Presentation to Standing Committee on Appropriations 21 April 2010. 1. Progress through the MIG Programme. Registration of EPWP Projects :. A total of 552 EPWP projects have been registered through MIG during the period April 2009 to March 2010 - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Presentation  to  Standing Committee on  Appropriations 21 April 2010

Presentation

to

Standing Committee on

Appropriations

21 April 2010

Page 2: Presentation  to  Standing Committee on  Appropriations 21 April 2010

Province No of

Projects MIG Funds

EC 276 4,297,108,042

FS 42 528,082,066

GT 3 26,612,500

KZN 0 0

LP 98 970,983,812

MP 94 2,574,729,937

NC 29 335,754,123

NW 0 0

WC 10 28,343,270

TOTAL 552 8,761,613,749

1. A total of 552 EPWP projects have been registered through MIG during the period April 2009 to March 2010

2. The value of projects that were registered under MIG amounts to R8 762 billion.

3. The type of projects registered include:

• Roads, sidewalks, storm-water

• Water and sanitation

• Sports Facilities

• Taxi Ranks, street trading

• Multi-purpose Halls

• Cemeteries etc

4. Municipalities in GT, KZN and NW have been under-reporting on EPWP projects.

1. Progress through the MIG ProgrammeRegistration of EPWP Projects :

Page 3: Presentation  to  Standing Committee on  Appropriations 21 April 2010

One of the Pre-2011 priorities of the Local Government Turn Around Strategy (LGTAS) is to upscale the Community Work Programme (CWP).

The CWP is now located in the Department of Co-operative Governance and Traditional Affairs (CoGTA) with effect from 1 April 2010.

The Minister accepted the Programme through a letter to the Minister in the Presidency: National Planning signed on 02 December 2009.

2. The Community Work Programme

Page 4: Presentation  to  Standing Committee on  Appropriations 21 April 2010

3. What is the Community Work Programme?

A. The CWP is part of EPWP, and complements the other components.

B. The Community Work Programme provides access to a minimum level of regular work - ie 2 days a week = 100 days a year.

C. It is an area-based programme, intended to be ongoing; this allows it to target the poorest areas: where market-based jobs are unlikely to come any time soon.

D. Site management is handled by implementing agencies appointed by the programme.

E. The CWP uses community participation to identify ‘useful work’ and priorities.

F. ‘Work’ is decided in Ward Committees or local development fora; it is multi-sectoral and contributes to public/community goods and services;

G. Start-up scale: 1,000 participants per siteH. CWP sites have a 65% labour intensity.

Page 5: Presentation  to  Standing Committee on  Appropriations 21 April 2010

CWP Allocation Breakdown

Components 2010/2011 2011/2012 2012/2013

Total CWP allocation (R million) 490 325 663 550 871 073

Programme management49 033 66 355 87 107

Wage costs 286 840 388 177 509 578

Non-wage costs at site level (Tools, materials, training, site management)

154 452 209 018 274 388

Indicator Annual performance

Past Current Projections

2006/07 2007/08 2008/09 2009/10 2010/11 2011/12 2012/13

Total number of work opportunities created

- - - - 57 368 77 635 101 916

4. Financial Implications & Performance Indicators