Page 1: PRESENTATION FOR: CITY OF MUSTANG …...2007 –Consent Order for Wastewater Treatment Plant 2008 –Engineering Report approved (Phase 1 and Phase 2) 2010 –Phase 1 Construction

CITY OF MUSTANG

December 16, 2014

Wastewater Treatment Plant Evaluation

WDB ENGINEERING

PRESENTATION FOR:

Page 2: PRESENTATION FOR: CITY OF MUSTANG …...2007 –Consent Order for Wastewater Treatment Plant 2008 –Engineering Report approved (Phase 1 and Phase 2) 2010 –Phase 1 Construction

History

Existing Conditions

Proposed Solutions

Future Considerations

Project Schedule

Construction Costs

Q & A

PRESENTATION OVERVIEW

WDB ENGINEERING

Page 3: PRESENTATION FOR: CITY OF MUSTANG …...2007 –Consent Order for Wastewater Treatment Plant 2008 –Engineering Report approved (Phase 1 and Phase 2) 2010 –Phase 1 Construction

2007 – Consent Order for Wastewater

Treatment Plant

2008 – Engineering Report approved

(Phase 1 and Phase 2)

2010 – Phase 1 Construction Complete

2012 – Addendum to Consent Order

HISTORY

WDB ENGINEERING

Page 4: PRESENTATION FOR: CITY OF MUSTANG …...2007 –Consent Order for Wastewater Treatment Plant 2008 –Engineering Report approved (Phase 1 and Phase 2) 2010 –Phase 1 Construction

Aug. 2014 – Mustang secured Cowan

Group Engineering (CGE) and WDB

Engineering

Aug. 2014 – Comprehensive site visit

conducted at the WWTP

Sept. 2014 – Meeting with DEQ

Nov. 2014 – Technical Memorandum

completed & submitted to DEQ

HISTORY

WDB ENGINEERING

Page 5: PRESENTATION FOR: CITY OF MUSTANG …...2007 –Consent Order for Wastewater Treatment Plant 2008 –Engineering Report approved (Phase 1 and Phase 2) 2010 –Phase 1 Construction

Design Flow Rate

Headworks

Grit Removal System & Associated Piping

Digester Basin

Waste Activated Sludge Holding Basin

Storm Holding Basins

SCADA/SBR Data Communications

EXISTING CONDITIONS

WDB ENGINEERING

Page 6: PRESENTATION FOR: CITY OF MUSTANG …...2007 –Consent Order for Wastewater Treatment Plant 2008 –Engineering Report approved (Phase 1 and Phase 2) 2010 –Phase 1 Construction

WWTP SITE MAP

Page 7: PRESENTATION FOR: CITY OF MUSTANG …...2007 –Consent Order for Wastewater Treatment Plant 2008 –Engineering Report approved (Phase 1 and Phase 2) 2010 –Phase 1 Construction

1. Headworks : Piping Modification in Pipe Gallery

PROPOSED SOLUTIONS

WDB ENGINEERING

Page 8: PRESENTATION FOR: CITY OF MUSTANG …...2007 –Consent Order for Wastewater Treatment Plant 2008 –Engineering Report approved (Phase 1 and Phase 2) 2010 –Phase 1 Construction

2. Site Piping Modifications to Bypass Digester and

Repair Digester Basin Air Piping

PROPOSED SOLUTIONS

WDB ENGINEERING

Page 9: PRESENTATION FOR: CITY OF MUSTANG …...2007 –Consent Order for Wastewater Treatment Plant 2008 –Engineering Report approved (Phase 1 and Phase 2) 2010 –Phase 1 Construction

3. Communications from Aqua-Aerobic to SCADA

PROPOSED SOLUTIONS

WDB ENGINEERING

Page 10: PRESENTATION FOR: CITY OF MUSTANG …...2007 –Consent Order for Wastewater Treatment Plant 2008 –Engineering Report approved (Phase 1 and Phase 2) 2010 –Phase 1 Construction

4. Modification of Existing SBR Mixers to Include a

Reversal Mode

PROPOSED SOLUTIONS

WDB ENGINEERING

Page 11: PRESENTATION FOR: CITY OF MUSTANG …...2007 –Consent Order for Wastewater Treatment Plant 2008 –Engineering Report approved (Phase 1 and Phase 2) 2010 –Phase 1 Construction

5. Headworks : New Bar Screen,

Headworks Pumps and Flow Metering

PROPOSED SOLUTIONS

WDB ENGINEERING

Page 12: PRESENTATION FOR: CITY OF MUSTANG …...2007 –Consent Order for Wastewater Treatment Plant 2008 –Engineering Report approved (Phase 1 and Phase 2) 2010 –Phase 1 Construction

6. Clean Existing SBR Basins & Mixers

PROPOSED SOLUTIONS

WDB ENGINEERING

Page 13: PRESENTATION FOR: CITY OF MUSTANG …...2007 –Consent Order for Wastewater Treatment Plant 2008 –Engineering Report approved (Phase 1 and Phase 2) 2010 –Phase 1 Construction

7. Install Floating Aerators in Storm Holding Basins

PROPOSED SOLUTIONS

WDB ENGINEERING

Page 14: PRESENTATION FOR: CITY OF MUSTANG …...2007 –Consent Order for Wastewater Treatment Plant 2008 –Engineering Report approved (Phase 1 and Phase 2) 2010 –Phase 1 Construction

8. Add Aeration to Waste Activated Sludge Holding

Basin

PROPOSED SOLUTIONS

WDB ENGINEERING

Page 15: PRESENTATION FOR: CITY OF MUSTANG …...2007 –Consent Order for Wastewater Treatment Plant 2008 –Engineering Report approved (Phase 1 and Phase 2) 2010 –Phase 1 Construction

9. Add/Repair Flow Meters to Measure Flow to/from

Storm Holding Basin

PROPOSED SOLUTIONS

WDB ENGINEERING

EXAMPLE MAGNETIC METER

Page 16: PRESENTATION FOR: CITY OF MUSTANG …...2007 –Consent Order for Wastewater Treatment Plant 2008 –Engineering Report approved (Phase 1 and Phase 2) 2010 –Phase 1 Construction

10. Evaluate Grit Removal System & Piping

PROPOSED SOLUTIONS

WDB ENGINEERING

Page 17: PRESENTATION FOR: CITY OF MUSTANG …...2007 –Consent Order for Wastewater Treatment Plant 2008 –Engineering Report approved (Phase 1 and Phase 2) 2010 –Phase 1 Construction

Phase IIA - Immediate

1. Headworks Piping Modifications

2. Site Piping Modifications

3. SCADA/SBR Communications

4. SBR Mixer Modification

PROJECT SCHEDULE

WDB ENGINEERING

Page 18: PRESENTATION FOR: CITY OF MUSTANG …...2007 –Consent Order for Wastewater Treatment Plant 2008 –Engineering Report approved (Phase 1 and Phase 2) 2010 –Phase 1 Construction

Phase IIB – Completion Date 11/1/2015

5. Headworks Bar Screen, New Pumps

and Flow Metering

6. Clean SBR Basins

7. Install Floating Aerators in Storm

Holding Basins

8. Add Aeration to WAS Holding Basin

9. Add Flow Meter to/from Storm Holding

Basin

PROJECT SCHEDULE

WDB ENGINEERING

Page 19: PRESENTATION FOR: CITY OF MUSTANG …...2007 –Consent Order for Wastewater Treatment Plant 2008 –Engineering Report approved (Phase 1 and Phase 2) 2010 –Phase 1 Construction

Phase IIC – Completion Date 11/1/2015

10. Evaluate Grit Removal System

PROJECT SCHEDULE

WDB ENGINEERING

Page 20: PRESENTATION FOR: CITY OF MUSTANG …...2007 –Consent Order for Wastewater Treatment Plant 2008 –Engineering Report approved (Phase 1 and Phase 2) 2010 –Phase 1 Construction

Phase IID – WWTP Expansion

Increase Capacity

Improve/Additional Treatment to Meet

New 208 Plan for Discharge to Canadian

River

Completion Date for Engineering Report –

7/1/2016

Water Reuse

FUTURE CONSIDERATIONS

WDB ENGINEERING

Page 21: PRESENTATION FOR: CITY OF MUSTANG …...2007 –Consent Order for Wastewater Treatment Plant 2008 –Engineering Report approved (Phase 1 and Phase 2) 2010 –Phase 1 Construction

Conceptual Construction Costs

Phase IIA - $133,500

Phase IIB - $840,000

Phase IIC - TBD

Phase IID - TBD

CONSTRUCTION COSTS

WDB ENGINEERING

Page 22: PRESENTATION FOR: CITY OF MUSTANG …...2007 –Consent Order for Wastewater Treatment Plant 2008 –Engineering Report approved (Phase 1 and Phase 2) 2010 –Phase 1 Construction

QUESTION

&

ANSWER

WDB ENGINEERING