Stage 1 Stage 2 Stage 3 Stage 4 Use of Microsoft Project in Construction 26 th March 2019 Paul Dolan Athlone Institute of Technology [email protected] (086)3801140

Upload: others

Post on 11-Jun-2020

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Presentation - Use of Microsoft Project in …...Stage 1 Stage 2 Stage 3 Stage 4 Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology

Stage 1

Stage 2

Stage 3

Stage 4

Use of Microsoft Project in Construction

26th March 2019

Paul DolanAthlone Institute of Technology

[email protected](086)3801140

Page 2: Presentation - Use of Microsoft Project in …...Stage 1 Stage 2 Stage 3 Stage 4 Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology

Stage 1

• Sequence

Stage 2

• Establish

Stage 3

• Estimate

Stage 4

• Programme

4 Stage“Thought Process3”

Page 3: Presentation - Use of Microsoft Project in …...Stage 1 Stage 2 Stage 3 Stage 4 Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology

Stage 1

• Sequence

Stage 2

• Establish

Stage 3

• Estimate

Stage 4

• Programme

Stage 1Sequence the Operations

1. Look at significant elements or stages of construction.

2. Based on the project documentation (BIM Model, Drawings, Bill of Quantities, Specifications) identify the main activities and think about a rough schedule.

Page 4: Presentation - Use of Microsoft Project in …...Stage 1 Stage 2 Stage 3 Stage 4 Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology

Stage 1

• Sequence

Stage 2

• Establish

Stage 3

• Estimate

Stage 4

• Programme

Stage 1Sequence the Operations

Page 5: Presentation - Use of Microsoft Project in …...Stage 1 Stage 2 Stage 3 Stage 4 Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology

Stage 1

• Sequence

Stage 2

• Establish

Stage 3

• Estimate

Stage 4

• Programme

3. Prepare a phasing diagram where appropriate.

Understand the link between the sequences of operations to be undertaken and the practicalities on site.

4. Do not have too many activities to begin with - 20 or 30 max.

5. Do not worry about minor details at this stage.

Stage 1Sequence the Operations

Block A

Block C

Block B

Page 6: Presentation - Use of Microsoft Project in …...Stage 1 Stage 2 Stage 3 Stage 4 Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology

Establish methods of work, choice of plant, determine quantities involved, assess risk.• Temporary works• Cranage• Material handling• Hoisting and access equipment• Scaffolding• Risk and uncertainty

Stage 1

• Sequence

Stage 2

• Establish

Stage 3

• Estimate

Stage 4

• Programme

Stage 2Establish Methods of

Work

Image courtesy of www.nce.co.uk

Page 7: Presentation - Use of Microsoft Project in …...Stage 1 Stage 2 Stage 3 Stage 4 Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology

Stage 1

• Sequence

Stage 2

• Establish

Stage 3

• Estimate

Stage 4

• Programme

Stage 2Establish Methods of

Work

Page 8: Presentation - Use of Microsoft Project in …...Stage 1 Stage 2 Stage 3 Stage 4 Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology

Stage 1

• Sequence

Stage 2

• Establish

Stage 3

• Estimate

Stage 4

• Programme

Stage 3Estimate Activity

Durations

• Resource availability• Plant • Labour• Supervision

i. Top-Down Estimating Analogous Estimates

ii. Bottom-Up Estimating Parametric Estimates

iii. Three Point Estimating Program Evaluation Review Technique (PERT)

=�� + 4�� +��

6

Page 9: Presentation - Use of Microsoft Project in …...Stage 1 Stage 2 Stage 3 Stage 4 Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology

Stage 1

• Sequence

Stage 2

• Establish

Stage 3

• Estimate

Stage 4

• Programme

1. List activities

2. Enter durations

3. Link activities with logic

• Mandatory dependencies. Hard Logic

• Discretionary dependencies. Soft Logic

• External dependencies.

Finish to Start Start to Start Finish to Finish Start to Finish

Stage 4Programme

Page 10: Presentation - Use of Microsoft Project in …...Stage 1 Stage 2 Stage 3 Stage 4 Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology

Stage 1

• Sequence

Stage 2

• Establish

Stage 3

• Estimate

Stage 4

• Programme

1. List activities

2. Enter durations

3. Link activities with logic

• Mandatory dependencies. Hard Logic

• Discretionary dependencies. Soft Logic

• External dependencies.

Finish to Start Start to Start Finish to Finish Start to Finish

Stage 4Programme

Page 11: Presentation - Use of Microsoft Project in …...Stage 1 Stage 2 Stage 3 Stage 4 Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology

Stage 1

• Sequence

Stage 2

• Establish

Stage 3

• Estimate

Stage 4

• Programme

1. List activities

2. Enter durations

3. Link activities with logic

• Mandatory dependencies. Hard Logic

• Discretionary dependencies. Soft Logic

• External dependencies.

Finish to Start

Start to Start Finish to Finish Start to Finish

Stage 4Programme

Page 12: Presentation - Use of Microsoft Project in …...Stage 1 Stage 2 Stage 3 Stage 4 Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology

Stage 1

• Sequence

Stage 2

• Establish

Stage 3

• Estimate

Stage 4

• Programme

1. List activities

2. Enter durations

3. Link activities with logic

• Mandatory dependencies. Hard Logic

• Discretionary dependencies. Soft Logic

• External dependencies.

Finish to Start Start to Start

Finish to Finish Start to Finish

Stage 4Programme

Page 13: Presentation - Use of Microsoft Project in …...Stage 1 Stage 2 Stage 3 Stage 4 Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology

Stage 1

• Sequence

Stage 2

• Establish

Stage 3

• Estimate

Stage 4

• Programme

1. List activities

2. Enter durations

3. Link activities with logic

• Mandatory dependencies. Hard Logic

• Discretionary dependencies. Soft Logic

• External dependencies.

Finish to Start Start to Start Finish to Finish

Start to Finish

Stage 4Programme

Page 14: Presentation - Use of Microsoft Project in …...Stage 1 Stage 2 Stage 3 Stage 4 Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology

Stage 1

• Sequence

Stage 2

• Establish

Stage 3

• Estimate

Stage 4

• Programme

1. List activities

2. Enter durations

3. Link activities with logic

• Mandatory dependencies. Hard Logic

• Discretionary dependencies. Soft Logic

• External dependencies. • Applying Lags and Leads can

modify the relationship between activities.

Stage 4Programme

Page 15: Presentation - Use of Microsoft Project in …...Stage 1 Stage 2 Stage 3 Stage 4 Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology

Stage 1

• Sequence

Stage 2

• Establish

Stage 3

• Estimate

Stage 4

• Programme

1. List activities

2. Enter durations

3. Link activities with logic

• Mandatory dependencies. Hard Logic

• Discretionary dependencies. Soft Logic

• External dependencies. • Applying Lags and Leads can

modify the relationship between activities.

Stage 4Programme

Page 16: Presentation - Use of Microsoft Project in …...Stage 1 Stage 2 Stage 3 Stage 4 Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology

Stage 1

• Sequence

Stage 2

• Establish

Stage 3

• Estimate

Stage 4

• Programme

1. List activities

2. Enter durations

3. Link activities with logic

• Mandatory dependencies Hard Logic

• Discretionary dependencies Soft Logic

• External dependencies. • Applying Lags and Leads can

modify the relationship between activities.

4. Use summary activities as headings to structure the schedule model

Stage 4Programme

Page 17: Presentation - Use of Microsoft Project in …...Stage 1 Stage 2 Stage 3 Stage 4 Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology

Stage 1

• Sequence

Stage 2

• Establish

Stage 3

• Estimate

Stage 4

• Programme

1. List activities

2. Enter durations

3. Link activities with logic

• Mandatory dependencies Hard Logic

• Discretionary dependencies Soft Logic

• External dependencies. • Applying Lags and Leads can

modify the relationship between activities.

4. Use summary activities as headings to structure the schedule model

Don't mistake the schedule model for reality!

Stage 4Programme

Page 18: Presentation - Use of Microsoft Project in …...Stage 1 Stage 2 Stage 3 Stage 4 Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology

Stage 1

• Sequence

Stage 2

• Establish

Stage 3

• Estimate

Stage 4

• Programme

Don't mistake the schedule model for reality!

Stage 4Programme

Page 19: Presentation - Use of Microsoft Project in …...Stage 1 Stage 2 Stage 3 Stage 4 Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology

Baselined Schedule

Page 20: Presentation - Use of Microsoft Project in …...Stage 1 Stage 2 Stage 3 Stage 4 Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology

Baselined Schedule

Page 21: Presentation - Use of Microsoft Project in …...Stage 1 Stage 2 Stage 3 Stage 4 Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology

Baselined Schedule with Progress Line

Page 22: Presentation - Use of Microsoft Project in …...Stage 1 Stage 2 Stage 3 Stage 4 Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology

Filter – Late Tasks

Page 23: Presentation - Use of Microsoft Project in …...Stage 1 Stage 2 Stage 3 Stage 4 Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology

Filter - Milestones

Page 24: Presentation - Use of Microsoft Project in …...Stage 1 Stage 2 Stage 3 Stage 4 Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology
Page 25: Presentation - Use of Microsoft Project in …...Stage 1 Stage 2 Stage 3 Stage 4 Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology
Page 26: Presentation - Use of Microsoft Project in …...Stage 1 Stage 2 Stage 3 Stage 4 Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology
Page 27: Presentation - Use of Microsoft Project in …...Stage 1 Stage 2 Stage 3 Stage 4 Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology

Bibliography

i. Architects' and Builders' Price Book, SPONS's - 2018

ii. Project Management Body of Knowledge, PMI - 6ed.

iii. Construction Planning, Programming and Control, Cooke and Williams - 2008

Stage 1

Stage 2

Stage 3

Stage 4

Thank You

Page 28: Presentation - Use of Microsoft Project in …...Stage 1 Stage 2 Stage 3 Stage 4 Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology

Stage 1

• Sequence

Stage 2

• Establish

Stage 3

• Estimate

Stage 4

• Programme

Paul DolanAthlone Institute of Technology