Page 1: Presentación de PowerPoint · Abengoa was the EPC Contractor The Project was executed successfully within time and budget O&M Contractor Abengoa is the O&M Contractor. The Plant

Presentación Corporativa2018

Case Study:

!Xina Solar One

Copyright @ Abengoa S.A. All rights reserved

Head of Solar Technology Department

Miguel Méndez Trigo

25/04/2019

ACSP Seminar, Santiago de Chile

Page 2: Presentación de PowerPoint · Abengoa was the EPC Contractor The Project was executed successfully within time and budget O&M Contractor Abengoa is the O&M Contractor. The Plant

Performance & Operation3Construction &

Commissioning2•

Project Development1

!Xina Solar One Insights

Page 3 Page 11 Page 16

2

Page 3: Presentación de PowerPoint · Abengoa was the EPC Contractor The Project was executed successfully within time and budget O&M Contractor Abengoa is the O&M Contractor. The Plant

1Project Development

3

Page 4: Presentación de PowerPoint · Abengoa was the EPC Contractor The Project was executed successfully within time and budget O&M Contractor Abengoa is the O&M Contractor. The Plant

Project Development

South Africa - Renewable Energy Independent Power Producer Procurement Program

National Target South Africa has a high level of Renewable Energy potential.

National commitment to transition to a low carbon economy.

17 800 MW of the 2030 target are expected to be from renewable energy.

Socio-economic and environmentally sustainable growth

Bid Windows A total of 4 Bid Windows have been deployed until 2018 BW 1 – 1,4 GW Total; CSP 150 MW (Kaxu Solar One and Khi Solar One)

BW 2 – 1,0 GW Total; CSP 50 MW

BW 3 – 1,5 GW Total; CSP 200 MW (Xina Solar One) BW 3.5 – 200 MW; CSP 200 MW

BW 4 – 1,0 GW; No CSP

CSP Technology Used Parabolic Trough + Molten Salt Storage (4 Power Plants, 350 MW)

Superheated Steam Tower + Steam Accumulators (1 Power Plant, 50 MW, in operation)

Molten Salts Tower (1 Power Plant, Financial Closure)

4

Renewable Installed Capacity

5,100 MW

CSP - 600 MW

Xina Solar One - 100 MW

Page 5: Presentación de PowerPoint · Abengoa was the EPC Contractor The Project was executed successfully within time and budget O&M Contractor Abengoa is the O&M Contractor. The Plant

South Africa Experience

5

Kaxu Solar One

PTC Plant Kaxu Solar One is the first Project

developed by Abengoa in South Africa, with a

total installed capacity of 100 MW with 2,5 h

TES

Khi Solar One

Superheated Steam Tower Plant Khi Solar

One, first Plant of its kind in the world, with a

total installed capacity of 50 MW with 2 h TES

Xina Solar One

PTC Plant Xina Solar One is the last Project

developed by Abengoa in South Africa, with a

total installed capacity of 100 MW with 5,5 h

TES

95.000 South African

Households

315.000 tons of CO2

emissions prevented

80.000 South African

Households

348.000 tons of CO2

emissions prevented

45.000 South African

Households

18.000 tons of CO2

emissions prevented

Page 6: Presentación de PowerPoint · Abengoa was the EPC Contractor The Project was executed successfully within time and budget O&M Contractor Abengoa is the O&M Contractor. The Plant

Abengoa’s roles

as key of sucess

6

Sponsor - Project Company

Abengoa is the main partner in the Project

Company with 40% of the shares

IDC, PIC and Xina Community Trust own 60%

EPC Contractor

Abengoa was the EPC Contractor

The Project was executed successfully within

time and budget

O&M Contractor

Abengoa is the O&M Contractor. The Plant

is currently under operation achieving the

expected performance with a reliable

operation

Abengoa as key player along all the stages in Xina Solar One Project

Developing, since the RFQ in 2013 – Sponsor

Financial Process in 2014 – Sponsor + Project Company

Construction 2015 – 2017 - EPC Contractor + Project Company

Operation 2017 – 2037 - O&M Contractor + Project Company

Project

Developer

R&D

Performance

Basic

Engineering

Detail

EngineeringProcurement

Construction

Commissioning

O&M

Page 7: Presentación de PowerPoint · Abengoa was the EPC Contractor The Project was executed successfully within time and budget O&M Contractor Abengoa is the O&M Contractor. The Plant

77

Power Purchase Agreement - Singularities

Dispatchability strategy: For this window, Off-Taker (Eskom) encouraged bidders to

offer solutions to maximize electricity generation during the evening

Energy rate: The commercial energy rate resulted in a reduction of 10% for previous Bid

windows

7

Normal

100%

Peak

270%Off Peak

0%

Incomes Reduction Design Improvement

Off Peak

0%

Page 8: Presentación de PowerPoint · Abengoa was the EPC Contractor The Project was executed successfully within time and budget O&M Contractor Abengoa is the O&M Contractor. The Plant

8

Main Design Improvements

Solar Field - New Trough Design (Space Tube ST8.2++)

8

• Abengoa selected the newest and

most innovative Trough ever design

to optimize the final Plant

configuration.

• Main difference with previous

designs is the aperture: 5,7m2

(standard Trough) vs 8,2m2 (largest

of the market)

• The design was tested and approved

during Due Diligence process

New design results in a reliable cost-effective solution

Stress analysis Performance evaluation

CFD analysis Prototype

Page 9: Presentación de PowerPoint · Abengoa was the EPC Contractor The Project was executed successfully within time and budget O&M Contractor Abengoa is the O&M Contractor. The Plant

9

Main Design Improvements

9

Huge Continuous slope

without terraces allowing an

important cost reduction on

earth movement

New erection tools to

reduce the installation

times and thus to

erection costs

Solar Field – Design and Construction Strategies

Page 10: Presentación de PowerPoint · Abengoa was the EPC Contractor The Project was executed successfully within time and budget O&M Contractor Abengoa is the O&M Contractor. The Plant

10

Main Design Improvements

10

HTF Pumps process modifications to

accommodate and improve the

start up from TES System in

normal operation.

Low pressure overflow system

design to reduce HTF inventory

Power Block – Design of TES and HTF systems

Page 11: Presentación de PowerPoint · Abengoa was the EPC Contractor The Project was executed successfully within time and budget O&M Contractor Abengoa is the O&M Contractor. The Plant

2Construction & Commissioning

11

Page 12: Presentación de PowerPoint · Abengoa was the EPC Contractor The Project was executed successfully within time and budget O&M Contractor Abengoa is the O&M Contractor. The Plant

Safety indicators QQS philosophy – Committed to Health & Safety

Safety indicators Total

Reports 1244

Near Misses 13

First Aid Cases 44

Medical Treatment Cases 7

Lost time Cases 5

Fatalities 0

12

Around 1,000 workers per month average

More than 3.8 millions of man hours

36 Months Project

ZERO Fatalities or serious injuries

One of the areas of focus for Abengoa’s management is

safety in the workplace

All the safety index of the projects were below the initial

targets

Page 13: Presentación de PowerPoint · Abengoa was the EPC Contractor The Project was executed successfully within time and budget O&M Contractor Abengoa is the O&M Contractor. The Plant

1

13

Planning and Key Milestones

13

2

Commissioning

3

Page 14: Presentación de PowerPoint · Abengoa was the EPC Contractor The Project was executed successfully within time and budget O&M Contractor Abengoa is the O&M Contractor. The Plant

14

Planning and Key Milestones – Project Execution Schedule

0

10

20

30

40

50

60

70

80

90

100

Jul-2014 Nov-2014 Mar-2015 Jul-2015 Nov-2015 Mar-2016 Jul-2016 Nov-2016 Mar-2017 Jul-2017

Molten Salt

tanks erection

Solar Field

Erection

Steam

Turbine

Foundation

First steam

generated

First Steam Turbine

Synchronization

Grid certificate tests

Practical Completion

Certificate

HTf filling

start

Project Completed before deadline (31st July 2017)

Notice to

Proceed

14

Page 15: Presentación de PowerPoint · Abengoa was the EPC Contractor The Project was executed successfully within time and budget O&M Contractor Abengoa is the O&M Contractor. The Plant

15

!Xina Solar One – Official Presentation to National Authority

Page 16: Presentación de PowerPoint · Abengoa was the EPC Contractor The Project was executed successfully within time and budget O&M Contractor Abengoa is the O&M Contractor. The Plant

3Performance & Operation

16

Page 17: Presentación de PowerPoint · Abengoa was the EPC Contractor The Project was executed successfully within time and budget O&M Contractor Abengoa is the O&M Contractor. The Plant

Facility Acceptance Tests

17

Page 18: Presentación de PowerPoint · Abengoa was the EPC Contractor The Project was executed successfully within time and budget O&M Contractor Abengoa is the O&M Contractor. The Plant

Facility Acceptance Tests

18

1

Page 19: Presentación de PowerPoint · Abengoa was the EPC Contractor The Project was executed successfully within time and budget O&M Contractor Abengoa is the O&M Contractor. The Plant

Facility Acceptance Tests

19

2-3

Page 20: Presentación de PowerPoint · Abengoa was the EPC Contractor The Project was executed successfully within time and budget O&M Contractor Abengoa is the O&M Contractor. The Plant

Facility Acceptance Tests

20

4-5

Page 21: Presentación de PowerPoint · Abengoa was the EPC Contractor The Project was executed successfully within time and budget O&M Contractor Abengoa is the O&M Contractor. The Plant

Facility Acceptance Tests

6

Acceptance Tests passed succesfully at the 1st attempt

21

Page 22: Presentación de PowerPoint · Abengoa was the EPC Contractor The Project was executed successfully within time and budget O&M Contractor Abengoa is the O&M Contractor. The Plant

O&M Capabilities

22

Page 23: Presentación de PowerPoint · Abengoa was the EPC Contractor The Project was executed successfully within time and budget O&M Contractor Abengoa is the O&M Contractor. The Plant

Daily Performance

Normal

100%

Peak

270%

Off Peak0%

0

200

400

600

800

1000

1200

0

20

40

60

80

100

12021.06.2018

Net Generation (MWhe) Hot Tank Level (%) DNI (W/m2)

23

Page 24: Presentación de PowerPoint · Abengoa was the EPC Contractor The Project was executed successfully within time and budget O&M Contractor Abengoa is the O&M Contractor. The Plant

0

100

200

300

400

500

600

700

800

900

1000

0

20

40

60

80

100

12009.06.2018

Net Generation (MWhe) Hot Tank Level (%) DNI (W/m2)

Daily Performance

Normal

100%

Peak

270%

Off Peak0%

24

Page 25: Presentación de PowerPoint · Abengoa was the EPC Contractor The Project was executed successfully within time and budget O&M Contractor Abengoa is the O&M Contractor. The Plant

Daily Performance

Normal

100%

Peak

270%

Off Peak0%

25

0

200

400

600

800

1000

1200

0

20

40

60

80

100

120

10.12.2018

Net Generation (MWhe) Hot Tank Level (%) DNI (W/m2)

Page 26: Presentación de PowerPoint · Abengoa was the EPC Contractor The Project was executed successfully within time and budget O&M Contractor Abengoa is the O&M Contractor. The Plant

0

100

200

300

400

500

600

700

800

900

1000

0

20

40

60

80

100

120

29.10.2018

Net Generation (MWhe) Hot Tank Level (%) DNI (W/m2)

Daily Performance

Normal

100%

Peak

270%

Off Peak0%

26

Page 27: Presentación de PowerPoint · Abengoa was the EPC Contractor The Project was executed successfully within time and budget O&M Contractor Abengoa is the O&M Contractor. The Plant

Daily Performance

27

Page 28: Presentación de PowerPoint · Abengoa was the EPC Contractor The Project was executed successfully within time and budget O&M Contractor Abengoa is the O&M Contractor. The Plant

Production Guaranteed Period

Production Guaranteed Period

• 12 months operating above

100% of the expected generation

80%

85%

90%

95%

100%

105%

dic.-17 ene.-18 feb.-18 mar.-18 abr.-18 may.-18 jun.-18 jul.-18 ago.-18 sep.-18 oct.-18 nov.-18

Xina - Guarantee Performance Evolution

28

Avg: 101.8%

Page 29: Presentación de PowerPoint · Abengoa was the EPC Contractor The Project was executed successfully within time and budget O&M Contractor Abengoa is the O&M Contractor. The Plant