Improving Program Performance at FAAAugust 7, 2007
EVM at FAA
• FAA goal is to manage entire program using EVMS in accordance with ANSI/EIA 748– Manage/measure all resources– Requires changes in behavior by all parties
• FAA EVM differs from legacy approach– Program level, not just contractors– All contractual effort measured, including FFP– Will not change existing contracts
3 3Federal AviationAdministration
Improving Program Performance at FAAAugust 7, 2007
EVM Objectives
FAA Program Performance Metrics are “Best in Class” (Government and Industry)
Green EVM Flag for all major programs assessed in FY05
(which have significant DME remaining)
Assess EVM for new major programs, establish targets and make progress
For all major programs, demonstrate EVM policy compliance and 50% of Program
Manager use of EVM
Expand Executive use of EVM in their decision making process
OMB-300 EVM Scoresare assessed all green
Baseline Program Performance Metrics to measure progress
(and see some evidence)
I
II
III
IV
V
VI
4 4Federal AviationAdministration
Improving Program Performance at FAAAugust 7, 2007
EVM Transformation – Goals for 2007
• Full EVM implementation by end of FY 07.
• EVM part of Program Managers toolkit.
• Full EVM reporting for all major investments.
• Use of EVM makes a major difference in ability of FAA programs to stay on track and within budget.
• Use of EVM contributes to FAA “NAS Modernization Program” being removed from the GAO High Risk List.
5 5Federal AviationAdministration
Improving Program Performance at FAAAugust 7, 2007
EVM Transformation – Goals for 2008
• Under Construction
6 6Federal AviationAdministration
Improving Program Performance at FAAAugust 7, 2007
Recent Accomplishments
• Expanded AMS standard program milestones– Mapped milestones to FAA standard WBS– Identified milestone decision authority– Recommended AMS changes to implement
• Developed a program level IBR guide– Recommended AMS changes to implement
• Established Portfolio/Program Performance Metrics (PPPM)– Piloting in one Service Unit now
7 7Federal AviationAdministration
Improving Program Performance at FAAAugust 7, 2007
Current Activities
• Proposed EVM surveillance, certification, and executive program performance reporting processes will be developed and implemented – FAA Flight Plan Goal for this year
• Certification• surveillance
– Based on NDIA guidelines– major contractor “Best Practices”
8 8Federal AviationAdministration
Improving Program Performance at FAAAugust 7, 2007
Pilot Program Reports
Financial Schedule Technical Resources ExternalProgram Manager
Program A
Program B
Program C
Program D
9 9Federal AviationAdministration
Improving Program Performance at FAAAugust 7, 2007
Summary and Supporting Metrics
G
Level 1 AMS Milestones
- Negative Deviations
G- Technical Variance At-Completion (TVAC)
G**- Value of remaining High Risks
G- Deployment
n/a- Test Results
Y- System Defects
G- Requirements Stability
Technical Metrics
Measure of technical metrics and milestones of work performed
Definition
PerformancePortfolio Metric
G
Level 1 AMS Milestones
- Negative Deviations
G- Technical Variance At-Completion (TVAC)
G**- Value of remaining High Risks
G- Deployment
n/a- Test Results
Y- System Defects
G- Requirements Stability
Technical Metrics
Measure of technical metrics and milestones of work performed
Definition
PerformancePortfolio Metric
Flight Plan Acquisition Program Goals
G- Schedule
G- To-Complete Performance Index (TCPI)
G- Schedule Variance-At-Completion (SVAC) %
G- Cost Variance-At-completion (CVAC) %
G- Negative Deviations
Level 1 AMS Milestones
G - Program Schedule Reserve
G- Schedule Performance Index (SPI)
G- Program Cost Reserve
G- Cost Performance Index (CPI)
EVM Metrics
Measure of schedule
performance of work
performed
Measure of cost
performance of work
performed
Definition
ScheduleCostPortfolio Metric
Flight Plan Acquisition Program Goals
G- Schedule
G- To-Complete Performance Index (TCPI)
G- Schedule Variance-At-Completion (SVAC) %
G- Cost Variance-At-completion (CVAC) %
G- Negative Deviations
Level 1 AMS Milestones
G - Program Schedule Reserve
G- Schedule Performance Index (SPI)
G- Program Cost Reserve
G- Cost Performance Index (CPI)
EVM Metrics
Measure of schedule
performance of work
performed
Measure of cost
performance of work
performed
Definition
ScheduleCostPortfolio Metric
G- Obligations
Flight Plan Acquisition Program Goals
G- Cost
Assessment of External
Reviews
Y
G
Y
External Interest
- OMB
-GAO
- IG
External Reviews
G- Funding
G- FAA
G- Support Contractors
Y- Prime Contractor
Resource Metrics
Measure of current
funding and staffing
Definition
ResourcesPortfolio Metric
G- Obligations
Flight Plan Acquisition Program Goals
G- Cost
Assessment of External
Reviews
Y
G
Y
External Interest
- OMB
-GAO
- IG
External Reviews
G- Funding
G- FAA
G- Support Contractors
Y- Prime Contractor
Resource Metrics
Measure of current
funding and staffing
Definition
ResourcesPortfolio Metric
Financial Schedule Technical Resources External Interest
ProgramManager
G G Y Y Y G
10 10Federal AviationAdministration
Improving Program Performance at FAAAugust 7, 2007
Civilian Agency/Industry Working Group
• Three meetings held to date– May 14, July 18, and August 6
• Charter developed and approved• Government and Industry co-chairs
– Government – Selected at the 8/6/07 meeting– Industry - PMSC Chair
11 11Federal AviationAdministration
Improving Program Performance at FAAAugust 7, 2007
FAA Contractor Meeting Sep 25, 2007
• Tentative Agenda– Transformation Progress Report– Portfolio/Program Performance Metrics– Program IBRs– EVM Certification– EVM Surveillance– GAO High Risk List
12 12Federal AviationAdministration
Improving Program Performance at FAAAugust 7, 2007
Summary Activities
• Expanding FAA EVM Council role to lead EVM Surveillance, program level IBR
• Collaborating with FAA CFO and ATO Finance to integrate EVM and financial management
• Assisting DOT EVM Policy and guidance formulation