preproduction status & results

8
GLAST LAT Project February 10, 2004 R. Johnson Tracker MCM Production Readiness Review 1 S erialN o. Type PW B from DDI R eceiving Inspection com plete R adius M achined Inspection of m achining hipped to Teledyne Flex Adaptor bond & trim Flex Adaptor Inspection SM T parts installed C onnectors installed ASIC die installed W ire bond Elect.Test (pre- encap) Encapsulate C onform al C oating Final Elect.Test Final Inspection S hipped to SLAC R eceiving inspection B aseline Elect.Test T/C & B urn- in FinalTest Final Inspection Shipped to IN FN S torage Bldg.33 176 LA T-D S-00077-5 174 LA T-D S-00077-5 574T LA T-D S-00077-5 512 LA T-D S-00077-5 227 LA T-D S-00077-5 225 LA T-D S-00077-5 196 LA T-D S-00077-5 169 LA T-D S-00077-5 175 LA T-D S-00077-5 197 LA T-D S-00077-5 224 LA T-D S-00077-5 228 LA T-D S-00077-5 519T LA T-D S-00077-5 572 LA T-D S-00077-5 226 LA T-D S-00077-5 173 LA T-D S-00077-5 576 LA T-D S-00077-5 513 LA T-D S-00077-5 587 LA T-D S-00077-5 528 LA T-D S-00077-5 562 LA T-D S-00077-5 374 LA T-D S-00077-5 347 LA T-D S-00077-5 364 LA T-D S-00077-5 593 LA T-D S-00077-5 518 LA T-D S-00077-5 578 LA T-D S-00077-5 187 LA T-D S-00077-5 584 LA T-D S-00077-5 516 LA T-D S-00077-5 509 LA T-D S-00077-5 523 LA T-D S-00077-5 514 LA T-D S-00077-5 359 LA T-D S-00077-5 524 LA T-D S-00077-5 571 LA T-D S-00077-5 185 LA T-D S-00077-5 190 LA T-D S-00077-5 510 LA T-D S-00077-5 519 LA T-D S-00077-5 394T LA T-D S-00077-5 206 LA T-D S-00077-5 SCRAP 184 LA T-D S-00077-5 SCRAP 335 LA T-D S-00077-5 SCRAP 515 LA T-D S-00077-5 S A M P LE 573 LA T-D S-00077-5 S A M P LE 194 LA T-D S-00077-5 SCRAP 147 LA T-DS -00077-5 SPARE LA T-D S -00898 227 LA T-DS -00077-5 SPARE LA T-D S -00898 563 LA T-DS -00077-5 SPARE LA T-D S -00898 236 LA T-D S-00368-4 230 LA T-D S-00368-4 235 LA T-D S-00368-4 237 LA T-D S-00368-4 242 LA T-D S-00368-4 1107 LA T-D S-00368-4 1113 LA T-D S-00368-4 1104 LA T-D S-00368-4 1102 LA T-D S-00368-4 1077 LA T-D S-00368-4 1119 LA T-DS -00368-4 SPARE LA T-D S -00899 1080 LA T-DS -00368-4 SPARE LA T-D S -00899 Preproduction Status & Preproduction Status & Results Results Qty. 10 completed thermal cycle, burn-in and final electrical test, Sent to INFN Qty. 14 thermal cycle complete, burn-in and final electrical test (ECD 2/12/04) Qty. 6 pre-encap electrical test (ship to SLAC ECD 2/13/04) Qty. 3 wire bonding (ECD 2-13-04) Qty. 2 samples of Pitch Adaptor sent to INFN Qty. 4 Scrap Qty. 4 “Short” TMCM, install pitch adaptor & SMT parts (ECD 2/20/04) Qty. 10 “Tall TMCM” (ECD 2/24/04) +2 spare parts on hand Qty. 40 short TMCM Qty. 10 tall TMCM Qty. 50 preproduction total Qty. 4 completed thermal cycle, burn-in and final electrical test, Sent to SLAC

Upload: makara

Post on 15-Jan-2016

18 views

Category:

Documents


0 download

DESCRIPTION

Preproduction Status & Results. Qty. 4 completed thermal cycle, burn-in and final electrical test, Sent to SLAC. Qty. 10 completed thermal cycle, burn-in and final electrical test, Sent to INFN. Qty. 14 thermal cycle complete, burn-in and final electrical test (ECD 2/12/04). - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Preproduction Status & Results

GLAST LAT Project February 10, 2004

R. Johnson Tracker MCM Production Readiness Review 1

Serial No. Type PWB from DDI

Receiving Inspection complete

Radius Machined

Inspection of

machining

Shipped to Teledyne

Flex Adaptor bond &

trim

Flex Adaptor

Inspection

SMT parts installed

Connectors installed

ASIC die installed

Wire bond Elect. Test (pre-

encap)

Encapsulate Conformal Coating

Final Elect. Test

Final Inspection

Shipped to SLAC

Receiving inspection

Baseline Elect. Test

T/C & Burn-in

Final Test Final Inspection

Shipped to INFN

Storage Bldg. 33

176 LAT-DS-00077-5174 LAT-DS-00077-5

574T LAT-DS-00077-5512 LAT-DS-00077-5227 LAT-DS-00077-5225 LAT-DS-00077-5196 LAT-DS-00077-5169 LAT-DS-00077-5175 LAT-DS-00077-5197 LAT-DS-00077-5224 LAT-DS-00077-5228 LAT-DS-00077-5

519T LAT-DS-00077-5572 LAT-DS-00077-5226 LAT-DS-00077-5173 LAT-DS-00077-5

576 LAT-DS-00077-5513 LAT-DS-00077-5587 LAT-DS-00077-5528 LAT-DS-00077-5562 LAT-DS-00077-5374 LAT-DS-00077-5347 LAT-DS-00077-5364 LAT-DS-00077-5593 LAT-DS-00077-5518 LAT-DS-00077-5578 LAT-DS-00077-5187 LAT-DS-00077-5584 LAT-DS-00077-5516 LAT-DS-00077-5509 LAT-DS-00077-5523 LAT-DS-00077-5514 LAT-DS-00077-5359 LAT-DS-00077-5524 LAT-DS-00077-5571 LAT-DS-00077-5185 LAT-DS-00077-5190 LAT-DS-00077-5510 LAT-DS-00077-5519 LAT-DS-00077-5

394T LAT-DS-00077-5206 LAT-DS-00077-5 SCRAP184 LAT-DS-00077-5 SCRAP335 LAT-DS-00077-5 SCRAP515 LAT-DS-00077-5 SAMPLE573 LAT-DS-00077-5 SAMPLE194 LAT-DS-00077-5 SCRAP147 LAT-DS-00077-5 SPARE LAT-DS-00898227 LAT-DS-00077-5 SPARE LAT-DS-00898563 LAT-DS-00077-5 SPARE LAT-DS-00898

236 LAT-DS-00368-4230 LAT-DS-00368-4235 LAT-DS-00368-4237 LAT-DS-00368-4242 LAT-DS-00368-41107 LAT-DS-00368-41113 LAT-DS-00368-41104 LAT-DS-00368-41102 LAT-DS-00368-41077 LAT-DS-00368-41119 LAT-DS-00368-4 SPARE LAT-DS-008991080 LAT-DS-00368-4 SPARE LAT-DS-00899

Preproduction Status & ResultsPreproduction Status & Results

Qty. 10 completed thermal cycle, burn-in and final electrical test, Sent to INFN

Qty. 14 thermal cycle complete, burn-in and final electrical test (ECD 2/12/04)

Qty. 6 pre-encap electrical test (ship to SLAC ECD 2/13/04)

Qty. 3 wire bonding(ECD 2-13-04)

Qty. 2 samples of Pitch Adaptor sent to INFNQty. 4 Scrap

Qty. 4 “Short” TMCM, install pitch adaptor & SMT parts(ECD 2/20/04)

Qty. 10 “Tall TMCM”(ECD 2/24/04) +2 spare parts on hand

Qty. 40 short TMCMQty. 10 tall TMCMQty. 50 preproduction total

Qty. 4 completed thermal cycle, burn-in and final electrical test, Sent to SLAC

Page 2: Preproduction Status & Results

GLAST LAT Project February 10, 2004

R. Johnson Tracker MCM Production Readiness Review 2

Pre-Encapsulation Test ResultsPre-Encapsulation Test Results

Example Pre-Encapsulation Test Session• Results from the most recent test session at Teledyne, SN 173, 359, 509,

516, 523, 524, 562, 571, 576, 578, 584, 593.• SN 523:

– One GTFE chip had a broken calibration mask and drew excess current. It was the only chip out of 312 that had to be replaced.

• SN 516: – One wire bond lifted on a GTFE address line.– Shorts cleared on the pitch adapter between two pairs of channels.

• SN 516– Passed the electrical test, but with 2 shorted channels. Inspection of that

region uncovered damaged wire bonds that had to be repaired.• SN 509

– Passed the electrical test, but with 2 shorted channels. Debris could be seen between the two traces and was cleaned out.

• These 4 were reworked and tested perfect the following day.• The other 8 were perfect in the initial test.

Page 3: Preproduction Status & Results

GLAST LAT Project February 10, 2004

R. Johnson Tracker MCM Production Readiness Review 3

Failed ASICsFailed ASICs

• The incidence of ASIC failure, requiring reworking of MCMs, is low enough that we can live with it, but…

• All chips were fully tested on the wafer before dicing, so in principle we should not find any failures.– Damage during lapping, dicing, picking, inspection?– Damage during MCM assembly?

• We are starting a program to isolate the problem by probing– Failed dice returned from Teledyne.– Fresh dice from GDSI.

New vacuum fixture to be used for probe testing loose GTFE chips.

Page 4: Preproduction Status & Results

GLAST LAT Project February 10, 2004

R. Johnson Tracker MCM Production Readiness Review 4

Preproduction Electrical ResultsPreproduction Electrical Results

• So far, no MCMs have failed at– Post encapsulation/conformal coat test at Teledyne.– 3-temperature test following thermal cycling at SLAC.– Burn-in.– Final test after burn-in.

• In fact, the number of bad channels has not increased at any of those test points with respect to the pre-encapsulation test.

• Of 4 MCMs checked so far by probing, none has even a single broken trace or wire bond at the channel inputs.

• Note that we have yet not seen any chips go bad on MCMs following encapsulation and final test, in the Mini-Tower or preproduction.– This is evidence that the chips are robust when protected from

physical damage and that the ASIC failures seen during pre-encapsulation testing are not results of infant mortality.

Page 5: Preproduction Status & Results

GLAST LAT Project February 10, 2004

R. Johnson Tracker MCM Production Readiness Review 5

Measures on MCM Board

C-C'

Nominal Measured Nominal Measured Measured

S/N 196 356.375 359.337 358.930

S/N 224 356.397 359.139 358.892

S/N 227 356.417 359.278 358.727

MCM Board

356.424

B-B'A-A'

359.000

A-A’

C-C’

B-B’

Page 6: Preproduction Status & Results

GLAST LAT Project February 10, 2004

R. Johnson Tracker MCM Production Readiness Review 6

Planarity on MCM Board

Reference points

P1

P2

P3

P4

P5

Max

Min

Δ(Max-Min)

Distances from best fit plane

S/N 227 S/N 224 S/N 196

-0.014 -0.012 -0.033

-0.006 0.000 -0.006

0.005 0.005 0.013

0.015 0.008 0.028

0.001 -0.002 -0.001

0.015 0.008 0.028

0.029 0.020 0.061

-0.014 -0.012 -0.033

P5P4P3P2P1

Page 7: Preproduction Status & Results

GLAST LAT Project February 10, 2004

R. Johnson Tracker MCM Production Readiness Review 7

Planarity of the Strips

Position on MCM Board

zA3 (300 µm from edge) -

zA2

zA4 (400 µm from edge) -

zA2

zA5 (500 µm from edge) -

zA2

Angle (degrees)

P1 0.007 0.021 0.021 7.9696P2 0.000 -0.001 -0.002 -0.5729P3 -0.006 -0.012 -0.019 -3.4336P4 0.006 0.006 -0.005 0.0000P5 0.003 -0.003 -0.010 -3.43360.0000P1 -0.001 -0.001 -0.003 0.0000P2 0.000 -0.002 -0.004 -1.1458P3 0.000 -0.010 -0.017 -5.7106P4 0.000 0.002 -0.006 1.1458P5 0.005 0.006 0.010 0.57290.0000P1 0.000 0.000 -0.002 0.0000P2 -0.001 -0.001 -0.002 0.0000P3 -0.009 -0.027 -0.036 -10.2040P4 0.000 -0.005 -0.017 -2.8624

s/n 227

s/n 224

Difference of Z coordinate between marked points and A0

s/n 196

A0 A2 A5A3 A4

200um 100um

Page 8: Preproduction Status & Results

GLAST LAT Project February 10, 2004

R. Johnson Tracker MCM Production Readiness Review 8

ConclusionsConclusions

• The MCM assembly procedure is able to deliver boards that meet all electrical requirements, generally with much less than the maximum of 8 bad channels per MCM.

• Some rework is required after wire bonding and before encapsulation.– The incidence of bad dice is low and seems to be decreasing.– We will do some work to understand whether chips are damaged

during lapping, dicing, picking, and inspection at GDSI.– The largest amount of rework results from physical damage to

wire bonds during handling. New fixtures will be made to reduce this.

• The finished MCMs conform to the designed height and straightness of the top edge, where G&A will wire bond.

• The perpendicularity of the top edge may be improved with a new fixture, but G&A is confident that it is adequate for good quality wire bonds to the SSDs (but possibly at a cost in wire bonding time).