prevailing wage rates system 6-28-19.pdffairfield darien r18a, power equipment operator:...
TRANSCRIPT
County Town Classification
Hourly
Rate Hourly BenefitFairfield Bethel R10b, Roofers: Slate & Tile 40.00 17.75 + a
Fairfield Bethel R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Fairfield Bethel R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
Fairfield Bethel R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Fairfield Bethel R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Fairfield Bethel R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Fairfield Bethel R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Fairfield Bethel R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Fairfield Bethel
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Fairfield Bethel R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Fairfield Bethel R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Fairfield Bethel
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 44.74 42.48
Fairfield Bethel R3d, Carpenters, Lathers, Resilient Floorlayers and Piledrivers 32.60 25.34
Fairfield Bethel
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 39.62
27.25+3% of gross
wage
Fairfield Bethel R4a, Glazier 37.18 21.05 + a
Fairfield Bethel R7a, Painter: Brush/Roller 33.62 21.05
Fairfield Bethel R8a, Laborers: Common or General 13.13 4.24
Fairfield Bethel
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Fairfield Bethel R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 43.62 32.06
Fairfield Bridgeport R10b, Roofers: Slate & Tile 40.00 17.75 + a
Prevailing Wage Rates SystemAnnual Adjusted July 1st Rates
Residential Rates
1/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitFairfield Bridgeport R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Fairfield Bridgeport R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
Fairfield Bridgeport R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Fairfield Bridgeport R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Fairfield Bridgeport R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Fairfield Bridgeport R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Fairfield Bridgeport R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Fairfield Bridgeport
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Fairfield Bridgeport R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Fairfield Bridgeport R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Fairfield Bridgeport
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 44.74 42.48
Fairfield Bridgeport R3d, Carpenters, Lathers, Resilient Floorlayers and Piledrivers 32.60 25.34
Fairfield Bridgeport
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 39.62
27.25+3% of gross
wage
Fairfield Bridgeport R4a, Glazier 37.18 21.05 + a
Fairfield Bridgeport R7a, Painter: Brush/Roller 33.62 21.05
Fairfield Bridgeport R8a, Laborers: Common or General 13.13 4.24
Fairfield Bridgeport
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Fairfield Bridgeport R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 43.62 32.06
Fairfield Brookfield R10b, Roofers: Slate & Tile 40.00 17.75 + a
Fairfield Brookfield R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Fairfield Brookfield R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
Fairfield Brookfield R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Fairfield Brookfield R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Fairfield Brookfield R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Fairfield Brookfield R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Fairfield Brookfield R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
2/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Fairfield Brookfield
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Fairfield Brookfield R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Fairfield Brookfield R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Fairfield Brookfield
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 44.74 42.48
Fairfield Brookfield R3d, Carpenters, Lathers, Resilient Floorlayers and Piledrivers 32.60 25.34
Fairfield Brookfield
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 39.62
27.25+3% of gross
wage
Fairfield Brookfield R4a, Glazier 37.18 21.05 + a
Fairfield Brookfield R7a, Painter: Brush/Roller 33.62 21.05
Fairfield Brookfield R8a, Laborers: Common or General 13.13 4.24
Fairfield Brookfield
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Fairfield Brookfield R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 43.62 32.06
Fairfield Danbury R10b, Roofers: Slate & Tile 40.00 17.75 + a
Fairfield Danbury R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Fairfield Danbury R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
Fairfield Danbury R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Fairfield Danbury R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Fairfield Danbury R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Fairfield Danbury R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Fairfield Danbury R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Fairfield Danbury
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Fairfield Danbury R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Fairfield Danbury R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Fairfield Danbury
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 44.74 42.48
Fairfield Danbury R3d, Carpenters, Lathers, Resilient Floorlayers and Piledrivers 32.60 25.34
Fairfield Danbury
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 39.62
27.25+3% of gross
wage
3/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitFairfield Danbury R4a, Glazier 37.18 21.05 + a
Fairfield Danbury R7a, Painter: Brush/Roller 33.62 21.05
Fairfield Danbury R8a, Laborers: Common or General 13.13 4.24
Fairfield Danbury
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Fairfield Danbury R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 43.62 32.06
Fairfield Darien R10b, Roofers: Slate & Tile 40.00 17.75 + a
Fairfield Darien R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Fairfield Darien R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
Fairfield Darien R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Fairfield Darien R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Fairfield Darien R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Fairfield Darien R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Fairfield Darien R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Fairfield Darien
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Fairfield Darien R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Fairfield Darien R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Fairfield Darien
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 44.74 42.48
Fairfield Darien R3d, Carpenters, Lathers, Resilient Floorlayers and Piledrivers 32.60 25.34
Fairfield Darien
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 34.50 29.64
Fairfield Darien R4a, Glazier 37.18 21.05 + a
Fairfield Darien R7a, Painter: Brush/Roller 33.62 21.05
Fairfield Darien R8a, Laborers: Common or General 13.13 4.24
Fairfield Darien
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Fairfield Darien R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 43.62 32.06
Fairfield Easton R10b, Roofers: Slate & Tile 40.00 17.75 + a
Fairfield Easton R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Fairfield Easton R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
4/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Fairfield Easton R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Fairfield Easton R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Fairfield Easton R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Fairfield Easton R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Fairfield Easton R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Fairfield Easton
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Fairfield Easton R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Fairfield Easton R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Fairfield Easton
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 44.74 42.48
Fairfield Easton R3d, Carpenters, Lathers, Resilient Floorlayers and Piledrivers 32.60 25.34
Fairfield Easton
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 39.62
27.25+3% of gross
wage
Fairfield Easton R4a, Glazier 37.18 21.05 + a
Fairfield Easton R7a, Painter: Brush/Roller 33.62 21.05
Fairfield Easton R8a, Laborers: Common or General 13.13 4.24
Fairfield Easton
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Fairfield Easton R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 43.62 32.06
Fairfield Fairfield R10b, Roofers: Slate & Tile 40.00 17.75 + a
Fairfield Fairfield R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Fairfield Fairfield R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
Fairfield Fairfield R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Fairfield Fairfield R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Fairfield Fairfield R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Fairfield Fairfield R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Fairfield Fairfield R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Fairfield Fairfield
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
5/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitFairfield Fairfield R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Fairfield Fairfield R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Fairfield Fairfield
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 44.74 42.48
Fairfield Fairfield R3d, Carpenters, Lathers, Resilient Floorlayers and Piledrivers 32.60 25.34
Fairfield Fairfield
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 39.62
27.25+3% of gross
wage
Fairfield Fairfield R4a, Glazier 37.18 21.05 + a
Fairfield Fairfield R7a, Painter: Brush/Roller 33.62 21.05
Fairfield Fairfield R8a, Laborers: Common or General 13.13 4.24
Fairfield Fairfield
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Fairfield Fairfield R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 43.62 32.06
Fairfield Greenwich R10b, Roofers: Slate & Tile 40.00 17.75 + a
Fairfield Greenwich R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Fairfield Greenwich R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
Fairfield Greenwich R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Fairfield Greenwich R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Fairfield Greenwich R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Fairfield Greenwich R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Fairfield Greenwich R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Fairfield Greenwich
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Fairfield Greenwich R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Fairfield Greenwich R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Fairfield Greenwich
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 44.74 42.48
Fairfield Greenwich R3d, Carpenters, Lathers, Resilient Floorlayers and Piledrivers 32.60 25.34
Fairfield Greenwich
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 34.50 29.64
Fairfield Greenwich R4a, Glazier 37.18 21.05 + a
Fairfield Greenwich R7a, Painter: Brush/Roller 33.62 21.05
6/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitFairfield Greenwich R8a, Laborers: Common or General 13.13 4.24
Fairfield Greenwich
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Fairfield Greenwich R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 43.62 32.06
Fairfield Monroe R10b, Roofers: Slate & Tile 40.00 17.75 + a
Fairfield Monroe R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Fairfield Monroe R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
Fairfield Monroe R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Fairfield Monroe R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Fairfield Monroe R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Fairfield Monroe R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Fairfield Monroe R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Fairfield Monroe
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Fairfield Monroe R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Fairfield Monroe R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Fairfield Monroe
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 44.74 42.48
Fairfield Monroe R3d, Carpenters, Lathers, Resilient Floorlayers and Piledrivers 32.60 25.34
Fairfield Monroe
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 39.62
27.25+3% of gross
wage
Fairfield Monroe R4a, Glazier 37.18 21.05 + a
Fairfield Monroe R7a, Painter: Brush/Roller 33.62 21.05
Fairfield Monroe R8a, Laborers: Common or General 13.13 4.24
Fairfield Monroe
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Fairfield Monroe R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 43.62 32.06
Fairfield New Canaan R10b, Roofers: Slate & Tile 40.00 17.75 + a
Fairfield New Canaan R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Fairfield New Canaan R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
Fairfield New Canaan R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
7/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitFairfield New Canaan R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Fairfield New Canaan R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Fairfield New Canaan R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Fairfield New Canaan R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Fairfield New Canaan
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Fairfield New Canaan R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Fairfield New Canaan R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Fairfield New Canaan
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 44.74 42.48
Fairfield New Canaan R3d, Carpenters, Lathers, Resilient Floorlayers and Piledrivers 32.60 25.34
Fairfield New Canaan
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 34.50 29.64
Fairfield New Canaan R4a, Glazier 37.18 21.05 + a
Fairfield New Canaan R7a, Painter: Brush/Roller 33.62 21.05
Fairfield New Canaan R8a, Laborers: Common or General 13.13 4.24
Fairfield New Canaan
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Fairfield New Canaan R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 43.62 32.06
Fairfield New Fairfield R10b, Roofers: Slate & Tile 40.00 17.75 + a
Fairfield New Fairfield R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Fairfield New Fairfield R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
Fairfield New Fairfield R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Fairfield New Fairfield R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Fairfield New Fairfield R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Fairfield New Fairfield R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Fairfield New Fairfield R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Fairfield New Fairfield
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Fairfield New Fairfield R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Fairfield New Fairfield R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
8/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Fairfield New Fairfield
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 44.74 42.48
Fairfield New Fairfield R3d, Carpenters, Lathers, Resilient Floorlayers and Piledrivers 32.60 25.34
Fairfield New Fairfield
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 39.62
27.25+3% of gross
wage
Fairfield New Fairfield R4a, Glazier 37.18 21.05 + a
Fairfield New Fairfield R7a, Painter: Brush/Roller 33.62 21.05
Fairfield New Fairfield R8a, Laborers: Common or General 13.13 4.24
Fairfield New Fairfield
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Fairfield New Fairfield R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 43.62 32.06
Fairfield Newtown R10b, Roofers: Slate & Tile 40.00 17.75 + a
Fairfield Newtown R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Fairfield Newtown R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
Fairfield Newtown R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Fairfield Newtown R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Fairfield Newtown R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Fairfield Newtown R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Fairfield Newtown R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Fairfield Newtown
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Fairfield Newtown R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Fairfield Newtown R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Fairfield Newtown
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 44.74 42.48
Fairfield Newtown R3d, Carpenters, Lathers, Resilient Floorlayers and Piledrivers 32.60 25.34
Fairfield Newtown
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 39.62
27.25+3% of gross
wage
Fairfield Newtown R4a, Glazier 37.18 21.05 + a
Fairfield Newtown R7a, Painter: Brush/Roller 33.62 21.05
Fairfield Newtown R8a, Laborers: Common or General 13.13 4.24
9/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Fairfield Newtown
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Fairfield Newtown R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 43.62 32.06
Fairfield Norwalk R10b, Roofers: Slate & Tile 40.00 17.75 + a
Fairfield Norwalk R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Fairfield Norwalk R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
Fairfield Norwalk R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Fairfield Norwalk R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Fairfield Norwalk R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Fairfield Norwalk R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Fairfield Norwalk R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Fairfield Norwalk
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Fairfield Norwalk R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Fairfield Norwalk R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Fairfield Norwalk
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 44.74 42.48
Fairfield Norwalk R3d, Carpenters, Lathers, Resilient Floorlayers and Piledrivers 32.60 25.34
Fairfield Norwalk
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 34.50 29.64
Fairfield Norwalk R4a, Glazier 37.18 21.05 + a
Fairfield Norwalk R7a, Painter: Brush/Roller 33.62 21.05
Fairfield Norwalk R8a, Laborers: Common or General 13.13 4.24
Fairfield Norwalk
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Fairfield Norwalk R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 43.62 32.06
Fairfield Redding R10b, Roofers: Slate & Tile 40.00 17.75 + a
Fairfield Redding R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Fairfield Redding R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
Fairfield Redding R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Fairfield Redding R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
10/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitFairfield Redding R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Fairfield Redding R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Fairfield Redding R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Fairfield Redding
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Fairfield Redding R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Fairfield Redding R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Fairfield Redding
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 44.74 42.48
Fairfield Redding R3d, Carpenters, Lathers, Resilient Floorlayers and Piledrivers 32.60 25.34
Fairfield Redding
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 39.62
27.25+3% of gross
wage
Fairfield Redding R4a, Glazier 37.18 21.05 + a
Fairfield Redding R7a, Painter: Brush/Roller 33.62 21.05
Fairfield Redding R8a, Laborers: Common or General 13.13 4.24
Fairfield Redding
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Fairfield Redding R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 43.62 32.06
Fairfield Ridgefield R10b, Roofers: Slate & Tile 40.00 17.75 + a
Fairfield Ridgefield R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Fairfield Ridgefield R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
Fairfield Ridgefield R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Fairfield Ridgefield R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Fairfield Ridgefield R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Fairfield Ridgefield R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Fairfield Ridgefield R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Fairfield Ridgefield
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Fairfield Ridgefield R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Fairfield Ridgefield R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
11/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Fairfield Ridgefield
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 44.74 42.48
Fairfield Ridgefield R3d, Carpenters, Lathers, Resilient Floorlayers and Piledrivers 32.60 25.34
Fairfield Ridgefield
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 39.62
27.25+3% of gross
wage
Fairfield Ridgefield R4a, Glazier 37.18 21.05 + a
Fairfield Ridgefield R7a, Painter: Brush/Roller 33.62 21.05
Fairfield Ridgefield R8a, Laborers: Common or General 13.13 4.24
Fairfield Ridgefield
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Fairfield Ridgefield R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 43.62 32.06
Fairfield Shelton R10b, Roofers: Slate & Tile 40.00 17.75 + a
Fairfield Shelton R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Fairfield Shelton R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
Fairfield Shelton R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Fairfield Shelton R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Fairfield Shelton R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Fairfield Shelton R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Fairfield Shelton R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Fairfield Shelton
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Fairfield Shelton R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Fairfield Shelton R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Fairfield Shelton
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 44.74 42.48
Fairfield Shelton R3d, Carpenters, Lathers, Resilient Floorlayers and Piledrivers 32.60 25.34
Fairfield Shelton
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 39.62
27.25+3% of gross
wage
Fairfield Shelton R4a, Glazier 37.18 21.05 + a
Fairfield Shelton R7a, Painter: Brush/Roller 33.62 21.05
Fairfield Shelton R8a, Laborers: Common or General 13.13 4.24
12/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Fairfield Shelton
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Fairfield Shelton R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 43.62 32.06
Fairfield Sherman R10b, Roofers: Slate & Tile 40.00 17.75 + a
Fairfield Sherman R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Fairfield Sherman R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
Fairfield Sherman R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Fairfield Sherman R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Fairfield Sherman R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Fairfield Sherman R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Fairfield Sherman R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Fairfield Sherman
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Fairfield Sherman R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Fairfield Sherman R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Fairfield Sherman
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 44.74 42.48
Fairfield Sherman R3d, Carpenters, Lathers, Resilient Floorlayers and Piledrivers 32.60 25.34
Fairfield Sherman
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 39.62
27.25+3% of gross
wage
Fairfield Sherman R4a, Glazier 37.18 21.05 + a
Fairfield Sherman R7a, Painter: Brush/Roller 33.62 21.05
Fairfield Sherman R8a, Laborers: Common or General 13.13 4.24
Fairfield Sherman
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Fairfield Sherman R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 43.62 32.06
Fairfield Stamford R10b, Roofers: Slate & Tile 40.00 17.75 + a
Fairfield Stamford R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Fairfield Stamford R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
Fairfield Stamford R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Fairfield Stamford R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
13/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitFairfield Stamford R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Fairfield Stamford R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Fairfield Stamford R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Fairfield Stamford
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Fairfield Stamford R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Fairfield Stamford R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Fairfield Stamford
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 44.74 42.48
Fairfield Stamford R3d, Carpenters, Lathers, Resilient Floorlayers and Piledrivers 32.60 25.34
Fairfield Stamford
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 34.50 29.64
Fairfield Stamford R4a, Glazier 37.18 21.05 + a
Fairfield Stamford R7a, Painter: Brush/Roller 33.62 21.05
Fairfield Stamford R8a, Laborers: Common or General 13.13 4.24
Fairfield Stamford
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Fairfield Stamford R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 43.62 32.06
Fairfield Stratford R10b, Roofers: Slate & Tile 40.00 17.75 + a
Fairfield Stratford R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Fairfield Stratford R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
Fairfield Stratford R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Fairfield Stratford R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Fairfield Stratford R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Fairfield Stratford R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Fairfield Stratford R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Fairfield Stratford
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Fairfield Stratford R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Fairfield Stratford R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
14/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Fairfield Stratford
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 44.74 42.48
Fairfield Stratford R3d, Carpenters, Lathers, Resilient Floorlayers and Piledrivers 32.60 25.34
Fairfield Stratford
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 39.62
27.25+3% of gross
wage
Fairfield Stratford R4a, Glazier 37.18 21.05 + a
Fairfield Stratford R7a, Painter: Brush/Roller 33.62 21.05
Fairfield Stratford R8a, Laborers: Common or General 13.13 4.24
Fairfield Stratford
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Fairfield Stratford R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 43.62 32.06
Fairfield Trumbull R10b, Roofers: Slate & Tile 40.00 17.75 + a
Fairfield Trumbull R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Fairfield Trumbull R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
Fairfield Trumbull R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Fairfield Trumbull R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Fairfield Trumbull R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Fairfield Trumbull R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Fairfield Trumbull R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Fairfield Trumbull
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Fairfield Trumbull R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Fairfield Trumbull R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Fairfield Trumbull
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 44.74 42.48
Fairfield Trumbull R3d, Carpenters, Lathers, Resilient Floorlayers and Piledrivers 32.60 25.34
Fairfield Trumbull
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 39.62
27.25+3% of gross
wage
Fairfield Trumbull R4a, Glazier 37.18 21.05 + a
Fairfield Trumbull R7a, Painter: Brush/Roller 33.62 21.05
Fairfield Trumbull R8a, Laborers: Common or General 13.13 4.24
15/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Fairfield Trumbull
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Fairfield Trumbull R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 43.62 32.06
Fairfield Weston R10b, Roofers: Slate & Tile 40.00 17.75 + a
Fairfield Weston R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Fairfield Weston R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
Fairfield Weston R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Fairfield Weston R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Fairfield Weston R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Fairfield Weston R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Fairfield Weston R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Fairfield Weston
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Fairfield Weston R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Fairfield Weston R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Fairfield Weston
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 44.74 42.48
Fairfield Weston R3d, Carpenters, Lathers, Resilient Floorlayers and Piledrivers 32.60 25.34
Fairfield Weston
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 39.62
27.25+3% of gross
wage
Fairfield Weston R4a, Glazier 37.18 21.05 + a
Fairfield Weston R7a, Painter: Brush/Roller 33.62 21.05
Fairfield Weston R8a, Laborers: Common or General 13.13 4.24
Fairfield Weston
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Fairfield Weston R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 43.62 32.06
Fairfield Westport R10b, Roofers: Slate & Tile 40.00 17.75 + a
Fairfield Westport R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Fairfield Westport R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
Fairfield Westport R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Fairfield Westport R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
16/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitFairfield Westport R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Fairfield Westport R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Fairfield Westport R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Fairfield Westport
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Fairfield Westport R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Fairfield Westport R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Fairfield Westport
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 44.74 42.48
Fairfield Westport R3d, Carpenters, Lathers, Resilient Floorlayers and Piledrivers 32.60 25.34
Fairfield Westport
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 39.62
27.25+3% of gross
wage
Fairfield Westport R4a, Glazier 37.18 21.05 + a
Fairfield Westport R7a, Painter: Brush/Roller 33.62 21.05
Fairfield Westport R8a, Laborers: Common or General 13.13 4.24
Fairfield Westport
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Fairfield Westport R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 43.62 32.06
Fairfield Wilton R10b, Roofers: Slate & Tile 40.00 17.75 + a
Fairfield Wilton R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Fairfield Wilton R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
Fairfield Wilton R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Fairfield Wilton R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Fairfield Wilton R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Fairfield Wilton R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Fairfield Wilton R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Fairfield Wilton
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Fairfield Wilton R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Fairfield Wilton R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
17/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Fairfield Wilton
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 44.74 42.48
Fairfield Wilton R3d, Carpenters, Lathers, Resilient Floorlayers and Piledrivers 32.60 25.34
Fairfield Wilton
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 39.62
27.25+3% of gross
wage
Fairfield Wilton R4a, Glazier 37.18 21.05 + a
Fairfield Wilton R7a, Painter: Brush/Roller 33.62 21.05
Fairfield Wilton R8a, Laborers: Common or General 13.13 4.24
Fairfield Wilton
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Fairfield Wilton R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 43.62 32.06
Hartford Avon R10a, Roofers: Composition 37.00 20.57
Hartford Avon R10b, Roofers: Slate & Tile 37.50 20.57
Hartford Avon R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Hartford Avon R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford Avon R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford Avon R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford Avon R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford Avon R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Hartford Avon R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford Avon R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford Avon
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford Avon R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford Avon R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Hartford Avon
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford Avon R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford Avon
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford Avon R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford Avon R7c, Painter: Drywall Finisher/Taper 16.25 2.70
18/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitHartford Avon R8a, Laborers: Common or General 13.09 1.63
Hartford Avon
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford Avon R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Hartford Berlin R10a, Roofers: Composition 37.00 20.57
Hartford Berlin R10b, Roofers: Slate & Tile 37.50 20.57
Hartford Berlin R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Hartford Berlin R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford Berlin R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford Berlin R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford Berlin R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford Berlin R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Hartford Berlin R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford Berlin R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford Berlin
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford Berlin R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford Berlin R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Hartford Berlin
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford Berlin R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford Berlin
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford Berlin R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford Berlin R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Hartford Berlin R8a, Laborers: Common or General 13.09 1.63
Hartford Berlin
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford Berlin R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Hartford Bloomfield R10a, Roofers: Composition 37.00 20.57
Hartford Bloomfield R10b, Roofers: Slate & Tile 37.50 20.57
Hartford Bloomfield R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
19/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitHartford Bloomfield R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford Bloomfield R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford Bloomfield R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford Bloomfield R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford Bloomfield R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Hartford Bloomfield R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford Bloomfield R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford Bloomfield
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford Bloomfield R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford Bloomfield R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Hartford Bloomfield
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford Bloomfield R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford Bloomfield
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford Bloomfield R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford Bloomfield R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Hartford Bloomfield R8a, Laborers: Common or General 13.09 1.63
Hartford Bloomfield
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford Bloomfield R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Hartford Bristol R10a, Roofers: Composition 37.00 20.57
Hartford Bristol R10b, Roofers: Slate & Tile 37.50 20.57
Hartford Bristol R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Hartford Bristol R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford Bristol R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford Bristol R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford Bristol R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford Bristol R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
20/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Hartford Bristol R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford Bristol R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford Bristol
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford Bristol R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford Bristol R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Hartford Bristol
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford Bristol R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford Bristol
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford Bristol R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford Bristol R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Hartford Bristol R8a, Laborers: Common or General 13.09 1.63
Hartford Bristol
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford Bristol R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Hartford Burlington R10a, Roofers: Composition 37.00 20.57
Hartford Burlington R10b, Roofers: Slate & Tile 37.50 20.57
Hartford Burlington R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Hartford Burlington R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford Burlington R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford Burlington R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford Burlington R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford Burlington R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Hartford Burlington R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford Burlington R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford Burlington
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford Burlington R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford Burlington R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
21/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Hartford Burlington
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford Burlington R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford Burlington
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford Burlington R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford Burlington R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Hartford Burlington R8a, Laborers: Common or General 13.09 1.63
Hartford Burlington
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford Burlington R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Hartford Canton R10a, Roofers: Composition 37.00 20.57
Hartford Canton R10b, Roofers: Slate & Tile 37.50 20.57
Hartford Canton R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Hartford Canton R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford Canton R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford Canton R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford Canton R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford Canton R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Hartford Canton R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford Canton R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford Canton
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford Canton R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford Canton R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Hartford Canton
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford Canton R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford Canton
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford Canton R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford Canton R7c, Painter: Drywall Finisher/Taper 16.25 2.70
22/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitHartford Canton R8a, Laborers: Common or General 13.09 1.63
Hartford Canton
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford Canton R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Hartford East Granby R10a, Roofers: Composition 37.00 20.57
Hartford East Granby R10b, Roofers: Slate & Tile 37.50 20.57
Hartford East Granby R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Hartford East Granby R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford East Granby R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford East Granby R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford East Granby R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford East Granby R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Hartford East Granby R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford East Granby R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford East Granby
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford East Granby R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford East Granby R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Hartford East Granby
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford East Granby R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford East Granby
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford East Granby R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford East Granby R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Hartford East Granby R8a, Laborers: Common or General 13.09 1.63
Hartford East Granby
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford East Granby R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Hartford East Hartford R10a, Roofers: Composition 37.00 20.57
Hartford East Hartford R10b, Roofers: Slate & Tile 37.50 20.57
Hartford East Hartford R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
23/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitHartford East Hartford R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford East Hartford R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford East Hartford R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford East Hartford R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford East Hartford R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Hartford East Hartford R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford East Hartford R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford East Hartford
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford East Hartford R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford East Hartford R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Hartford East Hartford
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford East Hartford R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford East Hartford
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford East Hartford R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford East Hartford R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Hartford East Hartford R8a, Laborers: Common or General 13.09 1.63
Hartford East Hartford
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford East Hartford R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Hartford East Windsor R10a, Roofers: Composition 37.00 20.57
Hartford East Windsor R10b, Roofers: Slate & Tile 37.50 20.57
Hartford East Windsor R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Hartford East Windsor R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford East Windsor R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford East Windsor R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford East Windsor R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford East Windsor R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
24/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Hartford East Windsor R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford East Windsor R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford East Windsor
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford East Windsor R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford East Windsor R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Hartford East Windsor
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford East Windsor R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford East Windsor
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford East Windsor R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford East Windsor R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Hartford East Windsor R8a, Laborers: Common or General 13.09 1.63
Hartford East Windsor
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford East Windsor R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Hartford Enfield R10a, Roofers: Composition 37.00 20.57
Hartford Enfield R10b, Roofers: Slate & Tile 37.50 20.57
Hartford Enfield R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Hartford Enfield R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford Enfield R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford Enfield R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford Enfield R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford Enfield R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Hartford Enfield R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford Enfield R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford Enfield
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford Enfield R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford Enfield R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
25/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Hartford Enfield
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford Enfield R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford Enfield
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford Enfield R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford Enfield R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Hartford Enfield R8a, Laborers: Common or General 13.09 1.63
Hartford Enfield
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford Enfield R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Hartford Farmington R10a, Roofers: Composition 37.00 20.57
Hartford Farmington R10b, Roofers: Slate & Tile 37.50 20.57
Hartford Farmington R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Hartford Farmington R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford Farmington R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford Farmington R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford Farmington R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford Farmington R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Hartford Farmington R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford Farmington R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford Farmington
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford Farmington R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford Farmington R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Hartford Farmington
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford Farmington R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford Farmington
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford Farmington R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford Farmington R7c, Painter: Drywall Finisher/Taper 16.25 2.70
26/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitHartford Farmington R8a, Laborers: Common or General 13.09 1.63
Hartford Farmington
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford Farmington R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Hartford Glastonbury R10a, Roofers: Composition 37.00 20.57
Hartford Glastonbury R10b, Roofers: Slate & Tile 37.50 20.57
Hartford Glastonbury R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Hartford Glastonbury R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford Glastonbury R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford Glastonbury R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford Glastonbury R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford Glastonbury R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Hartford Glastonbury R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford Glastonbury R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford Glastonbury
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford Glastonbury R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford Glastonbury R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Hartford Glastonbury
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford Glastonbury R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford Glastonbury
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford Glastonbury R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford Glastonbury R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Hartford Glastonbury R8a, Laborers: Common or General 13.09 1.63
Hartford Glastonbury
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford Glastonbury R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Hartford Granby R10a, Roofers: Composition 37.00 20.57
Hartford Granby R10b, Roofers: Slate & Tile 37.50 20.57
Hartford Granby R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
27/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitHartford Granby R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford Granby R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford Granby R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford Granby R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford Granby R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Hartford Granby R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford Granby R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford Granby
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford Granby R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford Granby R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Hartford Granby
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford Granby R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford Granby
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford Granby R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford Granby R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Hartford Granby R8a, Laborers: Common or General 13.09 1.63
Hartford Granby
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford Granby R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Hartford Hartford R10a, Roofers: Composition 37.00 20.57
Hartford Hartford R10b, Roofers: Slate & Tile 37.50 20.57
Hartford Hartford R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Hartford Hartford R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford Hartford R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford Hartford R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford Hartford R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford Hartford R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
28/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Hartford Hartford R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford Hartford R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford Hartford
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford Hartford R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford Hartford R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Hartford Hartford
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford Hartford R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford Hartford
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford Hartford R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford Hartford R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Hartford Hartford R8a, Laborers: Common or General 13.09 1.63
Hartford Hartford
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford Hartford R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Hartford Hartland R10a, Roofers: Composition 37.00 20.57
Hartford Hartland R10b, Roofers: Slate & Tile 37.50 20.57
Hartford Hartland R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Hartford Hartland R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford Hartland R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford Hartland R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford Hartland R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford Hartland R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Hartford Hartland R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford Hartland R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford Hartland
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford Hartland R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford Hartland R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
29/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Hartford Hartland
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford Hartland R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford Hartland
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford Hartland R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford Hartland R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Hartford Hartland R8a, Laborers: Common or General 13.09 1.63
Hartford Hartland
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford Hartland R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Hartford Manchester R10a, Roofers: Composition 37.00 20.57
Hartford Manchester R10b, Roofers: Slate & Tile 37.50 20.57
Hartford Manchester R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Hartford Manchester R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford Manchester R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford Manchester R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford Manchester R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford Manchester R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Hartford Manchester R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford Manchester R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford Manchester
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford Manchester R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford Manchester R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Hartford Manchester
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford Manchester R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford Manchester
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford Manchester R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford Manchester R7c, Painter: Drywall Finisher/Taper 16.25 2.70
30/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitHartford Manchester R8a, Laborers: Common or General 13.09 1.63
Hartford Manchester
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford Manchester R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Hartford Marlborough R10a, Roofers: Composition 37.00 20.57
Hartford Marlborough R10b, Roofers: Slate & Tile 37.50 20.57
Hartford Marlborough R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Hartford Marlborough R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford Marlborough R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford Marlborough R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford Marlborough R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford Marlborough R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Hartford Marlborough R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford Marlborough R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford Marlborough
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford Marlborough R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford Marlborough R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Hartford Marlborough
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford Marlborough R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford Marlborough
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford Marlborough R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford Marlborough R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Hartford Marlborough R8a, Laborers: Common or General 13.09 1.63
Hartford Marlborough
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford Marlborough R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Hartford New Britain R10a, Roofers: Composition 37.00 20.57
Hartford New Britain R10b, Roofers: Slate & Tile 37.50 20.57
Hartford New Britain R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
31/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitHartford New Britain R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford New Britain R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford New Britain R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford New Britain R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford New Britain R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Hartford New Britain R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford New Britain R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford New Britain
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford New Britain R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford New Britain R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Hartford New Britain
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford New Britain R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford New Britain
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford New Britain R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford New Britain R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Hartford New Britain R8a, Laborers: Common or General 13.09 1.63
Hartford New Britain
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford New Britain R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Hartford Newington R10a, Roofers: Composition 37.00 20.57
Hartford Newington R10b, Roofers: Slate & Tile 37.50 20.57
Hartford Newington R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Hartford Newington R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford Newington R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford Newington R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford Newington R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford Newington R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
32/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Hartford Newington R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford Newington R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford Newington
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford Newington R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford Newington R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Hartford Newington
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford Newington R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford Newington
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford Newington R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford Newington R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Hartford Newington R8a, Laborers: Common or General 13.09 1.63
Hartford Newington
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford Newington R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Hartford Plainville R10a, Roofers: Composition 37.00 20.57
Hartford Plainville R10b, Roofers: Slate & Tile 37.50 20.57
Hartford Plainville R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Hartford Plainville R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford Plainville R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford Plainville R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford Plainville R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford Plainville R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Hartford Plainville R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford Plainville R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford Plainville
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford Plainville R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford Plainville R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
33/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Hartford Plainville
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford Plainville R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford Plainville
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford Plainville R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford Plainville R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Hartford Plainville R8a, Laborers: Common or General 13.09 1.63
Hartford Plainville
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford Plainville R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Hartford Rocky Hill R10a, Roofers: Composition 37.00 20.57
Hartford Rocky Hill R10b, Roofers: Slate & Tile 37.50 20.57
Hartford Rocky Hill R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Hartford Rocky Hill R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford Rocky Hill R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford Rocky Hill R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford Rocky Hill R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford Rocky Hill R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Hartford Rocky Hill R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford Rocky Hill R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford Rocky Hill
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford Rocky Hill R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford Rocky Hill R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Hartford Rocky Hill
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford Rocky Hill R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford Rocky Hill
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford Rocky Hill R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford Rocky Hill R7c, Painter: Drywall Finisher/Taper 16.25 2.70
34/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitHartford Rocky Hill R8a, Laborers: Common or General 13.09 1.63
Hartford Rocky Hill
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford Rocky Hill R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Hartford Simsbury R10a, Roofers: Composition 37.00 20.57
Hartford Simsbury R10b, Roofers: Slate & Tile 37.50 20.57
Hartford Simsbury R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Hartford Simsbury R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford Simsbury R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford Simsbury R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford Simsbury R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford Simsbury R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Hartford Simsbury R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford Simsbury R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford Simsbury
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford Simsbury R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford Simsbury R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Hartford Simsbury
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford Simsbury R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford Simsbury
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford Simsbury R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford Simsbury R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Hartford Simsbury R8a, Laborers: Common or General 13.09 1.63
Hartford Simsbury
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford Simsbury R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Hartford South Windsor R10a, Roofers: Composition 37.00 20.57
Hartford South Windsor R10b, Roofers: Slate & Tile 37.50 20.57
Hartford South Windsor R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
35/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitHartford South Windsor R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford South Windsor R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford South Windsor R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford South Windsor R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford South Windsor R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Hartford South Windsor R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford South Windsor R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford South Windsor
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford South Windsor R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford South Windsor R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Hartford South Windsor
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford South Windsor R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford South Windsor
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford South Windsor R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford South Windsor R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Hartford South Windsor R8a, Laborers: Common or General 13.09 1.63
Hartford South Windsor
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford South Windsor R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Hartford Southington R10a, Roofers: Composition 37.00 20.57
Hartford Southington R10b, Roofers: Slate & Tile 37.50 20.57
Hartford Southington R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Hartford Southington R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford Southington R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford Southington R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford Southington R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford Southington R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
36/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Hartford Southington R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford Southington R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford Southington
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford Southington R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford Southington R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Hartford Southington
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford Southington R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford Southington
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford Southington R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford Southington R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Hartford Southington R8a, Laborers: Common or General 13.09 1.63
Hartford Southington
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford Southington R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Hartford Statewide R10a, Roofers: Composition 37.00 20.57
Hartford Statewide R10b, Roofers: Slate & Tile 37.50 20.57
Hartford Statewide R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Hartford Statewide R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford Statewide R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford Statewide R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford Statewide R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford Statewide R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Hartford Statewide R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford Statewide R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford Statewide
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford Statewide R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford Statewide R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
37/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Hartford Statewide
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford Statewide R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford Statewide
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford Statewide R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford Statewide R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Hartford Statewide R8a, Laborers: Common or General 13.09 1.63
Hartford Statewide
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford Statewide R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Hartford Suffield R10a, Roofers: Composition 37.00 20.57
Hartford Suffield R10b, Roofers: Slate & Tile 37.50 20.57
Hartford Suffield R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Hartford Suffield R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford Suffield R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford Suffield R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford Suffield R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford Suffield R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Hartford Suffield R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford Suffield R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford Suffield
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford Suffield R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford Suffield R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Hartford Suffield
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford Suffield R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford Suffield
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford Suffield R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford Suffield R7c, Painter: Drywall Finisher/Taper 16.25 2.70
38/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitHartford Suffield R8a, Laborers: Common or General 13.09 1.63
Hartford Suffield
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford Suffield R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Hartford West Hartford R10a, Roofers: Composition 37.00 20.57
Hartford West Hartford R10b, Roofers: Slate & Tile 37.50 20.57
Hartford West Hartford R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Hartford West Hartford R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford West Hartford R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford West Hartford R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford West Hartford R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford West Hartford R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Hartford West Hartford R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford West Hartford R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford West Hartford
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford West Hartford R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford West Hartford R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Hartford West Hartford
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford West Hartford R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford West Hartford
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford West Hartford R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford West Hartford R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Hartford West Hartford R8a, Laborers: Common or General 13.09 1.63
Hartford West Hartford
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford West Hartford R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Hartford Wethersfield R10a, Roofers: Composition 37.00 20.57
Hartford Wethersfield R10b, Roofers: Slate & Tile 37.50 20.57
Hartford Wethersfield R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
39/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitHartford Wethersfield R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford Wethersfield R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford Wethersfield R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford Wethersfield R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford Wethersfield R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Hartford Wethersfield R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford Wethersfield R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford Wethersfield
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford Wethersfield R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford Wethersfield R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Hartford Wethersfield
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford Wethersfield R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford Wethersfield
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford Wethersfield R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford Wethersfield R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Hartford Wethersfield R8a, Laborers: Common or General 13.09 1.63
Hartford Wethersfield
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford Wethersfield R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Hartford Windsor R10a, Roofers: Composition 37.00 20.57
Hartford Windsor R10b, Roofers: Slate & Tile 37.50 20.57
Hartford Windsor R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Hartford Windsor R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford Windsor R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford Windsor R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford Windsor R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford Windsor R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
40/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Hartford Windsor R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford Windsor R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford Windsor
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford Windsor R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford Windsor R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Hartford Windsor
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford Windsor R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford Windsor
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford Windsor R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford Windsor R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Hartford Windsor R8a, Laborers: Common or General 13.09 1.63
Hartford Windsor
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford Windsor R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Hartford Windsor Locks R10a, Roofers: Composition 37.00 20.57
Hartford Windsor Locks R10b, Roofers: Slate & Tile 37.50 20.57
Hartford Windsor Locks R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Hartford Windsor Locks R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Hartford Windsor Locks R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Hartford Windsor Locks R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Hartford Windsor Locks R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Hartford Windsor Locks R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Hartford Windsor Locks R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Hartford Windsor Locks R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Hartford Windsor Locks
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Hartford Windsor Locks R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Hartford Windsor Locks R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
41/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Hartford Windsor Locks
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Hartford Windsor Locks R3a, Carpenter (Including Drywall Hanging) 15.50
Hartford Windsor Locks
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Hartford Windsor Locks R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 15.33 1.56
Hartford Windsor Locks R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Hartford Windsor Locks R8a, Laborers: Common or General 13.09 1.63
Hartford Windsor Locks
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Hartford Windsor Locks R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Litchfield Barkhamsted R10a, Roofers: Composition 15.62 3.08
Litchfield Barkhamsted R12a, Truck Driver - 3 Axle 13.69 2.05
Litchfield Barkhamsted R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Litchfield Barkhamsted R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Litchfield Barkhamsted R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Litchfield Barkhamsted R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Litchfield Barkhamsted R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Litchfield Barkhamsted R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Litchfield Barkhamsted
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Litchfield Barkhamsted R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Litchfield Barkhamsted R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Litchfield Barkhamsted R20, HVAC Mechanics 11.00 1.49
Litchfield Barkhamsted R3, Carpenter 15.06 3.67
Litchfield Barkhamsted
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Litchfield Barkhamsted R7g, Painter: (Excluding Drywall Finishing) 8.96
Litchfield Barkhamsted R8a, Laborers: Common or General 13.17 2.89
Litchfield Barkhamsted
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Litchfield Bethlehem R10a, Roofers: Composition 15.62 3.08
42/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitLitchfield Bethlehem R12a, Truck Driver - 3 Axle 13.69 2.05
Litchfield Bethlehem R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Litchfield Bethlehem R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Litchfield Bethlehem R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Litchfield Bethlehem R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Litchfield Bethlehem R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Litchfield Bethlehem R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Litchfield Bethlehem
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Litchfield Bethlehem R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Litchfield Bethlehem R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Litchfield Bethlehem R20, HVAC Mechanics 11.00 1.49
Litchfield Bethlehem R3, Carpenter 15.06 3.67
Litchfield Bethlehem
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Litchfield Bethlehem R7g, Painter: (Excluding Drywall Finishing) 8.96
Litchfield Bethlehem R8a, Laborers: Common or General 13.17 2.89
Litchfield Bethlehem
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Litchfield Bridgewater R10a, Roofers: Composition 15.62 3.08
Litchfield Bridgewater R12a, Truck Driver - 3 Axle 13.69 2.05
Litchfield Bridgewater R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Litchfield Bridgewater R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Litchfield Bridgewater R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Litchfield Bridgewater R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Litchfield Bridgewater R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Litchfield Bridgewater R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Litchfield Bridgewater
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Litchfield Bridgewater R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
43/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitLitchfield Bridgewater R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Litchfield Bridgewater R20, HVAC Mechanics 11.00 1.49
Litchfield Bridgewater R3, Carpenter 15.06 3.67
Litchfield Bridgewater
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Litchfield Bridgewater R7g, Painter: (Excluding Drywall Finishing) 8.96
Litchfield Bridgewater R8a, Laborers: Common or General 13.17 2.89
Litchfield Bridgewater
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Litchfield Canaan R10a, Roofers: Composition 15.62 3.08
Litchfield Canaan R12a, Truck Driver - 3 Axle 13.69 2.05
Litchfield Canaan R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Litchfield Canaan R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Litchfield Canaan R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Litchfield Canaan R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Litchfield Canaan R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Litchfield Canaan R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Litchfield Canaan
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Litchfield Canaan R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Litchfield Canaan R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Litchfield Canaan R20, HVAC Mechanics 11.00 1.49
Litchfield Canaan R3, Carpenter 15.06 3.67
Litchfield Canaan
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Litchfield Canaan R7g, Painter: (Excluding Drywall Finishing) 8.96
Litchfield Canaan R8a, Laborers: Common or General 13.17 2.89
Litchfield Canaan
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Litchfield Colebrook R10a, Roofers: Composition 15.62 3.08
Litchfield Colebrook R12a, Truck Driver - 3 Axle 13.69 2.05
Litchfield Colebrook R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
44/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Litchfield Colebrook R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Litchfield Colebrook R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Litchfield Colebrook R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Litchfield Colebrook R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Litchfield Colebrook R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Litchfield Colebrook
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Litchfield Colebrook R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Litchfield Colebrook R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Litchfield Colebrook R20, HVAC Mechanics 11.00 1.49
Litchfield Colebrook R3, Carpenter 15.06 3.67
Litchfield Colebrook
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Litchfield Colebrook R7g, Painter: (Excluding Drywall Finishing) 8.96
Litchfield Colebrook R8a, Laborers: Common or General 13.17 2.89
Litchfield Colebrook
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Litchfield Cornwall R10a, Roofers: Composition 15.62 3.08
Litchfield Cornwall R12a, Truck Driver - 3 Axle 13.69 2.05
Litchfield Cornwall R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Litchfield Cornwall R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Litchfield Cornwall R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Litchfield Cornwall R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Litchfield Cornwall R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Litchfield Cornwall R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Litchfield Cornwall
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Litchfield Cornwall R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Litchfield Cornwall R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Litchfield Cornwall R20, HVAC Mechanics 11.00 1.49
45/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitLitchfield Cornwall R3, Carpenter 15.06 3.67
Litchfield Cornwall
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Litchfield Cornwall R7g, Painter: (Excluding Drywall Finishing) 8.96
Litchfield Cornwall R8a, Laborers: Common or General 13.17 2.89
Litchfield Cornwall
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Litchfield Goshen R10a, Roofers: Composition 15.62 3.08
Litchfield Goshen R12a, Truck Driver - 3 Axle 13.69 2.05
Litchfield Goshen R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Litchfield Goshen R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Litchfield Goshen R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Litchfield Goshen R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Litchfield Goshen R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Litchfield Goshen R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Litchfield Goshen
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Litchfield Goshen R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Litchfield Goshen R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Litchfield Goshen R20, HVAC Mechanics 11.00 1.49
Litchfield Goshen R3, Carpenter 15.06 3.67
Litchfield Goshen
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Litchfield Goshen R7g, Painter: (Excluding Drywall Finishing) 8.96
Litchfield Goshen R8a, Laborers: Common or General 13.17 2.89
Litchfield Goshen
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Litchfield Harwinton R10a, Roofers: Composition 15.62 3.08
Litchfield Harwinton R12a, Truck Driver - 3 Axle 13.69 2.05
Litchfield Harwinton R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Litchfield Harwinton R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
46/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitLitchfield Harwinton R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Litchfield Harwinton R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Litchfield Harwinton R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Litchfield Harwinton R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Litchfield Harwinton
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Litchfield Harwinton R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Litchfield Harwinton R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Litchfield Harwinton R20, HVAC Mechanics 11.00 1.49
Litchfield Harwinton R3, Carpenter 15.06 3.67
Litchfield Harwinton
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Litchfield Harwinton R7g, Painter: (Excluding Drywall Finishing) 8.96
Litchfield Harwinton R8a, Laborers: Common or General 13.17 2.89
Litchfield Harwinton
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Litchfield Kent R10a, Roofers: Composition 15.62 3.08
Litchfield Kent R12a, Truck Driver - 3 Axle 13.69 2.05
Litchfield Kent R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Litchfield Kent R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Litchfield Kent R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Litchfield Kent R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Litchfield Kent R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Litchfield Kent R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Litchfield Kent
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Litchfield Kent R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Litchfield Kent R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Litchfield Kent R20, HVAC Mechanics 11.00 1.49
Litchfield Kent R3, Carpenter 15.06 3.67
47/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Litchfield Kent
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Litchfield Kent R7g, Painter: (Excluding Drywall Finishing) 8.96
Litchfield Kent R8a, Laborers: Common or General 13.17 2.89
Litchfield Kent
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Litchfield Litchfield R10a, Roofers: Composition 15.62 3.08
Litchfield Litchfield R12a, Truck Driver - 3 Axle 13.69 2.05
Litchfield Litchfield R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Litchfield Litchfield R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Litchfield Litchfield R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Litchfield Litchfield R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Litchfield Litchfield R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Litchfield Litchfield R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Litchfield Litchfield
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Litchfield Litchfield R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Litchfield Litchfield R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Litchfield Litchfield R20, HVAC Mechanics 11.00 1.49
Litchfield Litchfield
R21, Asbestos/Toxic Waste Removal Laborers (does not include removal from
mechanical system) 15.15 3.18
Litchfield Litchfield R22a, Hazardous Material Handler from Mechanical Systems 12.30 2.06
Litchfield Litchfield R3, Carpenter 15.06 3.67
Litchfield Litchfield
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Litchfield Litchfield R7g, Painter: (Excluding Drywall Finishing) 8.96
Litchfield Litchfield R8a, Laborers: Common or General 13.17 2.89
Litchfield Litchfield
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Litchfield Morris R10a, Roofers: Composition 15.62 3.08
Litchfield Morris R12a, Truck Driver - 3 Axle 13.69 2.05
Litchfield Morris R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
48/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Litchfield Morris R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Litchfield Morris R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Litchfield Morris R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Litchfield Morris R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Litchfield Morris R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Litchfield Morris
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Litchfield Morris R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Litchfield Morris R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Litchfield Morris R20, HVAC Mechanics 11.00 1.49
Litchfield Morris R3, Carpenter 15.06 3.67
Litchfield Morris
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Litchfield Morris R7g, Painter: (Excluding Drywall Finishing) 8.96
Litchfield Morris R8a, Laborers: Common or General 13.17 2.89
Litchfield Morris
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Litchfield New Hartford R10a, Roofers: Composition 15.62 3.08
Litchfield New Hartford R12a, Truck Driver - 3 Axle 13.69 2.05
Litchfield New Hartford R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Litchfield New Hartford R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Litchfield New Hartford R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Litchfield New Hartford R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Litchfield New Hartford R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Litchfield New Hartford R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Litchfield New Hartford
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Litchfield New Hartford R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Litchfield New Hartford R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Litchfield New Hartford R20, HVAC Mechanics 11.00 1.49
49/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitLitchfield New Hartford R3, Carpenter 15.06 3.67
Litchfield New Hartford
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Litchfield New Hartford R8a, Laborers: Common or General 13.17 2.89
Litchfield New Hartford
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Litchfield New Milford R10a, Roofers: Composition 15.62 3.08
Litchfield New Milford R12a, Truck Driver - 3 Axle 13.69 2.05
Litchfield New Milford R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Litchfield New Milford R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Litchfield New Milford R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Litchfield New Milford R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Litchfield New Milford R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Litchfield New Milford R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Litchfield New Milford
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Litchfield New Milford R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Litchfield New Milford R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Litchfield New Milford R20, HVAC Mechanics 11.00 1.49
Litchfield New Milford R3, Carpenter 15.06 3.67
Litchfield New Milford
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Litchfield New Milford R7g, Painter: (Excluding Drywall Finishing) 8.96
Litchfield New Milford R8a, Laborers: Common or General 13.17 2.89
Litchfield New Milford
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Litchfield Norfolk R10a, Roofers: Composition 15.62 3.08
Litchfield Norfolk R12a, Truck Driver - 3 Axle 13.69 2.05
Litchfield Norfolk R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Litchfield Norfolk R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Litchfield Norfolk R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
50/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitLitchfield Norfolk R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Litchfield Norfolk R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Litchfield Norfolk R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Litchfield Norfolk
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Litchfield Norfolk R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Litchfield Norfolk R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Litchfield Norfolk R20, HVAC Mechanics 11.00 1.49
Litchfield Norfolk R3, Carpenter 15.06 3.67
Litchfield Norfolk
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Litchfield Norfolk R7g, Painter: (Excluding Drywall Finishing) 8.96
Litchfield Norfolk R8a, Laborers: Common or General 13.17 2.89
Litchfield Norfolk
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Litchfield North Canaan R10a, Roofers: Composition 15.62 3.08
Litchfield North Canaan R12a, Truck Driver - 3 Axle 13.69 2.05
Litchfield North Canaan R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Litchfield North Canaan R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Litchfield North Canaan R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Litchfield North Canaan R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Litchfield North Canaan R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Litchfield North Canaan R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Litchfield North Canaan
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Litchfield North Canaan R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Litchfield North Canaan R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Litchfield North Canaan R20, HVAC Mechanics 11.00 1.49
Litchfield North Canaan R3, Carpenter 15.06 3.67
Litchfield North Canaan
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
51/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitLitchfield North Canaan R7g, Painter: (Excluding Drywall Finishing) 8.96
Litchfield North Canaan R8a, Laborers: Common or General 13.17 2.89
Litchfield North Canaan
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Litchfield Plymouth R10a, Roofers: Composition 15.62 3.08
Litchfield Plymouth R12a, Truck Driver - 3 Axle 13.69 2.05
Litchfield Plymouth R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Litchfield Plymouth R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Litchfield Plymouth R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Litchfield Plymouth R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Litchfield Plymouth R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Litchfield Plymouth R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Litchfield Plymouth
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Litchfield Plymouth R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Litchfield Plymouth R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Litchfield Plymouth R20, HVAC Mechanics 11.00 1.49
Litchfield Plymouth R3, Carpenter 15.06 3.67
Litchfield Plymouth
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Litchfield Plymouth R7g, Painter: (Excluding Drywall Finishing) 8.96
Litchfield Plymouth R8a, Laborers: Common or General 13.17 2.89
Litchfield Plymouth
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Litchfield Roxbury R10a, Roofers: Composition 15.62 3.08
Litchfield Roxbury R12a, Truck Driver - 3 Axle 13.69 2.05
Litchfield Roxbury R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Litchfield Roxbury R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Litchfield Roxbury R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Litchfield Roxbury R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
52/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Litchfield Roxbury R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Litchfield Roxbury R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Litchfield Roxbury
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Litchfield Roxbury R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Litchfield Roxbury R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Litchfield Roxbury R20, HVAC Mechanics 11.00 1.49
Litchfield Roxbury R3, Carpenter 15.06 3.67
Litchfield Roxbury
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Litchfield Roxbury R7g, Painter: (Excluding Drywall Finishing) 8.96
Litchfield Roxbury R8a, Laborers: Common or General 13.17 2.89
Litchfield Roxbury
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Litchfield Salisbury R10a, Roofers: Composition 15.62 3.08
Litchfield Salisbury R12a, Truck Driver - 3 Axle 13.69 2.05
Litchfield Salisbury R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Litchfield Salisbury R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Litchfield Salisbury R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Litchfield Salisbury R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Litchfield Salisbury R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Litchfield Salisbury R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Litchfield Salisbury
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Litchfield Salisbury R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Litchfield Salisbury R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Litchfield Salisbury R20, HVAC Mechanics 11.00 1.49
Litchfield Salisbury R3, Carpenter 15.06 3.67
Litchfield Salisbury
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Litchfield Salisbury R7g, Painter: (Excluding Drywall Finishing) 8.96
53/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitLitchfield Salisbury R8a, Laborers: Common or General 13.17 2.89
Litchfield Salisbury
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Litchfield Sharon R10a, Roofers: Composition 15.62 3.08
Litchfield Sharon R12a, Truck Driver - 3 Axle 13.69 2.05
Litchfield Sharon R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Litchfield Sharon R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Litchfield Sharon R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Litchfield Sharon R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Litchfield Sharon R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Litchfield Sharon R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Litchfield Sharon
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Litchfield Sharon R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Litchfield Sharon R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Litchfield Sharon R20, HVAC Mechanics 11.00 1.49
Litchfield Sharon R3, Carpenter 15.06 3.67
Litchfield Sharon
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Litchfield Sharon R7g, Painter: (Excluding Drywall Finishing) 8.96
Litchfield Sharon R8a, Laborers: Common or General 13.17 2.89
Litchfield Sharon
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Litchfield Thomaston R10a, Roofers: Composition 15.62 3.08
Litchfield Thomaston R12a, Truck Driver - 3 Axle 13.69 2.05
Litchfield Thomaston R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Litchfield Thomaston R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Litchfield Thomaston R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Litchfield Thomaston R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Litchfield Thomaston R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
54/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitLitchfield Thomaston R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Litchfield Thomaston
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Litchfield Thomaston R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Litchfield Thomaston R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Litchfield Thomaston R20, HVAC Mechanics 11.00 1.49
Litchfield Thomaston R3, Carpenter 15.06 3.67
Litchfield Thomaston
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Litchfield Thomaston R7g, Painter: (Excluding Drywall Finishing) 8.96
Litchfield Thomaston R8a, Laborers: Common or General 13.17 2.89
Litchfield Thomaston
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Litchfield Torrington R10a, Roofers: Composition 15.62 3.08
Litchfield Torrington R12a, Truck Driver - 3 Axle 13.69 2.05
Litchfield Torrington R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Litchfield Torrington R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Litchfield Torrington R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Litchfield Torrington R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Litchfield Torrington R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Litchfield Torrington R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Litchfield Torrington
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Litchfield Torrington R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Litchfield Torrington R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Litchfield Torrington R20, HVAC Mechanics 11.00 1.49
Litchfield Torrington R3, Carpenter 15.06 3.67
Litchfield Torrington
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Litchfield Torrington R7g, Painter: (Excluding Drywall Finishing) 8.96
Litchfield Torrington R8a, Laborers: Common or General 13.17 2.89
55/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Litchfield Torrington
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Litchfield Warren R10a, Roofers: Composition 15.62 3.08
Litchfield Warren R12a, Truck Driver - 3 Axle 13.69 2.05
Litchfield Warren R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Litchfield Warren R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Litchfield Warren R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Litchfield Warren R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Litchfield Warren R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Litchfield Warren R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Litchfield Warren
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Litchfield Warren R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Litchfield Warren R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Litchfield Warren R20, HVAC Mechanics 11.00 1.49
Litchfield Warren R3, Carpenter 15.06 3.67
Litchfield Warren
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Litchfield Warren R7g, Painter: (Excluding Drywall Finishing) 8.96
Litchfield Warren R8a, Laborers: Common or General 13.17 2.89
Litchfield Warren
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Litchfield Washington R10a, Roofers: Composition 15.62 3.08
Litchfield Washington R12a, Truck Driver - 3 Axle 13.69 2.05
Litchfield Washington R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Litchfield Washington R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Litchfield Washington R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Litchfield Washington R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Litchfield Washington R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Litchfield Washington R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
56/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Litchfield Washington
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Litchfield Washington R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Litchfield Washington R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Litchfield Washington R20, HVAC Mechanics 11.00 1.49
Litchfield Washington R3, Carpenter 15.06 3.67
Litchfield Washington
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Litchfield Washington R7g, Painter: (Excluding Drywall Finishing) 8.96
Litchfield Washington R8a, Laborers: Common or General 13.17 2.89
Litchfield Washington
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Litchfield Watertown R10a, Roofers: Composition 15.62 3.08
Litchfield Watertown R12a, Truck Driver - 3 Axle 13.69 2.05
Litchfield Watertown R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Litchfield Watertown R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Litchfield Watertown R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Litchfield Watertown R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Litchfield Watertown R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Litchfield Watertown R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Litchfield Watertown
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Litchfield Watertown R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Litchfield Watertown R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Litchfield Watertown R20, HVAC Mechanics 11.00 1.49
Litchfield Watertown R3, Carpenter 15.06 3.67
Litchfield Watertown
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Litchfield Watertown R7g, Painter: (Excluding Drywall Finishing) 8.96
Litchfield Watertown R8a, Laborers: Common or General 13.17 2.89
Litchfield Watertown
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
57/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitLitchfield Winchester R10a, Roofers: Composition 15.62 3.08
Litchfield Winchester R12a, Truck Driver - 3 Axle 13.69 2.05
Litchfield Winchester R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Litchfield Winchester R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Litchfield Winchester R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Litchfield Winchester R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Litchfield Winchester R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Litchfield Winchester R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Litchfield Winchester
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Litchfield Winchester R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Litchfield Winchester R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Litchfield Winchester R20, HVAC Mechanics 11.00 1.49
Litchfield Winchester R3, Carpenter 15.06 3.67
Litchfield Winchester
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Litchfield Winchester R7g, Painter: (Excluding Drywall Finishing) 8.96
Litchfield Winchester R8a, Laborers: Common or General 13.17 2.89
Litchfield Winchester
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Litchfield Woodbury R10a, Roofers: Composition 15.62 3.08
Litchfield Woodbury R12a, Truck Driver - 3 Axle 13.69 2.05
Litchfield Woodbury R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Litchfield Woodbury R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Litchfield Woodbury R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Litchfield Woodbury R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Litchfield Woodbury R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Litchfield Woodbury R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Litchfield Woodbury
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
58/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitLitchfield Woodbury R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Litchfield Woodbury R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Litchfield Woodbury R20, HVAC Mechanics 11.00 1.49
Litchfield Woodbury R3, Carpenter 15.06 3.67
Litchfield Woodbury
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Litchfield Woodbury R7g, Painter: (Excluding Drywall Finishing) 8.96
Litchfield Woodbury R8a, Laborers: Common or General 13.17 2.89
Litchfield Woodbury
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Middlesex Chester R10a, Roofers: Composition 37.00 20.57
Middlesex Chester R10b, Roofers: Slate & Tile 37.50 20.57
Middlesex Chester R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Middlesex Chester R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Middlesex Chester R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Middlesex Chester R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Middlesex Chester R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Middlesex Chester R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Middlesex Chester R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Middlesex Chester R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Middlesex Chester
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Middlesex Chester R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Middlesex Chester R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Middlesex Chester
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Middlesex Chester R3a, Carpenter (Including Drywall Hanging) 17.24 1.60
Middlesex Chester
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Middlesex Chester R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
Middlesex Chester R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Middlesex Chester R8a, Laborers: Common or General 10.66 1.63
59/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Middlesex Chester
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Middlesex Chester
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
Middlesex Clinton R10a, Roofers: Composition 37.00 20.57
Middlesex Clinton R10b, Roofers: Slate & Tile 37.50 20.57
Middlesex Clinton R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Middlesex Clinton R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Middlesex Clinton R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Middlesex Clinton R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Middlesex Clinton R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Middlesex Clinton R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Middlesex Clinton R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Middlesex Clinton R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Middlesex Clinton
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Middlesex Clinton R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Middlesex Clinton R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Middlesex Clinton
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Middlesex Clinton R3a, Carpenter (Including Drywall Hanging) 17.24 1.60
Middlesex Clinton
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Middlesex Clinton R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
Middlesex Clinton R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Middlesex Clinton R8a, Laborers: Common or General 10.66 1.63
Middlesex Clinton
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Middlesex Clinton
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
Middlesex Cromwell R10a, Roofers: Composition 37.00 20.57
Middlesex Cromwell R10b, Roofers: Slate & Tile 37.50 20.57
60/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitMiddlesex Cromwell R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Middlesex Cromwell R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Middlesex Cromwell R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Middlesex Cromwell R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Middlesex Cromwell R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Middlesex Cromwell R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Middlesex Cromwell R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Middlesex Cromwell R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Middlesex Cromwell
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Middlesex Cromwell R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Middlesex Cromwell R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Middlesex Cromwell
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Middlesex Cromwell R3a, Carpenter (Including Drywall Hanging) 17.24 1.60
Middlesex Cromwell
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Middlesex Cromwell R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
Middlesex Cromwell R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Middlesex Cromwell R8a, Laborers: Common or General 10.66 1.63
Middlesex Cromwell
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Middlesex Cromwell
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
Middlesex Deep River R10a, Roofers: Composition 37.00 20.57
Middlesex Deep River R10b, Roofers: Slate & Tile 37.50 20.57
Middlesex Deep River R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Middlesex Deep River R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Middlesex Deep River R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Middlesex Deep River R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Middlesex Deep River R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
61/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitMiddlesex Deep River R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Middlesex Deep River R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Middlesex Deep River R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Middlesex Deep River
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Middlesex Deep River R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Middlesex Deep River R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Middlesex Deep River
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Middlesex Deep River R3a, Carpenter (Including Drywall Hanging) 17.24 1.60
Middlesex Deep River
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Middlesex Deep River R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
Middlesex Deep River R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Middlesex Deep River R8a, Laborers: Common or General 10.66 1.63
Middlesex Deep River
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Middlesex Deep River
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
Middlesex Durham R10a, Roofers: Composition 37.00 20.57
Middlesex Durham R10b, Roofers: Slate & Tile 37.50 20.57
Middlesex Durham R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Middlesex Durham R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Middlesex Durham R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Middlesex Durham R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Middlesex Durham R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Middlesex Durham R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Middlesex Durham R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Middlesex Durham R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Middlesex Durham
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
62/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitMiddlesex Durham R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Middlesex Durham R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Middlesex Durham
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Middlesex Durham R3a, Carpenter (Including Drywall Hanging) 17.24 1.60
Middlesex Durham
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Middlesex Durham R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
Middlesex Durham R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Middlesex Durham R8a, Laborers: Common or General 10.66 1.63
Middlesex Durham
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Middlesex Durham
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
Middlesex East Haddam R10a, Roofers: Composition 37.00 20.57
Middlesex East Haddam R10b, Roofers: Slate & Tile 37.50 20.57
Middlesex East Haddam R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Middlesex East Haddam R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Middlesex East Haddam R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Middlesex East Haddam R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Middlesex East Haddam R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Middlesex East Haddam R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Middlesex East Haddam R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Middlesex East Haddam R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Middlesex East Haddam
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Middlesex East Haddam R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Middlesex East Haddam R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Middlesex East Haddam
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Middlesex East Haddam R3a, Carpenter (Including Drywall Hanging) 17.24 1.60
63/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Middlesex East Haddam
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Middlesex East Haddam R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
Middlesex East Haddam R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Middlesex East Haddam R8a, Laborers: Common or General 10.66 1.63
Middlesex East Haddam
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Middlesex East Haddam
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
Middlesex East Hampton R10a, Roofers: Composition 37.00 20.57
Middlesex East Hampton R10b, Roofers: Slate & Tile 37.50 20.57
Middlesex East Hampton R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Middlesex East Hampton R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Middlesex East Hampton R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Middlesex East Hampton R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Middlesex East Hampton R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Middlesex East Hampton R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Middlesex East Hampton R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Middlesex East Hampton R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Middlesex East Hampton
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Middlesex East Hampton R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Middlesex East Hampton R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Middlesex East Hampton
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Middlesex East Hampton R3a, Carpenter (Including Drywall Hanging) 17.24 1.60
Middlesex East Hampton
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Middlesex East Hampton R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
Middlesex East Hampton R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Middlesex East Hampton R8a, Laborers: Common or General 10.66 1.63
64/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Middlesex East Hampton
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Middlesex East Hampton
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
Middlesex Essex R10a, Roofers: Composition 37.00 20.57
Middlesex Essex R10b, Roofers: Slate & Tile 37.50 20.57
Middlesex Essex R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Middlesex Essex R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Middlesex Essex R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Middlesex Essex R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Middlesex Essex R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Middlesex Essex R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Middlesex Essex R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Middlesex Essex R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Middlesex Essex
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Middlesex Essex R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Middlesex Essex R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Middlesex Essex
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Middlesex Essex R3a, Carpenter (Including Drywall Hanging) 17.24 1.60
Middlesex Essex
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Middlesex Essex R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
Middlesex Essex R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Middlesex Essex R8a, Laborers: Common or General 10.66 1.63
Middlesex Essex
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Middlesex Essex
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
Middlesex Haddam R10a, Roofers: Composition 37.00 20.57
Middlesex Haddam R10b, Roofers: Slate & Tile 37.50 20.57
65/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitMiddlesex Haddam R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Middlesex Haddam R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Middlesex Haddam R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Middlesex Haddam R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Middlesex Haddam R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Middlesex Haddam R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Middlesex Haddam R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Middlesex Haddam R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Middlesex Haddam
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Middlesex Haddam R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Middlesex Haddam R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Middlesex Haddam
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Middlesex Haddam R3a, Carpenter (Including Drywall Hanging) 17.24 1.60
Middlesex Haddam
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Middlesex Haddam R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
Middlesex Haddam R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Middlesex Haddam R8a, Laborers: Common or General 10.66 1.63
Middlesex Haddam
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Middlesex Haddam
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
Middlesex Killingworth R10a, Roofers: Composition 37.00 20.57
Middlesex Killingworth R10b, Roofers: Slate & Tile 37.50 20.57
Middlesex Killingworth R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Middlesex Killingworth R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Middlesex Killingworth R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Middlesex Killingworth R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Middlesex Killingworth R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
66/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitMiddlesex Killingworth R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Middlesex Killingworth R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Middlesex Killingworth R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Middlesex Killingworth
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Middlesex Killingworth R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Middlesex Killingworth R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Middlesex Killingworth
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Middlesex Killingworth R3a, Carpenter (Including Drywall Hanging) 17.24 1.60
Middlesex Killingworth
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Middlesex Killingworth R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
Middlesex Killingworth R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Middlesex Killingworth R8a, Laborers: Common or General 10.66 1.63
Middlesex Killingworth
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Middlesex Killingworth
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
Middlesex Middlefield R10a, Roofers: Composition 37.00 20.57
Middlesex Middlefield R10b, Roofers: Slate & Tile 37.50 20.57
Middlesex Middlefield R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Middlesex Middlefield R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Middlesex Middlefield R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Middlesex Middlefield R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Middlesex Middlefield R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Middlesex Middlefield R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Middlesex Middlefield R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Middlesex Middlefield R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Middlesex Middlefield
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
67/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitMiddlesex Middlefield R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Middlesex Middlefield R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Middlesex Middlefield
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Middlesex Middlefield R3a, Carpenter (Including Drywall Hanging) 17.24 1.60
Middlesex Middlefield
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Middlesex Middlefield R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
Middlesex Middlefield R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Middlesex Middlefield R8a, Laborers: Common or General 10.66 1.63
Middlesex Middlefield
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Middlesex Middlefield
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
Middlesex Middletown R10a, Roofers: Composition 37.00 20.57
Middlesex Middletown R10b, Roofers: Slate & Tile 37.50 20.57
Middlesex Middletown R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Middlesex Middletown R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Middlesex Middletown R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Middlesex Middletown R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Middlesex Middletown R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Middlesex Middletown R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Middlesex Middletown R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Middlesex Middletown R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Middlesex Middletown
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Middlesex Middletown R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Middlesex Middletown R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Middlesex Middletown
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Middlesex Middletown R3a, Carpenter (Including Drywall Hanging) 17.24 1.60
68/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Middlesex Middletown
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Middlesex Middletown R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
Middlesex Middletown R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Middlesex Middletown R8a, Laborers: Common or General 10.66 1.63
Middlesex Middletown
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Middlesex Middletown
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
Middlesex Old Saybrook R10a, Roofers: Composition 37.00 20.57
Middlesex Old Saybrook R10b, Roofers: Slate & Tile 37.50 20.57
Middlesex Old Saybrook R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Middlesex Old Saybrook R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Middlesex Old Saybrook R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Middlesex Old Saybrook R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Middlesex Old Saybrook R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Middlesex Old Saybrook R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Middlesex Old Saybrook R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Middlesex Old Saybrook R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Middlesex Old Saybrook
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Middlesex Old Saybrook R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Middlesex Old Saybrook R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Middlesex Old Saybrook
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Middlesex Old Saybrook R3a, Carpenter (Including Drywall Hanging) 17.24 1.60
Middlesex Old Saybrook
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Middlesex Old Saybrook R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
Middlesex Old Saybrook R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Middlesex Old Saybrook R8a, Laborers: Common or General 10.66 1.63
69/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Middlesex Old Saybrook
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Middlesex Old Saybrook
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
Middlesex Portland R10a, Roofers: Composition 37.00 20.57
Middlesex Portland R10b, Roofers: Slate & Tile 37.50 20.57
Middlesex Portland R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Middlesex Portland R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Middlesex Portland R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Middlesex Portland R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Middlesex Portland R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Middlesex Portland R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Middlesex Portland R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Middlesex Portland R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Middlesex Portland
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Middlesex Portland R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Middlesex Portland R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Middlesex Portland
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Middlesex Portland R3a, Carpenter (Including Drywall Hanging) 17.24 1.60
Middlesex Portland
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Middlesex Portland R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
Middlesex Portland R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Middlesex Portland R8a, Laborers: Common or General 10.66 1.63
Middlesex Portland
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Middlesex Portland
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
Middlesex Westbrook R10a, Roofers: Composition 37.00 20.57
Middlesex Westbrook R10b, Roofers: Slate & Tile 37.50 20.57
70/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitMiddlesex Westbrook R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Middlesex Westbrook R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Middlesex Westbrook R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Middlesex Westbrook R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Middlesex Westbrook R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Middlesex Westbrook R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Middlesex Westbrook R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Middlesex Westbrook R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Middlesex Westbrook
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Middlesex Westbrook R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Middlesex Westbrook R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Middlesex Westbrook
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Middlesex Westbrook R3a, Carpenter (Including Drywall Hanging) 17.24 1.60
Middlesex Westbrook
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Middlesex Westbrook R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
Middlesex Westbrook R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Middlesex Westbrook R8a, Laborers: Common or General 10.66 1.63
Middlesex Westbrook
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Middlesex Westbrook
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
New Haven Ansonia R10b, Roofers: Slate & Tile 40.00 17.75 + a
New Haven Ansonia R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New Haven Ansonia R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
New Haven Ansonia R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New Haven Ansonia R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New Haven Ansonia R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
71/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
New Haven Ansonia R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New Haven Ansonia R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New Haven Ansonia
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New Haven Ansonia R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New Haven Ansonia R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New Haven Ansonia
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New Haven Ansonia R3, Carpenter 16.78 1.60
New Haven Ansonia
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 38.50
28.61+3% of gross
wage
New Haven Ansonia R4a, Glazier 37.18 21.05 + a
New Haven Ansonia R7a, Painter: Brush/Roller 14.26 1.56
New Haven Ansonia R8a, Laborers: Common or General 10.66 1.63
New Haven Ansonia
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New Haven Ansonia R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.04 2.06
New Haven Beacon Falls R10b, Roofers: Slate & Tile 40.00 17.75 + a
New Haven Beacon Falls R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New Haven Beacon Falls R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
New Haven Beacon Falls R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New Haven Beacon Falls R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New Haven Beacon Falls R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New Haven Beacon Falls R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New Haven Beacon Falls R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New Haven Beacon Falls
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New Haven Beacon Falls R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New Haven Beacon Falls R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New Haven Beacon Falls
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
72/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitNew Haven Beacon Falls R3, Carpenter 16.78 1.60
New Haven Beacon Falls
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 39.62
27.25+3% of gross
wage
New Haven Beacon Falls R4a, Glazier 37.18 21.05 + a
New Haven Beacon Falls R7a, Painter: Brush/Roller 14.26 1.56
New Haven Beacon Falls R8a, Laborers: Common or General 10.66 1.63
New Haven Beacon Falls
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New Haven Beacon Falls R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.04 2.06
New Haven Bethany R10b, Roofers: Slate & Tile 40.00 17.75 + a
New Haven Bethany R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New Haven Bethany R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
New Haven Bethany R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New Haven Bethany R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New Haven Bethany R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New Haven Bethany R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New Haven Bethany R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New Haven Bethany
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New Haven Bethany R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New Haven Bethany R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New Haven Bethany
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New Haven Bethany R3, Carpenter 16.78 1.60
New Haven Bethany
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 38.50
28.61+3% of gross
wage
New Haven Bethany R4a, Glazier 37.18 21.05 + a
New Haven Bethany R7a, Painter: Brush/Roller 14.26 1.56
New Haven Bethany R8a, Laborers: Common or General 10.66 1.63
New Haven Bethany
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New Haven Bethany R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.04 2.06
73/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitNew Haven Branford R10b, Roofers: Slate & Tile 40.00 17.75 + a
New Haven Branford R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New Haven Branford R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
New Haven Branford R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New Haven Branford R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New Haven Branford R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New Haven Branford R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New Haven Branford R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New Haven Branford
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New Haven Branford R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New Haven Branford R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New Haven Branford
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New Haven Branford R3, Carpenter 16.78 1.60
New Haven Branford
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 38.50
28.61+3% of gross
wage
New Haven Branford R4a, Glazier 37.18 21.05 + a
New Haven Branford R7a, Painter: Brush/Roller 14.26 1.56
New Haven Branford R8a, Laborers: Common or General 10.66 1.63
New Haven Branford
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New Haven Branford R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.04 2.06
New Haven Cheshire R10a, Roofers: Composition 30.30 13.61
New Haven Cheshire R10b, Roofers: Slate & Tile 40.00 17.75 + a
New Haven Cheshire R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New Haven Cheshire R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
New Haven Cheshire R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New Haven Cheshire R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New Haven Cheshire R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
74/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
New Haven Cheshire R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New Haven Cheshire R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New Haven Cheshire
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New Haven Cheshire R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New Haven Cheshire R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New Haven Cheshire
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New Haven Cheshire R3, Carpenter 16.78 1.60
New Haven Cheshire
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 38.50
28.61+3% of gross
wage
New Haven Cheshire R4a, Glazier 37.18 21.05 + a
New Haven Cheshire R7a, Painter: Brush/Roller 14.26 1.56
New Haven Cheshire R8a, Laborers: Common or General 10.66 1.63
New Haven Cheshire
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New Haven Cheshire R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.04 2.06
New Haven Derby R10b, Roofers: Slate & Tile 40.00 17.75 + a
New Haven Derby R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New Haven Derby R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
New Haven Derby R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New Haven Derby R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New Haven Derby R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New Haven Derby R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New Haven Derby R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New Haven Derby
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New Haven Derby R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New Haven Derby R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New Haven Derby
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
75/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitNew Haven Derby R3, Carpenter 16.78 1.60
New Haven Derby
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 38.50
28.61+3% of gross
wage
New Haven Derby R4a, Glazier 37.18 21.05 + a
New Haven Derby R7a, Painter: Brush/Roller 14.26 1.56
New Haven Derby R8a, Laborers: Common or General 10.66 1.63
New Haven Derby
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New Haven Derby R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.04 2.06
New Haven East Haven R10b, Roofers: Slate & Tile 40.00 17.75 + a
New Haven East Haven R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New Haven East Haven R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
New Haven East Haven R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New Haven East Haven R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New Haven East Haven R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New Haven East Haven R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New Haven East Haven R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New Haven East Haven
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New Haven East Haven R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New Haven East Haven R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New Haven East Haven
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New Haven East Haven R3, Carpenter 16.78 1.60
New Haven East Haven
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 38.50
28.61+3% of gross
wage
New Haven East Haven R4a, Glazier 37.18 21.05 + a
New Haven East Haven R7a, Painter: Brush/Roller 14.26 1.56
New Haven East Haven R8a, Laborers: Common or General 10.66 1.63
New Haven East Haven
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New Haven East Haven R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.04 2.06
76/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitNew Haven Guilford R10b, Roofers: Slate & Tile 40.00 17.75 + a
New Haven Guilford R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New Haven Guilford R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
New Haven Guilford R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New Haven Guilford R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New Haven Guilford R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New Haven Guilford R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New Haven Guilford R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New Haven Guilford
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New Haven Guilford R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New Haven Guilford R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New Haven Guilford
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New Haven Guilford R3, Carpenter 16.78 1.60
New Haven Guilford
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 38.50
28.61+3% of gross
wage
New Haven Guilford R4a, Glazier 37.18 21.05 + a
New Haven Guilford R7a, Painter: Brush/Roller 14.26 1.56
New Haven Guilford R8a, Laborers: Common or General 10.66 1.63
New Haven Guilford
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New Haven Guilford R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.04 2.06
New Haven Hamden R10b, Roofers: Slate & Tile 40.00 17.75 + a
New Haven Hamden R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New Haven Hamden R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
New Haven Hamden R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New Haven Hamden R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New Haven Hamden R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New Haven Hamden R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
77/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitNew Haven Hamden R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New Haven Hamden
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New Haven Hamden R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New Haven Hamden R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New Haven Hamden
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New Haven Hamden R2, Marble and Tile Setter/Finisher 18.18 3.74
New Haven Hamden
R21, Asbestos/Toxic Waste Removal Laborers (does not include removal from
mechanical system) 15.15 3.18
New Haven Hamden R22a, Hazardous Material Handler from Mechanical Systems 12.30 2.06
New Haven Hamden R23, Structural Steel/Ironworker/Ornamental/Reinforcing/Structural 32.40 23.58
New Haven Hamden R3, Carpenter 16.78 1.60
New Haven Hamden R3e, Carpenter: Ceramic Flooring 18.18 3.74
New Haven Hamden R3f, Carpenter: Wood/Resilient/Vinyl Flooring 16.78 1.60
New Haven Hamden R3g, Carpenter: Acoustic Ceiling Tile 16.78 1.60
New Haven Hamden
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 38.50
28.61+3% of gross
wage
New Haven Hamden R4a, Glazier 37.18 21.05 + a
New Haven Hamden R7a, Painter: Brush/Roller 14.26 1.56
New Haven Hamden R7h, Painter: Taper/Paperhanger 17.17 2.80
New Haven Hamden R7i, Painter: Drywall 18.18 3.74
New Haven Hamden R8a, Laborers: Common or General 10.66 1.63
New Haven Hamden
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New Haven Hamden R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.04 2.06
New Haven Madison R10b, Roofers: Slate & Tile 40.00 17.75 + a
New Haven Madison R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New Haven Madison R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
New Haven Madison R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New Haven Madison R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New Haven Madison R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
78/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
New Haven Madison R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New Haven Madison R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New Haven Madison
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New Haven Madison R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New Haven Madison R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New Haven Madison
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New Haven Madison R3, Carpenter 16.78 1.60
New Haven Madison
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 38.50
28.61+3% of gross
wage
New Haven Madison R4a, Glazier 37.18 21.05 + a
New Haven Madison R7a, Painter: Brush/Roller 14.26 1.56
New Haven Madison R8a, Laborers: Common or General 10.66 1.63
New Haven Madison
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New Haven Madison R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.04 2.06
New Haven Meriden R10a, Roofers: Composition 30.30 13.61
New Haven Meriden R10b, Roofers: Slate & Tile 40.00 17.75 + a
New Haven Meriden R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New Haven Meriden R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
New Haven Meriden R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New Haven Meriden R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New Haven Meriden R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New Haven Meriden R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New Haven Meriden R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New Haven Meriden
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New Haven Meriden R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New Haven Meriden R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
79/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
New Haven Meriden
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New Haven Meriden R3, Carpenter 16.78 1.60
New Haven Meriden
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 38.50
28.61+3% of gross
wage
New Haven Meriden R4a, Glazier 37.18 21.05 + a
New Haven Meriden R7a, Painter: Brush/Roller 14.26 1.56
New Haven Meriden R8a, Laborers: Common or General 10.66 1.63
New Haven Meriden
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New Haven Meriden R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.04 2.06
New Haven Middlebury R10b, Roofers: Slate & Tile 40.00 17.75 + a
New Haven Middlebury R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New Haven Middlebury R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
New Haven Middlebury R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New Haven Middlebury R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New Haven Middlebury R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New Haven Middlebury R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New Haven Middlebury R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New Haven Middlebury
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New Haven Middlebury R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New Haven Middlebury R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New Haven Middlebury
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New Haven Middlebury R3, Carpenter 16.78 1.60
New Haven Middlebury
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 39.62
27.25+3% of gross
wage
New Haven Middlebury R4a, Glazier 37.18 21.05 + a
New Haven Middlebury R7a, Painter: Brush/Roller 14.26 1.56
New Haven Middlebury R8a, Laborers: Common or General 10.66 1.63
80/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
New Haven Middlebury
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New Haven Middlebury R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.04 2.06
New Haven Milford R10b, Roofers: Slate & Tile 40.00 17.75 + a
New Haven Milford R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New Haven Milford R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
New Haven Milford R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New Haven Milford R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New Haven Milford R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New Haven Milford R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New Haven Milford R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New Haven Milford
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New Haven Milford R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New Haven Milford R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New Haven Milford
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New Haven Milford R3, Carpenter 16.78 1.60
New Haven Milford
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 39.62
27.25+3% of gross
wage
New Haven Milford R4a, Glazier 37.18 21.05 + a
New Haven Milford R7a, Painter: Brush/Roller 14.26 1.56
New Haven Milford R8a, Laborers: Common or General 10.66 1.63
New Haven Milford
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New Haven Milford R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.04 2.06
New Haven Naugatuck R10b, Roofers: Slate & Tile 40.00 17.75 + a
New Haven Naugatuck R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New Haven Naugatuck R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
New Haven Naugatuck R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New Haven Naugatuck R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
81/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitNew Haven Naugatuck R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New Haven Naugatuck R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New Haven Naugatuck R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New Haven Naugatuck
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New Haven Naugatuck R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New Haven Naugatuck R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New Haven Naugatuck
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New Haven Naugatuck R3, Carpenter 16.78 1.60
New Haven Naugatuck
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 39.62
27.25+3% of gross
wage
New Haven Naugatuck R4a, Glazier 37.18 21.05 + a
New Haven Naugatuck R7a, Painter: Brush/Roller 14.26 1.56
New Haven Naugatuck R8a, Laborers: Common or General 10.66 1.63
New Haven Naugatuck
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New Haven Naugatuck R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.04 2.06
New Haven New Haven R10b, Roofers: Slate & Tile 40.00 17.75 + a
New Haven New Haven R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New Haven New Haven R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
New Haven New Haven R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New Haven New Haven R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New Haven New Haven R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New Haven New Haven R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New Haven New Haven R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New Haven New Haven
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New Haven New Haven R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New Haven New Haven R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
82/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
New Haven New Haven
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New Haven New Haven R3, Carpenter 16.78 1.60
New Haven New Haven
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 38.50
28.61+3% of gross
wage
New Haven New Haven R4a, Glazier 37.18 21.05 + a
New Haven New Haven R7a, Painter: Brush/Roller 14.26 1.56
New Haven New Haven R8a, Laborers: Common or General 10.66 1.63
New Haven New Haven
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New Haven New Haven R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.04 2.06
New Haven North Branford R10b, Roofers: Slate & Tile 40.00 17.75 + a
New Haven North Branford R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New Haven North Branford R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
New Haven North Branford R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New Haven North Branford R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New Haven North Branford R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New Haven North Branford R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New Haven North Branford R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New Haven North Branford
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New Haven North Branford R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New Haven North Branford R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New Haven North Branford
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New Haven North Branford R3, Carpenter 16.78 1.60
New Haven North Branford
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 38.50
28.61+3% of gross
wage
New Haven North Branford R4a, Glazier 37.18 21.05 + a
New Haven North Branford R7a, Painter: Brush/Roller 14.26 1.56
New Haven North Branford R8a, Laborers: Common or General 10.66 1.63
83/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
New Haven North Branford
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New Haven North Branford R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.04 2.06
New Haven North Haven R10b, Roofers: Slate & Tile 40.00 17.75 + a
New Haven North Haven R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New Haven North Haven R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
New Haven North Haven R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New Haven North Haven R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New Haven North Haven R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New Haven North Haven R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New Haven North Haven R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New Haven North Haven
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New Haven North Haven R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New Haven North Haven R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New Haven North Haven
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New Haven North Haven R3, Carpenter 16.78 1.60
New Haven North Haven
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 38.50
28.61+3% of gross
wage
New Haven North Haven R4a, Glazier 37.18 21.05 + a
New Haven North Haven R7a, Painter: Brush/Roller 14.26 1.56
New Haven North Haven R8a, Laborers: Common or General 10.66 1.63
New Haven North Haven
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New Haven North Haven R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.04 2.06
New Haven Orange R10b, Roofers: Slate & Tile 40.00 17.75 + a
New Haven Orange R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New Haven Orange R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
New Haven Orange R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New Haven Orange R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
84/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitNew Haven Orange R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New Haven Orange R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New Haven Orange R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New Haven Orange
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New Haven Orange R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New Haven Orange R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New Haven Orange
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New Haven Orange R3, Carpenter 16.78 1.60
New Haven Orange
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 38.50
28.61+3% of gross
wage
New Haven Orange R4a, Glazier 37.18 21.05 + a
New Haven Orange R7a, Painter: Brush/Roller 14.26 1.56
New Haven Orange R8a, Laborers: Common or General 10.66 1.63
New Haven Orange
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New Haven Orange R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.04 2.06
New Haven Oxford R10b, Roofers: Slate & Tile 40.00 17.75 + a
New Haven Oxford R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New Haven Oxford R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
New Haven Oxford R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New Haven Oxford R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New Haven Oxford R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New Haven Oxford R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New Haven Oxford R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New Haven Oxford
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New Haven Oxford R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New Haven Oxford R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
85/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
New Haven Oxford
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New Haven Oxford R3, Carpenter 16.78 1.60
New Haven Oxford
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 39.62
27.25+3% of gross
wage
New Haven Oxford R4a, Glazier 37.18 21.05 + a
New Haven Oxford R7a, Painter: Brush/Roller 14.26 1.56
New Haven Oxford R8a, Laborers: Common or General 10.66 1.63
New Haven Oxford
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New Haven Oxford R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.04 2.06
New Haven Prospect R10b, Roofers: Slate & Tile 40.00 17.75 + a
New Haven Prospect R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New Haven Prospect R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
New Haven Prospect R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New Haven Prospect R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New Haven Prospect R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New Haven Prospect R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New Haven Prospect R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New Haven Prospect
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New Haven Prospect R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New Haven Prospect R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New Haven Prospect
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New Haven Prospect R3, Carpenter 16.78 1.60
New Haven Prospect
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 39.62
27.25+3% of gross
wage
New Haven Prospect R4a, Glazier 37.18 21.05 + a
New Haven Prospect R7a, Painter: Brush/Roller 14.26 1.56
New Haven Prospect R8a, Laborers: Common or General 10.66 1.63
86/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
New Haven Prospect
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New Haven Prospect R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.04 2.06
New Haven Seymour R10b, Roofers: Slate & Tile 40.00 17.75 + a
New Haven Seymour R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New Haven Seymour R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
New Haven Seymour R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New Haven Seymour R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New Haven Seymour R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New Haven Seymour R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New Haven Seymour R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New Haven Seymour
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New Haven Seymour R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New Haven Seymour R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New Haven Seymour
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New Haven Seymour R3, Carpenter 16.78 1.60
New Haven Seymour
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 39.62
27.25+3% of gross
wage
New Haven Seymour R4a, Glazier 37.18 21.05 + a
New Haven Seymour R7a, Painter: Brush/Roller 14.26 1.56
New Haven Seymour R8a, Laborers: Common or General 10.66 1.63
New Haven Seymour
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New Haven Seymour R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.04 2.06
New Haven Southbury R10b, Roofers: Slate & Tile 40.00 17.75 + a
New Haven Southbury R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New Haven Southbury R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
New Haven Southbury R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New Haven Southbury R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
87/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitNew Haven Southbury R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New Haven Southbury R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New Haven Southbury R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New Haven Southbury
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New Haven Southbury R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New Haven Southbury R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New Haven Southbury
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New Haven Southbury R3, Carpenter 16.78 1.60
New Haven Southbury
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 39.62
27.25+3% of gross
wage
New Haven Southbury R4a, Glazier 37.18 21.05 + a
New Haven Southbury R7a, Painter: Brush/Roller 14.26 1.56
New Haven Southbury R8a, Laborers: Common or General 10.66 1.63
New Haven Southbury
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New Haven Southbury R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.04 2.06
New Haven Wallingford R10a, Roofers: Composition 30.30 13.61
New Haven Wallingford R10b, Roofers: Slate & Tile 40.00 17.75 + a
New Haven Wallingford R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New Haven Wallingford R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
New Haven Wallingford R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New Haven Wallingford R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New Haven Wallingford R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New Haven Wallingford R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New Haven Wallingford R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New Haven Wallingford
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New Haven Wallingford R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New Haven Wallingford R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
88/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
New Haven Wallingford
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New Haven Wallingford R3, Carpenter 16.78 1.60
New Haven Wallingford
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 38.50
28.61+3% of gross
wage
New Haven Wallingford R4a, Glazier 37.18 21.05 + a
New Haven Wallingford R7a, Painter: Brush/Roller 14.26 1.56
New Haven Wallingford R8a, Laborers: Common or General 10.66 1.63
New Haven Wallingford
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New Haven Wallingford R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.04 2.06
New Haven Waterbury R10b, Roofers: Slate & Tile 40.00 17.75 + a
New Haven Waterbury R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New Haven Waterbury R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
New Haven Waterbury R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New Haven Waterbury R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New Haven Waterbury R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New Haven Waterbury R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New Haven Waterbury R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New Haven Waterbury
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New Haven Waterbury R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New Haven Waterbury R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New Haven Waterbury
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New Haven Waterbury R3, Carpenter 16.78 1.60
New Haven Waterbury
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 39.62
27.25+3% of gross
wage
New Haven Waterbury R4a, Glazier 37.18 21.05 + a
New Haven Waterbury R7a, Painter: Brush/Roller 14.26 1.56
New Haven Waterbury R8a, Laborers: Common or General 10.66 1.63
89/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
New Haven Waterbury
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New Haven Waterbury R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.04 2.06
New Haven West Haven R10b, Roofers: Slate & Tile 40.00 17.75 + a
New Haven West Haven R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New Haven West Haven R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
New Haven West Haven R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New Haven West Haven R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New Haven West Haven R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New Haven West Haven R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New Haven West Haven R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New Haven West Haven
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New Haven West Haven R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New Haven West Haven R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New Haven West Haven
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New Haven West Haven R3, Carpenter 16.78 1.60
New Haven West Haven
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 38.50
28.61+3% of gross
wage
New Haven West Haven R4a, Glazier 37.18 21.05 + a
New Haven West Haven R7a, Painter: Brush/Roller 14.26 1.56
New Haven West Haven R8a, Laborers: Common or General 10.66 1.63
New Haven West Haven
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New Haven West Haven R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.04 2.06
New Haven Wolcott R10a, Roofers: Composition 30.30 13.61
New Haven Wolcott R10b, Roofers: Slate & Tile 40.00 17.75 + a
New Haven Wolcott R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New Haven Wolcott R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
New Haven Wolcott R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
90/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitNew Haven Wolcott R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New Haven Wolcott R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New Haven Wolcott R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New Haven Wolcott R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New Haven Wolcott
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New Haven Wolcott R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New Haven Wolcott R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New Haven Wolcott
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New Haven Wolcott R3, Carpenter 16.78 1.60
New Haven Wolcott
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 39.62
27.25+3% of gross
wage
New Haven Wolcott R4a, Glazier 37.18 21.05 + a
New Haven Wolcott R7a, Painter: Brush/Roller 14.26 1.56
New Haven Wolcott R8a, Laborers: Common or General 10.66 1.63
New Haven Wolcott
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New Haven Wolcott R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.04 2.06
New Haven Woodbridge R10b, Roofers: Slate & Tile 40.00 17.75 + a
New Haven Woodbridge R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New Haven Woodbridge R13, Cement Masons/Concrete Finisher and Tile Setter 17.89
New Haven Woodbridge R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New Haven Woodbridge R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New Haven Woodbridge R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New Haven Woodbridge R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New Haven Woodbridge R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New Haven Woodbridge
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New Haven Woodbridge R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New Haven Woodbridge R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
91/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
New Haven Woodbridge
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New Haven Woodbridge R3, Carpenter 16.78 1.60
New Haven Woodbridge
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 38.50
28.61+3% of gross
wage
New Haven Woodbridge R4a, Glazier 37.18 21.05 + a
New Haven Woodbridge R7a, Painter: Brush/Roller 14.26 1.56
New Haven Woodbridge R8a, Laborers: Common or General 10.66 1.63
New Haven Woodbridge
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New Haven Woodbridge R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.04 2.06
New London Bozrah R10a, Roofers: Composition 37.00 20.57
New London Bozrah R10b, Roofers: Slate & Tile 37.50 20.57
New London Bozrah R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New London Bozrah R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
New London Bozrah R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
New London Bozrah R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New London Bozrah R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New London Bozrah R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New London Bozrah R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New London Bozrah R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New London Bozrah
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New London Bozrah R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New London Bozrah R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New London Bozrah R18j, Power Group Operator: Asphalt Paver 37.51 24.05 + a
New London Bozrah
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New London Bozrah R3a, Carpenter (Including Drywall Hanging) 15.50
New London Bozrah
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
New London Bozrah R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
92/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitNew London Bozrah R7c, Painter: Drywall Finisher/Taper 16.25 2.70
New London Bozrah R8a, Laborers: Common or General 13.23 1.63
New London Bozrah
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New London Bozrah
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
New London Colchester R10a, Roofers: Composition 37.00 20.57
New London Colchester R10b, Roofers: Slate & Tile 37.50 20.57
New London Colchester R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New London Colchester R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
New London Colchester R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
New London Colchester R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New London Colchester R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New London Colchester R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New London Colchester R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New London Colchester R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New London Colchester
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New London Colchester R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New London Colchester R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New London Colchester R18j, Power Group Operator: Asphalt Paver 37.51 24.05 + a
New London Colchester
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New London Colchester R3a, Carpenter (Including Drywall Hanging) 15.50
New London Colchester
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
New London Colchester R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
New London Colchester R7c, Painter: Drywall Finisher/Taper 16.25 2.70
New London Colchester R8a, Laborers: Common or General 13.23 1.63
New London Colchester
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
93/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
New London Colchester
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
New London East Lyme R10a, Roofers: Composition 37.00 20.57
New London East Lyme R10b, Roofers: Slate & Tile 37.50 20.57
New London East Lyme R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New London East Lyme R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
New London East Lyme R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
New London East Lyme R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New London East Lyme R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New London East Lyme R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New London East Lyme R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New London East Lyme R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New London East Lyme
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New London East Lyme R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New London East Lyme R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New London East Lyme R18j, Power Group Operator: Asphalt Paver 37.51 24.05 + a
New London East Lyme
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New London East Lyme R3a, Carpenter (Including Drywall Hanging) 15.50
New London East Lyme
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
New London East Lyme R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
New London East Lyme R7c, Painter: Drywall Finisher/Taper 16.25 2.70
New London East Lyme R8a, Laborers: Common or General 13.23 1.63
New London East Lyme
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New London East Lyme
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
New London Franklin R10a, Roofers: Composition 37.00 20.57
New London Franklin R10b, Roofers: Slate & Tile 37.50 20.57
New London Franklin R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
94/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitNew London Franklin R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
New London Franklin R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
New London Franklin R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New London Franklin R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New London Franklin R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New London Franklin R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New London Franklin R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New London Franklin
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New London Franklin R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New London Franklin R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New London Franklin R18j, Power Group Operator: Asphalt Paver 37.51 24.05 + a
New London Franklin
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New London Franklin R3a, Carpenter (Including Drywall Hanging) 15.50
New London Franklin
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
New London Franklin R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
New London Franklin R7c, Painter: Drywall Finisher/Taper 16.25 2.70
New London Franklin R8a, Laborers: Common or General 13.23 1.63
New London Franklin
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New London Franklin
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
New London Griswold R10a, Roofers: Composition 37.00 20.57
New London Griswold R10b, Roofers: Slate & Tile 37.50 20.57
New London Griswold R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New London Griswold R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
New London Griswold R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
New London Griswold R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New London Griswold R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
95/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitNew London Griswold R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New London Griswold R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New London Griswold R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New London Griswold
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New London Griswold R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New London Griswold R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New London Griswold R18j, Power Group Operator: Asphalt Paver 37.51 24.05 + a
New London Griswold
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New London Griswold R3a, Carpenter (Including Drywall Hanging) 15.50
New London Griswold
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
New London Griswold R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
New London Griswold R7c, Painter: Drywall Finisher/Taper 16.25 2.70
New London Griswold R8a, Laborers: Common or General 13.23 1.63
New London Griswold
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New London Griswold
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
New London Groton R10a, Roofers: Composition 37.00 20.57
New London Groton R10b, Roofers: Slate & Tile 37.50 20.57
New London Groton R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New London Groton R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
New London Groton R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
New London Groton R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New London Groton R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New London Groton R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New London Groton R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New London Groton R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
96/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
New London Groton
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New London Groton R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New London Groton R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New London Groton R18j, Power Group Operator: Asphalt Paver 37.51 24.05 + a
New London Groton
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New London Groton R3a, Carpenter (Including Drywall Hanging) 15.50
New London Groton
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
New London Groton R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
New London Groton R7c, Painter: Drywall Finisher/Taper 16.25 2.70
New London Groton R8a, Laborers: Common or General 13.23 1.63
New London Groton
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New London Groton
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
New London Lebanon R10a, Roofers: Composition 37.00 20.57
New London Lebanon R10b, Roofers: Slate & Tile 37.50 20.57
New London Lebanon R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New London Lebanon R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
New London Lebanon R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
New London Lebanon R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New London Lebanon R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New London Lebanon R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New London Lebanon R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New London Lebanon R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New London Lebanon
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New London Lebanon R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New London Lebanon R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New London Lebanon R18j, Power Group Operator: Asphalt Paver 37.51 24.05 + a
97/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
New London Lebanon
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New London Lebanon R3a, Carpenter (Including Drywall Hanging) 15.50
New London Lebanon
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
New London Lebanon R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
New London Lebanon R7c, Painter: Drywall Finisher/Taper 16.25 2.70
New London Lebanon R8a, Laborers: Common or General 13.23 1.63
New London Lebanon
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New London Lebanon
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
New London Ledyard R10a, Roofers: Composition 37.00 20.57
New London Ledyard R10b, Roofers: Slate & Tile 37.50 20.57
New London Ledyard R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New London Ledyard R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
New London Ledyard R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
New London Ledyard R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New London Ledyard R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New London Ledyard R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New London Ledyard R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New London Ledyard R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New London Ledyard
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New London Ledyard R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New London Ledyard R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New London Ledyard R18j, Power Group Operator: Asphalt Paver 37.51 24.05 + a
New London Ledyard
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New London Ledyard R3a, Carpenter (Including Drywall Hanging) 15.50
New London Ledyard
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
98/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitNew London Ledyard R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
New London Ledyard R7c, Painter: Drywall Finisher/Taper 16.25 2.70
New London Ledyard R8a, Laborers: Common or General 13.23 1.63
New London Ledyard
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New London Ledyard
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
New London Lisbon R10a, Roofers: Composition 37.00 20.57
New London Lisbon R10b, Roofers: Slate & Tile 37.50 20.57
New London Lisbon R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New London Lisbon R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
New London Lisbon R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
New London Lisbon R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New London Lisbon R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New London Lisbon R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New London Lisbon R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New London Lisbon R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New London Lisbon
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New London Lisbon R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New London Lisbon R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New London Lisbon R18j, Power Group Operator: Asphalt Paver 37.51 24.05 + a
New London Lisbon
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New London Lisbon R3a, Carpenter (Including Drywall Hanging) 15.50
New London Lisbon
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
New London Lisbon R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
New London Lisbon R7c, Painter: Drywall Finisher/Taper 16.25 2.70
New London Lisbon R8a, Laborers: Common or General 13.23 1.63
New London Lisbon
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
99/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
New London Lisbon
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
New London Lyme R10a, Roofers: Composition 37.00 20.57
New London Lyme R10b, Roofers: Slate & Tile 37.50 20.57
New London Lyme R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New London Lyme R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
New London Lyme R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
New London Lyme R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New London Lyme R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New London Lyme R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New London Lyme R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New London Lyme R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New London Lyme
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New London Lyme R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New London Lyme R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New London Lyme R18j, Power Group Operator: Asphalt Paver 37.51 24.05 + a
New London Lyme
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New London Lyme R3a, Carpenter (Including Drywall Hanging) 15.50
New London Lyme
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
New London Lyme R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
New London Lyme R7c, Painter: Drywall Finisher/Taper 16.25 2.70
New London Lyme R8a, Laborers: Common or General 13.23 1.63
New London Lyme
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New London Lyme
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
New London Montville R10a, Roofers: Composition 37.00 20.57
New London Montville R10b, Roofers: Slate & Tile 37.50 20.57
New London Montville R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
100/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitNew London Montville R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
New London Montville R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
New London Montville R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New London Montville R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New London Montville R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New London Montville R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New London Montville R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New London Montville
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New London Montville R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New London Montville R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New London Montville R18j, Power Group Operator: Asphalt Paver 37.51 24.05 + a
New London Montville
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New London Montville R3a, Carpenter (Including Drywall Hanging) 15.50
New London Montville
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
New London Montville R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
New London Montville R7c, Painter: Drywall Finisher/Taper 16.25 2.70
New London Montville R8a, Laborers: Common or General 13.23 1.63
New London Montville
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New London Montville
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
New London New London R10a, Roofers: Composition 37.00 20.57
New London New London R10b, Roofers: Slate & Tile 37.50 20.57
New London New London R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New London New London R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
New London New London R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
New London New London R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New London New London R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
101/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitNew London New London R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New London New London R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New London New London R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New London New London
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New London New London R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New London New London R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New London New London R18j, Power Group Operator: Asphalt Paver 37.51 24.05 + a
New London New London
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New London New London R3a, Carpenter (Including Drywall Hanging) 15.50
New London New London
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
New London New London R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
New London New London R7c, Painter: Drywall Finisher/Taper 16.25 2.70
New London New London R8a, Laborers: Common or General 13.23 1.63
New London New London
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New London New London
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
New London North StoningtonR10a, Roofers: Composition 37.00 20.57
New London North StoningtonR10b, Roofers: Slate & Tile 37.50 20.57
New London North StoningtonR11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New London North StoningtonR13, Cement Masons/Concrete Finisher and Tile Setter 21.22
New London North StoningtonR15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
New London North StoningtonR18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New London North StoningtonR18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New London North StoningtonR18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New London North StoningtonR18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New London North StoningtonR18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
102/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
New London North Stonington
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New London North StoningtonR18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New London North StoningtonR18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New London North StoningtonR18j, Power Group Operator: Asphalt Paver 37.51 24.05 + a
New London North Stonington
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New London North StoningtonR3a, Carpenter (Including Drywall Hanging) 15.50
New London North Stonington
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
New London North StoningtonR7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
New London North StoningtonR7c, Painter: Drywall Finisher/Taper 16.25 2.70
New London North StoningtonR8a, Laborers: Common or General 13.23 1.63
New London North Stonington
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New London North Stonington
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
New London Norwich R10a, Roofers: Composition 37.00 20.57
New London Norwich R10b, Roofers: Slate & Tile 37.50 20.57
New London Norwich R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New London Norwich R12a, Truck Driver - 3 Axle 13.69 2.05
New London Norwich R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
New London Norwich R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
New London Norwich R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New London Norwich R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New London Norwich R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New London Norwich R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New London Norwich R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New London Norwich
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New London Norwich R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New London Norwich R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
103/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitNew London Norwich R18j, Power Group Operator: Asphalt Paver 37.51 24.05 + a
New London Norwich
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New London Norwich R3a, Carpenter (Including Drywall Hanging) 15.50
New London Norwich
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
New London Norwich R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
New London Norwich R7c, Painter: Drywall Finisher/Taper 16.25 2.70
New London Norwich R8a, Laborers: Common or General 13.23 1.63
New London Norwich
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New London Norwich
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
New London Old Lyme R10a, Roofers: Composition 37.00 20.57
New London Old Lyme R10b, Roofers: Slate & Tile 37.50 20.57
New London Old Lyme R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New London Old Lyme R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
New London Old Lyme R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
New London Old Lyme R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New London Old Lyme R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New London Old Lyme R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New London Old Lyme R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New London Old Lyme R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New London Old Lyme
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New London Old Lyme R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New London Old Lyme R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New London Old Lyme R18j, Power Group Operator: Asphalt Paver 37.51 24.05 + a
New London Old Lyme
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New London Old Lyme R3a, Carpenter (Including Drywall Hanging) 15.50
104/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
New London Old Lyme
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
New London Old Lyme R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
New London Old Lyme R8a, Laborers: Common or General 13.23 1.63
New London Old Lyme
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New London Old Lyme
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
New London Preston R10a, Roofers: Composition 37.00 20.57
New London Preston R10b, Roofers: Slate & Tile 37.50 20.57
New London Preston R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New London Preston R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
New London Preston R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
New London Preston R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New London Preston R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New London Preston R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New London Preston R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New London Preston R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New London Preston
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New London Preston R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New London Preston R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New London Preston R18j, Power Group Operator: Asphalt Paver 37.51 24.05 + a
New London Preston
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New London Preston R3a, Carpenter (Including Drywall Hanging) 15.50
New London Preston
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
New London Preston R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
New London Preston R7c, Painter: Drywall Finisher/Taper 16.25 2.70
New London Preston R8a, Laborers: Common or General 13.23 1.63
105/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
New London Preston
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New London Preston
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
New London Salem R10a, Roofers: Composition 37.00 20.57
New London Salem R10b, Roofers: Slate & Tile 37.50 20.57
New London Salem R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New London Salem R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
New London Salem R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
New London Salem R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New London Salem R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New London Salem R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New London Salem R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New London Salem R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New London Salem
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New London Salem R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New London Salem R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New London Salem R18j, Power Group Operator: Asphalt Paver 37.51 24.05 + a
New London Salem
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New London Salem R3a, Carpenter (Including Drywall Hanging) 15.50
New London Salem
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
New London Salem R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
New London Salem R7c, Painter: Drywall Finisher/Taper 16.25 2.70
New London Salem R8a, Laborers: Common or General 13.23 1.63
New London Salem
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New London Salem
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
New London Sprague R10a, Roofers: Composition 37.00 20.57
106/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitNew London Sprague R10b, Roofers: Slate & Tile 37.50 20.57
New London Sprague R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New London Sprague R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
New London Sprague R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
New London Sprague R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New London Sprague R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New London Sprague R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New London Sprague R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New London Sprague R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New London Sprague
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New London Sprague R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New London Sprague R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New London Sprague R18j, Power Group Operator: Asphalt Paver 37.51 24.05 + a
New London Sprague
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New London Sprague R3a, Carpenter (Including Drywall Hanging) 15.50
New London Sprague
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
New London Sprague R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
New London Sprague R7c, Painter: Drywall Finisher/Taper 16.25 2.70
New London Sprague R8a, Laborers: Common or General 13.23 1.63
New London Sprague
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New London Sprague
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
New London Stonington R10a, Roofers: Composition 37.00 20.57
New London Stonington R10b, Roofers: Slate & Tile 37.50 20.57
New London Stonington R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New London Stonington R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
New London Stonington R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
107/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
New London Stonington R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New London Stonington R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New London Stonington R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New London Stonington R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New London Stonington R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New London Stonington
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New London Stonington R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New London Stonington R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New London Stonington R18j, Power Group Operator: Asphalt Paver 37.51 24.05 + a
New London Stonington
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New London Stonington R3a, Carpenter (Including Drywall Hanging) 15.50
New London Stonington
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
New London Stonington R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
New London Stonington R7c, Painter: Drywall Finisher/Taper 16.25 2.70
New London Stonington R8a, Laborers: Common or General 13.23 1.63
New London Stonington
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New London Stonington
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
New London Voluntown R10a, Roofers: Composition 37.00 20.57
New London Voluntown R10b, Roofers: Slate & Tile 37.50 20.57
New London Voluntown R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New London Voluntown R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
New London Voluntown R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
New London Voluntown R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New London Voluntown R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New London Voluntown R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
108/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
New London Voluntown R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New London Voluntown R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New London Voluntown
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
New London Voluntown R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New London Voluntown R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New London Voluntown R18j, Power Group Operator: Asphalt Paver 37.51 24.05 + a
New London Voluntown
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New London Voluntown R3a, Carpenter (Including Drywall Hanging) 15.50
New London Voluntown
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
New London Voluntown R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
New London Voluntown R7c, Painter: Drywall Finisher/Taper 16.25 2.70
New London Voluntown R8a, Laborers: Common or General 13.23 1.63
New London Voluntown
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New London Voluntown
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
New London Waterford R10a, Roofers: Composition 37.00 20.57
New London Waterford R10b, Roofers: Slate & Tile 37.50 20.57
New London Waterford R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
New London Waterford R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
New London Waterford R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
New London Waterford R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
New London Waterford R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
New London Waterford R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
New London Waterford R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
New London Waterford R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
New London Waterford
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
109/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitNew London Waterford R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
New London Waterford R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
New London Waterford R18j, Power Group Operator: Asphalt Paver 37.51 24.05 + a
New London Waterford
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
New London Waterford R3a, Carpenter (Including Drywall Hanging) 15.50
New London Waterford
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
New London Waterford R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 17.10 1.56
New London Waterford R7c, Painter: Drywall Finisher/Taper 16.25 2.70
New London Waterford R8a, Laborers: Common or General 13.23 1.63
New London Waterford
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
New London Waterford
R9b, Plumbers - (Including HVAC Pipe Installation) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 16.67 2.63
Tolland Andover R10a, Roofers: Composition 37.00 20.57
Tolland Andover R10b, Roofers: Slate & Tile 37.50 20.57
Tolland Andover R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Tolland Andover R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Tolland Andover R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Tolland Andover R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Tolland Andover R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Tolland Andover R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Tolland Andover R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Tolland Andover R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Tolland Andover
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Tolland Andover R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Tolland Andover R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Tolland Andover
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Tolland Andover R3a, Carpenter (Including Drywall Hanging) 24.53 1.60
110/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Tolland Andover
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Tolland Andover R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 18.19 1.56
Tolland Andover R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Tolland Andover R8a, Laborers: Common or General 16.67 1.63
Tolland Andover
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Tolland Andover R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Tolland Bolton R10a, Roofers: Composition 37.00 20.57
Tolland Bolton R10b, Roofers: Slate & Tile 37.50 20.57
Tolland Bolton R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Tolland Bolton R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Tolland Bolton R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Tolland Bolton R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Tolland Bolton R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Tolland Bolton R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Tolland Bolton R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Tolland Bolton R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Tolland Bolton
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Tolland Bolton R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Tolland Bolton R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Tolland Bolton
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Tolland Bolton R3a, Carpenter (Including Drywall Hanging) 24.53 1.60
Tolland Bolton
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Tolland Bolton R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 18.19 1.56
Tolland Bolton R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Tolland Bolton R8a, Laborers: Common or General 16.67 1.63
Tolland Bolton
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
111/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitTolland Bolton R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Tolland Columbia R10a, Roofers: Composition 37.00 20.57
Tolland Columbia R10b, Roofers: Slate & Tile 37.50 20.57
Tolland Columbia R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Tolland Columbia R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Tolland Columbia R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Tolland Columbia R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Tolland Columbia R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Tolland Columbia R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Tolland Columbia R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Tolland Columbia R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Tolland Columbia
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Tolland Columbia R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Tolland Columbia R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Tolland Columbia
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Tolland Columbia R3a, Carpenter (Including Drywall Hanging) 24.53 1.60
Tolland Columbia
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Tolland Columbia R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 18.19 1.56
Tolland Columbia R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Tolland Columbia R8a, Laborers: Common or General 16.67 1.63
Tolland Columbia
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Tolland Columbia R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Tolland Coventry R10a, Roofers: Composition 37.00 20.57
Tolland Coventry R10b, Roofers: Slate & Tile 37.50 20.57
Tolland Coventry R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Tolland Coventry R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Tolland Coventry R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
112/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Tolland Coventry R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Tolland Coventry R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Tolland Coventry R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Tolland Coventry R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Tolland Coventry R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Tolland Coventry
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Tolland Coventry R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Tolland Coventry R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Tolland Coventry
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Tolland Coventry R3a, Carpenter (Including Drywall Hanging) 24.53 1.60
Tolland Coventry
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Tolland Coventry R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 18.19 1.56
Tolland Coventry R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Tolland Coventry R8a, Laborers: Common or General 16.67 1.63
Tolland Coventry
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Tolland Coventry R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Tolland Ellington R10a, Roofers: Composition 37.00 20.57
Tolland Ellington R10b, Roofers: Slate & Tile 37.50 20.57
Tolland Ellington R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Tolland Ellington R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Tolland Ellington R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Tolland Ellington R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Tolland Ellington R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Tolland Ellington R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Tolland Ellington R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Tolland Ellington R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
113/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Tolland Ellington
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Tolland Ellington R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Tolland Ellington R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Tolland Ellington
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Tolland Ellington R3a, Carpenter (Including Drywall Hanging) 24.53 1.60
Tolland Ellington
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Tolland Ellington R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 18.19 1.56
Tolland Ellington R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Tolland Ellington R8a, Laborers: Common or General 16.67 1.63
Tolland Ellington
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Tolland Ellington R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Tolland Hebron R10a, Roofers: Composition 37.00 20.57
Tolland Hebron R10b, Roofers: Slate & Tile 37.50 20.57
Tolland Hebron R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Tolland Hebron R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Tolland Hebron R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Tolland Hebron R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Tolland Hebron R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Tolland Hebron R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Tolland Hebron R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Tolland Hebron R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Tolland Hebron
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Tolland Hebron R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Tolland Hebron R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Tolland Hebron
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Tolland Hebron R3a, Carpenter (Including Drywall Hanging) 24.53 1.60
114/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Tolland Hebron
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Tolland Hebron R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 18.19 1.56
Tolland Hebron R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Tolland Hebron R8a, Laborers: Common or General 16.67 1.63
Tolland Hebron
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Tolland Hebron R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Tolland Mansfield R10a, Roofers: Composition 37.00 20.57
Tolland Mansfield R10b, Roofers: Slate & Tile 37.50 20.57
Tolland Mansfield R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Tolland Mansfield R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Tolland Mansfield R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Tolland Mansfield R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Tolland Mansfield R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Tolland Mansfield R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Tolland Mansfield R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Tolland Mansfield R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Tolland Mansfield
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Tolland Mansfield R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Tolland Mansfield R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Tolland Mansfield
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Tolland Mansfield R3a, Carpenter (Including Drywall Hanging) 24.53 1.60
Tolland Mansfield
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Tolland Mansfield R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 18.19 1.56
Tolland Mansfield R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Tolland Mansfield R8a, Laborers: Common or General 16.67 1.63
Tolland Mansfield
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
115/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitTolland Mansfield R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Tolland Somers R10a, Roofers: Composition 37.00 20.57
Tolland Somers R10b, Roofers: Slate & Tile 37.50 20.57
Tolland Somers R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Tolland Somers R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Tolland Somers R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Tolland Somers R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Tolland Somers R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Tolland Somers R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Tolland Somers R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Tolland Somers R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Tolland Somers
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Tolland Somers R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Tolland Somers R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Tolland Somers
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Tolland Somers R3a, Carpenter (Including Drywall Hanging) 24.53 1.60
Tolland Somers
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Tolland Somers R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 18.19 1.56
Tolland Somers R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Tolland Somers R8a, Laborers: Common or General 16.67 1.63
Tolland Somers
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Tolland Somers R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Tolland Stafford R10a, Roofers: Composition 37.00 20.57
Tolland Stafford R10b, Roofers: Slate & Tile 37.50 20.57
Tolland Stafford R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Tolland Stafford R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Tolland Stafford R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
116/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Tolland Stafford R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Tolland Stafford R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Tolland Stafford R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Tolland Stafford R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Tolland Stafford R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Tolland Stafford
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Tolland Stafford R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Tolland Stafford R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Tolland Stafford
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Tolland Stafford R3a, Carpenter (Including Drywall Hanging) 24.53 1.60
Tolland Stafford
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Tolland Stafford R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 18.19 1.56
Tolland Stafford R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Tolland Stafford R8a, Laborers: Common or General 16.67 1.63
Tolland Stafford
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Tolland Stafford R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Tolland Tolland R10a, Roofers: Composition 37.00 20.57
Tolland Tolland R10b, Roofers: Slate & Tile 37.50 20.57
Tolland Tolland R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Tolland Tolland R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Tolland Tolland R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Tolland Tolland R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Tolland Tolland R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Tolland Tolland R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Tolland Tolland R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Tolland Tolland R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
117/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Tolland Tolland
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Tolland Tolland R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Tolland Tolland R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Tolland Tolland
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Tolland Tolland R3a, Carpenter (Including Drywall Hanging) 24.53 1.60
Tolland Tolland
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Tolland Tolland R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 18.19 1.56
Tolland Tolland R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Tolland Tolland R8a, Laborers: Common or General 16.67 1.63
Tolland Tolland
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Tolland Tolland R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Tolland Union R10a, Roofers: Composition 37.00 20.57
Tolland Union R10b, Roofers: Slate & Tile 37.50 20.57
Tolland Union R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Tolland Union R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Tolland Union R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Tolland Union R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Tolland Union R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Tolland Union R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Tolland Union R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Tolland Union R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Tolland Union
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Tolland Union R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Tolland Union R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Tolland Union
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Tolland Union R3a, Carpenter (Including Drywall Hanging) 24.53 1.60
118/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Tolland Union
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Tolland Union R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 18.19 1.56
Tolland Union R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Tolland Union R8a, Laborers: Common or General 16.67 1.63
Tolland Union
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Tolland Union R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Tolland Vernon R10a, Roofers: Composition 37.00 20.57
Tolland Vernon R10b, Roofers: Slate & Tile 37.50 20.57
Tolland Vernon R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Tolland Vernon R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Tolland Vernon R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Tolland Vernon R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Tolland Vernon R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Tolland Vernon R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Tolland Vernon R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Tolland Vernon R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Tolland Vernon
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Tolland Vernon R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Tolland Vernon R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Tolland Vernon
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Tolland Vernon R3a, Carpenter (Including Drywall Hanging) 24.53 1.60
Tolland Vernon
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Tolland Vernon R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 18.19 1.56
Tolland Vernon R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Tolland Vernon R8a, Laborers: Common or General 16.67 1.63
Tolland Vernon
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
119/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitTolland Vernon R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Tolland Willington R10a, Roofers: Composition 37.00 20.57
Tolland Willington R10b, Roofers: Slate & Tile 37.50 20.57
Tolland Willington R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 43.92 15.84 + a
Tolland Willington R13, Cement Masons/Concrete Finisher and Tile Setter 21.22
Tolland Willington R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 53.37 33.705+a+b
Tolland Willington R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Tolland Willington R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Tolland Willington R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Tolland Willington R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Tolland Willington R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Tolland Willington
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Tolland Willington R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Tolland Willington R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Tolland Willington
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 37.98 38.31
Tolland Willington R3a, Carpenter (Including Drywall Hanging) 24.53 1.60
Tolland Willington
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 19.99 2.00
Tolland Willington R7b, Painter: Brush and Roller, Excludes Drywall Finishing/Taping 18.19 1.56
Tolland Willington R7c, Painter: Drywall Finisher/Taper 16.25 2.70
Tolland Willington R8a, Laborers: Common or General 16.67 1.63
Tolland Willington
R8b, Laborers: Landscape, Asbestos/Toxic Waste Removal, Lead Removal and
Encapsulation 14.96 4.63
Tolland Willington R9c, Plumber/Pipefitter (Including HVAC Pipe Installation) 16.67 2.63
Windham Ashford R1, Bricklayers 21.22
Windham Ashford R10c, Roofers 17.21 2.92
Windham Ashford R10d, Roofers: Composition (asphalt shingles) 31.10 14.46
Windham Ashford R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 38.35 16.25 + a
Windham Ashford R12a, Truck Driver - 3 Axle 13.69 2.05
Windham Ashford R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
120/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitWindham Ashford R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 47.15 26.785+a+b
Windham Ashford R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Windham Ashford R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Windham Ashford R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Windham Ashford R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Windham Ashford R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Windham Ashford
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Windham Ashford R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Windham Ashford R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Windham Ashford
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 31.57 25.92
Windham Ashford R20, HVAC Mechanics 11.00 1.49
Windham Ashford
R22, Hazardous Material Handler: Includes preparation, wetting, stripping,
removal, scrapping, vacuuming, bagging and disposing of all insulation
materials, whether they contain asbestos or not, from mechanical systems. 11.43 1.79
Windham Ashford R3, Carpenter 15.17 3.56
Windham Ashford R3h, Carpenter: Rough and Finish 15.50
Windham Ashford
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Windham Ashford R7g, Painter: (Excluding Drywall Finishing) 8.96
Windham Ashford R8a, Laborers: Common or General 13.17 2.89
Windham Ashford
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Windham Brooklyn R1, Bricklayers 21.22
Windham Brooklyn R10d, Roofers: Composition (asphalt shingles) 31.10 14.46
Windham Brooklyn R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 38.35 16.25 + a
Windham Brooklyn R12a, Truck Driver - 3 Axle 13.69 2.05
Windham Brooklyn R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Windham Brooklyn R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 47.15 26.785+a+b
121/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Windham Brooklyn R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Windham Brooklyn R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Windham Brooklyn R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Windham Brooklyn R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Windham Brooklyn R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Windham Brooklyn
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Windham Brooklyn R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Windham Brooklyn R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Windham Brooklyn
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 31.57 25.92
Windham Brooklyn R20, HVAC Mechanics 11.00 1.49
Windham Brooklyn
R22, Hazardous Material Handler: Includes preparation, wetting, stripping,
removal, scrapping, vacuuming, bagging and disposing of all insulation
materials, whether they contain asbestos or not, from mechanical systems. 11.43 1.79
Windham Brooklyn R3h, Carpenter: Rough and Finish 15.50
Windham Brooklyn
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Windham Brooklyn R7g, Painter: (Excluding Drywall Finishing) 8.96
Windham Brooklyn R8a, Laborers: Common or General 13.17 2.89
Windham Brooklyn
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Windham Canterbury R1, Bricklayers 21.22
Windham Canterbury R10d, Roofers: Composition (asphalt shingles) 31.10 14.46
Windham Canterbury R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 38.35 16.25 + a
Windham Canterbury R12a, Truck Driver - 3 Axle 13.69 2.05
Windham Canterbury R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Windham Canterbury R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 47.15 26.785+a+b
Windham Canterbury R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Windham Canterbury R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
122/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitWindham Canterbury R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Windham Canterbury R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Windham Canterbury R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Windham Canterbury
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Windham Canterbury R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Windham Canterbury R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Windham Canterbury
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 31.57 25.92
Windham Canterbury R20, HVAC Mechanics 11.00 1.49
Windham Canterbury
R22, Hazardous Material Handler: Includes preparation, wetting, stripping,
removal, scrapping, vacuuming, bagging and disposing of all insulation
materials, whether they contain asbestos or not, from mechanical systems. 11.43 1.79
Windham Canterbury R3h, Carpenter: Rough and Finish 15.50
Windham Canterbury
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Windham Canterbury R7g, Painter: (Excluding Drywall Finishing) 8.96
Windham Canterbury R8a, Laborers: Common or General 13.17 2.89
Windham Canterbury
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Windham Chaplin R1, Bricklayers 21.22
Windham Chaplin R10d, Roofers: Composition (asphalt shingles) 31.10 14.46
Windham Chaplin R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 38.35 16.25 + a
Windham Chaplin R12a, Truck Driver - 3 Axle 13.69 2.05
Windham Chaplin R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Windham Chaplin R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 47.15 26.785+a+b
Windham Chaplin R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Windham Chaplin R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Windham Chaplin R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Windham Chaplin R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
123/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitWindham Chaplin R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Windham Chaplin
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Windham Chaplin R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Windham Chaplin R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Windham Chaplin
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 31.57 25.92
Windham Chaplin R20, HVAC Mechanics 11.00 1.49
Windham Chaplin
R22, Hazardous Material Handler: Includes preparation, wetting, stripping,
removal, scrapping, vacuuming, bagging and disposing of all insulation
materials, whether they contain asbestos or not, from mechanical systems. 11.43 1.79
Windham Chaplin R3h, Carpenter: Rough and Finish 15.50
Windham Chaplin
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Windham Chaplin R7g, Painter: (Excluding Drywall Finishing) 8.96
Windham Chaplin R8a, Laborers: Common or General 13.17 2.89
Windham Chaplin
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Windham Eastford R1, Bricklayers 21.22
Windham Eastford R10d, Roofers: Composition (asphalt shingles) 31.10 14.46
Windham Eastford R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 38.35 16.25 + a
Windham Eastford R12a, Truck Driver - 3 Axle 13.69 2.05
Windham Eastford R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Windham Eastford R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 47.15 26.785+a+b
Windham Eastford R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Windham Eastford R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Windham Eastford R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Windham Eastford R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Windham Eastford R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Windham Eastford
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
124/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly BenefitWindham Eastford R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Windham Eastford R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Windham Eastford
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 31.57 25.92
Windham Eastford R20, HVAC Mechanics 11.00 1.49
Windham Eastford
R22, Hazardous Material Handler: Includes preparation, wetting, stripping,
removal, scrapping, vacuuming, bagging and disposing of all insulation
materials, whether they contain asbestos or not, from mechanical systems. 11.43 1.79
Windham Eastford R3h, Carpenter: Rough and Finish 15.50
Windham Eastford
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Windham Eastford R7g, Painter: (Excluding Drywall Finishing) 8.96
Windham Eastford R8a, Laborers: Common or General 13.17 2.89
Windham Eastford
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Windham Hampton R1, Bricklayers 21.22
Windham Hampton R10d, Roofers: Composition (asphalt shingles) 31.10 14.46
Windham Hampton R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 38.35 16.25 + a
Windham Hampton R12a, Truck Driver - 3 Axle 13.69 2.05
Windham Hampton R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Windham Hampton R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 47.15 26.785+a+b
Windham Hampton R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Windham Hampton R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Windham Hampton R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Windham Hampton R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Windham Hampton R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Windham Hampton
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Windham Hampton R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Windham Hampton R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
125/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Windham Hampton
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 31.57 25.92
Windham Hampton R20, HVAC Mechanics 11.00 1.49
Windham Hampton
R22, Hazardous Material Handler: Includes preparation, wetting, stripping,
removal, scrapping, vacuuming, bagging and disposing of all insulation
materials, whether they contain asbestos or not, from mechanical systems. 11.43 1.79
Windham Hampton R3h, Carpenter: Rough and Finish 15.50
Windham Hampton
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Windham Hampton R7g, Painter: (Excluding Drywall Finishing) 8.96
Windham Hampton R8a, Laborers: Common or General 13.17 2.89
Windham Hampton
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Windham Killingly R1, Bricklayers 21.22
Windham Killingly R10d, Roofers: Composition (asphalt shingles) 31.10 14.46
Windham Killingly R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 38.35 16.25 + a
Windham Killingly R12a, Truck Driver - 3 Axle 13.69 2.05
Windham Killingly R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Windham Killingly R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 47.15 26.785+a+b
Windham Killingly R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Windham Killingly R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Windham Killingly R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Windham Killingly R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Windham Killingly R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Windham Killingly
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Windham Killingly R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Windham Killingly R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Windham Killingly
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 31.57 25.92
Windham Killingly R20, HVAC Mechanics 11.00 1.49
126/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Windham Killingly
R22, Hazardous Material Handler: Includes preparation, wetting, stripping,
removal, scrapping, vacuuming, bagging and disposing of all insulation
materials, whether they contain asbestos or not, from mechanical systems. 11.43 1.79
Windham Killingly R3h, Carpenter: Rough and Finish 15.50
Windham Killingly
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Windham Killingly R7g, Painter: (Excluding Drywall Finishing) 8.96
Windham Killingly R8a, Laborers: Common or General 13.17 2.89
Windham Killingly
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Windham Plainfield R1, Bricklayers 21.22
Windham Plainfield R10d, Roofers: Composition (asphalt shingles) 31.10 14.46
Windham Plainfield R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 38.35 16.25 + a
Windham Plainfield R12a, Truck Driver - 3 Axle 13.69 2.05
Windham Plainfield R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Windham Plainfield R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 47.15 26.785+a+b
Windham Plainfield R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Windham Plainfield R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Windham Plainfield R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Windham Plainfield R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Windham Plainfield R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Windham Plainfield
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Windham Plainfield R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Windham Plainfield R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Windham Plainfield
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 31.57 25.92
Windham Plainfield R20, HVAC Mechanics 11.00 1.49
127/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Windham Plainfield
R22, Hazardous Material Handler: Includes preparation, wetting, stripping,
removal, scrapping, vacuuming, bagging and disposing of all insulation
materials, whether they contain asbestos or not, from mechanical systems. 11.43 1.79
Windham Plainfield R3h, Carpenter: Rough and Finish 15.50
Windham Plainfield
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Windham Plainfield R7g, Painter: (Excluding Drywall Finishing) 8.96
Windham Plainfield R8a, Laborers: Common or General 13.17 2.89
Windham Plainfield
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Windham Pomfret R1, Bricklayers 21.22
Windham Pomfret R10d, Roofers: Composition (asphalt shingles) 31.10 14.46
Windham Pomfret R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 38.35 16.25 + a
Windham Pomfret R12a, Truck Driver - 3 Axle 13.69 2.05
Windham Pomfret R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Windham Pomfret R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 47.15 26.785+a+b
Windham Pomfret R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Windham Pomfret R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Windham Pomfret R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Windham Pomfret R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Windham Pomfret R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Windham Pomfret
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Windham Pomfret R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Windham Pomfret R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Windham Pomfret
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 31.57 25.92
Windham Pomfret R20, HVAC Mechanics 11.00 1.49
128/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Windham Pomfret
R22, Hazardous Material Handler: Includes preparation, wetting, stripping,
removal, scrapping, vacuuming, bagging and disposing of all insulation
materials, whether they contain asbestos or not, from mechanical systems. 11.43 1.79
Windham Pomfret R3h, Carpenter: Rough and Finish 15.50
Windham Pomfret
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Windham Pomfret R7g, Painter: (Excluding Drywall Finishing) 8.96
Windham Pomfret R8a, Laborers: Common or General 13.17 2.89
Windham Pomfret
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Windham Putnam R1, Bricklayers 21.22
Windham Putnam R10d, Roofers: Composition (asphalt shingles) 31.10 14.46
Windham Putnam R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 38.35 16.25 + a
Windham Putnam R12a, Truck Driver - 3 Axle 13.69 2.05
Windham Putnam R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Windham Putnam R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 47.15 26.785+a+b
Windham Putnam R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Windham Putnam R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Windham Putnam R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Windham Putnam R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Windham Putnam R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Windham Putnam
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Windham Putnam R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Windham Putnam R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Windham Putnam
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 31.57 25.92
Windham Putnam R20, HVAC Mechanics 11.00 1.49
129/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Windham Putnam
R22, Hazardous Material Handler: Includes preparation, wetting, stripping,
removal, scrapping, vacuuming, bagging and disposing of all insulation
materials, whether they contain asbestos or not, from mechanical systems. 11.43 1.79
Windham Putnam R3h, Carpenter: Rough and Finish 15.50
Windham Putnam
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Windham Putnam R7g, Painter: (Excluding Drywall Finishing) 8.96
Windham Putnam R8a, Laborers: Common or General 13.17 2.89
Windham Putnam
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Windham Scotland R1, Bricklayers 21.22
Windham Scotland R10d, Roofers: Composition (asphalt shingles) 31.10 14.46
Windham Scotland R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 38.35 16.25 + a
Windham Scotland R12a, Truck Driver - 3 Axle 13.69 2.05
Windham Scotland R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Windham Scotland R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 47.15 26.785+a+b
Windham Scotland R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Windham Scotland R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Windham Scotland R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Windham Scotland R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Windham Scotland R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Windham Scotland
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Windham Scotland R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Windham Scotland R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Windham Scotland
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 31.57 25.92
Windham Scotland R20, HVAC Mechanics 11.00 1.49
130/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Windham Scotland
R22, Hazardous Material Handler: Includes preparation, wetting, stripping,
removal, scrapping, vacuuming, bagging and disposing of all insulation
materials, whether they contain asbestos or not, from mechanical systems. 11.43 1.79
Windham Scotland R3h, Carpenter: Rough and Finish 15.50
Windham Scotland
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Windham Scotland R7g, Painter: (Excluding Drywall Finishing) 8.96
Windham Scotland R8a, Laborers: Common or General 13.17 2.89
Windham Scotland
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Windham Sterling R1, Bricklayers 21.22
Windham Sterling R10d, Roofers: Composition (asphalt shingles) 31.10 14.46
Windham Sterling R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 38.35 16.25 + a
Windham Sterling R12a, Truck Driver - 3 Axle 13.69 2.05
Windham Sterling R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Windham Sterling R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 47.15 26.785+a+b
Windham Sterling R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Windham Sterling R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Windham Sterling R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Windham Sterling R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Windham Sterling R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Windham Sterling
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Windham Sterling R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Windham Sterling R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Windham Sterling
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 31.57 25.92
Windham Sterling R20, HVAC Mechanics 11.00 1.49
131/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Windham Sterling
R22, Hazardous Material Handler: Includes preparation, wetting, stripping,
removal, scrapping, vacuuming, bagging and disposing of all insulation
materials, whether they contain asbestos or not, from mechanical systems. 11.43 1.79
Windham Sterling R3h, Carpenter: Rough and Finish 15.50
Windham Sterling
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Windham Sterling R7g, Painter: (Excluding Drywall Finishing) 8.96
Windham Sterling R7g, Painter: (Excluding Drywall Finishing) 8.96
Windham Sterling R8a, Laborers: Common or General 13.17 2.89
Windham Sterling
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Windham Thompson R1, Bricklayers 21.22
Windham Thompson R10d, Roofers: Composition (asphalt shingles) 31.10 14.46
Windham Thompson R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 38.35 16.25 + a
Windham Thompson R12a, Truck Driver - 3 Axle 13.69 2.05
Windham Thompson R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Windham Thompson R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 47.15 26.785+a+b
Windham Thompson R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Windham Thompson R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Windham Thompson R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Windham Thompson R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Windham Thompson R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Windham Thompson
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Windham Thompson R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Windham Thompson R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Windham Thompson
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 31.57 25.92
Windham Thompson R20, HVAC Mechanics 11.00 1.49
132/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Windham Thompson
R22, Hazardous Material Handler: Includes preparation, wetting, stripping,
removal, scrapping, vacuuming, bagging and disposing of all insulation
materials, whether they contain asbestos or not, from mechanical systems. 11.43 1.79
Windham Thompson R3h, Carpenter: Rough and Finish 15.50
Windham Thompson
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Windham Thompson R7g, Painter: (Excluding Drywall Finishing) 8.96
Windham Thompson R8a, Laborers: Common or General 13.17 2.89
Windham Thompson
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Windham Willimantic R1, Bricklayers 21.22
Windham Willimantic R10d, Roofers: Composition (asphalt shingles) 31.10 14.46
Windham Willimantic R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 38.35 16.25 + a
Windham Willimantic R12a, Truck Driver - 3 Axle 13.69 2.05
Windham Willimantic R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Windham Willimantic R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 47.15 26.785+a+b
Windham Willimantic R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Windham Willimantic R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Windham Willimantic R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Windham Willimantic R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Windham Willimantic R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Windham Willimantic
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Windham Willimantic R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Windham Willimantic R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Windham Willimantic
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 31.57 25.92
Windham Willimantic R20, HVAC Mechanics 11.00 1.49
133/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Windham Willimantic
R22, Hazardous Material Handler: Includes preparation, wetting, stripping,
removal, scrapping, vacuuming, bagging and disposing of all insulation
materials, whether they contain asbestos or not, from mechanical systems. 11.43 1.79
Windham Willimantic R3h, Carpenter: Rough and Finish 15.50
Windham Willimantic
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Windham Willimantic R7g, Painter: (Excluding Drywall Finishing) 8.96
Windham Willimantic R8a, Laborers: Common or General 13.17 2.89
Windham Willimantic
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Windham Windham R1, Bricklayers 21.22
Windham Windham R10d, Roofers: Composition (asphalt shingles) 31.10 14.46
Windham Windham R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 38.35 16.25 + a
Windham Windham R12a, Truck Driver - 3 Axle 13.69 2.05
Windham Windham R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Windham Windham R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 47.15 26.785+a+b
Windham Windham R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Windham Windham R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Windham Windham R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Windham Windham R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Windham Windham R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Windham Windham
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Windham Windham R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Windham Windham R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Windham Windham
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 31.57 25.92
Windham Windham R20, HVAC Mechanics 11.00 1.49
134/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Windham Windham
R22, Hazardous Material Handler: Includes preparation, wetting, stripping,
removal, scrapping, vacuuming, bagging and disposing of all insulation
materials, whether they contain asbestos or not, from mechanical systems. 11.43 1.79
Windham Windham R3h, Carpenter: Rough and Finish 15.50
Windham Windham
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Windham Windham R7g, Painter: (Excluding Drywall Finishing) 8.96
Windham Windham R8a, Laborers: Common or General 13.17 2.89
Windham Windham
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
Windham Woodstock R1, Bricklayers 21.22
Windham Woodstock R10d, Roofers: Composition (asphalt shingles) 31.10 14.46
Windham Woodstock R11, Sprinkler Fitters (Fire Sprinklers) (Trade License required: F-1,2,3,4) 38.35 16.25 + a
Windham Woodstock R12a, Truck Driver - 3 Axle 13.69 2.05
Windham Woodstock R13, Cement Masons/Concrete Finisher and Tile Setter 10.50 .48
Windham Woodstock R15, Elevator Mechanics (Trade License required: R-1,2,5,6) 47.15 26.785+a+b
Windham Woodstock R18a, Power Equipment Operator: Backhoe/Excavator 2 Cubic Yards and Over 40.64 24.80 + a
Windham Woodstock R18c, Power Equipment Operator: Bulldozer Fine Grade 39.88 24.80 + a
Windham Woodstock R18d, Power Equipment Operator: Combination Hoe and Loader 38.87 24.80 + a
Windham Woodstock R18e, Power Equipment Operator: Loader (3 cubic yards up to 7 cubic yards) 38.55 24.80 + a
Windham Woodstock R18f, Power Equipment Operator: Loader (7 cubic yards or over) 40.97 24.80 + a
Windham Woodstock
R18g, Power Equipment Operator: Backhoe/Excavator under 2 cubic yards;
Rubber Tire Backhoe/Excavator 39.88 24.80 + a
Windham Woodstock R18h, Power Equipment Operator: Bulldozer (Rough Grade Dozer) 38.55 24.80 + a
Windham Woodstock R18i, Power Equipment Operator: Loader (under 3 cubic yards) 37.34 24.80 + a
Windham Woodstock
R19, Sheet Metal Mechanics (Including HVAC Duct Installation) (Trade License
required: SM-1,2,3,4,5,6) 31.57 25.92
Windham Woodstock R20, HVAC Mechanics 11.00 1.49
135/136 As of: 6/28/19
County Town Classification
Hourly
Rate Hourly Benefit
Windham Woodstock
R22, Hazardous Material Handler: Includes preparation, wetting, stripping,
removal, scrapping, vacuuming, bagging and disposing of all insulation
materials, whether they contain asbestos or not, from mechanical systems. 11.43 1.79
Windham Woodstock R3h, Carpenter: Rough and Finish 15.50
Windham Woodstock
R4, Electricians (Trade License required: E1,2 L-5,6 C-5,6 T-1,2 L-1,2, V-
1,2,7,8,9) 15.53 2.57
Windham Woodstock R7g, Painter: (Excluding Drywall Finishing) 8.96
Windham Woodstock R8a, Laborers: Common or General 13.17 2.89
Windham Woodstock
R9a, Plumbers - (Excluding HVAC Work) (Trade License required: P-
1,2,6,7,8,9 J-1,2,3,4 SP-1,2) 14.25 2.31
136/136 As of: 6/28/19