Job Order Contracting (JOC)2011 TEAM Conference

Presented by…

Kenny Voss

JOC: Overview

Job Order Contracting 101

Why JOC

Brief Introduction JOC

JOC Contract Details

Fixed Unit Price List

Adjustment Factors

Bonding & LD Requirements

Traffic Control

Implementation of JOC

Scope of Projects

MoDOT Timeline

Questions and Answers

Job Order Contracting 101

What is Job Order Contracting?

Job Order Contracting 101

Why JOC?

• Time and Cost Savings

• Reduce Change Orders

• Build Working Relationships

• Minimize Unbalanced Bidding

Job Order Contracting 101

Definition:

“A job order contract is a long term,

indefinite delivery-indefinite quantity

contract for construction services

delivered on an on-call basis through

firm fixed price delivery orders based

on pre-established unit prices.”

Job Order Contracting 101

What is JOC?

• IDIQ contract for a specified time period

• Defined geographical regions

• Pricing based on Fixed Unit Price List

• JOC adjustment factors include overhead & profit

• “On-call" contractor at competitive rate

• High performance incentive

Job Order Contracting 101

Types of Projects

JOC is intended for minor new construction, maintenance and repairs

Bridge maintenance

Asphalt/Concrete pavement repair

Guardrail/Guardcable repair

General Drainage maintenance

Signal/Lighting repair

Mowing/Landscaping

Building maintenance

Some JOC contracts

very specific (e.g., bridge maintenance);

Others allow for broader range

(e.g., general maintenance)

JOC Contract Details

How does JOC work at MoDOT?

JOC Contract Details

Fixed Unit Price List

Based on bid history & industry feedback

Tasks includes all labor, equipment and materials

Unit prices are complete and in-place construction

Quantities defined in Job Order

Payment for non-fixed items

JOC Contract Details

Adjustment Factors

Business Costs - Profit and Overhead

Normal Work Hour Factor

Nighttime Work Factor

Weekend Factor

Accelerated Repair

JOC Contract Details

How to Bid?

Item Description Approx.

Qty

Unit Unit Price Bid Amount

618-99.16

Normal Work Adjustment Factor

150,000.00 DLR 1.150 172,500.00

618-99.16

Nighttime Work Adjustment Factor

800,000.00 DLR 1.200 960,000.00

618-99.16

Weekend Work Adjustment Factor

50,000.00 DLR 1.250 62,500.00

Bid Total 1,195,000.00

JOC Contract Details

Bonding and Liquidated Damages

Bonding Based on Anticipated Budget

LD’s Accelerated Repair

LD’s for Nighttime Lane Closures

LD’s for Start & Finish

Delay Provisions

JOC Contract Details

Traffic Control

Work Hour Restrictions

Traffic Control Plan Types

• Single Lane, Double Lane, Triple Lane and Ramp Closure

• One-Lane Two-Way Operation with Flaggers

Additional Traffic Control Items

Traffic Control by MoDOT Forces

JOC Contract Details

Construction Phase

Joint Site Visit

Develop Scope of Work

Issue Job Order

Complete Work

JOC Contract Details

Example Job Order

Item Description Fixed Unit

Price

Quantity Price

SP125C (PG70-22) Per Ton

(Over 1000 Tons)

$55.75 1107.6

Tons

$18,793.33

SP190C (70-22) Per Ton (over 1000

tons)

$53.75 770.5

Tons

$41,414.61

Tack Coat $3.40 180 Gal $612.00

Mobilization – Coldmilling &

Resurfacing (Over 1000 tons)

$3,200.00 1 Each $3,200.00

Milling Per SY (4 In. to 6 In. Thick) $2.25 3520 SY $7,920.00

Subtotal: $71,939.94

Nighttime Work Factor 1.200

Subtotal: $86,327.92

Accelerated Repair $2,500.00 1 Ea $2,500.00

TOTAL: $88,827.92

Implementation of JOC

MoDOT’s JOC Program

Implementation of JOC

Status of Implementation

Pilot projects in D4 & D6 – 2010

Incorporate lessons learned – December 2010

Educate MoDOT staff – Early 2011

Update/Develop Fixed Unit Price List – Early 2011

Educate and collaborate with industry – January 2011

Expand scope and location of JOC projects – 2011

Implementation of JOC

Lessons Learned

Increased quantity based items

Added traffic control options

Added extension option

Non-fixed items

SiteManager changes