Plan Estimate Program Schedule Execute Update Performance
Safety Quality Wrench-time
Primavera™ P6 Advanced Training for
Shutdowns, Turnarounds & Outages A user guide, reference book and three-day training course written for Planners and Schedulers who wish to learn best-practice methods to plan, manage and control shutdown, turnaround and outage projects in the energy sector using Primavera™ P6
3 Day Event Instructed by Ej Lister
STONAVIGATOR™ Specialist
Day 1: Planning & Estimating
Day 2: Programming & Scheduling
Day 3: Execution Management & Control
CPM Solutions Ltd. presents
Copyright © 2013 CPM Solutions Ltd.
Please contact us for additional copies.
All rights reserved.
No part of this manual may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording, or otherwise, without written prior permission of the creator.
V1 - First printing 2007
CPM Solutions Ltd.
Head Office & Training Center
Suite #200 – 4170 Still Creek Drive
Burnaby, British Columbia
Canada, V5C 6C6
Phone: 1-604-294-1577 | Fax: 1-604-294-609546350 | www.cpmsolutions.ca CPM Solutions Ltd. and STONAVIGATOR™ provide industry with Shutdown, Turnaround, Outage and Engineering, Procurement and Construction products, services and training. Visit our website for more information: www.cpmsolutions.ca
Course Agenda i
Primavera™ P6 Advanced Training for Shutdowns, Turnarounds & Outages www.cpmsolutions.ca ©2013
Course Agenda Day 1 – Theme: Planning and Estimating
The theme for this session is Planning and Estimating, where the student will learn the rules of creating a plan and estimating its resource requirements. The student will learn to use the Field Planning Form prior to creating a layout in Primavera™ P6 and entering the plan within a specific Work Breakdown Structure bucket.
At the end of Day 1 the student will have a STO Project in Primavera™ P6 with several Worklist / Work Order Plans assigned to their appropriate WBS bucket, ready for the next session (Day 2) to begin Programming and Scheduling.
8:00am - 8:30am - Introductions and Course Overview
8:30am - 9:00am - Presentation – STO Project Methodology and Technology
9:00am - 10:00am - Exercise – Primavera™ P6 Lesson 1: Create your STO Project Logging-in and Navigating Create the EPS (Enterprise Project Structure) Create a STO Projects and Establish Defaults Creating OBS Responsible Manager
10:00am - 10:15am - Coffee Break
10:15am - 11:00pm - Exercise – Primavera™ P6 Lesson 2: Work Breakdown Structure
11:00pm - 11:30pm - Exercise – Primavera™ P6 Lesson 3: Creating Phase Calendars Template Pre, Shutdown, Mechanical, Startup, Post
11:30pm - 12:00pm - Exercise – Primavera™ P6 Lesson 4: Creating Activity Codes
12:00pm - 1:00pm - Lunch
1:00pm - 1:30pm - Exercise – Primavera™ P6 Lesson 5: Creating Layouts Planning, Scheduling, Updating
1:30pm - 2:00pm - Exercise – Primavera™ P6 Lesson 6: Managing Data
2:00pm - 3:00pm - Group Exercise – Creating a Work Order Task Plan Fill-out a FPF (Field Planning Form) for Stationary and/or Rotating
Equipment with logic, resources and estimates
3:00pm - 3:15pm - Coffee Break
3:15pm - 4:30pm - Group Exercise - Continued
Course Agenda ii
Primavera™ P6 Advanced Training for Shutdowns, Turnarounds & Outages www.cpmsolutions.ca ©2013
Day 2 – Theme: Programming and Scheduling
The theme for this session is Programming and Scheduling, where the student will learn the difference between them, and learn to create programming codes and how to assign them, both manually and globally. The student will learn the various methods of scheduling; how to apply them, and when to use them. The highlight of this session will be Dynamic Schedule Management (DSM) for driving, not monitoring their STO project.
At the end of Day 2 the student will have a STO Project in Primavera™ P6 that represents a Plan, in preparation for the next session of Execution Management and Control.
8:00am - 10:00am - Exercise – Primavera™ P6 Lesson 9: Creating Activity Plans Adding Activities Relationships (Predecessors and Successors) Copy Activity Plans
10:00am - 10:15am - Coffee Break
10:15am - 10:45am - Exercise – Primavera™ P6 Lesson 9: Adding Steps Creating Templates ROC (Rules of Credit)
10:45am - 11:00am - Presentation – Dynamic Schedule Management (DSM) Scheduling Methodology Scheduling Techniques
11:00am - 12:00am - Exercise – Primavera™ P6 Lesson 10: Prioritizing Work Orders Using Work Order Tasks Using Work Order Task Activities
12:00pm - 1:00pm - Lunch
1:00pm - 2:00pm - Group Workshop Exercise – The Execution Strategy Establish the Execution Strategy Shutdown, Mechanical, Startup Resources Management
2:00pm - 3:00pm - Exercise – Primavera™ P6 Lesson 11: Resource Levelling Optimizing the Plan Productivity Factors
3:00pm - 3:15pm - Coffee Break
3:00pm - 4:00pm - Exercise – Primavera™ P6 Lesson 12: Saving a Baseline
4:00pm - 4:30pm - Presentation – Execution Phase – Best-practices KPI’s: Safety, Quality, Efficiency
Course Agenda iii
Primavera™ P6 Advanced Training for Shutdowns, Turnarounds & Outages www.cpmsolutions.ca ©2013
Day 3 – Theme: Execution Management and Control
The theme for this session is Execution Management and Control, where the student will learn how to create reports for distribution (Daily Shift Reports) and analysis (Key Performance Reports) using the Primavera™ P6 Report Writer with Filters and Batch Printing. The student will create a new Layout for Updating while establishing the methodology for obtaining accurate and timely Field Updates.
The student will learn to update and using DSM (Dynamic Schedule Management) learn to produce a new Daily Shift Report (Plan) to accommodate the Field Execution Coordinators based on resource and asset availability.
At the end of this session the student will have a complete understanding of Planning, Estimating, Programming, Scheduling, Updating and Reporting to ensure an effective and efficient STO project with a combined effort of Planners, Schedulers and Field Execution Coordinators.
8:00am - 9:00am - Presentation – Earned-value Performance CPI and SPI Planned, Earned and Actual
9:00am - 10:00am - Exercise – Primavera™ P6 Lesson 13: Creating Reports Creating Report Groups Creating Shift Reports Creating Performance Reports
10:00am - 10:15am - Coffee Break
10:15am - 11:30am - Presentation – Updating and Progressing Activities (Shift Reports)
11:30am - 12:00pm - Exercise – Primavera™ P6 Lesson 14: Updating Activities Create an Update / Status Layout Updating and Progressing Establish a New Plan (DSM)
12:00pm - 1:00pm - Lunch
1:00pm - 2:00pm - Exercise – Primavera™ P6 Lesson 15: Earned-value Performance Performance Management S-curves by WBS
2:45pm - 3:00pm - Coffee Break
3:00pm - 4:00pm - Review – Questions – Certificates and Photos Course Evaluation Forms
Table of Contents
Primavera® P6™ Advanced Training for Shutdowns, Turnarounds & Outages www.cpmsolutions.ca ©2013
Course Agenda .................................................................................................................................. i Course Overview .............................................................................................................................. iv Flow of Lessons ................................................................................................................................ v
Instructor .......................................................................................................................................... vi
Common Shutdown and Turnaround Terminology and Definitions ..................................................... vii
Lesson 1: Create your STO Project ...................................................................................................... 1
Logging In .......................................................................................................................................... 2 Navigating ......................................................................................................................................... 3
Establish the EPS (Enterprise Project Structure) .............................................................................. 4 Establish the OBS (Organizational Breakdown Structure)................................................................. 5 Create a New Project Wizard ............................................................................................................ 6 Entering Project Name ...................................................................................................................... 7
Entering Project Start and End Dates ................................................................................................ 8 Entering Responsible Manager ......................................................................................................... 9
Selecting Assignment Rate Type .................................................................................................... 10 Running Project Architect ................................................................................................................ 11
Projects Window .............................................................................................................................. 12 Project Details ................................................................................................................................. 13 General Tab .................................................................................................................................... 14
Dates Tab ........................................................................................................................................ 15 Notebook Tab .................................................................................................................................. 16
Codes Tab ....................................................................................................................................... 18 Defaults Tab .................................................................................................................................... 19 Settings Tab .................................................................................................................................... 20
Calculations Tab .............................................................................................................................. 21
User Preferences ............................................................................................................................ 22 Admin Preferences .......................................................................................................................... 23
Lesson 2: Work Breakdown Structure ................................................................................................. 24
Work Breakdown Structure – Best-Practices ................................................................................... 25 Viewing WBS Elements ................................................................................................................... 28
Creating the WBS Hierarchy ........................................................................................................... 29 Exercise: Creating a Work Breakdown Structure ............................................................................ 30
Lesson 3: Calendars ........................................................................................................................... 32
Best- Practices – Phase and WBS Calendars ................................................................................. 33 Calendar Assignments .................................................................................................................... 34
Worktime Types .............................................................................................................................. 35 Global Calendars ............................................................................................................................. 36 Viewing a Global Calendar .............................................................................................................. 37 Adding a Project Calendar............................................................................................................... 38
Setting the Work Days ..................................................................................................................... 39 Setting Worktime for Phase Calendars............................................................................................ 40 Creating Resource Productivity Calendars ...................................................................................... 41 Workshop: Creating Phase Calendars ............................................................................................ 42 Workshop Results ........................................................................................................................... 43
Lesson 4: Creating Activity Codes ...................................................................................................... 45
Table of Contents
Primavera™ P6 Advanced Training for Shutdowns, Turnarounds & Outages www.cpmsolutions.ca ©2013
Activity Codes .................................................................................................................................. 46
Creating Activity Codes ................................................................................................................... 47 Workshop: Creating Activity Codes ................................................................................................. 49
User Fields Overview ...................................................................................................................... 52 Defining a User Field ....................................................................................................................... 53
Lesson 5: Creating Layouts ................................................................................................................ 55
Layouts – Best-Practices ................................................................................................................. 56 Layouts in Primavera P6 ................................................................................................................. 57
Opening an Existing Activity Layout ................................................................................................ 58 Gantt Chart ...................................................................................................................................... 60 Activity Usage Spreadsheet ............................................................................................................ 61 Activity Network ............................................................................................................................... 62 Activity Table ................................................................................................................................... 63
Customizing a Layout ...................................................................................................................... 64
Selecting Columns .......................................................................................................................... 65 Using Hint Help in Columns Dialog Box .......................................................................................... 66
Displaying Activity Details ................................................................................................................ 67 Selecting Details Tabs ..................................................................................................................... 68 Saving Layouts ................................................................................................................................ 69
Workshop: Creating a Planning Layout ........................................................................................... 71
Lesson 6: Managing Data ................................................................................................................... 73
Project Documents .......................................................................................................................... 74 Creating a Document Record .......................................................................................................... 75 Files Tab .......................................................................................................................................... 77
Assigning a Project Document to an Activity ................................................................................... 78
Viewing Document Details ............................................................................................................... 80 Grouping Data ................................................................................................................................. 81 Group and Sort Dialog Box .............................................................................................................. 82
Grouping by Date ............................................................................................................................ 84 Collapsing/Expanding Grouped Data .............................................................................................. 85
Sorting Activities .............................................................................................................................. 86 Sorting Multiple Fields ..................................................................................................................... 87
Filtering Activities ............................................................................................................................ 89 Filters Dialog Box ............................................................................................................................ 90 Applying a Default Filter .................................................................................................................. 91 Creating a Filter ............................................................................................................................... 92 Using Multiple Filters ....................................................................................................................... 94 Applying the All Activities Filter ........................................................................................................ 95
Lesson 7: Resources, Productivity and Cost....................................................................................... 97
Roles and Responsibilities (OBS) – Best-Practices ........................................................................ 98 Roles and Responsibilities Sheet - Example ................................................................................... 99 Resources and Roles .................................................................................................................... 100 Scheduler/Programmer (Pitcher) Clock ......................................................................................... 101 Defining Roles ............................................................................................................................... 102 Prices Tab ..................................................................................................................................... 103
Table of Contents
Primavera™ P6 Advanced Training for Shutdowns, Turnarounds & Outages www.cpmsolutions.ca ©2013
Limits Tab ...................................................................................................................................... 104
Baseball Metaphor ........................................................................................................................ 105 OBS (Organizational Breakdown Structure) .................................................................................. 106
Resources – Best-Practices .......................................................................................................... 107 Defining Resources ....................................................................................................................... 112 Resource Details ........................................................................................................................... 113 Details Tab .................................................................................................................................... 114 Units & Prices Tab ......................................................................................................................... 115
Assigning Resources, Tools and Materials.................................................................................... 116 Workshop: Adding Resources, Tools and Materials ...................................................................... 117
Workshop Exercise – Work Order (Task) Planning & Estimating ...................................................... 119
Best-Practices - Planning .............................................................................................................. 120 Best-Practices - Estimating ........................................................................................................... 126
Equipment Network Logic (graphical) ............................................................................................ 140
Field Planning Form (example) ..................................................................................................... 141 Assigning Planners by Planned Job Package ............................................................................... 142
Field Planning Workshop Exercise ................................................................................................ 143
Lesson 8: Creating Activity Plans ...................................................................................................... 146
Tasks and Activities ....................................................................................................................... 147
Activity Components ...................................................................................................................... 148 Adding Activities using a Planning Layout ..................................................................................... 149
Adding Activities to Tasks .............................................................................................................. 150 Using Activity Details Tabs ............................................................................................................ 151 Assigning Activity Type ................................................................................................................. 152
Using Steps ................................................................................................................................... 154
Best- Practices – Creating Relationships ...................................................................................... 155 Network Logic Diagram ................................................................................................................. 156 Relationship Types ........................................................................................................................ 157
Relationships with Lag .................................................................................................................. 158 Creating Relationships in the Gantt Chart ..................................................................................... 159
Creating Relationships using Link Activities Feature ..................................................................... 160 Creating Relationships in the Activity Network .............................................................................. 161
Using the GoTo Feature ................................................................................................................ 162 Assigning Lag ................................................................................................................................ 163 Workshop: Creating Relationships ................................................................................................ 164
Lesson 9: Adding Steps .................................................................................................................... 166
Adding Steps to Activities using the .Planning Layout ................................................................... 167
Lesson 10: Prioritizing Work Orders ................................................................................................. 170
Creating Task Priorities ................................................................................................................. 171
Creating Task Priorities – continued. ............................................................................................. 172
Exercise: The Execution Strategy ..................................................................................................... 174
The Execution Plan - Best-Practices ............................................................................................. 175
The Execution Plan (example) ...................................................................................................... 176 The Execution Plan – OBS / WBS ................................................................................................. 181
Table of Contents
Primavera™ P6 Advanced Training for Shutdowns, Turnarounds & Outages www.cpmsolutions.ca ©2013
Lesson 11: Scheduling ...................................................................................................................... 183
Best-Practices - Scheduling .......................................................................................................... 184 Scheduling – Step-by-Step ............................................................................................................ 185
What is the Data Date? ................................................................................................................. 186 Total Float ..................................................................................................................................... 187 Circular Relationships (Loops) ...................................................................................................... 188 Scheduling a Project ..................................................................................................................... 189 Schedule Log ................................................................................................................................ 190
Constraints .................................................................................................................................... 191 Commonly Use Constraints ........................................................................................................... 192 Mandatory Start ............................................................................................................................. 193 Mandatory Finish ........................................................................................................................... 194 Activity Network Logic Dependant ................................................................................................. 195
Adding Notebook Topic ................................................................................................................. 197
Levelling Overview ........................................................................................................................ 199 Front Loading the Project .............................................................................................................. 200
Handling Resource Conflicts ......................................................................................................... 201 Setting Equipment (Task) Levelling Priorities ................................................................................ 202 Setting User Preferences prior to Levelling ................................................................................... 204
Levelling ........................................................................................................................................ 205 Selecting Resources ..................................................................................................................... 207
Adding Levelling Priorities ............................................................................................................. 208 Viewing the Levelling Log .............................................................................................................. 209 Analyzing the Leveled Project ....................................................................................................... 210
Workshop: Levelling (Optimizing the Plan) .................................................................................... 212
Lesson 12: Saving a Baseline ........................................................................................................... 217
Baselines ....................................................................................................................................... 218 Creating a Baseline ....................................................................................................................... 219
Categorizing the Baseline .............................................................................................................. 220 Assigning a Baseline ..................................................................................................................... 221
Viewing Baseline Bars ................................................................................................................... 222 Displaying Baseline Bars ............................................................................................................... 223
Customizing the Activity Table ...................................................................................................... 224 Saving the Layout .......................................................................................................................... 225 Bar Labels Tab .............................................................................................................................. 226
Lesson 13: Creating Reports ............................................................................................................ 229
Best-Practices - Reporting ............................................................................................................. 230 Reports Window ............................................................................................................................ 231 Run an Existing Report ................................................................................................................. 232
Run Report Dialog Box .................................................................................................................. 233 Print Preview ................................................................................................................................. 234 Printing Reports ............................................................................................................................. 235 Report Wizard ............................................................................................................................... 236 Create or Modify Report ................................................................................................................ 237 Select Subject Area ....................................................................................................................... 237 Select Additional Subject Areas .................................................................................................... 238
Table of Contents
Primavera™ P6 Advanced Training for Shutdowns, Turnarounds & Outages www.cpmsolutions.ca ©2013
Configure Selected Subject Areas ................................................................................................. 239
Adding a Filter to the Report .......................................................................................................... 240 Adding a Report Title ..................................................................................................................... 241
Generating the Report ................................................................................................................... 242 Print Preview ................................................................................................................................. 243 Saving a Report ............................................................................................................................. 244 Assigning a Report to a Report Group .......................................................................................... 245 Creating a Report Using the Current Layout ................................................................................. 246
Workshop: Building Reports in Primavera ..................................................................................... 250
Lesson 14: Updating Activities .......................................................................................................... 252
Best-Practices – Updating the Plan ............................................................................................... 253 The Data Date ............................................................................................................................... 254 The Updating Layout ..................................................................................................................... 256
Workshop: Create the Updating Layout ........................................................................................ 257
Progress Spotlight ......................................................................................................................... 258 Statusing Activities ........................................................................................................................ 259
The Data Date Filter for Layouts and Reports ............................................................................... 260 The Data Date Filter for Global Change ........................................................................................ 261 Updating Activity % Complete ....................................................................................................... 263
Lesson 15: Earned-value Performance (EvP) ................................................................................... 266
Best-Practices – Performance Management ................................................................................. 267
Project Controls ............................................................................................................................. 268 Trending Data ................................................................................................................................ 269 Key Performance Indicators and Status Data ................................................................................ 270
Index ................................................................................................................................................. 272
Course Evaluation – STO300 ........................................................................................................... 273
Course Overview iv
Primavera™ P6 Advanced Training for Shutdowns, Turnarounds & Outages www.cpmsolutions.ca ©2013
Co
urs
e O
verv
iew
Course Overview
This 3 day intensive training course is designed by STOnavigator™ Masters© for the individuals responsible for the planning, scheduling and execution management and control functions associated with shutdowns, turnarounds, outages and capital projects.
To maximize the effectiveness of Primavera P6™ for managing these projects we’ve designed a course that not only focuses on the ability to use the software effectively, it focuses also on providing best-practice management tools for effective estimating, schedule development and field execution to ensure your overall project meets you key performance targets associated with safety, cost, duration, worker efficiency and quality.
Attendees will learn how to properly develop a plan based on realistic estimates, how to apply productivity factors and measure performance, how to develop and manage a dynamic schedule using the Primavera P6™ levelling capabilities and how to get buy-in from field execution and operations coordinators during the outage.
Objective
The objective of this course is to provide instruction on navigating and managing data in the Primavera P6™ environment while teaching industry best-practices for planning, scheduling and executing an efficient shutdown, turnaround, outage or capital project.
Vision
The Planning Team will assist with establishing the Key Performance Targets and control the project to meet or exceed them.
Key Performance Indicators
Key Performance Targets Phase
Budget / Workscope Based on Risk/Cost Benefit Strategic Planning
Duration Based on Shutdown/Start-up and Longest-path
Planning and Scheduling
Safety / Environment
Zero Incidents Execution
Quality Zero rework, zero leaks Execution
Direct Wrench-time 55% Execution
Flow of Lessons v
Primavera™ P6 Advanced Training for Shutdowns, Turnarounds & Outages www.cpmsolutions.ca ©2013
Co
urs
e O
verv
iew
Flow of Lessons
The steps (lessons) outlined below have been purposefully sequenced in the progression in which a real-life STO project should be planned, scheduled and controlled:
Presentation: STO Project Methodology and Technology
Presentation: Planning, Scheduling and Field Execution Roles
Lesson 1: Creating a STO Project and Setting Defaults
Lesson 2: Creating the Work Breakdown Structure (WBS)
Lesson 3: Creating Phase Calendars
Lesson 4: Creating Activity Codes
Lesson 5: Creating Layouts
Lesson 6: Managing Data
Presentation: Worklist Management and Control
Presentation: Creating a Planned Job Package
Group Workshop Exercise: Work Order (Task) Activity Planning
Presentation: Resources and Productivity
Lesson 7: Resources and Productivity
Lesson 8: Creating Activity Plans
Presentation: Establish Key Performance Indicators (KPI’s)
Presentation: Defining the Execution Plan
Lesson 9: Adding Steps
Lesson 10: Prioritizing Work Orders
Presentation: Dynamic Schedule Management (DSM)
Lesson 11: Scheduling
Lesson 12: Saving a Baseline
Lesson 13: Creating Reports
Lesson 15: Updating Activities
Lesson 16: Earned Value Performance
Course Overview vi
Primavera™ P6 Advanced Training for Shutdowns, Turnarounds & Outages www.cpmsolutions.ca ©2013
Instr
ucto
r Instructor
Ej (Ted) Lister is an internationally recognized innovative leader and sought-
after Shutdown, Turnaround and Outage Navigator and Keynote Speaker and
Presenter; author of several books and manuals relevant to STO Best-
Practices. Gifted, patient and enthusiastic communicator and people-person;
projects are not successful, the project team is.
25 years of combined experience in the field and in the war-room. Certified Red
Seal Electrician and Instrumentation Technologist. Qualified Planner/Scheduler
and Project Controls Specialist with HR and Change Management
accreditations. Ej is the Editor of STO Navigator™ learning blog, contributing
weekly to share knowledge and experience to more than 10,000 visitors
monthly. In 2005 Ej published Successful Change Management and is currently
completing a High Performance Organization book Lead, Manage or Dig.
Favorite Quote: “Grown-ups invented work to keep playing together…”