presentation on value at risk
TRANSCRIPT
-
8/3/2019 Presentation on Value at Risk
1/22
PRESENTATION ON VALUE
AT RISK
-
8/3/2019 Presentation on Value at Risk
2/22
MEANING OF VAR
Var is a single number, whish encapsulates wholeinformation about the risk in a portfolio.
It measures potential loss from an unlikely adverse
event in a normal market environment. It involves using historical data on market prices
and rates, the current portfolio positions, andmodels for pricing those positions.
These inputs are then combined in different ways,
depending on the method, to derive an estimate of aparticular percentile of the loss distribution.
-
8/3/2019 Presentation on Value at Risk
3/22
VAR AND DURATION
Value-at-Risk is directly linked to the concept ofduration in situations where a portfolio is exposed toone risk factor only, the interest rate. Durationmeasures the exposure to the risk factor. Value-at-Risk incorporates duration with the probability of anadverse move in the interest rate.
-
8/3/2019 Presentation on Value at Risk
4/22
EXAMPLE
The VAR of a $100 million portfolio invested in a 5-yearnote. At the 95% level over one month, the portfolio VARwas found to be $1.7 million. Can we relate this numberto the portfolio duration? The typical duration for a 5-yearnote is 4.5 years. Assume now that the current yield y is
5%. From historical data, we find that the worst increasein yields over a month at the 95% is 0.40%. The worstloss, or VAR, is then given byWorst Dollar Loss = Duration x 1/(1+y) x Portfolio Value xWorstYield IncreaseVAR = 4.5 Years x (1/1.05) x $100m x 0.4%which is also $1.7 million! Thus the value at risk is directly
related to the conceptof duration. The VAR approach,however, is more general, because it allows investors toinclude many assets such as foreign currencies,commodities and equities, which are exposed to othersources of risk than interest rate movements.
-
8/3/2019 Presentation on Value at Risk
5/22
The uses of VaR?
How much risk is a particular investment
style or asset class adding to yourportfolio?
What is the risk of both the fund's assetsand liabilities?
How and why has a portfolio's risk changedover the last measurement period?
-
8/3/2019 Presentation on Value at Risk
6/22
ADVANTAGE OF VAR
Quantifies potential losses in simpleterms (a 5% chance of a loss
exceeding $1 million) Has met with approval from various
regulatory bodies concerned withthe risks faced by financial
institutions Is versatile
-
8/3/2019 Presentation on Value at Risk
7/22
DISADVANTAGE OF VAR
Estimation difficulties, and sensitivity toestimation methods used
Potential to create a false sense of security
Tends to underestimate worst-caseoutcomes
The VaR of a specific position doesntalways translate well into the VaR of the
overall portfolio
It fails to incorporate positive outcomes,thus painting an incomplete picture
-
8/3/2019 Presentation on Value at Risk
8/22
HISTORICAL SIMULATION
Historical simulations represent thesimplest way of estimating the Value atRisk for many portfolios.
In this approach, the VaR for a portfolio isestimated by creating a hypothetical timeseries of returns on that portfolio.
-
8/3/2019 Presentation on Value at Risk
9/22
Assessment
Past is not prologue
Trends in the data
New assets or market risks
-
8/3/2019 Presentation on Value at Risk
10/22
The Model-Building Approach
The main alternative to historical simulationis to make assumptions about theprobability distributions of return on the
market variables and calculate theprobability distribution of the change in thevalue of the portfolio analytically
This is known as the model building
approach or the variance-covarianceapproach
-
8/3/2019 Presentation on Value at Risk
11/22
Position
Exposures
Volatilities
s * 2.33= 99%
Correlations VARVAR
-
8/3/2019 Presentation on Value at Risk
12/22
Daily Volatilities
252
year
day
W
!W
In option pricing we measure volatilityper year
In VaR calculations we measure volatilityper day
-
8/3/2019 Presentation on Value at Risk
13/22
Finding 1 Year VAR
1 Year VAR
= 1 Day VAR*
SQRT(250)
1 WEEK SQRT(5)
1 MONTH SQRT(21)
3 MONTH SQRT(62.5)
1 YEAR SQRT(250)
Time Adjustment
-
8/3/2019 Presentation on Value at Risk
14/22
Variance Covariance
VAR Result
Finding x%Confidence
VAR
99% VAR=VARResult
* 2.33
-
8/3/2019 Presentation on Value at Risk
15/22
Microsoft Example
We have a position worth $10million in Microsoft shares
The volatility of Microsoft is 2% perday (about 32% per year)
We use N=10 and X=99
-
8/3/2019 Presentation on Value at Risk
16/22
Microsoft Example
The standard deviation of thechange in the portfolio in 1 day is
$200,000 The standard deviation of the
change in 10 days is
200 000 10 456, $632,!
-
8/3/2019 Presentation on Value at Risk
17/22
Microsoft Example
We assume that the expected changein the value of the portfolio is zero
We assume that the change in thevalue of the portfolio is normallydistributed
Since N(2.33)=0.01, the VaR is
2 33 632 456 473 621. , $1, ,v !
-
8/3/2019 Presentation on Value at Risk
18/22
AT&T Example
Consider a position of $5 million inAT&T
The daily volatility of AT&T is 1%(approx 16% per year)
The S.D per 10 days is
The VaR is50 000 10 144, $158,!
158 114 2 33 405, . $368,v !
-
8/3/2019 Presentation on Value at Risk
19/22
Portfolio
Now consider a portfolio consistingof both Microsoft and AT&T
Suppose that the correlationbetween the returns is 0.3
-
8/3/2019 Presentation on Value at Risk
20/22
S.D. of Portfolio
A standard result in statistics statesthat
In this case WX
= 200,000 and WY=
50,000 and V = 0.3. The standard
deviation of the change in theportfolio value in one day is therefore220,227
YXYXYXWVWWW!W
222
-
8/3/2019 Presentation on Value at Risk
21/22
VaR for Portfolio
The 10-day 99% VaR for the portfoliois
The benefits of diversification are
(1,473,621+368,405)1,622,657=$219,369
-
8/3/2019 Presentation on Value at Risk
22/22