presented by: nam do tom wazny · • piers effectively reduced each span by 4 m each side •...
TRANSCRIPT
![Page 1: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/1.jpg)
Presented by:Nam DoTom Wazny
1
![Page 2: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/2.jpg)
• About BridgePro
• Tender Package & Client Requirements
• Design Challenges
o Flooding
o Vibration
• Construction Methodology
• Additional Features
Slide 2
Topics Discussed:
![Page 3: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/3.jpg)
Bridge / Piling and Marine construction contractor in Tasmania
• Founded 2010 – Latrobe (North West region)
• 50 employees
• Competitive market
• Design & Construction packages
Aim: deliver the safest and most economical solution
in the shortest practicable timeframe
Slide 3
About Us:
![Page 4: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/4.jpg)
Slide 4
Marine Construction
• Piling, Wharves, Dolphins
• Modular Road Transportable Jackup Barge
![Page 5: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/5.jpg)
Double T Beam Bridge
• Up to 15 m long spans
• SM1600 rating
• 4 day replacement from demolition, piling, installation and roadwork
Slide 6
![Page 6: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/6.jpg)
Tub Beam Bridge
Slide 7
• Typically 18+ m spans
• SM1600 rating
• Modular alternative to Super T Beams
![Page 7: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/7.jpg)
Pedestrian Bridges
Slide 9
• 5+ kPa rating
• Walking Tracks
• Multifunction Bridges
![Page 8: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/8.jpg)
Seaport Pedestrian Bridge
Slide 10
![Page 9: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/9.jpg)
Client Requirements & Tender Process
• Client requirements
• Public Use and Access
• Minimal Maintenance
• Light Service Vehicle Access
• Tendering:
• Original and alternative options
• Short timeframe
Slide 11
Conforming Design
Alternative Design
![Page 10: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/10.jpg)
Low Cost Bridge Solution
Matagarup Bridge Yandhai Nepean Crossing Seaport Pedestrian Bridge
Swan River - Perth370 m long x 8m wide x 72m heightCompleted in 07/2018 (from 11/2015) Budget: $M 91.5
Nepean River – Sydney NSW250m long x 8m wide x 13m heightCompleted in 10/2018 (from 12/2014)Budget: $M 50.0
Tamar River – Launceston TAS120m long x 4m wide x 1.5m heightCompleted in 07/2018 (from 12/2017)Budget: $M 2.4
Slide 12
![Page 11: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/11.jpg)
Design Challenges:
• Flood loading
o High flood Level
o Log impact design
o Complex hydrodynamic study
• Vibration
• Long Spans
• Geometric limits
Slide 15
![Page 12: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/12.jpg)
Geometry Restrictions:
• Long spans: 40 m at centre
• Waterway access maintained
• Pedestrian walkway grades
• Height limit: RL 7.0 m AHD
• Flood level: RL 5.2 m AHD
Slide 16
1:33 RampFlat1:14 Ramp(3 landings)
~ 1.5 m Truss Depth
(With clearance)
![Page 13: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/13.jpg)
• AS4100 and AS5100 Standards
• 5 kPa loading
• 20 kN Vehicle point load
Slide 17
Structural Design Inputs
![Page 14: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/14.jpg)
• 20 kN point loading
• Strategic beam placement – typical tyre placement
Slide 18
Vehicle Access
![Page 15: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/15.jpg)
• AS4100 and AS5100 Standards
• 5 kPa loading
• 20 kN Vehicle point load
• Flood Loading
• Vibration
• Soil stiffness profiles
Slide 19
Structural Design Inputs
![Page 16: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/16.jpg)
• Silty swamp at the surface
• Firmer rock below
Slide 20
Piling and Soil Stiffness
0 m
5 m
10 m
Silt
Doleritecobbles
Sandstone/ Mudstone
20 mTypical Pile Toe
![Page 17: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/17.jpg)
Flood Analysis:
• Complicated Hydraulic Model
• Collison impact by 5t vessel
moving at 20km/h
• Buoyancy and lifting reduced by
pile brace blocks
Slide 21
![Page 18: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/18.jpg)
• Increased lateral stiffness
• Reduced effective span
• Improved deflection and
vibration amplitude
• Viewing platform
Slide 22
Quad Pod Pier
![Page 19: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/19.jpg)
• Piers effectively reduced each span by 4 m each side
• Reduced deflection
• Reduced vibration amplitude
Slide 23
Quad Pod Pier
![Page 20: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/20.jpg)
• 95 t superstructure
• Tubular truss
• 3 Chords per Side
o Lateral Stiffness
o Torsional Stiffness
Slide 24
Truss Geometry
![Page 21: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/21.jpg)
• Torsional Stiffness
o Reduced floor member deflection
o Localised deflection acceptable
o Semi-fixed transverse members
Slide 25
Truss Geometry
![Page 22: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/22.jpg)
Vibration Analysis:
Slide 26
• Slimmer and longer bridge (spans)
• Different models were analysed to determine
the natural frequency of the bridge
• Final results:
o 1.77 Hz lateral
o 3.64 Hz vertical
• Allowance for retrofitting proprietary
damping if required.
![Page 23: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/23.jpg)
• Pier Connection
• 5 Tubes Connecting to Welded Column
• Durability Considerations
Slide 27
Challenging Connections
1
2
3
4
5
Span
Pier
![Page 24: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/24.jpg)
• Pier Connection
• 5 Tubes Connecting to Welded Column
• Durability Considerations
Slide 28
Challenging Connections
![Page 25: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/25.jpg)
Construction Challenges
Slide 29
![Page 26: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/26.jpg)
Construction Challenges:
• Small, restricted area behind rowing club
• Unstable ground - retaining wall required
oContainer base platform with screwed piles
oCondition monitoring before/during and after piling
• Temporary piles to anchor temporary bridge for loading/unloading to barge
Slide 30
Existing bank retaining wall
Flood levy
Work-site zone
Containerbase platform
Bank stability with amour rock
![Page 27: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/27.jpg)
Construction Challenges:
• Siteworks began in December 2017• Working hours restricted
due to hotel’s resident and other functions held in this area
• Tide daily movement• Twice a day up to 5m high
• Risk of construction barge bottoming out
Slide 31
Seaport pile group location
![Page 28: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/28.jpg)
Construction Challenges:
• Seaport piling• Slow water flow create a
high build-up silt depth
• Not suitable for jack-up barge
• Small operation window: set-up barge / position pile-guide frame / pitching and then piling
• Tight tolerance allowable due to precast pile brace block.
Slide 32
![Page 29: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/29.jpg)
Construction Challenges:
• Seaport piling• Slow water flow create a
high build-up silt depth
• Not suitable for jack-up barge
• Small operation window: set-up barge / position pile-guide frame / pitching and then piling
• Tight tolerance allowable due to precast pile brace block.
Slide 33
![Page 30: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/30.jpg)
Construction Challenges:
• Equipment limitation
• Limited timeframe due to weather conditions
• Installed by components rather than by span sections using hydraulic lifting bed and tide movement with jack-up barge.• Unstable due to unbalanced
weight• Using pile brace block as a
counter weight along with existing temporary screwed piles
• Small footprint limiting crane capacity (130T)
Slide 34
![Page 31: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/31.jpg)
Bridge fully assembled within 9 days
Slide 35D1
![Page 32: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/32.jpg)
Bridge fully assembled within 9 days
Slide 36D2
![Page 33: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/33.jpg)
Bridge fully assembled within 9 days
Slide 37D3
![Page 34: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/34.jpg)
Bridge fully assembled within 9 days
Slide 38
D4
![Page 35: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/35.jpg)
Bridge fully assembled within 9 days
Slide 39
D5
![Page 36: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/36.jpg)
Bridge fully assembled within 9 days
Slide 40D6
![Page 37: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/37.jpg)
Bridge fully assembled within 9 days
Slide 41
D7
![Page 38: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/38.jpg)
Bridge fully assembled within 9 days
Slide 42
D8
![Page 39: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/39.jpg)
Bridge fully assembled within 9 days
Slide 43D9
![Page 40: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/40.jpg)
• Programmable Lighting
• Handrail Integrated Lighting
• Electrical / Water Services at each pier
Slide 45
Additional Features
![Page 41: Presented by: Nam Do Tom Wazny · • Piers effectively reduced each span by 4 m each side • Reduced deflection ... other functions held in this area •Tide daily movement •Twice](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7f3ad50348386f598084/html5/thumbnails/41.jpg)
Slide 46
Additional Features