presentation for: city of mustang …...2007 –consent order for wastewater treatment plant 2008...
TRANSCRIPT
CITY OF MUSTANG
December 16, 2014
Wastewater Treatment Plant Evaluation
WDB ENGINEERING
PRESENTATION FOR:
History
Existing Conditions
Proposed Solutions
Future Considerations
Project Schedule
Construction Costs
Q & A
PRESENTATION OVERVIEW
WDB ENGINEERING
2007 – Consent Order for Wastewater
Treatment Plant
2008 – Engineering Report approved
(Phase 1 and Phase 2)
2010 – Phase 1 Construction Complete
2012 – Addendum to Consent Order
HISTORY
WDB ENGINEERING
Aug. 2014 – Mustang secured Cowan
Group Engineering (CGE) and WDB
Engineering
Aug. 2014 – Comprehensive site visit
conducted at the WWTP
Sept. 2014 – Meeting with DEQ
Nov. 2014 – Technical Memorandum
completed & submitted to DEQ
HISTORY
WDB ENGINEERING
Design Flow Rate
Headworks
Grit Removal System & Associated Piping
Digester Basin
Waste Activated Sludge Holding Basin
Storm Holding Basins
SCADA/SBR Data Communications
EXISTING CONDITIONS
WDB ENGINEERING
WWTP SITE MAP
1. Headworks : Piping Modification in Pipe Gallery
PROPOSED SOLUTIONS
WDB ENGINEERING
2. Site Piping Modifications to Bypass Digester and
Repair Digester Basin Air Piping
PROPOSED SOLUTIONS
WDB ENGINEERING
3. Communications from Aqua-Aerobic to SCADA
PROPOSED SOLUTIONS
WDB ENGINEERING
4. Modification of Existing SBR Mixers to Include a
Reversal Mode
PROPOSED SOLUTIONS
WDB ENGINEERING
5. Headworks : New Bar Screen,
Headworks Pumps and Flow Metering
PROPOSED SOLUTIONS
WDB ENGINEERING
6. Clean Existing SBR Basins & Mixers
PROPOSED SOLUTIONS
WDB ENGINEERING
7. Install Floating Aerators in Storm Holding Basins
PROPOSED SOLUTIONS
WDB ENGINEERING
8. Add Aeration to Waste Activated Sludge Holding
Basin
PROPOSED SOLUTIONS
WDB ENGINEERING
9. Add/Repair Flow Meters to Measure Flow to/from
Storm Holding Basin
PROPOSED SOLUTIONS
WDB ENGINEERING
EXAMPLE MAGNETIC METER
10. Evaluate Grit Removal System & Piping
PROPOSED SOLUTIONS
WDB ENGINEERING
Phase IIA - Immediate
1. Headworks Piping Modifications
2. Site Piping Modifications
3. SCADA/SBR Communications
4. SBR Mixer Modification
PROJECT SCHEDULE
WDB ENGINEERING
Phase IIB – Completion Date 11/1/2015
5. Headworks Bar Screen, New Pumps
and Flow Metering
6. Clean SBR Basins
7. Install Floating Aerators in Storm
Holding Basins
8. Add Aeration to WAS Holding Basin
9. Add Flow Meter to/from Storm Holding
Basin
PROJECT SCHEDULE
WDB ENGINEERING
Phase IIC – Completion Date 11/1/2015
10. Evaluate Grit Removal System
PROJECT SCHEDULE
WDB ENGINEERING
Phase IID – WWTP Expansion
Increase Capacity
Improve/Additional Treatment to Meet
New 208 Plan for Discharge to Canadian
River
Completion Date for Engineering Report –
7/1/2016
Water Reuse
FUTURE CONSIDERATIONS
WDB ENGINEERING
Conceptual Construction Costs
Phase IIA - $133,500
Phase IIB - $840,000
Phase IIC - TBD
Phase IID - TBD
CONSTRUCTION COSTS
WDB ENGINEERING
QUESTION
&
ANSWER
WDB ENGINEERING