TRANSCRIPT
Presented to:
By:
Date:
Federal AviationAdministrationApproval Process
Overview
Cranes or Other Objects
United Parcel Service
Mike Manis, Support Specialist, MIA ATCT
February 11, 2009
Federal AviationAdministration
2Crane Process OverviewFebruary 11, 2009
A Crane is Needed
• Code of Federal Regulations – Part 77• Any object that affects navigable airspace
Federal AviationAdministration
3Crane Process OverviewFebruary 11, 2009
Different Governmental Agencies
• If on the Airport, Dade County Aviation Department will have separate, additional approval requirements and process.
• FAA has several divisions• Responsibility on Crane Operator to obtain
all needed approvals
Federal AviationAdministration
4Crane Process OverviewFebruary 11, 2009
FAA System
• File notice via internet
https://oeaaa.faa.gov/oeaaa/external/portal.jsp
Federal AviationAdministration
5Crane Process OverviewFebruary 11, 2009
FAA OE/AAA Website
Federal AviationAdministration
6Crane Process OverviewFebruary 11, 2009
FAA OE/AAA Website
• Instructions in middle of page
Federal AviationAdministration
7Crane Process OverviewFebruary 11, 2009
FAA OE/AAA Website
• Step 1: Register as a user• Either New User Registration link:
• Can file by postal mail, takes more time
Federal AviationAdministration
8Crane Process OverviewFebruary 11, 2009
FAA OE/AAA Website – Registration
Federal AviationAdministration
9Crane Process OverviewFebruary 11, 2009
FAA OE/AAA Website – Login
• Login with Username and Password• Help: 202-580-7500 or email:
Federal AviationAdministration
10Crane Process OverviewFebruary 11, 2009
FAA OE/AAA Website - Portal
• Step 2: Input Information• Where to input information• Off Airport or On Airport
Federal AviationAdministration
11Crane Process OverviewFebruary 11, 2009
If on MIA Airport, also Contact DCAD
• Step 3: (If Required)• If on MIA Airport, also contact Dade County
Aviation Department.• José Ramos, Chief of Aviation Planning
305-876-8080
Federal AviationAdministration
12Crane Process OverviewFebruary 11, 2009
After Input Into OE/AAA, What Next?
• Use FAA Aeronautical Study Number for reference
• In 2008 there were 128 on airport (NRA) cases in Miami-Dade County
Federal AviationAdministration
13Crane Process OverviewFebruary 11, 2009
Case Data Example
Federal AviationAdministration
14Crane Process OverviewFebruary 11, 2009
After Input Into OE/AAA, What Next?
• Different FAA Divisions and Military can respond
• AT-OES (Obstruction Evaluation Service)• AF (Airway Facilities a.k.a. Technical Ops)• FP (Flight Procedures)• ADO (Airport District Office)• FS (Flight Standards)• FM (Frequency Management)
Federal AviationAdministration
15Crane Process OverviewFebruary 11, 2009
FAA Divisions and Military continued
• USAF – Air Force• USN – Navy• USA – Army• AT-OSG (Operations Service Group)• ATCT (Air Traffic Control Tower)
• All may respond, but must respond by deadline to give input
Federal AviationAdministration
16Crane Process OverviewFebruary 11, 2009
Division Response Example
Federal AviationAdministration
17Crane Process OverviewFebruary 11, 2009
One Project Could Be Several Cases
• South Terminal Crane Project had three Aeronautical Study Numbers:
• View of Project Cases (FAA users View)
Federal AviationAdministration
18Crane Process OverviewFebruary 11, 2009
Project Closest Points Made Cases
Federal AviationAdministration
19Crane Process OverviewFebruary 11, 2009
ASN Data Available to FAA Users
• Case Data – Summary Information• Part 77 – Impact to IFR Procedures• POS – Penetration of Surfaces Report• Design Surfaces• Documents (email, maps, etc)• Correspondence Archive (Determinations,
Extensions, etc)• Division Responses (Used in Determination)
Federal AviationAdministration
20Crane Process OverviewFebruary 11, 2009
Objective – Determination Letter
• Either No Hazard, or• No Hazard with Provisions• Typical: Crane has Flags and Lights at Night• Also: Could Require NOTAM(S)
Issued for IFR Procedure Modification - Departure Procedures or
Instrument Approach Procedures
Federal AviationAdministration
21Crane Process OverviewFebruary 11, 2009
Case Data Example
• Part 77 Results
Federal AviationAdministration
22Crane Process OverviewFebruary 11, 2009
Final Step
• Project Complete• Advise FAA and/or MIA Airport
Federal AviationAdministration
23Crane Process OverviewFebruary 11, 2009
AIRPORT Part 77 Surfaces
Federal AviationAdministration
24Crane Process OverviewFebruary 11, 2009
Websites and Contact Information
https://oeaaa.faa.gov/oeaaa/external/portal.jsp
FAA Miami ATCT: Mike [email protected]