    undersigned.

    Yours sincerely,

    For BG&E Pty Limited

    TOM BENN

    Associate

  • 5 4 3 2 1 0

    55.60

    55.75

    56.10

    56.25

    (54.6

    0)

    (54.5

    5)

    55.05

    55.55

    55.45

    55.30

    (54.6

    0)55

    .50

    55.30

    55.45

    55.60

    (54.6

    6)

    (54.9

    5)

    (54.5

    6 )

    (54.9

    9)(5

    5.20)

    (55.4

    0)(5

    5.65)

    (55.6

    4)

    55.75

    56.05

    55.15

    1:35

    (55.7

    0)(5

    5.95)

    FALL

    1:40

    55.55

    55.50

    FALL 1:

    55

    FALL 1:47

    56.05

    55.95

    55.57

    nGnFnEnDnCnB

    n6

    n5

    n4

    n2

    n1

    Q P N M L K J H G F E D

    1

    2

    3

    4

    5

    6

    C

    n3

    nA

    DSD573

    RL: 54.34RL: 54.70

    AWNING OVER

    MACQUARIE UNIVERSITY STATIONEXISTING LANSCAPED EMBANKMENT

    EXISTING SYDNEY METRO SUBSTATION

    BSD572

    ASD572

    NEW STATION PLAZA

    AWNING OVER

    CSD573

    RETAIL

    SOP MU6

    SOP MU8

    INSIDE FACE OF STURCTURE

    FACE OF SHORING WALL

    DEMOLISH EXISTING BALUSTRADE IN AREA SHADED LIGHT ORANGE

    NEW BALUSTRADE

    Q1

    SECOND RESERVE

    FIRST RESERVE

    SITE BOUNDARY

    SITE BOUNDARY

    AMP OWNERSHIP

    SITE

    BO

    UN

    DAR

    Y

    HER

    RIN

    G R

    OAD

    AMENITIES

    RL 56.65ENTERTAINMENT

    SYDNEY METRO OWNERSHIP

    1

    2

    NEW MALL ENTRY

    3

    LOT 100 DP1190494

    LOT 120 DP1130457

    RL 50.67LOT 122 DP1130457

    STATION ENTRY

    STEPS AND SEATS TO PAVED SLAB

    nH

    GR

    ID 1

    5

    E1

    4 50

    500500

    29800

    500

    1450

    0

    E2 E3 E4 E5 E6

    WATERLOO ROAD

    HSD571

    JSD570

    NEW SUSPENDED CONCRETE SLAB TO RETAIL TENANCY

    NEW STONE PAVERS ON SUSPENDED CONCRETE SLAB

    NEW SUSPENDED CONCRETE SLAB

    TO RETAIL TENANCY

    5494

    NEW STONE PAVERS TO STEPS AND WALKWAY

    PAVING SLAB ON COMPACTED FILL

    CONCRETE SLAB ON GROUND

    NEW STREET TREESREINSTATE EXISTING KERB AND

    FOOTPATH

    SITE

    BO

    UN

    DAR

    Y

    RL 50.20

    FIR

    ST R

    ESER

    VE

    smAsmA

    GSD575

    FSD575

    ESD574

    NEW STAIR FROMABOVE CONNECTINGTO EXISTING STAIRAT LEVEL 2

    NEW STAIR & EXTENDED RISERS ABOVE EXISTING STAIR & SERVICE SHAFT

    SECOND RESERVE

    FIRST RESERVE

    PT 2/ 1047085 SUBSTRATUM OWNED BY SYDNEY METROLIMITED IN HEIGHT TO RL40

    EXISTING VEHICLE RAMP

    EXISTING VEHICLE RAMP

    NEW STAIR FROMABOVE CONNECTINGTO EXISTING STAIRAT LEVEL 2

    EXISTING ROOF

    REMOVE SYDNEY METRO CONCRETE DWARF WALL AT SIDE OF STEPS & INTEGRATE FINISHES WITH STATION PLAZA

    RL 56.31

    RL 56.05

    100026000

    123456789

    C/L UP TRACK

    C/L PLATFORMSOP MU5

    SOP MU2

    ENTERTAINMENTRL 56.31

    RL 56.50

    RL 50.20

    ICE RINK CLADDING ABOVE

    ICE RINK CLADDING ABOVE

    NEW PLANTER AT PLAZA LEVEL ANDNEW RETAINING WALL

    EXISTING SYDNEY METRO RETAINING WALL

    NEW GREEN FACADE

    RL 50.80

    RL 50.79

    NEW 2m HIGH PALISADE FENCE

    RL 55.75

    RL 55.60

    RL 55.50

    RL 55.15

    RL 55.30

    RL 55.75

    RL 56.00

    1. STATION PLAZA - NEW RAISED PUBLIC SPACE CONNECTING MALL ENTRY TO RAILWAY STATION ENTRY

    2. PLAZA PAVEMENT TO FINISH FLUSH WITH EDGE OF STATION ENTRY PODIUM. REMOVE EXISTING BALUSTRADE FOR PURPOSE OF GROUND PLANE CONTINUITY

    3. RAMP AND STEPS WITH SEATING ALLOWING ACCESS TO PLAZA. SHALLOW FOOTINGS TO SUPPORT STAIRS, RETAINING WALLS AND PLANTER BOXES

    LEGEND SC STEEL COLUMNSOP PARRAMATTA RAIL LINK SETOUT POINTSLAB ON GROUND OR COMPACTED FILL TO STRUCTURAL ENGINEER'S DESIGN

    SUSPENDED SLAB TO STRUCTURAL ENGINEER'S DESIGN

    STEEL FRAME STRUCTURE TO STRUCTURAL ENGINEERS DETAILS

    CANTILEVERED SLAB TO STRUCTURAL ENGINEERS DETAILS

    Key Plan

    0

    Scale: , 1:500 @ A3 Project Number:Drawing Number:Revision:Date:© NH Architecture & Hames Sharley

    Status:Path:

    North:1:250 @ A1

    20for Herring Rd Corner Podium Development

    HERRRING ROAD

    WA

    TER

    LOO

    RO

    AD

    P27/05/20

    C:\Users\o.wellings\Documents\Revit Local Files\2018\51108 MCIRHOST R2018_o.wellings.rvt

    SD21051108INITIAL DRAFT FOR REVIEW

    Macquarie Centre Detailed DALEVEL 3 PLAN - RAIL RESERVES STATION PLAZA

    1st RESERVE

    2nd RESERVE

    Entry Cav

    ern

    Service

    s Cave

    rn

    New Structure - No Change From Previous DA Additional 2 Levels to Existing Structure

    New belowground fire exitpassage

    Sydney Metro Presentation - Interface Sketches

  • RL 47900NEW L1A

    RL 51100NEW L2A

    RL 56500NEW L3A

    RL 63000NEW L4A

    n4n2n1 n3SI

    TE B

    OU

    ND

    ARY

    MACQUARIE UNIVERISTY

    STATION

    WATERLOO ROAD

    ENVELOPE

    TRUCK TUNNEL

    RETAIL

    RL 54.35

    RAI

    L 1S

    T R

    ESER

    VE B

    OU

    ND

    ARY

    RAI

    L 2N

    D R

    ESER

    VE B

    OU

    ND

    ARY

    STATION PLAZA

    STATION

    1RETAIL

    2 3

    NATURAL GROUND LINESHOWN DASHED

    3729

    RL 69000ROOF SLAB

    RL 55.75

    RL 47900NEW L1A

    RL 51100NEW L2A

    RL 56500NEW L3A

    RL 63000NEW L4A

    n4n2n1 n3

    SITE

    BO

    UN

    DAR

    Y

    MACQUARIE UNIVERISTY

    STATION

    WATERLOO ROAD

    ENVELOPE

    TRUCK TUNNEL

    CAR PARK RAMP

    RETAIL

    RETAIL

    HEADLAND

    RAI

    L 1S

    T R

    ESER

    VE B

    OU

    ND

    ARY

    RAI

    L 2N

    D R

    ESER

    VE B

    OU

    ND

    ARY

    BUIL

    DIN

    G E

    NVE

    LOPE

    DEMOLISH BALUSTRADE

    RAMP

    STATION PLAZA

    STATION

    1RETAIL

    2 3

    NATURAL GROUND LINESHOWN DASHED

    FOOTINGS TO STRUCTURAL ENGINEER'S DETAIL.

    3123

    RL 69000ROOF SLAB

    RL 55.80RL 55.55

    1. STATION PLAZA - NEW RAISED PUBLIC SPACE CONNECTING MALL ENTRY TO RAILWAY STATION ENTRY

    2. PLAZA PAVEMENT TO FINISH FLUSH WITH EDGE OF STATION ENTRY PODIUM. REMOVE EXISTING BALUSTRADE FOR PURPOSE OF GROUND PLANE CONTINUITY

    3. RAMP AND STEPS WITH SEATING ALLOWING ACCESS TO PLAZA. SHALLOW FOOTINGS TO SUPPORT STAIRS, RETAINING WALLS AND PLANTER BOXES

    LEGEND SC STEEL COLUMNSOP PARRAMATTA RAIL LINK SETOUT POINTSLAB ON GROUND OR COMPACTED FILL TO STRUCTURAL ENGINEER'S DESIGN

    SUSPENDED SLAB TO STRUCTURAL ENGINEER'S DESIGN

    STEEL FRAME STRUCTURE TO STRUCTURAL ENGINEERS DETAILS

    Key Plan

    0

    Scale: , 1:500 @ A3 Project Number:Drawing Number:Revision:Date:© NH Architecture & Hames Sharley

    Status:Path:

    1:200 @ A1

    16for Herring Rd Corner Podium Development

    HERRRING ROAD

    WA

    TER

    LOO

    RO

    AD

    M27/05/20

    C:\Users\o.wellings\Documents\Revit Local Files\2018\51108 MCIRHOST R2018_o.wellings.rvt

    SD57251108DRAFT

    Macquarie Centre Detailed DASECTIONS - RAIL RESRVE - STATION PLAZA

    1 : 200A SECTION - STATION PLAZA RAMP

    1 : 200B SECTION - STATION PLAZA RAMP

    B

    A

    Footings at 7m centres approxsupported on high strength rock.Working loads approx.G = 1900kNQ = 350kN

    Low Strength Rock

    High Strength Rock

    High Strength Rock

    Existing Fill

    Rock profiles base on DouglasPartners investigtation

    1st R

    ES

    ER

    VE

    2nd

    RE

    SE

    RV

    E

    2nd

    RE

    SE

    RV

    E

    Structural isolationbetween developmentsB

    OU

    ND

    AR

    Y

    Permanent structure willcantilever to ensure nofoundations in the 1stReserve

    1 : 200A SECTION - STATION PLAZA RAMP

    Existing ground level

    1 : 200B SECTION - STATION PLAZA RAMP

    Low Strength Rock

    Existing ground level

    1st R

    ES

    ER

    VE

    & B

    OU

    ND

    AR

    Y

    Footings at 7m centres approxsupported on high strength rock.Working loads approx.G = 1900kNQ = 350kN

  • RL 47900NEW L1A

    RL 51100NEW L2A

    RL 56500NEW L3A

    RL 63000NEW L4A

    n5n4n2n1 n3

    GREEN FACADE

    PARAPET

    TRUCK TUNNEL

    CAR PARK RAMP

    RETAIL

    RETAIL

    RL 88.70ENVELOPE

    MACQUARIE UNIVERISTY

    STATION

    RAILCORP SUBSTATION

    SITE

    BO

    UN

    DAR

    Y

    RAI

    L 1S

    T R

    ESER

    VE B

    OU

    ND

    ARY

    RAI

    L 2N

    D R

    ESER

    VE B

    OU

    ND

    ARY

    BUIL

    DIN

    G E

    NVE

    LOPE

    EXISTING PEDESTRIAN PATHWAY BEYOND

    EAST STATION SERVICES SHAFT

    LINE OF FACE OF SHORING WALL

    LINE OF INSIDE FACE OF STRUCTURE

    NEW FOOTINGS TO STRUCTURAL ENGINEER'S DETAILS

    NEW BALUSTRADE

    25m OFFSET

    WATERLOO ROAD

    NATURAL GROUND LINE SHOWN DASHED

    FOOTINGS TO STRUCTURAL ENGINEER'S DETAIL. MAX. 1.5m BELOW NATURAL GROUND LINE

    1511

    RL 69000ROOF SLAB

    MALL

    EGRESSCORRIDOR

    1245

    RL 47900NEW L1A

    RL 51100NEW L2A

    RL 56500NEW L3A

    RL 63000NEW L4A

    n6n5n4n2n1 n3

    MALLSTATION PLAZA

    STATION

    TRUCK TUNNEL

    CAR PARK RAMP

    RL 55.50RL 54.35

    RL 51.59RETAIL

    CAR PARK

    PARAPET

    RETAIL

    FOOD COURT

    PLANT

    RL 82.20

    VOID

    SITE

    BO

    UN

    DAR

    Y

    RAI

    L 1S

    T R

    ESER

    VE B

    OU

    ND

    ARY

    RAI

    L 2N

    D R

    ESER

    VE B

    OU

    ND

    ARY

    BUIL

    DIN

    G E

    NVE

    LOPE

    NEW BALUSTRADE

    NEW WSUD TANK IN FOREGROUND SHOWN DASHED

    WATERLOO ROAD

    1MALL ENTRY

    2 3

    MACQUARIE UNIVERSITY

    STATION

    NATURAL GROUND LINESHOWN DASHED

    FOOTINGS TO STRUCTURAL ENGINEER'S DETAIL.

    2204

    RL 69000ROOF SLAB

    NEW FOOTINGS TO STRUCTURAL ENGINEER'S DETAILS

    EXISTING SYDNEY METRO STATION ENTRY CAVERN STRUCTURE

    RL 48.90

    2873

    1. STATION PLAZA - NEW RAISED PUBLIC SPACE CONNECTING MALL ENTRY TO RAILWAY STATION ENTRY

    2. PLAZA PAVEMENT TO FINISH FLUSH WITH EDGE OF STATION ENTRY PODIUM. REMOVE EXISTING BALUSTRADE FOR PURPOSE OF GROUND PLANE CONTINUITY

    3. RAMP AND STEPS WITH SEATING ALLOWING ACCESS TO PLAZA. SHALLOW FOOTINGS TO SUPPORT STAIRS, RETAINING WALLS AND PLANTER BOXES

    LEGEND SC STEEL COLUMNSOP PARRAMATTA RAIL LINK SETOUT POINTSLAB ON GROUND OR COMPACTED FILL TO STRUCTURAL ENGINEER'S DESIGN

    SUSPENDED SLAB TO STRUCTURAL ENGINEER'S DESIGN

    STEEL FRAME STRUCTURE TO STRUCTURAL ENGINEERS DETAILS

    Key Plan

    0

    Scale: , 1:500 @ A3 Project Number:Drawing Number:Revision:Date:© NH Architecture & Hames Sharley

    Status:Path:

    1:200 @ A1

    16for Herring Rd Corner Podium Development

    HERRRING ROAD

    WA

    TER

    LOO

    RO

    AD

    N27/05/20

    C:\Users\o.wellings\Documents\Revit Local Files\2018\51108 MCIRHOST R2018_o.wellings.rvt

    SD57351108DRAFT

    Macquarie Centre Detailed DASECTIONS - RAIL RESERVE - STATION PLAZA

    1 : 200D SECTION - THROUGH EAST WING

    1 : 200C SECTION - STATION PLAZA - MALL ENTRY

    D

    C

    Low Strength Rock

    High Strength Rock

    2nd

    RE

    SE

    RV

    E

    1st R

    ES

    ER

    VE

    & B

    OU

    ND

    AR

    Y

    2nd

    RE

    SE

    RV

    E

    Low Strength Rock

    High Strength Rock

    1 : 200C SECTION - STATION PLAZA - MALL ENTRY

    1st R

    ES

    ER

    VE

    & B

    OU

    ND

    AR

    Y

    Exi

    stin

    g F

    ire S

    tair

    Exi

    t Re-

    built

    Sto

    rmw

    ater

    Tre

    atm

    ent

    1 : 200D SECTION - THROUGH EAST WING

    Existing ground level Existing ground level

    Vertical rock face. Nopiles and anchors

    Vertical rock face. Nopiles and anchors

    EXISTING SYDNEY METRO

    SUBSTATIONC

    /L U

    P TR

    ACK

    C/L

    DO

    WN

    TR

    ACK

    C/L

    PLA

    TFO

    RM

    TOP OF RAIL FFL 26500

    5000

    INDICATIVETUNNEL

    DIAMETERPLATFORM MID LEVEL FFL 27675

    CONCOURSE LEVEL FFL 33075

    5000VARIES (SEE NOTE 1)

    22880

    SYDNEY METRO SERVICES SHAFT FIRST RESERVE

    5000

    TOP OF FIRST RESERVE THE GREATER OF 5m OR EXTENT OF SYDNEY METRO SUBSTRATUM ABOVE CROWN (UNKNOWN)

    C/L

    EAST

    EN

    TRY

    CAV

    ERN

    SIDE OF FIRST RESERVE THE GREATER OF 5m OFF TUNNEL OR EXTENT OF SYDNEY METRO SUBSTRATUM IN WATERLOO ROAD (UNKNOWN)

    INDICATIVETUNNEL

    DIAMETER

    ESTIMATED TUNNEL DEPTH, SIZE AND LOCATION, TO BE CONFIRMED BY SYDNEY METRO

    WATERLOO ROAD

    AMP

    TITL

    E BO

    UN

    DAR

    Y

    EXISTING SYDNEY METRO EAST

    SERVICES SHAFT

    RL 32.570

    NEW AIR INLETAT BOUNDARYSTRENGTHENING TO EXISTING WALL AND FOOTINGS TO STRUCTURAL ENGINEER'S DETAILS

    NEW EGRESS STAIR TO BE BUILT ABOVE EXISTING STAIR WELL

    LOCATION OF RETAINING WALL & STRIP FOOTING NOTED IN HISTORIC DRAWINGS BETWEEN GRIDS N & P LIKELY DEMOLISHED WHEN METRO BUILT

    EXISTING WALL FOUNDATION IN THIS AREA

    FOOTINGS OF EXISTING STAIR BETWEEN GRIDS M & N

    SYDNEY METRO TUNNEL FIRST RESERVE

    SYD

    NEY

    MET

    RO

    TI

    TLE

    BOU

    ND

    ARY

    RL 32.310

    Footings at 9m centres approx.supported on high strengthrock. Working loads approx.G = 3500kNQ = 770kN

    Footings at 7m centres approxsupported on high strength rock.Working loads approx.G = 1900kNQ = 350kN

  • RL 47900NEW L1A

    RL 51100NEW L2A

    RL 56500NEW L3A

    RL 63000NEW L4A

    1 2 3 4

    RL 68125NEW L4A MEZZ

    EXISTING SYDNEY METRO

    SUBSTATION

    NEW ICE RINK

    NEW RETAIL

    EXISTING BIG W

    EXISTING CAR PARK & TRUCKS

    EXISTING CAR PARK

    8125

    6350

    1950

    4500

    RL 56.650

    AMENITIES

    3000

    RL 72.825

    NEW AUTHORITY METER ROOMNEW PLENUM IN EXISTING STRUCTURE

    C/L

    UP

    TRAC

    K

    C/L

    DO

    WN

    TR

    ACK

    C/L

    PLA

    TFO

    RM

    TOP OF RAIL FFL 26500

    5000

    INDICATIVETUNNEL

    DIAMETERPLATFORM MID LEVEL FFL 27675

    CONCOURSE LEVEL FFL 33075

    5000VARIES (SEE NOTE 1)

    22880

    SYDNEY METRO SERVICES SHAFT FIRST RESERVE

    5000

    TOP OF FIRST RESERVE THE GREATER OF 5m OR EXTENT OF SYDNEY METRO SUBSTRATUM ABOVE CROWN (UNKNOWN)

    SECOND RESERVE FROM BOUNDARY

    C/L

    EAST

    EN

    TRY

    CAV

    ERN

    SIDE OF FIRST RESERVE THE GREATER OF 5m OFF TUNNEL OR EXTENT OF SYDNEY METRO SUBSTRATUM IN WATERLOO ROAD (UNKNOWN)

    INDICATIVETUNNEL

    DIAMETER

    ESTIMATED TUNNEL DEPTH, SIZE AND LOCATION, TO BE CONFIRMED BY SYDNEY METRO

    WATERLOO ROAD

    AMP

    TITL

    E BO

    UN

    DAR

    Y

    EXISTING FOOTINGSAPPROXIMATE LOCATION

    EXACT LOCATION OF EXISTING RISERS AND ROCK CUT UNKNOWN

    EXISTING FOOTINGS NEAR GRID P

    EXISTING SYDNEY METRO EAST

    SERVICES SHAFT

    RL 32.570

    NEW AIR INLETAT BOUNDARYSTRENGTHENING TO EXISTING WALL AND FOOTINGS TO STRUCTURAL ENGINEER'S DETAILS

    NEW EGRESS STAIR TO BE BUILT ABOVE EXISTING STAIR WELL

    25000

    LOCATION OF RETAINING WALL & STRIP FOOTING NOTED IN HISTORIC DRAWINGS BETWEEN GRIDS N & P LIKELY DEMOLISHED WHEN METRO BUILT

    RL 39.100

    EXISTING WALL FOUNDATION IN THIS AREA

    FOOTINGS OF EXISTING STAIR BETWEEN GRIDS M & N

    RL 41.350

    W19

    W16

    W1 & W2

    RL 44.750

    SYDNEY METRO TUNNEL FIRST RESERVE

    SYD

    NEY

    MET

    RO

    TI

    TLE

    BOU

    ND

    ARY

    BOTTOM OF FIRST RESERVE AT SHAFT THE GREATER OF 5m FROM THE INVERT OF SHAFT OR EXTENT OF SYDNEY METRO PROPERTY

    RL 32.310

    NOTE 1

    ILLUSTRATIVE SECTION ONLY - SYDNEY METRO GRID AND MACQUARIE CENTRE BOUNDARY & GRIDLINES ARE NOT ORTHOGONAL. LEVEL OF TUNNEL AT THIS POINT NOT KNOWN. EXTENT OF SYDNEY METRO SUBSTRATA IN WATERLOO ROAD NOT KNOWN

    NOTE 2SUBSTRATUM IN WATERLOO ROAD MAY EXTEND TO TITLE BOUNDARY

    Key Plan

    0

    Scale: , 1:500 @ A3 Project Number:Drawing Number:Revision:Date:© NH Architecture & Hames Sharley

    Status:Path:

    1:250 @ A1

    20for Herring Rd Corner Podium Development

    HERRRING ROAD

    WA

    TER

    LOO

    RO

    AD

    E25/05/20

    C:\Users\o.wellings\Documents\Revit Local Files\2018\51108 MCIRHOST R2018_o.wellings.rvt

    SD57451108INITIAL DRAFT FOR REVIEW

    Macquarie Centre Detailed DASECTIONS - RAIL RESERVE WATERLOO ROAD

    1 : 200SECTION - RAIL RESERVES GRID PE

    E

    Existing footings demolished and rebuilt withlocalised excavation to suit. No additional bulkexcavation proposed. Footings support walls thatcontribute to the lateral resisting system for thebuilding. Footings loads will be determined duringdetailed design that will be undertaken after the DAis approved.

    1st R

    ES

    ER

    VE

    & B

    OU

    ND

    AR

    Y

    2nd

    RE

    SE

    RV

    E

    High Strength Rock

    2 Additional Levels toExisting Structure

  • RL 56500NEW L3A

    RL 63000NEW L4A

    1 2 3

    RL 44750LEVEL 1A

    RL 50250LEVEL 2A

    RL 39400LEVEL 0A

    RL 68125NEW L4A MEZZ

    RL 40.000

    TITL

    E BO

    UN

    DAR

    Y

    C/L

    UP

    TRAC

    K

    C/L

    DO

    WN

    TR

    ACK

    C/L

    PLA

    TFO

    RM

    TOP OF RAIL FFL 26500

    5000

    FIRST RESERVE

    INDICATIVETUNNEL

    DIAMETERPLATFORM MID LEVEL FFL 27675

    CONCOURSE LEVEL FFL 33075

    5000

    SYDNEY METRO SUBSTRATUM

    (FIRST RESERVE)

    5000

    TOP OF FIRST RESERVE THE GREATER OF 5m OR EXTENT OF SYDNEY METRO SUBSTRATUM ABOVE CROWN (UNKNOWN)

    SECOND RESERVE FROM SUBSTRATUM

    25000

    PT 2/ 1047085 SUBSTRATUM OWNED BY SYDNEY METROLIMITED IN HEIGHT TO RL40

    UNLIMITED IN DEPTH

    NEW CINEMAAUDITORIUM

    C/L

    CAV

    ERN

    NEW CLADDNG ANDINSULATED PANEL WALLS INDICATED WITH DASHED LINE

    EXISTING FOOTINGS

    NEW TUNNEL FOR TRANSFORMER DELIVERY

    NEW ICE RINK PLANT DECK

    RL 41.300 PMF

    RL 69.609

    RL 40.400

    NEW PERSONNEL CORRIDOR BEYOND

    PERSONNEL HATCH IN EXISTING GARDEN, NEW PATH AND STEPS FROM FOOTPATH AND LANDSCAPING

    NEW EQUIPMENT HATCH IN EXISTING SERVICE ROAD

    NEW FR SUBSTATION INLET DUCT

    EXISTING BASEMENT NEW CHAMBER SUBSTATION

    EXISTING BASEMENT - NEW CABLE TRENCH

    EXISTING BIG W

    EXISTING CAR PARK

    SIDE OF FIRST RESERVE THE GREATER OF 5m OFF TUNNEL OR EXTENT OF SYDNEY METRO SUBSTRATUM IN WATERLOO ROAD (UNKNOWN)

    NEW CONDUIT / STRUCTURAL FOOTINGS ZONE

    WATERLOO ROAD

    EXISTING CAR PARK & TRUCKS

    EXISTING RAMP COLUMN FOOTING DEPTH UNKNOWN

    EXISTING RAMP

    INDICATIVETUNNEL

    DIAMETER

    ESTIMATED TUNNEL DEPTH, SIZE AND LOCATION, TO BE CONFIRMED BY SYDNEY METRO

    NOTE 15414

    600

    13381

    1000

    8800 8800

    R 35

    60

    NOTE 1

    ILLUSTRATIVE SECTION ONLY - SYDNEY METRO GRID AND MACQUARIE CENTRE BOUNDARY & GRIDLINES ARE NOT ORTHOGONAL. LEVEL OF TUNNEL AT THIS POINT NOT KNOWN. EXTENT OF SYDNEY METRO SUBSTRATA IN WATERLOO ROAD NOT KNOWN

    NOTE 2SUBSTRATUM IN WATERLOO ROAD MAY EXTEND TO TITLE BOUNDARY

    RL 56500NEW L3A

    RL 63000NEW L4A

    1 2 3

    RL 44750LEVEL 1A

    RL 50250LEVEL 2A

    RL 39400LEVEL 0A

    RL 68125NEW L4A MEZZ

    RL 72.825

    C/L

    DO

    WN

    TR

    ACK

    C/L

    PLA

    TFO

    RM

    TOP OF RAIL FFL 26500

    FIRST RESERVE

    PLATFORM MID LEVEL FFL 27675

    CONCOURSE LEVEL FFL 33075

    5000

    SYDNEY METRO SUBSTRATUM

    (FIRST RESERVE)

    TOP OF FIRST RESERVE THE GREATER OF 5m OR EXTENT OF SYDNEY METRO SUBSTRATUM ABOVE CROWN (UNKNOWN)

    SECOND RESERVEFROM SUBSTRATUM

    (SEE NOTE 1)6269 13476 28550

    C/L

    CAV

    ERN

    SIDE OF FIRST RESERVE THE GREATER OF 5m OFF TUNNEL OR EXTENT OF SYDNEY METRO SUBSTRATUM IN WATERLOO ROAD (UNKNOWN)

    INDICATIVETUNNEL

    DIAMETER

    ESTIMATED TUNNEL DEPTH, SIZE AND LOCATION, TO BE CONFIRMED BY SYDNEY METRO

    8800 8800

    25000 FROM BOUNDARY NEAR GRID M

    RL 40.00

    TITL

    E BO

    UN

    DAR

    Y

    EXISTING RAILCORP

    SUBSTATION

    NEW RETAIL

    EXISTING BIG W

    EXISTING CAR PARK & TRUCKS

    EXISTING CAR PARK

    EXISTING FOOTINGS

    NEW FOOTINGS TO SUPPORT STAIR, TO STRUCTURAL ENGINEER'S DETAILS

    STRENGTHENING TO EXISTING WALL AND FOOTINGS TO STRUCTURAL ENGINEER'S DETAILS

    NEW EGRESS STAIR TO BE BUILT ABOVE EXISTING STAIR WELL

    WATERLOO ROAD

    PT 2/ 1047085 SUBSTRATUM OWNED BY SYDNEY METROLIMITED IN HEIGHT TO RL40

    UNLIMITED IN DEPTH

    EXISTING BIG W MEZZANINE

    NEW ICE RINK

    EXISTING LANDSCAPING

    EXISTING FOOTINGS OF STAIR BETWEEN GRIDS M & N

    RL 39.100 RL 39.100W2

    W16BEYOND: EXISTING STAIR BETWEEN GRIDS M & N

    Key Plan

    0

    Scale: , 1:500 @ A3 Project Number:Drawing Number:Revision:Date:© NH Architecture & Hames Sharley

    Status:Path:

    1:200 @ A1

    16for Herring Rd Corner Podium Development

    HERRRING ROAD

    WA

    TER

    LOO

    RO

    AD

    E25/05/20

    C:\Users\o.wellings\Documents\Revit Local Files\2018\51108 MCIRHOST R2018_o.wellings.rvt

    SD57551108INITIAL DRAFT FOR REVIEW

    Macquarie Centre Detailed DASECTIONS - RAIL RESERVE WATERLOO ROAD

    1 : 200SECTION NEAR GRID DG

    1 : 200SECTION NEAR GRID MF

    GF

    New structural core wall footing Allow for the provision of tension groundanchors below.Geotech engineer to review impact onMetro.

    No excavation into the 1streserve. Base of footings0.5m above 1st Reserve.

    CORE 4

    L0 (CarPark)

    L1 (Big W)

    L2 (Woolies)

    L3(Cinemas)

    L4 (Rink)

    Roof

    ESD574

    FSD575

    existing shown yellow

    new shown green

    approximate line of rockshown on original structuraldrawings

    CORE 1 CORE 2 CORE 3 CORE 4 REFER SHEET 1FOR KEY PLAN

    ELEVATIONS OF CORE WALLSLOOKING FROM WATERLOO RD

    approximate line of existingsurface shown dashed

    approx extent of metroservices shaft

    Existing demo existing stair andstructure.No additional bulk excavationrequired.Localised discrete foundationsproposed for new structure.

    2 Additional Levels toExisting Structure

    2nd

    RE

    SE

    RV

    E

    1st R

    ES

    ER

    VE

    1st R

    ES

    ER

    VE

    & B

    OU

    ND

    AR

    Y

    High Strength Rock