Primavera Cost Control Application
User’s Guide
Version 9.11.0.0December 2012
Lega l Not i ces
Oracle Primavera Cost Control Application
Copyright © 1998, 2012, Oracle and/or its affiliates. All rights reserved.Oracle and Java are registered trademarks of Oracle and/or its affiliates. Other names may be trademarks of their respective owners.
This software and related documentation are provided under a license agreement containing restrictions on use and disclosure and are protected by intellectual property laws. Except as expressly permitted in your license agreement or allowed by law, you may not use, copy, reproduce, translate, broadcast, modify, license, transmit, distribute, exhibit, perform, publish or display any part, in any form, or by any means. Reverse engineering, disassembly, or decompilation of this software, unless required by law for interoperability, is prohibited.
The information contained herein is subject to change without notice and is not warranted to be error-free. If you find any errors, please report them to us in writing.
If this is software or related documentation that is delivered to the U.S. Government or anyone licensing it on behalf of the U.S. Government, the following notice is applicable:
U.S. GOVERNMENT END USERS: Oracle programs, including any operating system, integrated software, any programs installed on the hardware, and/or documentation, delivered to U.S. Government end users are “commercial computer software" pursuant to the applicable Federal Acquisition Regulation and agency-specific supplemental regulations. As such, use, duplication, disclosure, modification, and adaptation of the programs, including any operating system, integrated software, any programs installed on the hardware, and/or documentation, shall be subject to license terms and license restrictions applicable to the programs. No other rights are granted to the U.S. Government.
This software or hardware is developed for general use in a variety of information management applications. It is not developed or intended for use in any inherently dangerous applications, including applications that may create a risk of personal injury. If you use this software or hardware in dangerous applications, then you shall be responsible to take all appropriate failsafe, backup, redundancy, and other measures to ensure its safe use. Oracle Corporation and its affiliates disclaim any liability for any damages caused by use of this software or hardware in dangerous applications.
This software or hardware and documentation may provide access to or information on content, products and services from third parties. Oracle Corporation and its affiliates are not responsible for and expressly disclaim all warranties of any kind with respect to third-party content, products, and services. Oracle Corporation and its affiliates will not be responsible for any loss, costs, or damages incurred due to your access to or use of third-party content, products, or services.
O r a c l e C o r p o r a t i o n
ii Primavera Cost Control Application User’s Guide • Copyright @ 1998, 2012, Oracle and/or its affiliates. All rights reserved
O r a c l e C o r p o r a t i o n
Primavera Cost Control Application User’s Guide • Copyright @ 1998, 2012, Oracle and/or its affiliates. All rights reserved. iii
Table of Contents
Introduction to Primavera Cost Controls . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1What You Receive with this Application . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1
Platform Structure. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2Business Processes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7Dashboards . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9Cash Flows. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9Manager Sheets . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .10Reports. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .15
Setting Up the Primavera Cost Controls Application . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16What You Need to Do . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .16
O r a c l e C o r p o r a t i o n
iv Primavera Cost Control Application User’s Guide • Copyright @ 1998, 2012, Oracle and/or its affiliates. All rights reserved
I n t roduc t ion to P r imavera Cos t Cont ro l s
Primavera Cost Controls is an application for managing project costs. It contains the tools you need to manage your project’s:
Budget functions, including budget approvals, transfers, and changes, as well as estimating, fund appropriations, and a cash flow graph
Purchasing functions, including blanket POs, change orders, invoices, journal entries, payment applications and payments, and work authorizations
Vendor functions, including vendor evaluations, vendor approvals, contracts, and RFBs
Resource functions, including timesheets and a basic set of roles to which you can assign your company resources
These tools encompass business process forms, workflows, reports. and management tracking sheets to monitor your project on a daily basis. Although you must enter your company users into Primavera Unifier, add your company’s data into the management tracking sheets, and grant your company users permissions to use Unifier, the rest of the Cost Controls application—the business process forms, workflows, sheet structures, and budget calculations—are already designed and configured for use.
What You Rece ive w i th th i s App l i ca t ion
Primavera Unifier has been installed on your system and the Primavera Cost Controls Application has been downloaded. With the Primavera Cost Controls Application, you receive the following components, already designed and configured for your use:
Selected platform structure to support the cost controls application
A suite of business processes that work together to accomplish the tasks of cost control
A suite of reports to keep you abreast of cost control progress
The information in this document refers to instructions in the following PDF files:
Primavera uDesigner User’s Guide
Primavera Unifier Administration Guide
Primavera Unifier User’s Guide
You can download these PDFs from the Help menu on the menu bar.
O r a c l e C o r p o r a t i o n
Primavera Cost Control Application User’s Guide • Copyright © 1998, 2012, Oracle and/or its affiliates. All rights reserved. 1
Platform Structure
Primavera Unifier is shipped with two modules:
Primavera uDesigner
Primavera Unifier
Primavera uDesigner
For Primavera uDesigner, in Design Mode, the following nodes in the left Navigator are populated with the components necessary for the Primavera Cost Controls Application:
Business Processes node and a suite of business processes (see the list below)
Although the business processes for this application are already designed and set up for use, you can use this node if you want to add and remove fields from business process forms.
See the Primavera uDesigner User’s Guide:
“Overview of Business Processes” chapter
“Designing a Form” chapter
“Designing a Workflow” chapter
Schedule Manager node and these forms:
An activity attribute form (necessary to set up the schedule)
A resource assignment attribute form for assigning a resource type to an activity
Although the Schedule Manager is already designed and set up for use with this application, you can use this node if you want to add and remove fields from the Schedule Manager attribute forms.
See the Primavera uDesigner User’s Guide:
“Schedule Manager Overview” chapter
“Designing a Form” chapter
Resource Manager node and this form:
A role attribute form to specify the roles necessary to perform the work of the project, such as “carpenter.”
The Resource Manager is set up with a role attribute form that is linked to the Schedule Manager for the purpose of populating activities on the Schedule Sheet with roles for the work to be done on the project. The attribute form is already designed and set up for use with this application, but you can use this node if you want to add and remove fields from the Resource Manager role attribute form.
See the Primavera uDesigner User’s Guide:
“Resource Manager Overview” chapter
“Designing a Form” chapter
O r a c l e C o r p o r a t i o n
2 Primavera Cost Control Application User’s Guide • Copyright © 1998, 2012, Oracle and/or its affiliates. All rights reserved
Primavera Unifier
For Primavera Unifier, under the Company Workspace tab, in Administration Mode, the following nodes in the left Navigator are populated with the components necessary for the Primavera Cost Controls Application:
Cost Manager node and these forms:
A fund attribute form to set up funding and the funding sheet
A cost attribute form to set up the cost sheet
Although the Cost Manager is already designed and set up for use with this application, you can use this node if you want to add and remove fields from the cost and fund attribute forms.
See the Primavera uDesigner User’s Guide:
“Cost Manager Overview” chapter
“Designing a Form” chapter
Shell Manager node and the following shells:
An anchor shell called All Projects
A project shell called Projects
Although the Shell Manager is already designed and set up for use with this application, you can use this node if you want to add and remove fields from the shell attribute form.
See the Primavera uDesigner User’s Guide:
“Shell Manager Overview” chapter
“Designing a Form” chapter
Data Structure Setup node and these components:
Data cube definitions
Data views for reports and dashboards
Although the data structure is already designed and set up for use with this application, you can use this node if you want to make changes to the data views for the reports and dashboards.
See the Primavera Unifier Administration Guide:
“Data Views” topic in the Company Administration chapter
Access Control node where you can grant user permissions to areas of the application.
Use this node to grant persmissions to your company users to work in areas of Unifier.
See the Primavera Unifier Administration Guide:
“Managing Permissions and Access Control” topic in the Company Administration chapter
O r a c l e C o r p o r a t i o n
Primavera Cost Control Application User’s Guide • Copyright © 1998, 2012, Oracle and/or its affiliates. All rights reserved. 3
User Administration node and the following groups to which you can add users so that they have access to the application:
All company users
Company administrators
Creator (of a business process)
Project Administrators
Reviewer
Use this node to add users to Primavera Unifier. In this node, you can also assign users to groups.
See the Primavera Unifier Administration Guide:
“Adding and Managing Company Users” topic in the Company Administration chapter
Configuration node and these sub-nodes with appropriate data for Primaver Cost Controls operation:
Shell Manager and an anchor shell called All Projects, as well as a project shell called Projects
Each business process provided with this application (see list below)
Although the Resource Manager, the Shell Manager, and the business processes are already designed and set up for use with this application, you can use this node if you want to make changes to the configuration of a shell or business process, or add/modify a role in the Resource Manager.
See the Primavera Unifier Administration Guide:
“How to Create and Set Up Shells“ topic in the Shell Administration chapter
“Configuring Business Processes” topic in the Business Processes Setup chapter
Standards & Libraries node and the following sub-nodes with appropriate data for Primavera Cost Controls operation:
Cash Flow > Data Sources
Cash Flow > Distribution Profiles
Although the Standards & Libraries node is already set up for use with this application, you can use this node if you want to change cash flow data sources or distribution profiles.
See the Primavera Unifier Administration Guide:
“Setting Up Cash Flow” topic in the Cost Management Setup chapter
O r a c l e C o r p o r a t i o n
4 Primavera Cost Control Application User’s Guide • Copyright © 1998, 2012, Oracle and/or its affiliates. All rights reserved
Company Workspace node and the following sub-nodes in the Navigator with appropriate data for Primavera Cost Controls operation:
Business Process Setup
Resource Manager
Rules
Auto-update Status Setup
Although the Company Workspace node is already set up for use with this application, you can use this node if you want to change the setup of company-level business processes, add roles to the Resource Manager, or to change the rules and auto-update status for funding functions in the Cost Manager.
See the Primavera Unifier Administration Guide:
For business process setup, see the “Configuring Business Processes” topic in the Business Process Setup chapter
For information on rules and status updating, see the Cost Management Setup chapter
For instructions on adding roles to the Resource Manager, see the topic “Creating Roles and Resources” in the Resource Manager Setup chapter
Templates node and the following template components with appropriate data for Primavera Cost Controls operation:
Costs Sheets > Project Cost Sheet
Funding - Funding Sheets > Funding Sheet
General Spends SOV > General Spends SOV
Rules
Schedule Sheets > Project Schedule Sheet
Although a template is already designed and set up for use with Primavera Cost Controls functions, you can use this node to change the template for your project cost sheet, funding sheet, SOV, project schedule sheet, or rules for cost calculations.
See the Primavera Unifier Administration Guide:
“Creating a Project Template” topic in the Program and Project Administration chapter
Templates > Shells node and a Projects shell node. Under the Projects node are the following template components with appropriate data for Primavera Cost Controls operation:
Access Control
User Administration > Users (default user: OOTB Admin)
User Administration > Groups > shell level group permissions for All Project Users, Creator, Project Administrators, Reviewer
Although a shell template called Projects is already designed and set up for use with Primavera Cost Controls functions, you can use this node to change these pieces that are included in the template:
Access control and user/group administration to automatically add users to the shell
Business processes that you want to automatically include in the project
A dashboard to display summary cost control information on the landing page
O r a c l e C o r p o r a t i o n
Primavera Cost Control Application User’s Guide • Copyright © 1998, 2012, Oracle and/or its affiliates. All rights reserved. 5
Templates > Shells node (continued)
Setup > Business Processes
Setup > Dashboards > Cost Controls
Setup > Gates
Rules
Cost Manager > Cash Flow > Project Cash Flow > Cost Controls Cash Flow
Cost Sheets > Project Cost Sheet
Funding > Funding Sheets > Project Funding Sheet
General Spends SOV (contains a default sheet structure)
Payment Applications (contains a default sheet structure)
Document Manager > Documents (contains a default folder structure)
Schedule Manager > Schedule Sheets > Project Schedule Sheet
Reports (see list below)
Rules
A setup for project gates
A set of rules to govern cost calculations
A Cost Manager with cashflows, a project cost sheet, project funding sheet, SOV sheet, and payment applications sheet
A Document Manager to store drawings, spreadsheets, image files, specifications, and other documentation about the project.
A Schedule Manager with a project schedule sheet
Reports specific to Primavera Cost Control
See the Primavera Unifier Administration Guide:
“Managing Permissions and Access Control” topic in the Company Administration chapter
“Adding and Managing Company Users” topic and the ”User and Group Administration” topic in the Company Administration chapter
“Setting up Business Processes” topic in the Business Processes Setup chapter
”Create a Shell Template” topic and “Setting up Shells” topic in the Shell Administration chapter
“Configuring Shell Dashboards” topic in the Shell Administration chapter
“How to Set Up Gates” topic in the Shell Administration chapter
“Setting Up Cost Sheets” and Creating and Setting Up Cost Templates” topics in the Cost Management Setup chapter
“Setting Up the Funding Manager” topic in the Cost Management Setup chapter
“Setting Up Schedule of Values (SOV)” topic in the Cost Management Setup chapter
“About the Document Manager” and “Setting up the Document Manager” topics in the Document Manager Setup chapter
“Setting up User-Defined Reports” topic in the Reports Setup chapter
O r a c l e C o r p o r a t i o n
6 Primavera Cost Control Application User’s Guide • Copyright © 1998, 2012, Oracle and/or its affiliates. All rights reserved
Business Processes
Following is a list of the business processes you receive with the Primavera Cost Controls application and a short description of each one. These business processes have been designed for immediate use; they do not need to be configured or set up.
Business Process Description
Blanket Purchase Orders A company-level purchase order that supports umbrella agreements with vendors to provide services across multiple projects. Released on a per-project-period basis with work authorizations billed against a set maximum money amount.
Budget Approval A shell-level business process used to approve the initial project budget.
Includes a workflow for budget approval.
Budget Changes Business process for requesting additional (or less) budget authorization than previously approved.
Includes a workflow for change approval.
Budget Transfers Business process for transferring budget from one WBS code to another. Typically used to release contingency to other cost items.
Includes a workflow for the transfer and approval.
Change Orders Business process for committing a formal change to a contract.
Includes a workflow for change approval.
Contracts Form for gathering key contract information, such as names and phone numbers, for reference or use in procurement workflows.
Includes a workflow for contract approval.
Estimates Project “scratch pad” for developing multiple project estimates (SD, DD, CD, or alternates) and identifying the preferred scenario.
Fund Appropriations A business process for assigning fund account to projects.
Includes a workflow for approvals.
Invoices General business process for requesting and approving payments against commitments.
Includes a workflow for approvals.
Journal Entries Business process for adjusting spending line items. Usually used to reassign costs to alternate cost centers or GL codes.
Includes a workflow for approvals.
Payment Applications A business process for making spends against projects.
Includes a workflow for payment approval.
O r a c l e C o r p o r a t i o n
Primavera Cost Control Application User’s Guide • Copyright © 1998, 2012, Oracle and/or its affiliates. All rights reserved. 7
Payments A business process to hold checks processed information from financial system.
PO Amendments A business process for approving purchase order changes.
Includes a workflow for amendment approval.
Potential Change Orders A business process for initiating a potential change order from a contractor.
Includes a workflow for potential change order approval.
Purchase Orders Project-level business process for requesting and issuing commitments with a vendor.
Includes a workflow for PO approval.
Request for Bid Business process for publishing bids, inviting participantys, providing updates, and receiving and comparing bids. Enables Unifier users to invite non-Unifier users to enter bid information online.
Includes a workflow for the bidding process, including analysis and award.
Request for Substitution A business process for requesting to substitute identical material or equipment for what was specified in the contract.
Includes a workflow for the substitution approval.
Risks & Issues Log for documenting, tracking, and estimating the impacts of open issues and risks.
Timesheets A business process used by company personnel for charging hours to projects.
Includes a workflow for submission and approval.
Vendors A register of vendors, used to track contact information, invite bidders, prepare commitments, and send payments.
Vendor Evaluations A business process for evaluating vendor performance to use in consideration for future work on projects.
Includes a workflow for evaluations and approval of vendor.
Vendor Prequal Requests A business process to request that a new vendor be pre-qualified for considertaion for future work on projects.
Includes a workflow for vendor approval.
Work Releases A shell-level business process that references the blanket purchase order.
Includes a workflow for approval.
Business Process Description
O r a c l e C o r p o r a t i o n
8 Primavera Cost Control Application User’s Guide • Copyright © 1998, 2012, Oracle and/or its affiliates. All rights reserved
Dashboards
Configurable dashboards provide executive-level information in an at-a-glance format. With the Primavera Cost Controls application, you will receive a pre-designed dashboard showing Project Cost:
The dashboard consists of four blocks that aggregate project business process records:
Contracts by Status
Payment Applications by Status
Change Orders by Reason
Potential Change Orders by Reason
Cash Flows
With the Primavera Cost Controls application, you receive a cost control cash flow that shows baseline, forecast, and actuals curves in an S-curve display. Once your project/shell is in operation, your manager sheets are set up, and the business processes are in use, Primavera Unifier will collect the curve data from the Cost Sheet and produce the cost control cash flow curves.
O r a c l e C o r p o r a t i o n
Primavera Cost Control Application User’s Guide • Copyright © 1998, 2012, Oracle and/or its affiliates. All rights reserved. 9
Manager Sheets
You will receive the following sheets for the Cost, Funding, Schedule, and Resource Managers, respectively.
Cost Sheets
You receive two Cost Sheets with the Primavera Cost Controls application: a company-level cost sheet and a project-level cost sheet.
Company-Level Cost Sheet
The company-level cost sheet displays cost data across projects or shells. Projects or shells on the company cost sheet are added by default as project- or shell-level cost sheets are created. Projects and shells are listed in order by number. Data rolls up to the company cost sheet columns from project or shell cost sheet columns.
The company-level Cost Sheet contains the following columns:
This column: Shows the:
Project Number Project number
Project Name Project name
Original Budget Sum of all the costs for each cost code breakdown in each project.
Pending Budget Revisions Sum of all budget revisions for each cost code breakdown in each project.
Approved Budget Revisions Sum of all approved budget revision costs for each cost code breakdown in each project.
Revised Budget Sum of all the revised budget numbers for each cost code breakdown in each project.
Risks & Issues Sum of all closed “Risk and Issues” business process records in each project
Forecasts Sum of all the revised budget numbers, plus forecast adjustments, plus open risks and issues for each cost code in the project.
Original Commitments Sum of all the approved contract and approved purchase orders for each cost code breakdown in the project.
Pending Commitments Sum of all the pending change orders and pending PO amendments for each cost code breakdown in the project.
Approved Commitment Changes
Sum of all the approved change orders and approved PO amendments for each cost code breakdown in the project.
O r a c l e C o r p o r a t i o n
10 Primavera Cost Control Application User’s Guide • Copyright © 1998, 2012, Oracle and/or its affiliates. All rights reserved
Project/Shell-Level Cost Sheet
The project or shell cost sheet is a detailed accounting of the project’s or shell’s budget and costs. The project/shell cost sheet rows contain unique WBS codes (or cost codes), which can be used to link project or shell costs to the general ledger for finance. Cost information is added to this sheet automatically from business processes when transactions occur.
The project/shell-level Cost Sheet contains the following columns:
Commitments Sum of all the original commitments and approved commitment changes for each cost code in the project.
Pending Actuals Sum of all the pending payment applications and pending invoices for each cost code in the project.
Actuals Sum of all the approved payment applications and approved invoices for each cost code in the project.
Original Variance Difference between the original budget and the original commitments for each cost code in the project.
Approved Variance Difference between the revised budget and the revised commitments for each cost code in the project.
Variance Difference between the forecase and the revised budget for each cost code in the project.
Budget Percent Revised budget, divided by the total of the revised budget
Commitments Percent The "Revised Commitments" for each WBS code, divided by the total "Revised Commitments" for the project.
This Column: Shows the:
Cost Code Cost code
Cost Name Cost name
Estimates Sum of all the (closed) estimates for each cost code in the project.
Original Budget Sum of all the costs for each cost code in the project.
Pending Budget Revisions Sum of all pending budget changes, plus pending budget transfers for each cost code in the project.
Approved Budget Revisions Sum of all approved budget changes, plus approved budget transfers for each cost code in the project.
Revised Budget Sum of all the original budget and approved budget changes for each cost code in the project.
This column: Shows the:
O r a c l e C o r p o r a t i o n
Primavera Cost Control Application User’s Guide • Copyright © 1998, 2012, Oracle and/or its affiliates. All rights reserved. 11
Risks & Issues Sum of all closed “Risk and Issues” business process records in each project
Original Commitments Sum of all the approved contract and approved purchase orders for each cost code in the project.
Pending Commitments Sum of all the pending change orders and pending PO amendments for each cost code in the project.
Approved Commitment Changes
Sum of all the approved change orders and approved PO amendments for each cost code in the project.
Revised Commitments Sum of all the original commitments and approved commitment changes for each cost code in the project.
Pending Actuals Sum of all the pending payment applications and pending invoices for each cost code in the project.
Actuals Received Sum of all the approved payment applications and approved invoices for each cost code in the project.
Forecast Adjustment Sum of all approved Forecast Adjustment buisess process records
Forecast Sum of all the revised budget numbers, plus forecast adjustments, plus open risks and issues for each cost code in the project.
Original Variance Difference between the original budget and the original commitments for each cost code in the project.
Approved Variance Difference between the revised budget and the revised commitments for each cost code in the project.
Variance Difference between the forecase and the revised budget for each cost code in the project.
Budget Percent Revised budget, divided by the total of the revised budget
Commitments Percent The "Revised Commitments" (as defined above) for each WBS code, divided by the total "Revised Commitments" for the project.
This Column: Shows the:
O r a c l e C o r p o r a t i o n
12 Primavera Cost Control Application User’s Guide • Copyright © 1998, 2012, Oracle and/or its affiliates. All rights reserved
Funding Sheets
You receive two Funding Sheets with the Primavera Cost Controls application: a company-level funding sheet and a project-level funding sheet.
Company-Level Funding Sheet
The company funding sheet tracks all sources of funding for the expenses of all projects or shells.
Funding sources at project or shell sheet level are rolled up to the company sheet, which maintains the overall fund information. The columns on the company funding sheet are used to track project and shell level funding and keep track of fund balances.
Fund assignments are added to this sheet via a Fund Appropriations business process. Each project or shell fund assignments are totalled on the project/shell sheet, and rolled up to the company sheet.
Each row in the company funding sheet corresponds to one fund.
The company-level funding sheet contains the following columns:
Project/Shell-Level Funding Sheet
The project/shell funding sheet tracks how funding is being allocated and consumed at the project/shell level. It tracks individual transactions, which are rolled up to the company funding sheet. Fund allocation, assignment, and credits can be done manually, or through business processes.
Each row in the project/shell funding sheet corresponds to a fund that has been allocated for use on this project/shell.
The project/shell-level funding sheet contains the following columns:
This column: Shows the:
Fund Code Fund code
Fund Name Fund name
Project Funding Each project’s funding transactions and total.
Manual Funding by Project Manual entry of each project’s funding transactions and total.
Transient Records Funded at Project Level
"Fund Appropriations" that are in process (have not yet reached approved terminal status).
Records Funded at Project Level
Records that have been approved for funding.
Fund Remaining Balance Project funding, minus the total Transient Records Funded at Project Level and total Records Funded at Project level
This column: Shows the:
Fund Code Fund code
Fund Name Fund name
O r a c l e C o r p o r a t i o n
Primavera Cost Control Application User’s Guide • Copyright © 1998, 2012, Oracle and/or its affiliates. All rights reserved. 13
Schedule Sheet
With the Primavera Cost Controls Application, you receive a Project Schedule Sheet. It displays project/shell activities and tasks. On it, you can assign resources to tasks, create relationships between activities, track schedule progress and variables, and calculate the schedule’s critical path.
Each project/shell can have multiple schedule sheets, and one master schedule sheet. This master sheet drives project start and end dates, tracks the project’s progress, and serves as the interface between the Schedule Manager and other Primavera Unifier modules. In particular, the master schedule updates resource assignment information in the Resource Manager, which affects timesheets and resource utilization figures; and it integrates cost items on the schedule with the Cost Manager. You can refresh resource rates on the schedule sheet and post the new rates to the Cost Manager, update the cost sheet with assignment costs, and refresh costs on the sheet to recalculate labor costs and post them to the cost sheet.
The project/shell-level schedule sheet contains the following columns:
Project Funding Allocation amount of each fund for the project
Manual Funding by Project Manual entry of each project’s funding transactions and total.
Transient Records Funded at Project Level
"Fund Appropriations" that are in process (have not yet reached approved terminal status).
Records Funded at Project Level
Records that have been approved for funding.
Fund Remaining Balance Project funding, minus the total Transient Records Funded at Project Level and total Records Funded at Project level
This column: Shows the:
Row ID Row ID
Activity Name Activity name
Start Date Starting date for the activity.
Finish date Finish date of the activity
Duration Amount of time (usually in days) the activity should take.
week columns Progress of the activity by day
This column: Shows the:
O r a c l e C o r p o r a t i o n
14 Primavera Cost Control Application User’s Guide • Copyright © 1998, 2012, Oracle and/or its affiliates. All rights reserved
Reports
The following reports are included with the Primavera Cost Controls application and need no additional setup. These reports should give you insight into the progress of your project cost control.
Shell-Level Reports Budget Alert
Budget Approval Details
Budget Approval Summary
Budget Changes Summary
Budget Transfers Summary
Change Orders
Contracts Details
Contracts Summary
Project Cost Summary
Estimates Summary
Invoices Details
Invoices Summary
Journal Entries Summary
Payments Summary
PO Amendments Summary
Pending Change Orders Progress
Purchase Orders Summary
Purchase Orders Detail
Requests for Bid Summary
Requests for Substitution Summary
Risk Items Summary
Work Releases Summary
Company-Level Reports Blanket Purchase Orders Summary
Timesheets Summary
Vendors Summary
Vendor Prequal Requests Summary
Vendor Evaluations Summary
Shell- and Company-Level Report Pending Invoices and Pay Apps
O r a c l e C o r p o r a t i o n
Primavera Cost Control Application User’s Guide • Copyright © 1998, 2012, Oracle and/or its affiliates. All rights reserved. 15
Set t ing Up the P r imavera Cos t Cont ro l s App l i ca t ion
The Primavera Cost Controls application has been designed and configured for immediate use. However, there are a few actions you need to take to complete the setup.
What You Need to Do
Create a project/sub-shell.
The Primavera Cost Controls Application is shipped with an anchor shell called “All Projects.” You will need to create at least one project or sub-shell under this shell. We have provided a shell template to use to create the project/sub-shell. For instructions on creating this project/shell, please see the “Creating a Shell by Copying a Template or Shell” topic in the Shell Administration chapter of the Primavera Unifier Administration Guide.
Add users to the company.
For instructions on adding users to the company, please see the “Adding and Managing Company Users” topic in the Company Administration chapter of the Primavera Unifier Administration Guide.
We recommend that you add all your users to the group categories we have provided. Doing so makes assignments and permissions more efficient.
Assign users to the shell.
Once you have added users to the company and assigned them to groups, you can then assign them to your project or shell. For instructions on assigning users to a shell, please see the “Managing Shell Users and Groups” topic in the Shell Administration chapter of the Primavera Unifier Administration Guide.
Grant users permissions to the application.
For instructions on granting user permissions to the Primavera Cost Controls application, please see the “Managing Permissions and Access Control” topic in the Company Administration chapter of the Primavera Unifier Administration Guide.
Add rows to the Cost, Funding, and Schedule sheets.
Primavera Unifier provides the basic structure for these sheets; that is, the columns of information you are likely to need on the sheets. However, you will need to add the rows to these sheets that will contain your company data. For example, you will need to add WBS (cost) codes to the Cost Sheet according to how they are structured in your company. You will need to add your funding sources to the Funding Sheet. You will need to add activities to the Schedule Sheet.
You may also have been given access to additional features of Unifier and uDesigner. You can use these features to make other changes to the Primavera Cost Controls business process forms, workflows, rules, cashflows, data cubes, and data structure; however, we do not recommend using these features until you are familiar with Primavera Unifier and how it works.
O r a c l e C o r p o r a t i o n
16 Primavera Cost Control Application User’s Guide • Copyright © 1998, 2012, Oracle and/or its affiliates. All rights reserved
• For instructions on adding rows to a Cost Sheet, please see the topic “Adding Cost Rows (WBS Codes)” in the Cost Management Setup chapter of the Primavera Unifier Administration Guide.
• For instructions on adding rows to a Funding Sheet, please see the topic “Creating a Project/Shell Funding Sheet” in the Cost Management Setup chapter of the Primavera Unifier Administration Guide.
• For instructions on adding activities to a Schedule Sheet, please see the topic “Schedule Sheet Activities” in the Schedule Manager chapter of the Primavera Unifier User’s Guide.
O r a c l e C o r p o r a t i o n
Primavera Cost Control Application User’s Guide • Copyright © 1998, 2012, Oracle and/or its affiliates. All rights reserved. 17