presentation on “ improving power plant efficiency

44
1 PRESENTATION ON PRESENTATION ON “ IMPROVING POWER PLANT “ IMPROVING POWER PLANT EFFICIENCY EFFICIENCY OPERATOR PERSPECTIVE” OPERATOR PERSPECTIVE” by by General Manager ( Farakka Unit) NTPC Limited e-mail [email protected] G. J. Deshpande

Upload: others

Post on 26-Dec-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

1

PRESENTATION ON PRESENTATION ON

“ IMPROVING POWER PLANT “ IMPROVING POWER PLANT EFFICIENCY EFFICIENCY

OPERATOR PERSPECTIVE”OPERATOR PERSPECTIVE”

byby

General Manager ( Farakka Unit)NTPC Limited

e-mail [email protected]

G. J. Deshpande

Page 2: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

2

PRESENTATION OUTLINE1. Overview Of NTPC

2. Objectives & Approach

• Indian Scenario & Potentials Of Heat Rate

Improvement In India

• Power Plant Heat Rate: Salient Features & Concepts

• Methodology For Heat Rate Improvement

Ø Strategies Adopted

1. Summary Of Observations

2. Techniques & Systems Demonstrated To

Recover Losses

3. What Is To Be Done For Indian Power Sector?

Page 3: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

3

NTPC NTPC -- VISIONVISION

To be a world class integrated power major, To be a world class integrated power major, powering India’s growth, with increasing powering India’s growth, with increasing

global presenceglobal presence

NTPC WAS FORMED ON 7TH

NOVEMBER 1975

Page 4: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

4

NTPC IN INDIAN POWER SECTORNTPC IN INDIAN POWER SECTOR

NTPC contributes more than oneNTPC contributes more than one--fourth of Indiafourth of India’’s total power s total power generation with less than onegeneration with less than one--fifth capacity.fifth capacity.

TOTAL CAPACITYAS ON 31.03.2006TOTAL CAPACITYAS ON 31.03.2006

ALL INDIA

NTPC

NTPC24,249

MW19.50 %

ofAll

India 124,311

MW

19.50%

GENERATION2005-2006

GENERATION2005-2006

ALL INDIA

NTPC

NTPC170.88

BUs27.686%

ofAll

India 617.203

BUs

27.686%

Page 5: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

5

NTPC OWNED

OWNED BY JVCs

2640425GRAND TOTAL 7401GAS/ LIQ. FUEL3143COAL

25,35021TOTAL

3,95507GAS/ LIQ. FUEL 21,39514COAL

Commissioned Capacity (MW)

No. of Projects

Projects

OVERVIEW OF NTPC INSTALLED CAPACITY

Page 6: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

6

Capacity expansion programmeCapacity expansion programme

2003100

1133316795

2024924249 26404

29409

51000

75000

01000020000300004000050000600007000080000

1982

1987

1992

1997

2002

2005

2006

2007

2012

2017

Commissioned Planned

MW

2007- End of X Plan , 2012 - End of XI Plan , 2017- End of XII Plan

++

PRESENT INSTALLED CAPACITY

Page 7: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

7

“Plant Performance Improvement”

Operator perspective

““Plant Performance Improvement”Plant Performance Improvement”

Operator perspectiveOperator perspective

Page 8: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

8

What it Means to the OperatorWhat it Means to the Operator

n Maintaining the operating parameters at or

better to the design value

n Take measures to Improve upon the

performance of various systems

Ø strategy to reduce accounted loss and

Ø strategy to reduce Un-accounted loss

Page 9: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

9

BenefitsBenefitsn Ease of Operation

n Low breakdown

n Low cost of Maintenance

n Life cycle Improvement

n Lower Heat rate

Lower cost of Generation

Page 10: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

10

Indian Thermal Power SectorSome of the Reasons for Low Generation Efficiency

• Emphasis on plant load factor instead of ‘efficient generation’

• Degradation of equipment resulting in loss of capacity

• Delayed overhauls (Seasonal Constraints)

• Financial constraints in adequate maintenance

• Lack of awareness on efficiency related issues:

§ Inadequate MIS systems (analysis of financial impact of various

operating parameters)

§ Inadequate monitoring system for parameters

§ Non availability of performance measuring instruments at Stations

§ No dedicated group to target efficiency improvement

§ Maintenance management & Operation management systems

Page 11: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

11

An average increase of 1 % in the Efficiency would result in:§ Coal savings of approx. 11 million tons per annum

§ Rupees savings worth Rs.13,000 Million

§ 3% CO2 reduction per annum (approx.13.5 million tons per annum)

§ Higher productivity from the same resources is equivalent to capacity addition

§ Lower generation cost per kWh

Why Efficiency is Important ?Why Efficiency is Important ?

Impact of Efficiency Improvement – Indian Scenario

Page 12: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

12

INDIAN SCENARIO: DESIGN HEAT RATE TRENDS*

1950 (TDBFP)

1950 (MDBFP)

1950 (TDBFP)

1985

2060

2170 -2060

2370

2470

Turbine HR

(kcal/kwh)

2294210 / 250150 ata 535/535 deg C1990 +

2294500170 ata 535/535 deg C1984 +

2335210 (Siemens)150 ata 535/535 deg C1983 +

2423210/Russian)130 ata 535/535 deg C1977-82

2552-2423110 - 120130 ata 535/535 deg C1961-75

60 -10070 Kg/cm2, 496 deg C to 90 ata 538 deg C

1961-75

2294250 / 500170 ata 538/538 deg C

30 - 57.560 Kg/cm2, 482 deg C1951-60

Calculated Unit HR

(kcal/kwh)

UNIT SIZE

(MW)

STEAM PRESSUREPERIOD

* Above are best design values/ design heat rates of individual unit varies based on reference ambient, coal quality, design and supply dates

Page 13: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

13

What is Heat Rate?

• Heat rate is the amount of chemical energy that must be

supplied to produce one unit of electrical energy.

• Heat rate is a measure of how efficiently it converts the

chemical energy contained in fuel into electrical energy.

• Since, coal chemical energy is measured in kilocalories

(kCal) and electrical energy is measured in ‘unit’ i.e.

kilowatt-hours (kWh), the units of heat rate are

kilocalories per kilowatt-hours (kCal/kWh).

• Empirically, 1% improvement in efficiency is equal to 3%

improvement in heat rate.

Page 14: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

14

(5 to 15 kCal/kWh)

(25 to 100 kCal/kWh)

Minimizing Unaccountable( e.g. valve leakage, high accuracy measurements, etc.)

CondenserMills &

CombustionOptimization

‘What can not be measured can not be saved’Method: Periodic Measurement of Deterioration ( simplified tests )

Reducing Auxiliary Power Consumption( e.g. BFP, CW system & ESP power consumption)

Page 15: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

15

Hypothetical Heat Rate Curves

1950

2050

2150

2250

2350

2450

20 40 60 80 100

Load (%)

Hea

t R

ate

(kca

l/kw

h)

Heat Rate Deviations in Power Plants

Losses-A

Losses-BDesign

Expected

Actual

Losses-A= Expected – Design; Losses B= Actual - Expected

Page 16: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

16

ActualActual--Expected: Segregation of LossesExpected: Segregation of Losses

ACCOUNTABLE UNACCOUNTABLE

• Deviations in critical parameters from design or expected

• Deterioration in equipment performance

• Fuel characteristics• Auxiliaries power consumption• Operation practice

• Passing of valves

• Equipments where

performance assessment

difficult e.g. LP turbine

• Radiation losses

• Uncertainties of Instruments

Accountable are categorized into Controllable (Recoverable) & Non-controllable

Page 17: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

17

EFFECT OF CRITICAL PARAMETERS ON HEAT RATEEFFECT OF CRITICAL PARAMETERS ON HEAT RATE

108.0010 degCFW Temp

6.708.005 mm HgCond Back Pr

4.3612.0010 MWLOAD

5.556.0010 degCRH Steam

6.206.0010 degCMS Temp

7.3012.0010 kgMS Pr

4.7612.0020 T/hrRH Spray

Impact (kCal/kWh)Variation

0.810.3020 T/hrSH Spray

500 MW Unit200 MW Unit

Page 18: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

18

2 % change in HP or IP Turbine Efficiency in a 210 MW unit leads to change in HR by about

8 kcal/kWh

Effect of Turbine Efficiency on Heat Rate

HP/IP Turbine Efficiency

Page 19: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

Efforts for Improvement in Turbine EfficiencyEfforts for Improvement in Turbine Efficiency

• Alumina Blasting of Turbine Components

• Refinning of Inter-stage sealing fins and balance drum / gland sealing fins.

Page 20: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

Alumina Blasting of Turbine ComponentsAlumina Blasting of Turbine Components

• Alumina Blasting of HP turbine Rotor and Casing being done to

remove the Silica deposit from the bladding surface. The deposits

on the blades & turbine steam path increases flow path surface

roughness and decrease the flow area of the cascade. This result s

in reduced efficiency of turbine cylinder.

• Cleaning of deposits from Turbine components results in increase

in turbine efficiency.

Page 21: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

RefinningRefinning of Interof Inter--stage sealing fins stage sealing fins

• Inter-stage sealing fins are provided at each stages to seal the gap between moving & stationary parts i.e. Rotor blades & casing / guide blades & rotor.

• 5 fins are provided at each stage ( 18 x 5= 90 fins) to create l abyrinth effect and hence sealing.

• Radial clearances at these fins play vital role in turbine efficiency.

• Clearances of these sealing fins tends to increase over a period of time due to wear / tear / warping of fins.

• Increase in sealing fin clearances result in short circuiting of steam and increase in steam quantity and first stage pressure requirement for generating same load in turn.

• Increased first stage pressure results in increase in Heat rate and deterioration of turbine efficiency.

Page 22: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

HP Turbine Casing Fins ArrangementHP Turbine Casing Fins Arrangement

Page 23: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

HP Turbine Casing after RefinningHP Turbine Casing after Refinning

Inter-stage Fins

Page 24: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

HP Turbine Rotor after RefinningHP Turbine Rotor after Refinning

Balance Drum Fins

Gland Fins

Page 25: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

Comparison of Performance Before & After Comparison of Performance Before & After RefinningRefinning

20272094Heat Rate4

88.35 %86.67 %91.7 %IP Cylinder efficiency

3

156.4 Ksc at 502 MW

164 Ksc at 498 MW

162 Ksc(max)

1st Stage Pressure

2

88.65 %83.49%89 %HP Cylinder efficiency

1

After RefinningBeforeDesignParametersS.No

Page 26: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

26

Major Other losses in turbine cycle

§ Loss due to high back pressure

§ Loss due to RH attemperation

§ Loss due to low HRH temperature

§ Loss due to passing of high energy drain valves

Page 27: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

27

Condenser performance deterioration leads to about 20 to 30 mm Hg deviation in vacuum. Main reason for deterioration is due to

Ø tube foulingØ air ingressØ high heat loadØ CW FlowØ CW inlet temp

Condenser Performance

Page 28: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

28

0

10

20

30

40

50

60

70

0 2 4 6 8 10 12 14 16 18 20

Period Since Overhaul (Weeks)

Dec

reas

e in

Hea

t Tr

ansf

er R

ate

(%)

With Tube Cleaning Without Tube Cleaning

Fouling V/s Cleaning Effects On Heat Transfer In Condenser

Example

Page 29: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

29

• Decision for condenser cleaning

1. Cleaning of tubes at Part load / during opportunity shut down

2. Fixing limit for deterioration in vacuum 10-15 mm

• Cleaning at part load / Opportunity S/D

1. Butterfly Valve - Effective isolation 2. Bullet/HP jet cleaning -Availability of cleaning

Action to reduce losses

Condenser Performance

Page 30: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

30

• Monitoring/CheckingØ air flow measurementØ air-steam mixture depressionØ dissolved O2

• Online Sealing of air ingress pointØ use of sealing compounds

• Identification of Air ingress point

ØSteam pressurization during OverhaulingsØOthers:Øoffline flood test during O/H Ø online Helium leak detection

Condenser PerformanceCondenser Air - Ingress

Page 31: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

31

• High heat load due to

Ø poor Turbine performance

Ø passing of high energy drains

Ø poor condenser upkeep

Ø low inlet steam parameters

• Low CW flow

Ø poor pump performance

Ø low intake level

Ø Tube choking

• CW inlet temperature

Ø Higher CW inlet temperature due to poor CT performance

Condenser PerformanceOther Factors

Page 32: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

32

• Use of absolute pressure transmitter for Condenser back pressure measurement.

• Grid measurement for back pressure & CW outlet temperature

• Air flow measurement for vacuum pump/ejector

• Temperature measurement for air -steam mixture

• CW flow validation

• Calibration of instruments

Performance Assessment

Condenser Performance

Page 33: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

33

• Dry flue gas loss (controllable)

• Loss due to moisture and H2 in fuel

• Combustible loss with BA and FA

(controllable)

• Heat loss due to bad insulations & other

unaccounted losses

Major Boiler losses

Page 34: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

34

• High excess air and high exit FG temp attribute to increased DFG

• FG O2 at APH inlet is a feed back to adjust excess air, which is

sometimes misleading.

• Excess air optimization thro’ monitoring of CO in exit FG will be

more effective

• Reduction in FG quantity at APH inlet will reduce FG exit temp.

• Reduction of tempering air will reduce exit FG temp

• Arresting air ingress in flue path

• Ensuring steady coal quality thro’ blending

• Maintaining cleaned heat transfer surfaces thro’ timely soot blowing

Measures to reduce dry flue gas loss

Page 35: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

35

Control combustible loss with ash

• Firing of coal from multiple sources attribute to wide

variation in combustible loss with ash

• Ensure proper PF fineness

• Retrofitting of online LOI monitoring instrument

• Retrofitting of remote operable classifiers

• Ensure proper excess air and PA to SA ratio

Page 36: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

36

Steps involved in Boiler Performance Optimization

• Balancing of coal and air flow in coal pipes of each mill using ASME dirty pitot kit & rotary probe

• Air heater performance testing

• Combustion regime evaluation to ascertain level of combustion completion

• Evolving an optimum boiler operating regime by testing boiler under different conditions.

Feedback from these tests is also used to cross-check the ‘on line’ station instruments and to plan the work to be undertaken during next overhaul.

Performance Improvement: (Boiler & Auxiliaries)

Page 37: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

37

(Typical example)

Loss (Energy loss & vacuum) due to High Energy drain valve passi ng is about 7-9 kcal / kWh(Taking about nominal passing of 4 valves out of 20 valves)

High Energy Drains

• Installation of thermocouples on down stream of High Energy drains along with display facility at control room.

• Progressive replacement of High energy drain valves by superior quality valves.

Remedial Measures

Passing of High Energy drain valve affects in 3 ways

1. Loss of High Energy steam

2. Deterioration in Condenser Vacuum

3. Damage to the valve

Page 38: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

38

Strategy: Application of new technologies to identify& measure losses to prioritize repair

Example: Cycle Isolation problems: Valve Leakage (Passing), Radiation Losses

• Valves have considerable potential to reduce unaccountable losses • Applicable to:ØReheater & Super heater spray valvesØHigh energy drainsØHP heater alternate drainsØBoiler feed-pump & condensate pump re-circulation lines

Reduction of Unaccountable Losses

Use of multiple technologies like acoustics & IR - Thermography (IRT) to identify ‘passing’ and estimate extent of passing to

prioritize maintenance

Page 39: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

39

Summary of Observations

• Combustion optimization: Reduction in Air leakages

• Air-fuel ratio optimization: periodic adjustments in mills & installing

appropriate orifices periodically.

• Air-preheater performance: deterioration in condition of baskets & seals

with time

• Furnace parameter profile: Optimization of operational parameters &

calibration/validation of on-line instruments for day to day operation

• Performance Optimization of ESPs: Flue gas conditioning techniques like

water fogging & sodium conditioning have demonstrated savings o f auxiliary

power consumption.

Page 40: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

40

Measures Adopted

1. Formalization of ‘Efficiency Management

System (EMS)’

2. Three step process:

• No cost or low cost options for initiating a

Program

• Medium cost options

• Long term actions for sustainability

Page 41: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

41

Step 1: No cost or low cost items

1. Organizing efficiency awareness programs.

2. Involvement of higher management is essential

3. Establishing a ‘Efficiency group’ by relocating two or three sui table

engineers at each Station.

4. Focus on critical parameter monitoring, calculation of deviations,

segregation into ‘controllable parameters’, action plan

identification.

5. Daily MIS to Station / utility management on financial impacts

6. Daily, weekly, monthly trending of parameters & financial impact s

7. Identification of high potential areas ( to start with it could be

condenser, valves, mills & combustion optimization)

Page 42: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

42

Step:2- Strengthening Efficiency Group

1. Strengthening of analysis & testing related functions:

i. Periodic calibration of on-line instrumentsii. Evaluation of performance based on on-line

measurements2. Benchmarking of performance after overhaul,

periodic evaluation to assess degradation for actions.

3. Establishment of multi-disciplinary ‘Performance Optimization Groups (POGs).

Technologies are fascinating but they are only tools

Page 43: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

43

Step-3: Steps for sustainability

1. Acquisition of medium cost equipment at station level & high cost equipment at utility level

2. Periodic testing of equipment / systems3. Evaluation of deviations to assess degradation ( loss

areas)4. Validation of on-line instruments5. Identification of items for maintenance / replacement

based on degradation & financial implications6. Testing after repair / overhauling, to evaluate

effective ness of actions

Page 44: PRESENTATION ON “ IMPROVING POWER PLANT EFFICIENCY

44

Thank You