presentation-2 the project cycle

Upload: kunal-thakur

Post on 03-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Presentation-2 the Project Cycle

    1/61

    The Project Cycle

    Presentation 2 for Sotik Tea Company

    Harrie Knoef10-11th January 2008

    www.btgworld.com

  • 7/28/2019 Presentation-2 the Project Cycle

    2/61

    slide 2/60

    1. Phases in the project cycle

    2. Pre-investment phase Opportunity study

    Pre-feasibility study

    Feasibility study

    3. Investment phase

    4. Operational phase

    Contents

  • 7/28/2019 Presentation-2 the Project Cycle

    3/61

    slide 3/60

    Phases in the project cycle

    Pre-investment

    phase

    Investmentphase

    Operational

    phase

    Pre-feasibilitystudy

    Feasibility

    study

    Opportunity

    study

    Project

    recommendation

    Negotiation,contracting

    Engineering,

    design

    Construction

    Pre-production

    marketingTraining

    Commissioning,

    start-up

    Maintenance,

    improvements

    Expansion,Innovation

    Go/no-go

  • 7/28/2019 Presentation-2 the Project Cycle

    4/61

    slide 4/60

    Pre-investment phase

    The pre-investment phase starts with a problem or anidea, and ends in a project recommendation

    It may include a range of assessments and studies,

    such as: Opportunity study

    Pre-feasibility study

    Feasibility study

    Accuracy

    Investment

    costs

  • 7/28/2019 Presentation-2 the Project Cycle

    5/61

    slide 5/60

    Opportunity study

    An opportunity study is an assessment to determine

    whether there are opportunities for a project For example: whether there are possible solutions for

    an existing problem (e.g. high energy costs,unreliable energy supply, environmental concerns)

    Or, are there similar examples of success/failures Often not a formal study entrepreneurs usually

    take the initiative, informally discuss their problemand possible solutions with their peers and experts

    Outcome is a project idea (e.g. a cogenerationproject)

    Sotik: completed

  • 7/28/2019 Presentation-2 the Project Cycle

    6/61

    slide 6/60

    Pre-feasibility study

    A pre-feasibility study is a quick assessment of thebasic feasibility of a certain project idea.

    It determines whether basic technical / organisational

    requirements are met, and whether the solution is

    cost effective.

    Pre-feasibility studies are often executed by external

    experts, and have a short lead time (weeks).

    The study should indicate whether or not a feasibilitystudy is justified.

  • 7/28/2019 Presentation-2 the Project Cycle

    7/61slide 7/60

    Feasibility study

    A feasibility study is an extensive assessment of thefeasibility of a certain project

    Key elements include (see next slides): Technical issues

    Environmental issues Financial feasibility

    Organisational issues

    Risk analyses

    Financing

    The feasibility study should result in a project

    recommendation and a bankable project document

  • 7/28/2019 Presentation-2 the Project Cycle

    8/61slide 8/60

    Feasibility study: technical issues (1)

    Technical assessments should determine whichsystem is required, and what are the inputs and

    outputs

    Basis for the technical assessment is an analysis of

    on-site processes, for example: Determine current energy demand (heat and electricity) and

    projected developments therein: energy consumption, peak

    demand, load profiles, steam condition requirements, etc

    Determine fuel availability and attributes (moisture, contaminants,morphology, ash content, density, calorific value)

    Integration of CHP plant to the local project site

  • 7/28/2019 Presentation-2 the Project Cycle

    9/61slide 9/60

    Feasibility study: technical issues (2)

    Technology selection, for instance: combustion/steam cycle or gasification/engine

    steam turbine or steam engine or ORC

    anaerobic digestion

    Technology attributes heat and power output

    efficiency

    fuel requirements fuel pretreatment

    O&M requirements

  • 7/28/2019 Presentation-2 the Project Cycle

    10/61slide 10/60

    Steam engine vs Steam turbine

    Advantages Disadvantages

    Steam engine Low cost at low power ratings

    Robust design, long life

    expectancy

    Good performance at lower

    loads

    Low capacity (10%)

    Possible higher temperature

    heat supply

    Low consumables

    Higher capacity (>500 kW)

    Higher cost in smaller scale

    Less suitable for intermittent

    use

    Steam engines for smaller loads, intermittent operation, at low biomass price

    Steam turbines for higher loads, continuous operation, biomass may be to be

    bought

  • 7/28/2019 Presentation-2 the Project Cycle

    11/61slide 11/60

    ORC (Organic Rankine Cycle)

    For instance in Ludwigsfelde, Germany Wood-fired boiler

    Wood consumption: 18700 ton/yr

    1,5 MWe, 10 MWth

    7500 hrs/yr 86% availability

    Fully remote controlled from Italy

  • 7/28/2019 Presentation-2 the Project Cycle

    12/61slide 12/60

    Feasibility study: environmental issues

    Environmental assessment should indicate to whatextent the project can meet local / national

    environmental standards

    Example:

    Assessment of emission regulations (e.g. dust, NOx, SOx) Comparison with expected (rated) emissions from systems

    Determine required emission control systems (flue gas filters, de-

    NOx)

    Legal requirement Kenya: EIA, Environmental ImpactAssessment

  • 7/28/2019 Presentation-2 the Project Cycle

    13/61slide 13/60

    Feasibility study: environmental issues

    emission control [1]

    Main contaminants: particles, NOx, CO

    Aspects to consider Environmental legislation Local situation Technological state of the art BAT: Best Available Technology

    Levels of control (and measures)

    Fuel side (prevention) Conversion side (prevention) Flue gas side (end-of-pipe)

  • 7/28/2019 Presentation-2 the Project Cycle

    14/61slide 14/60

    Feasibility study: environmental issues

    emission control [2]

    Fuel side (prevention): moisture content, fuel size, no contaminants quality clauses in fuel delivery contracts

    Conversion side (prevention): optimal process control (partial vs full load) multiple air supply/staged combustion flue gas circulation (NOx control)

    Flue gas side (end-of-pipe): particles: (multi)cyclones, fabric filters, electrostatic filters NOx: catalytic reduction (combined with SOx)

  • 7/28/2019 Presentation-2 the Project Cycle

    15/61slide 15/60

    Energy demand analysis

    Load curves and load duration curves

    Annual basis

    Monthly basis

    Daily basis

    Hourly basis

  • 7/28/2019 Presentation-2 the Project Cycle

    16/61slide 16/60

    Feasibility study: energy demand

    -

    50

    100

    150

    200

    250

    300

    1 4 710

    13

    16

    19

    22

    25

    28

    31

    34

    37

    40

    43

    46

    49

    52

    Duration [weeks]

    heatdemand[GJ]

    Load duration

    curve

    annual basis

    Load curve

    annual basis

    0

    50

    100

    150

    200

    250

    300

    1 4 710

    13

    16

    19

    22

    25

    28

    31

    34

    37

    40

    43

    46

    49

    52

    weeks of the year

    heatdemand[GJ]

    Maximum

    240

    GJ/wkAverage

    168

    GJ/wk

    Heat demand is

    often leading

  • 7/28/2019 Presentation-2 the Project Cycle

    17/61slide 17/60

    Feasibility study: energy demand

    Load duration curve

    daily basis

    0.00

    0.50

    1.00

    1.50

    2.00

    2.50

    0:0

    0

    2:0

    0

    4:0

    0

    6:0

    0

    8:0

    0

    10:00

    12:00

    14:00

    16:00

    18:00

    20:00

    22:00

    time of the day

    heatdemand

    [GJ]

    -

    0.50

    1.00

    1.50

    2.00

    2.50

    1 3 5 7 9 11 13 15 17 19 21 23

    Duration per day [hours]

    heatdema

    nd[GJ]

    Load curve

    daily basis

    Maximum

    2.2 GJ/hr

    620 kWth

    Maximum day

    Average day

    0.00

    0.50

    1.00

    1.50

    2.00

    2.50

    0:0

    0

    2:0

    0

    4:0

    0

    6:0

    0

    8:0

    0

    10:00

    12:00

    14:00

    16:00

    18:00

    20:00

    22:00

    time of the day

    heatdemand

    [GJ]

    -

    0.50

    1.00

    1.50

    2.00

    2.50

    1 3 5 7 9 11 13 15 17 19 21 23

    Duration per day [hours]

    heatdema

    nd[GJ]

    Maximum

    1.4 GJ/hr

    388 kWth

  • 7/28/2019 Presentation-2 the Project Cycle

    18/61slide 18/60

    Feasibility study: financial issues (1)

    The financial assessments determine the cost-effectiveness of an investment

    Financial

    analysesProject

    financing

    Investment costs

    Operating costs

    Revenues

    Other parameters

    Indicators

    Overviews

    Sensitivity

    parameters

  • 7/28/2019 Presentation-2 the Project Cycle

    19/61slide 19/60

    Feasibility study: financial issues (2)

    Investment costs Determine fixed investment costs (land, buildings, equipment,

    installation, commissioning) Determine working capital (in comparison to current situation), e.g.

    additional stock, accounts payable, accounts receivable

    Annual costs and revenues Annual costs are for example fuel (biomass), personnel,

    maintenance, administrative costs Annual revenues are for example fuel savings, avoided energy

    costs, revenues from energy sales, carbon credits

    Other parameters Depreciation rate, tax rate Project duration, equipment lifetime

  • 7/28/2019 Presentation-2 the Project Cycle

    20/61slide 20/60

    Investment costs (example)

    Civil works and building 1 m

    Fuel handling/feeding 1 m

    CHP plant 10 m

    Utilities / auxiliary equipment 2 m

    Engineering 1 m

    Start-up and commissioning 2 m

    Total costs 17 m

    ? = What is inside the Capital expenses

  • 7/28/2019 Presentation-2 the Project Cycle

    21/61slide 21/60

    Operational costs

    Fuel costs different suppliers, variation in time

    Labour costs: ~ 5% of investment costs

    labour requirements level of automation

    Maintenance costs: ~ 2.5% of investment maintenance costs quality of boiler / investment costs

    Other costs: costs for pre-treatment, capital,heat distribution, insurance, grid connection,

    etc.

  • 7/28/2019 Presentation-2 the Project Cycle

    22/61

    slide 22/60

    Feasibility study: financial issues (3)

    Financial analyses1. Determine financial indicators (IRR, NPV, RoI, Payback

    Period)

    2. Determine production costs, cashflow, profit-loss and

    balance sheets3. Determine the sensitivity of indicators to parameter

    variations (e.g. investment costs, number of operating

    hours, etc.

  • 7/28/2019 Presentation-2 the Project Cycle

    23/61

    slide 23/60

    Feasibility study: financial issues (4)

    Ad 1. Most commonly used financialindicators: IRR (Internal Rate of Return): average annual return of

    the project, regardless of how it is financed

    NPV (Net Present Value): value of the investment in thepresent year when discounting future cashflows RoI (Return on Investment): average annual return on

    equity = annual profits / investment costs (%) Payback Period: indicates the number of years before

    the initial investment is repaid = investment / annualprofit (yr)

  • 7/28/2019 Presentation-2 the Project Cycle

    24/61

    slide 24/60

    Feasibility study: financial issues (5)

    Ad2. Financial overviews Production costs: overview of costs of production

    (including operational costs, overheads, depreciation,

    financial costs

    Cashflows: projection of ingoing and outgoing cashflows, determining financing needs

    Profit-loss accounts: projection of annual accounts,

    determining annual profits or losses, and taxes

    Balance sheets: projection of assets and liabilities

  • 7/28/2019 Presentation-2 the Project Cycle

    25/61

    slide 25/60

    Feasibility study: financial issues (6)

    Ad3. Sensitivity analyses: Assessing how variations in certain parameters influence

    the financial performance of the project

    Determine the important parameters, to estimate risks

    Determine at what level of variation the project is stillcost-effective

  • 7/28/2019 Presentation-2 the Project Cycle

    26/61

    slide 26/60

    Feasibility study: financial issues (8)

  • 7/28/2019 Presentation-2 the Project Cycle

    27/61

    slide 27/60

    Feasibility study: financial issues (9)

    Financing Determine financing needs (fixed investments, interest during

    construction, working capital)

    Determine financing mix (equity, loans, subsidies)

    Risk assessment

    Some general observations Maximisation of subsidies and loans give the highest Return on

    Investment, and reduces the risk for the investor

    Often an iterative process, depending on the availability of equity

    and loan conditions

    F ibilit t d fi i l i (10)

  • 7/28/2019 Presentation-2 the Project Cycle

    28/61

    slide 28/60

    Feasibility study: financial issues (10)

    technical specification - caseHeat demand

    Number of houses 56

    Specific heat demand 90 GJ/yr

    Total heat demand 5,040 GJ/yr

    Maximum heat demand 2.2 GJ/hr

    619 kW th

    Heating season duration 30 weeks/yr

    Boiler specifications

    DH system losses 5%

    Design capacity boiler 652 kW th

    Fuel requirements

    Boiler efficiency 75%

    Heat input boiler 6,720 GJ/yr

    Fuel type wood chips

    Moisture content 40% wet basis

    Net calorific value 10 GJ/ton

    Total amount of wood 672 ton/yr

    Average wood flow 133 kg/hr

    Maximum wood flow 223 kg/hr

  • 7/28/2019 Presentation-2 the Project Cycle

    29/61

    slide 29/60

    Feasibility study: financial issues (11)

    financial analyses - case

    Investment costsSpec. investment system 200 EUR/kWth

    Investment costs 130,409 EUR

    Financial parametersInterest rate 6%

    Economic lifetime 15 yr

    Fuel supply 672 ton/yr

    Fuel costs 4 EUR/ton

    Current price energy 10 EUR/GJ

    Labour costs 5% of invest. boiler

    Maintenance costs 2.5% of invest. boiler

  • 7/28/2019 Presentation-2 the Project Cycle

    30/61

    slide 30/60

    Feasibility study: financial issues (12)

    cost price analyses - case

    Capital costs 13,427 EUR/yr

    Fuel costs 2,688 EUR/yr

    Labour costs 6,520 EUR/yrMaintenance costs 3,260 EUR/yr

    Total costs 25,896 EUR/yr

    Cost price energy 5.14 EUR/GJ

  • 7/28/2019 Presentation-2 the Project Cycle

    31/61

    slide 31/60

    Feasibility study: financial issues (13)

    Simple cost/benefit analyses - case

    Total annual costs 25,896 EUR/yr

    Total annual revenues 50,400 EUR/yrNet result 24,504 EUR/yr

    Return on investment 19%

    Simple payback time 5 yr

  • 7/28/2019 Presentation-2 the Project Cycle

    32/61

    slide 32/60

    Feasibility study: financial issues (14)

    Sensitivity analyses - case

    What if - analysis (Excel: Data/Table)

    Remark: take into account probability of parametervariation

    0%

    5%

    10%

    15%

    20%

    25%

    30%

    35%

    40%

    - 4 8 12 16 20

    Fuel price [EUR/ton]

    ReturnonInvestment[%]

    150

    175

    200

    225

    250

  • 7/28/2019 Presentation-2 the Project Cycle

    33/61

    slide 33/60

    Feasibility study: financial issues (15)

    Sensitivity analyses - case

    Scenario analysis (Excel: Tools/Scenarios)

    Remark: take realistic sets of parameters

    Scenario 1 Scenario 2

    Investment costs boiler 250 150

    Efficiency boiler 85% 65%

    Fuel costs 6 2

    Labour costs 3% 8%

    Maintenance costs 1% 5%

    Return on Investment 15% 27%

  • 7/28/2019 Presentation-2 the Project Cycle

    34/61

    slide 34/60

    Feasibility study: financial issues (16)

    Financing scheme - case

    Energy

    company

    Financial

    Investors

    Fuel

    suppliers

    Developers,

    management

    Commercial

    bank

    Development

    bank

    CDM, JI Fund

    Environmental

    fund

    25%

    50%

    25%

    project

  • 7/28/2019 Presentation-2 the Project Cycle

    35/61

    slide 35/60

    Feasibility study: organisational issues

    Internal / external project

    Ownership and partnership

    What parties to include, responsibilities, shares

    Planning Example

    For industries, energy production is often not core business. Theymay prefer to undertake such activities in a separate company. Insuch a company, other shareholders can be sought: e.g. biomass

    suppliers, utility companies or private equity companies. Theindustry may choose to retain a majority position (51% of theshares) in order to keep control.

  • 7/28/2019 Presentation-2 the Project Cycle

    36/61

    slide 36/60

    Feasibility study: non-techno/economics

    Legislation (emission, energy, etc.)

    Environmental impacts

    Permissions

    Socio-economic benefits

    Success factors include: Fuel availability

    Technical reliability

    Profitability Organization structure

    Public perception

  • 7/28/2019 Presentation-2 the Project Cycle

    37/61

    slide 37/60

    Feasibility study: challenges

    Obtaining correct data of current and futuresituation Input data on wood availability, power and heat demand

    Assessment of local boundary conditions and desires

    Selecting the proper technology (define criteria) Dimensioning of the cogen plant

    Financing

  • 7/28/2019 Presentation-2 the Project Cycle

    38/61

    slide 38/60

    Project Recommendation phase

    Go No Go decision to be taken by project management team,

    shareholders,

    project developers,

    investors,

    bankers,

    Public perception Emissions (pollutants, smell)

    Visual (building, steam, smoke)

    Noise Transport

    General perception towards bio-energy

  • 7/28/2019 Presentation-2 the Project Cycle

    39/61

    slide 39/60

    Recommendations (1)

    Set-up an organization scheme: taking into account the interest of all parties involved:

    fuel supplier(s), operating entity of bio-energy plant,

    energy consumer, financing parties, authorities,

    technology suppliers

    identify relations and necessary agreements between

    parties involved (i.e. fuel delivery agreements, energy

    supply agreements)

    evaluate different organization models

  • 7/28/2019 Presentation-2 the Project Cycle

    40/61

    slide 40/60

    Recommendations (2)

    Special attention to fuel supply: characteristics

    seasonal aspects

    base price

    transport (+costs)

    pretreatment requirements (+costs) storage (+costs)

    contractability

    Special attention to energy consumers

    delivery conditions consumption assurance

    price assurance

  • 7/28/2019 Presentation-2 the Project Cycle

    41/61

    slide 41/60

    Recommendations (3)

    Involve local parties and authorities in anearly stage

    Take into consideration all potential succes

    and failure factors also seemingly less important factors

    its better to mention and refute than not to mention at all

  • 7/28/2019 Presentation-2 the Project Cycle

    42/61

    slide 42/60

    Negotiation & Contracting phase

    Permit preparation and application Environmental permit

    Building permit

    Biomass fuel contracting

    Negotiations with equipment suppliers

    Contracts with project team

    Negotiations with financing institutes

    Risk mitigation and allocation

    Negotiations with local community (NIMBY?)

  • 7/28/2019 Presentation-2 the Project Cycle

    43/61

    slide 43/60

    Negotiation and contracting

    Fuel supply

    Availability is not the same as contractability

    Logistic aspects

    Guarantees and assurances: price assurance (long term contracts) delivery assurance (seasonal fluctuations)

    quality assurance (fuel characteristics vs boiler

    requirements)

  • 7/28/2019 Presentation-2 the Project Cycle

    44/61

    slide 44/60

    Engineering design [1]

    Data collection / analyses Definition, quality and quantity of the biomass fuel to be

    delivered to the project facility

    Economic parameters like fuel costs, electric power and

    heat sales price, local labor rates, availability and costsof utilities, estimated time schedule

    Location of the plant and its environment, road access,

    grid connection point, availability of water, gas and other

    requirements (dependent on type of plant)

  • 7/28/2019 Presentation-2 the Project Cycle

    45/61

    slide 45/60

    Engineering design [2]

    Plant Conceptual design Preliminary process design and flow diagram

    Heat and mass balance

    Process description

    Plant control philosophy Conceptual lay-out and plot plan

    List of major equipment

    Time schedule for EPC of the plant

    Identify major environmental issues connected with theproposed project

  • 7/28/2019 Presentation-2 the Project Cycle

    46/61

    slide 46/60

    Engineering design [3], plot plan

  • 7/28/2019 Presentation-2 the Project Cycle

    47/61

    slide 47/60

    Detailed design [1]

    Optional: mostly done by technology supplier

    Process description

    HAZOP study on Health and Safety

    what-if questions

    PFDs Process Flow Diagram

    PIDs Process Instrumentation Diagrams

    Cost price determination (quotations)

    Financial evaluation of the project

  • 7/28/2019 Presentation-2 the Project Cycle

    48/61

    slide 48/60

    Detailed design [1], PID

    TE = thermocouple

    TT = T-transmitter

    A = alarm

    TIR = T-indicator

    and recording

  • 7/28/2019 Presentation-2 the Project Cycle

    49/61

    slide 49/60

    Detailed design [2], I/O listing

    (Instrumentation & Operating range)

    To excell sheet

  • 7/28/2019 Presentation-2 the Project Cycle

    50/61

    slide 50/60

    Detailed design [3], M&E-balance

    General M&E balance: to excell sheet (BTG)

    Detailed M&E balance:

    at each main gas stream (engineering company)

  • 7/28/2019 Presentation-2 the Project Cycle

    51/61

    slide 51/60

    Investment phase

    Finance

    Civil works

    Fabrication main components

    Construction on-site

    Permitting

    Training

    Documentation

  • 7/28/2019 Presentation-2 the Project Cycle

    52/61

    slide 52/60

    Tendering of equipment supply

    Optional

    Systematic approach using internationallyaccepted procurement procedures for therequired equipment and services supply

    Tender document details the scope andspecs of the equipment and services supply

    Supply offer should provide provisions for: After-sales service Spare parts Training of operators

  • 7/28/2019 Presentation-2 the Project Cycle

    53/61

    slide 53/60

    Operational phase

    Commissioning

    Optimation, modifications

    Operation, maintenance

    Expansion, innovation

    Replication

    Portfolio projects

    Monitoring (technical performance andoptional carbon credits)

    F ibilit lt ti

  • 7/28/2019 Presentation-2 the Project Cycle

    54/61

    slide 54/60

    Feasibility results vs practice Investment tend to become higher than expected,

    because of:

    Delays Too optimistic planning and cost estimate (often to secure finance

    from banks)

    Additional desires

    Mistakes during engineering phase

    New legislation on HSE, emissions,

    This results often in lack of working capital

    Fuel switch and portfolio projects are very successful

  • 7/28/2019 Presentation-2 the Project Cycle

    55/61

    slide 55/60

    CHP problems in practice

    Trained/skilled operators

    Wrong technology selected (Burundi)

    No stable load conditions or changing load

    Sustainable wood supply chains

    Managing a new CHP installation

    Lack of spare parts (remote areas)

    Bad matching of boiler vs turbine

    Lower efficiency, higher maintenance

  • 7/28/2019 Presentation-2 the Project Cycle

    56/61

    slide 56/60

  • 7/28/2019 Presentation-2 the Project Cycle

    57/61

    slide 57/60

    Financing route (1)

  • 7/28/2019 Presentation-2 the Project Cycle

    58/61

    slide 58/60

    Financing route (2)

  • 7/28/2019 Presentation-2 the Project Cycle

    59/61

    slide 59/60

    Stakeholders

    So, can become complex

  • 7/28/2019 Presentation-2 the Project Cycle

    60/61

    slide 60/60

    Video - BIM

  • 7/28/2019 Presentation-2 the Project Cycle

    61/61

    Thank you for your attention!

    Harrie Knoef

    BTG biomass technology group BV

    www.btgworld.com

    [email protected]

    Ph: +31-53-4861190

    http://www.btgworld.com/mailto:[email protected]:[email protected]://www.btgworld.com/