PRIMERGY
PRIMERGY RX300 S2Server System Monika SpanjaartFujitsu Siemens Computers GmbH München81730 Muniche-mail: email: [email protected].: (089) 61001160Fax: (++49) 700 / 372 00000 Sprachen: En
Edition Dezember 2004
Comments… Suggestions… Corrections…The User Documentation Department would like toknow your opinion of this manual. Your feedback helpsus optimize our documentation to suit your individual needs.
Fax forms for sending us your comments are included inthe back of the manual.
There you will also find the addresses of the relevantUser Documentation Department.
Certified documentation according to DIN EN ISO 9001:2000To ensure a consistently high quality standard anduser-friendliness, this documentation was created tomeet the regulations of a quality management system which complies with the requirements of the standardDIN EN ISO 9001:2000.
cognitas. Gesellschaft für Technik-Dokumentation mbHwww.cognitas.de
Copyright and Trademarks
Copyright © 2004 Fujitsu Siemens Computers GmbH.All rights reserved.Delivery subject to availability; right of technical modifications reserved.
All hardware and software names used are trademarks of their respective manufacturers.
This manual is printed on paper treated with chlorine-free bleach.
Introduction
Procedure
Safety notes
Replacement routines
Appendix
Index
Contents1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11.1 Overview of the documentation . . . . . . . . . . . . . . . . . . 11.2 Notational conventions . . . . . . . . . . . . . . . . . . . . . . . 4
2 Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
3 Safety notes . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
4 Replacement routines . . . . . . . . . . . . . . . . . . . . . 134.1 Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . 134.1.1 Opening the server . . . . . . . . . . . . . . . . . . . . . . . 134.2 Replacing the operating panel . . . . . . . . . . . . . . . . . . 134.3 Replacing USB module . . . . . . . . . . . . . . . . . . . . . 154.4 Replacing the floppy disk drive . . . . . . . . . . . . . . . . . 174.5 Replacing the LocalView module . . . . . . . . . . . . . . . . 174.6 Replacing CD/DVD drive . . . . . . . . . . . . . . . . . . . . . 174.7 Replacing the Power backplane . . . . . . . . . . . . . . . . . 174.8 Replacing the SCSI backplane . . . . . . . . . . . . . . . . . 184.8.1 Replacing the 1st SCSI-Backplane . . . . . . . . . . . . . . . 184.8.2 Replacing the 2nd SCSI backplane . . . . . . . . . . . . . . . 204.9 Replacing the hot-plug PCI board . . . . . . . . . . . . . . . . 204.10 Replacing the IDTemp Combo . . . . . . . . . . . . . . . . . . 224.11 Replacing the processor heat sink . . . . . . . . . . . . . . . . 234.12 Replacing the system board . . . . . . . . . . . . . . . . . . . 24
5 Appendix . . . . . . . . . . . . . . . . . . . . . . . . . . . . 275.1 Board layouts . . . . . . . . . . . . . . . . . . . . . . . . . . 275.1.1 Operating panel . . . . . . . . . . . . . . . . . . . . . . . . . 275.1.2 USB panel board . . . . . . . . . . . . . . . . . . . . . . . . 275.1.3 Power Backplane . . . . . . . . . . . . . . . . . . . . . . . . 285.1.4 SCSI Backplane . . . . . . . . . . . . . . . . . . . . . . . . . 305.1.4.1 1st SCSI backplane and 2nd 2-channel SCSI backplane . . . . 305.1.4.2 2nd 1-channel SCSI backplane . . . . . . . . . . . . . . . . . 325.1.5 IDTemp Combo . . . . . . . . . . . . . . . . . . . . . . . . . 335.1.6 System Board . . . . . . . . . . . . . . . . . . . . . . . . . . 345.2 Cabling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35
Index . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
Service Supplement
1 IntroductionThe PRIMERGY RX300 S2 Server is an Intel-based server for medium-sized networks and large companies. The server is suitable for use as a file server as well as an application, information, or Internet server.
1.1 Overview of the documentation
Concept and target groups
This Service Supplement completes the information given in the Operating Manual, the Options Guide and the Technical Manual of the system board.
The activities described in this manual may only be performed by service personnel.
Service CD
Service partners of Fujitsu Siemens can order a Service CD. On the CD the following manuals are available in pdf format:
– The “Security” manual– The Operating Manual for PRIMERGY RX300 S2– The Technical Manual for the system board D1889– The Options Guide for PRIMERGY RX300 S2– The Service Supplement PRIMERGY RX300 S2– The “BIOS Setup” manual
Service Supplement 1
2
Overview of the documentation Introduction
Info
Deta
Feat
Insta– E– O– C– I
Trou
Insta– h– h– h– h
Infor– F– B– J– L– R
Exte
– E– I
p– I– I– I– I– I– I– I– C
S– C
P
Cab
Table
rmation/procedure Manual
iled safety notes Safety
ures and technical data of the server Operating Manual
llation and operation, among other things:xternal portsperationonfiguration of the server
nstallation of the rack mounting kit
bleshooting
llation/removal of all hot-plug components:ot-plug power supply unitsot-plug hard disk drivesot-plug magnetic tape driveot-plug PCI boards
mation about the system board:eatures of the system boardoard layoutumper settingsED displayseplacing the battery
Technical Manual
nsions and upgrades
xtending/replacing the main memorynstalling a second processor / replacing the rocessor / replacing the heat sink
nstalling the ROMB upgrade kitnstalling accessible drivesnstalling a Local View modulenstalling controller in the non-hot-plug PCI slotsnstalling RemoteView componentsnstalling the external SCSI interfacenstalling a parallel interfaceonverting from the SCSI 1-channel to the CSI 2-channel versiononverting from low-profile slots to standard CI slots
Options Guide
ling
1: Overview of the documentation PRIMERGY RX300 S2
Service Supplement
Service Supplement 3
Introduction Overview of the documentation
I For some components only the installation routine is described in the Options Guide. Removing this components proceed in reverse order.
Replacement routines:– Replacing the operating panel– Replacing the USB connector panel– Replacing the floppy disk drive– Replacing the DVD-ROM drive– Replacing the processor fan holder– Replacing the Power backplane– Replacing the SCSI backplane– Replacing the hot-plug PCI print– Replacing the IDTEMP Combo– Reinstalling the processor heat sink– Replacing the system board
Service Supplement
Settings and Board layouts
BIOS setup BIOS Setup
Information/procedure Manual
Table 1: Overview of the documentation PRIMERGY RX300 S2
Notational conventions Introduction
1.2 Notational conventions
The following notational conventions are used in this manual:
Text in italics indicates commands, menu items or software programs.
„Quotation marks“ indicate names of chapters and terms that are being emphasized.
Ê describes activities that must be performed in the order shown.
V CAUTION! pay particular attention to texts marked with this symbol. Failure to observe this warning may endanger your life, destroy the system or lead to the loss of data.
I indicates additional information, notes and tips.
Table 2: Notational conventions
4 Service Supplement
2 ProcedureV CAUTION!
The actions described in these instructions should only be performed by service personnel.
Ê First of all please familiarize yourself with the safety instructions in the chapter “Safety notes” on page 7.
Ê Ensure that all required manuals (see Service CD) are available, printing out the PDF files if necessary. You will definitely need the Operating Manual for the server, the Options Guide for the server and the Technical Manual for the system board.
Ê Shut down the server correctly, switch it off, pull out the power plug, and open the server as described in the section “Opening the server” on page 13.
Ê Replace the faulty component as described in the relevant chapter.
Ê Close the server.1
Ê Connect the cables. 1
Ê Connect the server to the power outlet.1
Ê Start the operating system.1
Ê If necessary, configure the server as required.1
1 This procedures are described in the Operating Manual.
Service Supplement 5
3 Safety notesI The following safety notes are also provided in the “Safety” manual.
This device complies with the relevant safety regulations for data processing equipment.
V CAUTION!
The actions described in these instructions should only be performed by service personnel.
Before operating the device
V CAUTION!
● During installation and before operating the device, observe the instructions on environmental conditions for your device.
● If the device is brought in from a cold environment, condensation may form both inside and on the outside of the machine.
Wait until the device has acclimatized to room temperature and is absolutely dry before starting it up. Material damage may be caused to the device if this requirement is not observed.
● Transport the device only in the original packaging or in packaging that protects it from knocks and jolts.
Installation and operation
V CAUTION!
● If the rack model is integrated in an installation that receives power from an industrial (public) power supply network with the IEC309 connector, the (public) power supply protection must comply with the requirements for the non-industrial (public) power supply networks for the type A connector.
● The server automatically sets itself to a voltage in the range of 100 V to 240 V. Make sure that your local voltage is within this range.
● This device has a specially approved power cable and must only be connected to a grounded insulated socket.
Service Supplement 7
Safety notes
● Ensure that the power socket on the device or the grounded wall outlet is freely accessible.
● The ON/OFF button does not disconnect the device from the mains voltage. To disconnect the line voltage completely, remove all power plugs from the grounded insulated sockets.
V CAUTION!
● Always connect the device and the attached peripherals to the same power circuit. Otherwise you run the risk of losing data if, for example, the central processing unit is still running but the peripheral device (e.g. storage subsystem) has failed during a power outage.
● Data cables to peripheral devices must be adequately shielded.
● To the LAN wiring the requirements apply in accordance with the standards EN 50173 and EN 50174-1/2. As minimum requirement the use of a protected LAN line of category 5 for 10/100 MBps Ethernet, and/or of category 5e for Gigabit Ethernet is considered. The requirements of the specification ISO/IEC 11801 are to be considered.
● Route the cables in such a way that they do not form a potential hazard (make sure no-one can trip over them) and that they cannot be damaged. When connecting up a device, refer to the relevant notes in this manual.
● Never connect or disconnect data transmission lines during a storm (lightning hazard).
● In emergencies (e.g. damaged casing, controls or cables, penetration of liquids or foreign matter), switch off the device immediately, remove the power plug and contact your sales outlet or customer service team.
● Proper operation of the device (in accordance with IEC 60950/EN 60950) is only ensured if the casing is completely assembled and the rear covers for the installation openings have been put in place (electric shock, cooling, fire protection, interference suppression).
● Only install system expansions that satisfy the requirements and rules governing safety and electromagnetic compatibility and relating to telecommunications terminal equipment. If you install other expan-sions, you may damage the system or violate the safety regulations
8 Service Supplement
Safety notes
and regulations governing RFI suppression. Information on which system expansions are suitable can be obtained from the customer service centre or your sales outlet.
V CAUTION!
● The components or parts marked with a warning label (e.g. lightning symbol) may only be opened, removed or exchanged by authorized, qualified personnel. The hot-plug power supply units are exceptions to this rule.
● The warranty expires if the device is damaged during the installation or replacement of system expansions.
● You may only set those resolutions and refresh rates specified in the „Technical data“ section of the monitor description. Otherwise, you may damage your monitor. If you are in any doubt, contact your sales outlet or customer service centre.
Batteries
V CAUTION!
● Incorrect replacement of batteries may lead to a risk of explosion. The batteries may only be replaced with identical batteries or with a type recommended by the manufacturer (see the Technical Manual for the system board).
● Do not throw batteries into the trash can. They must be disposed of in accordance with local regulations concerning special waste.
● The battery must be disposed of in accordance with local regulations concerning special waste.
● Replace the lithium battery on the system board in accordance with the instructions in the Technical Manual for the system board.
● All batteries containing pollutants are marked with a symbol (a crossed-out garbage can). In addition, the marking is provided with the chemical symbol of the heavy metal decisive for the classification as a pollutant:
Cd Cadmium Hg Mercury Pb Lead
Service Supplement 9
Safety notes
Notes on handling CDs and CD-/DVD-ROM drives
V CAUTION!
● Use only CDs in proper condition in the CD-/DVD-ROM drive of your server to prevent data loss, damage to the device and injuries.
● Therefore, check each CD for damage, cracks, breakage etc. before inserting it in the drive.
Please note that any additional labels applied may change the mechanical properties of a CD and cause imbalance.
Damaged and imbalanced CDs can break at high drive speeds (data loss).
Under certain conditions sharp-edged pieces of broken CDs can penetrate the cover of the drive (damage to the device) and be thrown out of the device (danger of injury, particularly on uncovered body parts such as the face or neck).
I You protect the CD-/DVD-ROM drive and prevent mechanical damage, as well as premature wearing of the CDs, by observing the following suggestions:
– Only insert the CDs in the drive when needed and remove them after use.
– Store the CDs in suitable sleeves.– Protect the CDs from exposure to heat and direct sunlight.
10 Service Supplement
Safety notes
Note about the laser
The CD-/DVD-ROM drive is classified for laser class 1 according to IEC 60825-1.
V CAUTION!
The CD-/DVD-ROM drive contains a laser diode (LED). Sometimes the LED produces a stronger laser beam than laser class 1. Direct view into this laser beam is dangerous.
Never remove parts of the CD-/DVD-ROM drive assembly!
Modules with electrostatic-sensitive components:
Systems and components that might be damaged by electrostatic discharge (ESD) are marked with the following label:
Figure 1: ESD label
When you handle components fitted with ESDs, you must observe the following points under all circumstances:
● Remove the power plug from the power socket before inserting or removing components containing ESDs.
● You must always discharge yourself of static charges (e.g. by touching a grounded object) before working.
● The equipment and tools you use must be free of static charges.
● Only touch the components at the positions highlighted in green (touch points).
● Do not touch any exposed pins or conductors on a component.
● Use a grounding cable designed for this purpose to connect yourself to the system unit as you install components.
Service Supplement 11
Safety notes
● Place all components on a static-safe base.
I You will find a detailed description for handling ESD components in the relevant European or international standards (DIN EN 61340-5-1, ANSI/ESD S20.20).
12 Service Supplement
4 Replacement routinesV CAUTION!
Observe the safety instructions in the chapter “Safety notes” on page 7.
4.1 Preparation
I You will find a detailed description of ’Opening the server’ and ’Removing the front cover’ in the Options Guide PRIMERGY RX300 S2.
Ê Terminate all applications and shut down the server correctly.
Ê If your operating system has not switched off the server, press the on/off switch.
Ê Pull all power connectors out of the power outlets.
4.1.1 Opening the server
Ê Loosen the two knurled screws and pull the server as far as possible out of the rack.
Depending on how accessible the server is in the rack cabinet, it can make sense to remove it from the cabinet. You will find a detailed description in the Options Guide or the Operating Manual.
Ê Push the two locking buttons and remove the cover.
Ê Slide the cover to the rear side and remove it.
4.2 Replacing the operating panel
Ê Open the server as described in the section “Opening the server” on page 13.
Service Supplement 13
Replacing the operating panel Replacement routines
Figure 2: Unlocking the operating panel module
Ê Press the locking handle downward.
Ê Push the frame to the front side.
Figure 3: Removing the connector from the operating panel
Ê Remove the cable from the operating panel and pull it out of the cable clamp.
Ê Pull the frame outward to the front side.
14 Service Supplement
Replacement routines Replacing USB module
Figure 4: Removing the operating panel out of the frame
Ê Remove the operating panel out of the frame.
The installation takes place in reverse order.
Information about the cabling you will find the „appendix“ of the Options Guide.
4.3 Replacing USB module
Ê Open the server as described in the section “Opening the server” on page 13.
Ê Remove the USB connector from the system board.
Service Supplement 15
Replacing USB module Replacement routines
Figure 5: Unlocking the USB module frame
Ê Unlock the USB module fame.
Ê Push USB module frame to the front side.
Figure 6: Removing the USB module frame
Ê Pull the USB module frame out.
Ê Remove the cable from the connector of the USB panel and out of the clamp.
Ê Remove the backplane.
16 Service Supplement
Replacement routines Replacing the floppy disk drive
The installation takes place in reverse order
I Do not forget to replace the insulation foil and be sure that the lower border of the black cover is inside of the metal holder.
Information about the cabling you will find in the „appendix“ of the Options Guide.
4.4 Replacing the floppy disk drive
You will find a detailed description of ’Replacing the floppy disk drive’ in the Options Guide PRIMERGY RX300 S2.
4.5 Replacing the LocalView module
You will find a detailed description of ’Replacing the LocalView module’ in the Options Guide PRIMERGY RX300 S2.
4.6 Replacing CD/DVD drive
You will find a detailed description of ’Replacing the CD/DVD drive’ in the Options Guide PRIMERGY RX300 S2.
4.7 Replacing the Power backplane
Ê Open the server as described in the section “Opening the server” on page 13.
Service Supplement 17
Replacing the SCSI backplane Replacement routines
Figure 7: Removing power backplane
Ê Remove all cables.
Ê Remove the screw.
Ê Push the backplane to the right side out of the stamping in the plate.
Ê Take the backplane out.
The Installation takes place in reverse order.
Information about the cabling you will find the „appendix“ of the Options Guide.
4.8 Replacing the SCSI backplane
Ê Open the server as described in the section “Opening the server” on page 13.
4.8.1 Replacing the 1st SCSI-Backplane
Ê Remove the fan box.
I You will find a detailed description of ’Removing the fan box’ in the Options Guide PRIMERGY RX300 S2.
18 Service Supplement
Replacement routines Replacing the SCSI backplane
Figure 8: Removing the 1st SCSI backplane
Ê Remove all cables from SCSI Backplane.
Ê Open the knurled screw (1).
Ê Twist the SCSI backplane holder t slightly (2).
V CAUTION
Do not damage the hooks which form a hinge for the SCSI backplane.
Ê Pull the SCSI backplane holder out (3).
2 3
1
Service Supplement 19
Replacing the hot-plug PCI board Replacement routines
Figure 9: Removing the backplane from the holder
Ê Unlock the backplane from the snap-fits.
Ê Remove the SCSI backplane from the holder.
The Installation takes place in reverse order.
4.8.2 Replacing the 2nd SCSI backplane
I You will find a detailed description of ’Replacing 2nd SCSI backplane’ in the Options Guide PRIMERGY RX300 S2.
4.9 Replacing the hot-plug PCI board
Ê Open the server as described in the section “Preparation” on page 13.
Ê e controllers from both hot-plug PCI slots.
Ê Remove the cable from the connector on hot-plug Board.
20 Service Supplement
Replacement routines Replacing the hot-plug PCI board
Figure 10: Removing the hot-plug board
Ê Unlock the snap-fits.
V CAUTION
Be very careful, the PCI holders are delicate and easily damaged.
Ê Remove the board.
Ê Insert the new board and press it down.
V CAUTION
Be careful, the PCI holders are delicate and easily damaged. They must lock correctly.
The Installation takes place in reverse order.
Information about the cabling you will find in the „appendix“ of the Options Guide.
Service Supplement 21
Replacing the IDTemp Combo Replacement routines
4.10 Replacing the IDTemp Combo
This board includes two important system components:– EEPROM for the chassis ID and Ident number of the server– temperature sensor for monitoring the environment temperature
The data for the EEPROM, and the current temperature values as well, are transmitted to the system board via the connected I2C bus. The IDTEMP combo must be correctly installed in order:– to monitor the temperature correctly,– to enable the server management to display the correct system picture,– to install the server using ServerStart.
V CAUTION!
The IDTEMP combo may not be changed because of the information which is in the EEPROM to identify the system.If the combo is defective, a spare part must be ordered specially by specifying the ident number (see the type label).
Ê Open the server as described in the section “Preparation” on page 13.
Ê Remove the fan box.
I Information to this item you will find in the ’PRIMERGY RX300 S2 Options Guide’.
Figure 11: Removing the IDTemp Combo with its holder
Ê Push the holder with the IDTemp Combo outward.
22 Service Supplement
Replacement routines Replacing the processor heat sink
Figure 12: Removing the IDTemp Combo from its holder
Ê Remove the connector clamp.
Ê Insert the IDTemp Combo into the holder.
The Installation takes place in reverse order.
Information about the cabling you will find in the „appendix“ of the Options Guide PRIMERGY RX300 S2.
4.11 Replacing the processor heat sink
Ê Open the server as described in the Options Guide PRIMERGY RX300 S2.
Ê Remove the air duct over the main memory and the processors (see Options Guide PRIMERGY RX300 S2).
Ê Loosen the four screws on the heat sink socket in a crossover pattern (Options Guide PRIMERGY RX300 S2).
Ê Loosen the heat sink by turning it back and forth and then lift it out.
Ê Clean the upper side of the processor using a lint-free cloth.
Ê Remove the protective cover from the new heat sink.
Ê Place the heat sink on the processor socket (see Options Guide PRIMERGY RX300 S2).
Ê Fasten the heat sink by tightening the four screws in a crossover pattern.
Service Supplement 23
Replacing the system board Replacement routines
Ê Reinstall the air duct over the main memory and the processors (see Options Guide)
The installation takes place in reverse order.
4.12 Replacing the system board
Ê Open the server as described in the section “Preparation” on page 13.
Ê Remove the fan box, processor heat sinks, processors, and PCI controllers. If a riser card is installed, it has to be removed too.
I Information to this item you will find in the ’PRIMERGY RX300 S2 Options Guide’.
Figure 13: Removing the cables from the system board
24 Service Supplement
Replacement routines Replacing the system board
Ê Remove the cables from the system board.
Ê Remove the part of the cable duct cover, that is marked.See Options Guide PRIMERGY RX300 S2 in chaper „external SCSI interface“.
Ê Remove all screws. See also board layout in section “System Board” on page 34.
Figure 14: Removing system board
V CAUTION
Hold the board at its memory slots of the RAID cache and the main memory, but not at the remaining heat sinks.
Ê Pull the system board somewhat to the front side (1).
Ê Pull the system board out. You will need to tilt it at an angle to do this (2).
Ê Insert the new system board. You will need to angle this in order to fit it, as you did when removing the old one.
1
2
Service Supplement 25
Replacing the system board Replacement routines
V CAUTION
Be careful with the I/O field insulation. When you insert the system bord, the I/O field insulation can be removed from the I/O field and can be pressed down.
Ê Position the system board carefully, ensuring the exact alignment of the holes with the corresponding supports.
Figure 15: Springs for the heat sink
V CAUTION
Springs under the system board must be aligned properly under the screw holes.
Ê Press the board down at both the fixing points (the two back marked holes on the layout drawing “System Board” on page 34).
Ê Fix the board with all screws.
I The 6 screws under the fan cage must fix also the black plastic holders for the fan cage.
The Installation takes place in reverse order.
Information about the cabling you will find in the „appendix“ of the Options Guide.
26 Service Supplement
5 Appendix
5.1 Board layouts
5.1.1 Operating panel
Part number: A3C40052694
Figure 16: Operating panel
5.1.2 USB panel board
Part number: A3C40052698
Figure 17: USB panel board
Connector Description
X1 Connector operating panel to system board
X1
X1 X2
Service Supplement 27
Board layouts Appendix
5.1.3 Power Backplane
Part number: A3C40051768
Figure 18: Power Backplane
Connector Description
X1 Connector USB cable to system board
X2 External USB connectors
Connector Cable number Description
X1 - SV 1
X2 - SV 2
X3
X4
X5
X6
X7
X1
X2
28 Service Supplement
Appendix Board layouts
X3 A3C40057188 Power 24 polig to system board
X4 A3C40057447 12 V to system board
X5 A3C40057191 Power to 1st SCSI backplane
X6 A3C400058003 power to 2nd SCSI backplane and CD-ROM drive
X7 A3C40057192 PC 98 connector to system board
Connector Cable number Description
Service Supplement 29
Board layouts Appendix
5.1.4 SCSI Backplane
5.1.4.1 1st SCSI backplane and 2nd 2-channel SCSI backplane
Part number: A3C40052609
Figure 19: 1st SCSI backplane side facing the system board
Connector Description
X1 SCSI cable
X5 Power
X7 SCSI control cable
X8 I2C connector
X1
X7
X8
X5
30 Service Supplement
Appendix Board layouts
Figure 20: 1st SCSI backplane side facing hard disks
X2
X3
X4
Service Supplement 31
Board layouts Appendix
5.1.4.2 2nd 1-channel SCSI backplane
Part number: A3C40053292
Figure 21: 2nd SCSI Backplane facing to the system board
Connector Description
X1 SCSI cable to the system board
X5 Power
X6 I2C connector
X7 SCSI control cable
X8 SCSI cable to the 1st SCSI backplane
X1
X7
X6
X5
X8
32 Service Supplement
Appendix Board layouts
Figure 22: 2nd SCSI backplane side facing the hard disks
5.1.5 IDTemp Combo
Figure 23: IDTemp Combo
Connector Description
X1 I2C connector
X2
X3
X4
X1
Service Supplement 33
Board layouts Appendix
5.1.6 System Board
Figure 24: System board
34 Service Supplement
Appendix Cabling
I You will find the connector description and the extension in the „technical manual of system board D1889“.
5.2 Cabling
I You will find the drawings of the cabling and the list of cabling in the „Options Guide PRIMERGY RX300 S2“
Service Supplement 35
Cabling Appendix
36 Service Supplement
Index
EESD (devices sensitive to electrostaticdischarge) 11ESD-sensitive devices 11
Hheat sink 23holder of the 1st SCSI backplane 19hot-plug PCI board 20Hot-plug Print 20
II/O field insulation 26IDTemp Combo 22
Llight-emitting diode (LED) 11lithium battery 9locking handle operating panel
module 14locking handle USB module 16
Mmeaning of the symbols 4
Nnotational conventions 4note about the laser 11
Ooperating panel 13Overview documentation 1
Pprocessor heat sink 23
Ttarget group 1touche points 11
Service Supplement 37
Index
38 Service Supplement
Comments on PRIMERGY RX300 S2 Service Supplement
CommentsSuggestionsCorrections
✁
Submitted by
Fujitsu Siemens Computers GmbHUser Documentation81730 MunichGermany
Fax: (++49) 700 / 372 00000
email: [email protected]://manuals.fujitsu-siemens.com
Comments on PRIMERGY RX300 S2 Service Supplement
CommentsSuggestionsCorrections
✁
Submitted by
Fujitsu Siemens Computers GmbHUser Documentation81730 MunichGermany
Fax: (++49) 700 / 372 00000
email: [email protected]://manuals.fujitsu-siemens.com
PRIMERGY
PRIMERGY RX300 S2Server System Options GuideMonika SpanjaartFujitsu Siemens Computers GmbH München81730 Muniche-mail: email: [email protected].: (089) 61001-160Fax: (++49) 700 / 372 00000U41601-J-Z156-1-76Sprachen: En
Edition December 2004
Comments… Suggestions… Corrections…The User Documentation Department would like toknow your opinion of this manual. Your feedback helpsus optimize our documentation to suit your individual needs.
Fax forms for sending us your comments are included inthe back of the manual.
There you will also find the addresses of the relevantUser Documentation Department.
Certified documentation according to DIN EN ISO 9001:2000To ensure a consistently high quality standard anduser-friendliness, this documentation was created tomeet the regulations of a quality management system which complies with the requirements of the standardDIN EN ISO 9001:2000.
cognitas. Gesellschaft für Technik-Dokumentation mbHwww.cognitas.de
Copyright and Trademarks
Copyright © 2004 Fujitsu Siemens Computers GmbH.All rights reserved.Delivery subject to availability; right of technical modifications reserved.
All hardware and software names used are trademarks of their respective manufacturers.
This manual is printed on paper treated with chlorine-free bleach.
Introduction
Procedure
Safety notes
Preparation
Main memory
Processors
ROMB (RAID on Motherboard)
Accessible drives
PCI slots
RemoteView components
Continued
External SCSI interface
Parallel interface
Converting from 1- to 2-channel version
Converting from low-profile to standard PCI Slots
Completion
Appendix
Related publications
Index
Contents1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11.1 Overview of the documentation . . . . . . . . . . . . . . . . . . 11.2 Options and upgrade . . . . . . . . . . . . . . . . . . . . . . . 31.3 Notational conventions . . . . . . . . . . . . . . . . . . . . . . . 6
2 Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
3 Safety notes . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
4 Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . 154.1 Removing the server form the rack . . . . . . . . . . . . . . . 154.2 Opening the server . . . . . . . . . . . . . . . . . . . . . . . 17
5 Main memory . . . . . . . . . . . . . . . . . . . . . . . . . . 195.1 Memory module population . . . . . . . . . . . . . . . . . . . 195.2 Upgrading/replacing the main memory . . . . . . . . . . . . . 22
6 Processors . . . . . . . . . . . . . . . . . . . . . . . . . . . 276.1 Installing a second processor . . . . . . . . . . . . . . . . . . 276.2 Replacing the processor . . . . . . . . . . . . . . . . . . . . . 32
7 ROMB (RAID on Motherboard) . . . . . . . . . . . . . . . . 357.1 Installing the ROMB upgrade kit . . . . . . . . . . . . . . . . . 35
8 Accessible drives . . . . . . . . . . . . . . . . . . . . . . . 378.1 Installing a FD drive . . . . . . . . . . . . . . . . . . . . . . . 388.2 Installing a LocalView module . . . . . . . . . . . . . . . . . . 438.3 Installing the CD/ DVD-ROM drive . . . . . . . . . . . . . . . . 50
9 PCI slots . . . . . . . . . . . . . . . . . . . . . . . . . . . . 559.1 Installing a PCI controller in a low-profile slot . . . . . . . . . . 569.2 Installing the PCI controller in the riser card . . . . . . . . . . . 589.3 Population of the PCI slots . . . . . . . . . . . . . . . . . . . . 61
10 RemoteView components . . . . . . . . . . . . . . . . . . . 6310.1 Installing the chipDISK . . . . . . . . . . . . . . . . . . . . . . 6310.2 RemoteView Service Board S2 LP . . . . . . . . . . . . . . . 64
U41601-J-Z156-1-76 Options Guide
Contents
11 External SCSI interface . . . . . . . . . . . . . . . . . . . . . 6711.1 Installing the external SCSI interface . . . . . . . . . . . . . . . 67
12 Parallel interface . . . . . . . . . . . . . . . . . . . . . . . . . 7912.1 Installing a parallel interface . . . . . . . . . . . . . . . . . . . 79
13 Converting from 1- to 2-channel version . . . . . . . . . . . . 8513.1 Removing 2nd SCSI backplane . . . . . . . . . . . . . . . . . . 8713.2 Installing 2nd SCSI backplane . . . . . . . . . . . . . . . . . . 90
14 Converting from low-profile to standard PCI Slots . . . . . . 9314.1 Removing lp slot cage . . . . . . . . . . . . . . . . . . . . . . 9314.2 Installing Riser card . . . . . . . . . . . . . . . . . . . . . . . . 96
15 Completion . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9915.1 Closing the server . . . . . . . . . . . . . . . . . . . . . . . . . 99
16 Appendix . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10316.1 Cabling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10316.2 Configuration diagram . . . . . . . . . . . . . . . . . . . . . 10616.3 Hard disk mirroring . . . . . . . . . . . . . . . . . . . . . . . 107
Related publications . . . . . . . . . . . . . . . . . . . . . . . . . . . 109
Index . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111
Options Guide U41601-J-Z156-1-76
1 IntroductionThe PRIMERGY RX300 S2 has been designed for multi-server configurations (clusters), front-end solutions, e-commerce applications and ERP solutions. The PRIMERGY RX300 S2 is outstanding for applications and fields of use that demand maximum scalability, performance and availability in a space-saving rack cabinet.
The PRIMERGY RX300 S2 offers very great expandability with up to 6 hard disks for a rack server and takes up just 2 height units (U) in a 19-inch rack.
1.1 Overview of the documentation
I PRIMERGY manuals are available in PDF format on the ServerBooks CD which is supplied in the ServerView Suite package for every server system.
These PDF files can also be downloaded free of charge from the Internet: at http://manuals.fujitsu-siemens.com you will find an overview page with the online documentation available on the Internet. You can go to the PRIMERGY Server documentation by clicking on “intel based Servers”.
Concept and target groups
This Options Guide shows you how you can expand and upgrade the server.
I The Operating Manual for the server describes how you install/remove the hot-plug components.
The activities described in this manual may only be performed by specialist personnel with technical training.
Additional documentation about the server
The PRIMERGY TX300 S2 documentation comprises the following additional manuals:
– The “Security” manual (printed copy always supplied with the server, and available as a PDF file on the ServerBooks CD supplied)
– The “Guarantee” manual (printed copy always supplied with the server, and available as a PDF file on the ServerBooks CD supplied)
U41601-J-Z156-1-76 Options Guide 1
Overview of the documentation Introduction
– The Operating Manual for PRIMERGY RX300 S2 S2 (PDF available on the ServerBooks CD supplied)
– The Technical Manual for the system board D1889 (PDF available on the ServerBooks CD supplied)
– The “BIOS Setup” manual (PDF available on the ServerBooks CD supplied)– The “PRIMERGY ServerView Suite - ServerStart” manual (printed copy
always supplied with the server, and available as PDF file on the ServerBooks CD supplied)
I You can order a supplementary ServerBooks CD by sending an e-mail to the following address, quoting your server data: [email protected]
Further sources of information:
– Technical Manual on the relevant rack– Manual on the monitor– Manual on ServerView Server Management– Manual on the RemoteView Remote Test and Diagnostics System – Manual on LocalView– Documentation on boards and drives– Documentation on your operating system– Information files on your operating system
(see also chapter „Related publications“ on page 109)
2 Options Guide U41601-J-Z156-1-76
Introduction Options and upgrade
1.2 Options and upgrade
Second processor
The system board can be upgraded with a second processor. Only processors of the same type may be used on the system board. The second processor must have the same clock frequency and the same cache as the first processor.
Upgrading of the main memory
The eight slots for the main memory are suitable for PC2-3200 DDR DIMM memory modules. The organization in four memory banks, 0 to 3, permits rapid memory access with two-way interleaving.
Memory modules must always be incorporated in pairs. A memory bank must always be equipped fully with the same type of memory modules.
ROMB (RAID on motherboard)
The System is extended with an on board Intel I/O processor. If the controller is activated, the on-board 2 channel U320 SCSI-Controller supports RAID Level 0, 1, 10, 5 and 50 on both SCSI channels
"MegaRaid PCI Express™ ROMB" can be activated with two different upgrading kits.
Additional accessible drives
One 3.25-inch bay and one 3,5-inch bay are available for accessible drives.
One 5.25-inch bay can be installed with a 3.5 inch x 0.5 inch floppy disk drive or a LocalView module and the other bay can be installed with a 5.25-inch x 0,5 inch DVD-ROM drive.
LocalView module (alphanumeric system display)
The LocalView module provides you with the option of displaying system infor-mation and hardware system faults alphanumerically. This is an intelligent module with a micro-controller and its own memory, which functions indepen-dently of the server system.
U41601-J-Z156-1-76 Options Guide 3
4
Options and upgrade Introduction
The Lboth allowmatiothe L
Hard
the inaccoAttacSCSsimpand trepla
Addi
The sa PCwork
PCI sthat hOper
Optio
Optiocontrshortheigh
Rem
RemThe tmemdiagn
ocalView module consists of an LCD display panel and a toggle switch, accommodated in a suitable mount. The mechanical mechanism used s the LCD display panel to be pulled out and flapped out. Further infor-n on operating the display modes are provided in the documentation on ocalView module.
disk drives
stallation up to six HDD modules is possible. Each HDD module can mmodate a SCSI hard disk drive with an SCA (Single Connector hment) interface and a height of at most 1 inch. The connection to the I backplane is made without cables via the SCA interface. This makes it le to plug in or pull out the HDD modules. If the server has a RAID controller he corresponding RAID configuration, faulty HDD modules can also be ced while the system is operating.
tional controllers in non-hot-plug PCI slots
ystem board offers five PCI slots. Slots 1-3 are non-hot-plug PCI slots with I bus speed of 100 MHz. If slot 1 and slot 2 are not occupied, slot 3 can with the PCI bus speed of 133 MHz (IDoubleOP™).
lots 4 and 5 are hot-plug PCI slots which can be equipped with controllers ave hot-plug capability (the hot-plug PCI slots are described in the ating Manual).
nal riser card
nally you can install a Riser card into slot 5, which can be equipped with 3 ollers. The bus speed is 100 MHz. Two slots (6 and 7) can be equipped with standard PCI controllers and slot 8 can be equipped with a full length full t PCI controller.
oteView
oteView provides you with a comprehensive test and diagnostics package. est and diagnostics software is stored on a chipDISK. The chipDISK is a ory component with an IDE interface. In the event of a fault the test and ostics software is automatically loaded from the chipDISK and executed.
Options Guide U41601-J-Z156-1-76
U41601-J-Z156-1-76 Options Guide 5
Introduction Options and upgrade
RemoteView Service Board S2 LP (2U/3U)
The RemoteView Service Board S2 LP (RSB S2 LP) is a PCI board with a completely independent system, i.e. it has its own operating system with Web server and SNMP agents and can optionally be equipped with an external power supply. The RSB permits remote diagnosis for system analysis, remote system configuration and remote restart even in the event of operating system failure or hardware faults. It has its own LAN connection. All the functions of the RSB are available via a LAN.
External SCSI interface
One channel of the on-board SCSI controller can optionally be made available externally.
Parallel interface for printers
As an option, a parallel interface can be provided for printers.
Conversion of SCSI 1-channel version to SCSI 2-channel version
The internal SCSI configuration can be converted from a 1-channel version to a 2-channel version. The hard disk access times are shortened. Use of the 2-channel version together with a RAID controller increases the availability of the system.
Notational conventions Introduction
1.3 Notational conventions
The following notational conventions are used in this manual:
Text in italics indicates commands, menu items or software programs.
„Quotation marks“ indicate names of chapters and terms that are being emphasized.
Ê describes activities that must be performed in the order shown.
V CAUTION! pay particular attention to texts marked with this symbol. Failure to observe this warning may endanger your life, destroy the system or lead to the loss of data.
I indicates additional information, notes and tips.
Table 1: Notational conventions
6 Options Guide U41601-J-Z156-1-76
2 ProcedureV CAUTION!
The actions described in these instructions should only be performed by technical specialists or service personnel. Equipment repairs should only be performed by authorized, qualified staff. Any unauthorized opening and improper repairs could expose the user to risks (electric shock, energy hazards, fire hazards) and could also damage the equipment. Please note that any unauthorized opening of the device will result in the invalidation of the warranty and exclusion from all liability.
Ê First of all please familiarize yourself with the safety instructions in the section chapter „Safety notes“ on page 9.
Ê Ensure that all required manuals (see „Additional documentation about the server“ on page 1) are available, printing out the PDF files if necessary. You will definitely need the Operating Manual for the server and the Technical Manual for the system board.
Ê Shut down the server correctly, switch it off, pull out the power plug, and open the server as described in the chapter „Preparation“ on page 15.
Ê Extend or upgrade your server as described in the relevant chapter.
I The Operating Manual for the server describes how you install/remove the hot-plug components.
Ê Close the server, connect it to the power outlet, and switch it on as described in the chapter „Completion“ on page 99.
Ê Start the operating system and, if necessary, configure it as required (see the Operating Manual).
U41601-J-Z156-1-76 Options Guide 7
3 Safety notesI The following safety notes are also provided in the “Safety” manual.
This device complies with the relevant safety regulations for data processing equipment.
If you have any questions about where you can set up the device, contact your sales outlet or our customer service team.
V CAUTION!
The actions described in these instructions should only be performed by technical specialists. Equipment repairs should only be performed by authorized, qualified staff. Any unauthorized openings and improper repairs could expose the user to risks (electric shock, energy hazards, fire hazards) and could also damage the equipment. Please note that any unauthorized openings of the device will result in the invalidation of the warranty and exclusion from all liability.
Before operating the device
V CAUTION!
● During installation and before operating the device, observe the instructions on environmental conditions for your device
● If the device is brought in from a cold environment, condensation may form both inside and on the outside of the machine.
Wait until the device has acclimatized to room temperature and is absolutely dry before starting it up. Material damage may be caused to the device if this requirement is not observed.
● Transport the device only in the original packaging or in packaging that protects it from knocks and jolts.
U41601-J-Z156-1-76 Options Guide 9
Safety notes
Installation and operation
V CAUTION!
● If the rack model is integrated in an installation that receives power from an industrial (public) power supply network with the IEC309 connector, the (public) power supply protection must comply with the requirements for the non-industrial (public) power supply networks for the type A connector.
● The server automatically sets itself to a voltage in the range of 100 V to 240 V. Make sure that your local voltage is within this range.
● This device has a specially approved power cable and must only be connected to a grounded insulated socket.
● Ensure that the power socket on the device or the grounded wall outlet is freely accessible.
● The ON/OFF button does not disconnect the device from the mains voltage. To disconnect the line voltage completely, remove the power plug(s) from the grounded insulated socket(s).
V CAUTION!
● Always connect the device and the attached peripherals to the same power circuit. Otherwise you run the risk of losing data if, for example, the central processing unit is still running but the peripheral device (e.g. storage subsystem) has failed during a power outage.
● Data cables to peripheral devices must be adequately shielded.
● To the LAN wiring the requirements apply in accordance with the standards EN 50173 and EN 50174-1/2. As minimum requirement the use of a protected LAN line of category 5 for 10/100 MBps Ethernet, and/or of category 5e for Gigabit Ethernet is considered. The requirements of the specification ISO/IEC 11801 are to be considered.
● Route the cables in such a way that they do not form a potential hazard (make sure no-one can trip over them) and that they cannot be damaged. When connecting up a device, refer to the relevant notes in this manual.
● Never connect or disconnect data transmission lines during a storm (lightning hazard).
10 Options Guide U41601-J-Z156-1-76
Safety notes
● In emergencies (e.g. damaged casing, controls or cables, penetration of liquids or foreign matter), switch off the device immediately, remove the power plug(s) and contact your sales outlet or customer service team.
● Proper operation of the device (in accordance with IEC 60950/EN 60950) is only ensured if the casing is completely assembled and the rear covers for the installation openings have been put in place (electric shock, cooling, fire protection, interference suppression).
● Only install system expansions that satisfy the requirements and rules governing safety and electromagnetic compatibility and relating to telecommunications terminal equipment. If you install other expan-sions, you may damage the system or violate the safety regulations and regulations governing RFI suppression. Information on which system expansions are suitable can be obtained from the customer service centre or your sales outlet.
V CAUTION!
● The components marked with a warning label (e.g. lightning symbol) may only be opened, removed or exchanged by authorized, qualified personnel. The hot-plug power supply units are exceptions to this rule.
● The warranty expires if the device is damaged during the installation or replacement of system expansions.
● You may only set those resolutions and refresh rates specified in the „Technical data“ section of the monitor description. Otherwise, you may damage your monitor. If you are in any doubt, contact your sales outlet or customer service centre.
Batteries
V CAUTION!
● Incorrect replacement of batteries may lead to a risk of explosion. The batteries may only be replaced with identical batteries or with a type recommended by the manufacturer (see the technical manual for the system board D1889).
● Do not throw batteries into the trash can. They must be disposed of in accordance with local regulations concerning special waste.
U41601-J-Z156-1-76 Options Guide 11
Safety notes
● The battery must be disposed of in accordance with local regulations concerning special waste.
● Replace the lithium battery on the system board in accordance with the instructions in the technical manual for the system board D1889.
● All batteries containing pollutants are marked with a symbol (a crossed-out garbage can). In addition, the marking is provided with the chemical symbol of the heavy metal decisive for the classification as a pollutant:
Cd Cadmium Hg Mercury Pb Lead
Notes on handling CDs and CD-/DVD-ROM drives
V CAUTION!
● Use only CDs in proper condition in the CD-/DVD-ROM drive of your server to prevent data loss, damage to the device and injuries.
● Therefore, check each CD for damage, cracks, breakage etc. before inserting it in the drive.
Please note that any additional labels applied may change the mechanical properties of a CD and cause imbalance.
Damaged and imbalanced CDs can break at high drive speeds (data loss).
Under certain conditions sharp-edged pieces of broken CDs can penetrate the cover of the drive (damage to the device) and be thrown out of the device (danger of injury, particularly on uncovered body parts such as the face or neck).
I You protect the CD-/DVD-ROM drive and prevent mechanical damage, as well as premature wearing of the CDs, by observing the following suggestions:
– Only insert the CDs in the drive when needed and remove them after use.
– Store the CDs in suitable sleeves.– Protect the CDs from exposure to heat and direct sunlight.
12 Options Guide U41601-J-Z156-1-76
Safety notes
Note about the laser
The CD-/DVD-ROM drive is classified for laser class 1 according to IEC 60825-1.
V CAUTION!
The CD-/DVD-ROM drive contains a laser diode (LED). Sometimes the LED produces a stronger laser beam than laser class 1. Direct view into this laser beam is dangerous.
Never remove parts of the CD-/DVD-ROM drive assembly!
Modules with electrostatic-sensitive components
Systems and components that might be damaged by electrostatic discharge (ESD) are marked with the following label:
Figure 1: ESD label
When you handle components fitted with ESDs, you must observe the following points under all circumstances:
● Remove the power plug(s) from the power socket(s) before inserting or removing components containing ESDs.
● You must always discharge yourself of static charges (e.g. by touching a grounded object) before working.
● The equipment and tools you use must be free of static charges.
● Only touch the components at the positions highlighted in green (touch points).
● Do not touch any exposed pins or conductors on a component.
● Use a grounding cable designed for this purpose to connect yourself to the system unit as you install components.
U41601-J-Z156-1-76 Options Guide 13
Safety notes
● Place all components on a static-safe base.
I You will find a detailed description for handling ESD components in the relevant European or international standards (DIN EN 61340-5-1, ANSI/ESD S20.20).
14 Options Guide U41601-J-Z156-1-76
4 PreparationV CAUTION!
Observe the safety instructions in the chapter „Safety notes“ on page 9.
4.1 Removing the server form the rack
Ê Terminate all applications and shut down the server correctly.
Ê If your operating system has not switched off the sever, press the on/off switch.
Ê Pull all power connectors out of the power outlets.
Figure 2: Loosening the knurled screws
Ê Loosen the four knurled screws (1) and pull the server as far as possible out of the rack (2).
2
1
1
U41601-J-Z156-1-76 Options Guide 15
Removing the server form the rack Preparation
Depending on how accessible the server is in the rack cabinet, it can make sense to remove it from the cabinet. If you do not want to remove the server from the rack cabinet, please skip this page.
Figure 3: Removing the server from the rack cabinet
Ê Disconnect all cables on the rear of the server.
Ê Pull the server outward as far as it will go (1), release the hooks (2), then pull out the Server completely.
V CAUTION!
At least two people are needed to lift the server out of the rack cabinet.
1
2
16 Options Guide U41601-J-Z156-1-76
Preparation Opening the server
4.2 Opening the server
Figure 4: Removing the top cover
Ê Pess the two locking buttons (1) downward and remove the cover (2).
Ê Slide the cover to the rear side and remove it (2).
1
12
U41601-J-Z156-1-76 Options Guide 17
5 Main memoryV CAUTION!
Observe the safety instructions in the chapter „Safety notes“ on page 9.
The system board supports up to 16 Gbytes of main memory. 8 slots (4 memory banks with 2 slots each) are provided for the main memory. Each memory bank is equipped with two 512-Mbyte, 1-Gbyte or 2-Gbyte registered DDR2 400 (PC2-3200) memory modules.
A memory bank can optionally be configured as a hot-spare bank.
As memory bank 3 is already equipped either with 1-Gbyte, 2-Gbyte or4-Gbyte of memory in the basic unit, up to 3 memory upgrades can be fitted, one to each banks 2, 1 and 0.
ECC with memory scrubbing and with the Single Device Data Correction (SDDC, Chipkill) function is standard.
5.1 Memory module population
Figure 5: Structure of the main memory in memory banks and memory modules
– The memory modules have to be based on x4 organized SDRAM and must be populated in pairs
Memory bank 0 - DIMM-0A
Memory bank 0 - DIMM-0B
Memory bank 1 - DIMM-1A
Memory bank 1 - DIMM-1B
Memory bank 2 - DIMM-2A
Memory bank 2 - DIMM-2B
Memory bank 3 - DIMM-3A
Memory bank 3 - DIMM-3B
U41601-J-Z156-1-76 Options Guide 19
Memory module population Main memory
– Each pair must consist of identical memory modules (2-way Interleaved-mode).
– The memory module capacity can differ for the various memory banks: e.g. memory bank 0A/0B can be equipped with two 512-Mbyte memory modules, and memory bank 1A/1B with two 1-Gbyte memory modules.
– Only single ranked modules are permitted.
The following table shows the required memory population sequence:
Memory mirroring
Either 4 or 8 identical memory modules are required for memory mirroring:
DIMM-3A/DIMM-3B DIMM-2A/DIMM-2B DIMM-1A/DIMM-1B DIMM-0A/DIMM-0B
populated empty empty empty
populated populated empty empty
populated populated populated empty
populated populated populated populated
Memory bank
3 2 1 0
Channel (module)
A B A B A B A B
population 4 identical memory modules - -
4 identical memory modules 4 identical memory modules
20 Options Guide U41601-J-Z156-1-76
Main memory Memory module population
Figure 6: Diagram Memory Mirroring
I For more information see BIOS-Setup manual (see chapter „Related publications“ auf Seite 109).
� Supported for 8 DIMMs of DDR2-400 ( PC2-3200 )� The diagonal mirroring implementation shown below allows bandwidth on
both channels to be fully utilized during normal operation� Every write to memory is issued twice, one to primary location, and again to
mirror location� Memory has two full copies of all data and a complete copy on each channel
� System Requirements� 4 DIMMs with completely identical devices in slots 3 & 4 on each channel� 4 DIMMs with completely identical devices in slots 1 & 2 on each channel
Lindenhurst MCH
DIMM
A1
DIMM
A2
DIMM
A3
DIMM
A4
D IMM
B 1
D IMM
B 2
D IMM
B 3
D IMM
B 4
Channel A
Channel B
Memory Subsystem
Mirror Mirror PrimaryPrimary
Memory Mirroring with 4 or 8 DIMMs
DIM
M A3
DIMM
B3D
IMM
B2
DIMM
A3D
IMM
B 3
DIM
M A2
DIM
M A4
DIM
M B4
U41601-J-Z156-1-76 Options Guide 21
Upgrading/replacing the main memory Main memory
5.2 Upgrading/replacing the main memory
Ê Open the server as described in the chapter „Safety notes“ on page 9.
Removing the air duct over the main memory and the processors
Figure 7: Removing the air duct over the main memory and the processors
Ê Lift out the air duct over the main memory.
22 Options Guide U41601-J-Z156-1-76
Main memory Upgrading/replacing the main memory
Figure 8: populating memory module slots
Figure 9: Removing a memory module
Ê Press the holders on either side of the mounting location concerned outward (1).
Ê Pull the memory module out of the mounting location (2).
1
12
U41601-J-Z156-1-76 Options Guide 23
Upgrading/replacing the main memory Main memory
Figure 10: Inserting a memory module
Ê Press the holders on either side of the mounting location concerned outward.
Ê Insert the memory module in the mounting location (1) until the holders at the sides engage (2).
2
2
24 Options Guide U41601-J-Z156-1-76
Main memory Upgrading/replacing the main memory
Inserting air duct
Figure 11: Installing the air duct over the memory and processors
Ê Reinstall the air duct over the system fans.
V CAUTION!
Ensure that no damage is caused to the cables!
U41601-J-Z156-1-76 Options Guide 25
Upgrading/replacing the main memory Main memory
Figure 12: Guiding edge between the air duct and fanbox
Figure 13: Support point of the air duct.
Ê Pay attention to the guiding edge between the air duct and the fan box (1) and ensure a correct fit, especially at the places (2, 3 and 4).
Ê Close the server, connect it to the power outlet, and switch it on as described in the chapter „Completion“ on page 99.
1
2
3 4
26 Options Guide U41601-J-Z156-1-76
6 ProcessorsV CAUTION!
Observe the safety instructions in the chapter „Safety notes“ on page 9.
V CAUTION!
Processors are modules which can react extremely sensitively to electro-static discharges and which must therefore always be handled with care. After a processor has been removed from its protective sleeve or from its socket, place it with its smooth side down on a non-conducting, antistatic surface. Never push a processor over a surface.
6.1 Installing a second processor
The system board can be upgraded with a second processor. The upgrade kit consists of a processor, and a heat sink.
V CAUTION!
Only processors of the same type may be used on the system board. The second processor must have the same clock frequency and the same cache as the first processor. For dual operation, use a suitable multipro-cessor operating system.
Ê Open the server as described in the chapter „Preparation“ on page 15.
Ê Remove the air duct over the main memory (see chapter „Main memory“ on page 19).
U41601-J-Z156-1-76 Options Guide 27
Installing a second processor Processors
Figure 14: Removing processor dummy module
Ê Pull the processor dummy out.
V CAUTION!
Keep the dummy cover for future use. If you remove the processor again and do not replace it with a new one, reinstall the dummy cover to ensure that the system is cooled properly.
28 Options Guide U41601-J-Z156-1-76
Processors Installing a second processor
Figure 15: Empty processor slot
Ê Release the socket lifter by pressing it sideways and pull it upward as far as it will go.
Figure 16: Inserting processor
1
2
U41601-J-Z156-1-76 Options Guide 29
Installing a second processor Processors
Ê Position the new processor over the socket and then carefully press it into the socket (1).
V CAUTION!
The processor can only be installed in one particular direction. Note the marking on one of the corners. To avoid damaging the pins or the processor, do not force it into the socket.
Ê Lock the processor in the socket by returning the socket lifter to its original position (2).
Ê Remove the protective cover on the underside of the heat sink.
Figure 17: places of the springs round the heat sink support pins
Ê Check whether the springs round the heat sink support pins are aligned centrally.
30 Options Guide U41601-J-Z156-1-76
Processors Installing a second processor
Figure 18: Installing heat sink
Ê Place the heat sink on the processor.
Ê Fasten the heat sink by tightening the four screws in a crossover pattern.
V CAUTION!
Never install a processor without a heat sink as otherwise the processor may overheat, causing a shut-down of the system.
Ê Reinstall the ventilation duct over the system fans see chapter „Main memory“ on page 19.
V CAUTION!
Ensure a correct fit of the airduct and that no damage is caused to the cables
Ê Close the server, connect it to the power outlet, and switch it on as described in the chapter „Completion“ on page 99.
U41601-J-Z156-1-76 Options Guide 31
Replacing the processor Processors
6.2 Replacing the processor
V CAUTION
Only processors of the same type may be used on the system board. The second processor must have the same clock frequency and the same cache as the first processor. For dual operation, use a suitable multipro-cessor operating system.
Ê Open the server as described in the chapter „Preparation“ on page 15.
Ê Remove the air duct over the main memory and the processors (see page 22.
Figure 19: Removing the heat sink
Ê Loosen the four screws in a crossover pattern.
Ê Loosen the heat sink by turning it back and forth and then lift it out.
32 Options Guide U41601-J-Z156-1-76
Processors Replacing the processor
Figure 20: Removing an installed processor
Ê Release the socket lifter by pressing it sideways and pull it upward as far as it will go (1).
Ê Lift the installed processor carefully out of the socket (2).
2
1
U41601-J-Z156-1-76 Options Guide 33
Replacing the processor Processors
Figure 21: Inserting a new processor
Ê Position the new processor over the socket and then carefully press it into the socket (1).
V CAUTION!
The processor can only be installed in one particular direction. Note the marking on one of the corners (2). To avoid damaging the pins or the processor, do not force it into the socket.
Ê Lock the processor in place in the socket by returning the socket lifter to its original position (3).
Ê Remove the protective cover on the underside of the heat sink.Do not touche the pad.
Ê Place the heat sink on the processor socket (see page 31).
Ê Fasten the heat sink by tightening the four screws in a crossover pattern.
Ê Reinstall the air duct over the main memory and the processors (see „Inserting air duct“ on page 25).
Ê Close the server, connect it to the power outlet, and switch it on as described in the chapter „Completion“ on page 99.
1
2
3
34 Options Guide U41601-J-Z156-1-76
7 ROMB (RAID on Motherboard)V CAUTION!
Observe the safety instructions in the chapter „Safety notes“ on page 9.
The on-board SCSI controller can be upgraded to a RAID5 (RAID 0, 1, 5, 10, 50) controller with a "MegaRaid PCI Express™ ROMB" upgrade kit. In this case the on-board INTEL I/O processor is activated by installing a license key and a cache module.
Two different upgrade kits are offered:
– Upgrade kit S26361-F3091-E128, consisting of an iButton license key and a 256 MB cache module.
– Upgrade kit S26361-F3091-E328, consisting of an iButton license key and a 128 MB cache module with a battery also integrated on the module (iTBBU=integrated Transportable Battery Backup Unit).
7.1 Installing the ROMB upgrade kit
Ê Open the server as described in the chapter „Preparation“ on page 15.
Figure 22: Cache module (with battery) and iButton
I Only for cache module with battery.
Ê Remove the screw (1) on the battery and connect the cable (2) on the module.
12
U41601-J-Z156-1-76 Options Guide 35
Installing the ROMB upgrade kit ROMB (RAID on Motherboard)
Figure 23: Installing the iButton and the Cache module
Ê Install the iButton on the system board (1).
Ê Press the holders on either side of the mounting location outward.
Ê Insert the cache module.
Ê Press the cache module downward until the holders on either side of the mounting location are engaged.
Ê Close the server, connect it to the power outlet, and switch it on as described in the chapter „Completion“ on page 99.
I Information on the configuration is provided in the Technical Manual for the system board.
1
36 Options Guide U41601-J-Z156-1-76
8 Accessible drivesV CAUTION!
Observe the safety instructions in the chapter „Safety notes“ on page 9.
I Two free bays are available for accessible drives. One 3,5 Inch x 0,5 Inch is for a FD drive and one 5,25 inch x 0,5 inch is for a CD/DVD-ROM drive available. A local view module can also be installed Into the upper bay (FD drive).
V CAUTION!
For installing a FD drive or a CD-/DVD drive frames and cables are necessary.
U41601-J-Z156-1-76 Options Guide 37
Installing a FD drive Accessible drives
8.1 Installing a FD drive
Ê Open the server as described in the chapter „Preparation“ on page 15.
Removing a FD drive dummy module
Figure 24: Unlocking the FD drive dummy module
Ê Unlock the FD drive dummy module (1).
Ê Push the FD drive dummy module to the front (2).
1
2
38 Options Guide U41601-J-Z156-1-76
Accessible drives Installing a FD drive
Figure 25: Removing dummy module
Ê Pull the FD drive dummy module out to the front side.
V CAUTION!
Keep the dummy module for future use. If you remove the FD drive again and do not replace it with a new one, the dummy module must be reinstalled to comply with EMC regulations and to satisfy cooling requirements and fire protection measures.
U41601-J-Z156-1-76 Options Guide 39
Installing a FD drive Accessible drives
Installing FD drive
Figure 26: Insert FD drive into the mounting frame.
I The mouning frame and the cable is deliverd in the accessory pack with the PRIMERGY RX300 S2.
Ê Insert the FD drive into the mounting frame. Regard the plastic pins. They fix the dive in the frame.
Ê Connect the cable.
40 Options Guide U41601-J-Z156-1-76
Accessible drives Installing a FD drive
Figure 27: Inserting FD drive module
Ê Thread the flat cable in the bay.
Ê Push the FD drive module into the bay, until it locks.
U41601-J-Z156-1-76 Options Guide 41
Installing a FD drive Accessible drives
Figure 28: Connecting FD drive cable
Ê Connect the FD cable to the system board.
Ê Close the server, connect it to the power outlet, and switch it on as described in the chapter „Completion“ on page 99.
42 Options Guide U41601-J-Z156-1-76
Accessible drives Installing a LocalView module
8.2 Installing a LocalView module
The LocalView module is an optional extra for the servers of the PRIMERGY series. On the display panel of the LocalView module you can read status messages directly on the server. These status messages provide information on the system and notify you of hardware faults (e.g. fan failure, CPU over voltage, etc.).
The LocalView module can be pulled out like a sliding drawer. You can also angle the LocalView display panel downward.
The LocalView module can be installed in the 3,5/0,5 inch bay of the FD drive.
Figure 29: LocalView module
Ê Open the server as described in the chapter „Preparation“ on page 15.
Ê If a FD dummy module is installed it must be removed (see „Removing a FD drive dummy module“ on page 38).
U41601-J-Z156-1-76 Options Guide 43
Installing a LocalView module Accessible drives
Removing the FD Drive
Figure 30: Unlocking the the FD Drive module (for better visibility, the fanbox is removed)
Ê Unlock (1) the FDD module.
Ê Push the FDD module to the front (2).
1
2
44 Options Guide U41601-J-Z156-1-76
Accessible drives Installing a LocalView module
Figure 31: Removing FD drive cable
Ê Remove the FD drive cable from the system board.
U41601-J-Z156-1-76 Options Guide 45
Installing a LocalView module Accessible drives
Figure 32: Removing FD-Drive module
Ê Pull the FD drive module out. to the front side.
46 Options Guide U41601-J-Z156-1-76
Accessible drives Installing a LocalView module
Figure 33: Threading the cable (for better visibility, the fanbox is removed)
Ê Push the cable for the LocalView module through the bay to the front.
U41601-J-Z156-1-76 Options Guide 47
Installing a LocalView module Accessible drives
Figure 34: Connecting the cable to the LocalView module
Ê Connect the cable to the LocalView module.
48 Options Guide U41601-J-Z156-1-76
Accessible drives Installing a LocalView module
Figure 35: Inserting the LocalView module
Ê Slide the LocalView module into the mounting location until it latches in place.
I Further information on operation and display modes is provided in the documentation for the LocalView module.
Ê Close the server, connect it to the power outlet, and switch it on as described in the chapter „Completion“ on page 99.
U41601-J-Z156-1-76 Options Guide 49
Installing the CD/ DVD-ROM drive Accessible drives
8.3 Installing the CD/ DVD-ROM drive
Ê Open the server as described in the chapter „Preparation“ on page 15.
Removing the CD/DVD drive dummy module
Figure 36: Unlocking the CD/DVD drive dummy module
Ê Unlock (1) the CD/DVD drive dummy module.
Ê Push the FDD module to the front (2).
1
2
50 Options Guide U41601-J-Z156-1-76
Accessible drives Installing the CD/ DVD-ROM drive
Figure 37: Removing dummy module
Ê Remove the dummy module.
V CAUTION!
Keep the dummy module for future use. If you remove the accessible drive again and do not replace it with a new one, the dummy module must be reinstalled to comply with EMC regulations and to satisfy cooling requirements and fire protection measures.
U41601-J-Z156-1-76 Options Guide 51
Installing the CD/ DVD-ROM drive Accessible drives
Figure 38: Installing the CD/DVD drive into its mounting frame
Ê Install the CD/DVD Drive in the mounting frame (the mounting frame is delivered with the drive, and the IDE cable is included to the assessory pack of the server. Regard the plastic pins which fix the drive in the frame.
Figure 39: Connecting the CD/DVD drive cables
1
52 Options Guide U41601-J-Z156-1-76
Accessible drives Installing the CD/ DVD-ROM drive
Ê Thread the power cable (1) through the bay and connect it to the CD Drive (see also chapter „Appendix“ on page 103).
Ê Connect the IDE cable to the drive (see also chapter „Appendix“ on page 103)
Figure 40: Pushing the CD/DVD drive into the bay
Ê Push the drive into the bay completely.
Ê Close the server, connect it to the power outlet, and switch it on as described in the chapter „Completion“ on page 99.
U41601-J-Z156-1-76 Options Guide 53
9 PCI slotsV CAUTION!
Observe the safety instructions in the chapter „Safety notes“ on page 9.
Standard configuration
The system board offers five PCI slots. Slots 1-3 are non-hot-plug PCI slots . If two or three slots are occupied, the bus speed is 100 MHz, but, if only slot 3 is occupied IOOP™ rules allow this slot to operate at 133 MHz.
I The PCI slot 4 and 5 are hot-plug slots, that can be equipped with hot-plug RAID controllers. You will find the description of the hot-plug slots in the users manual.
Optional configuration with riser card
Three standard slots are available with a riser card: 1 x PCI-X 64-bit/100 MHz, long, standard height; 2 x PCI-X 64-bit/100 MHz, short, standard height.
U41601-J-Z156-1-76 Options Guide 55
Installing a PCI controller in a low-profile slot PCI slots
9.1 Installing a PCI controller in a low-profile slot
Ê Open the server as described in the chapter „Preparation“ on page 15.
Figure 41: Remove the slot cover
Ê Push the green PCI board holder toward the rear (1).
Ê Remove the slot cover of the PCI slot (2).
V CAUTION
Keep the rear cover of the PCI slot for future use. If you remove the controller again and do not replace it with a new one, the rear cover must be reinstalled to comply with EMC regulations and to satisfy cooling requirements and fire protection measures.
1
2
56 Options Guide U41601-J-Z156-1-76
PCI slots Installing a PCI controller in a low-profile slot
Figure 42: Inserting controller
Ê Install the controller in the PCI slot and press it carefully into the associated plug-in location on the system board (1). Ensure that the rear cover fits into the recesses (a).
Ê Close the green PCI board holder (2).
Ê If required, connect the cables to the controller and other components.
Ê Close the server, connect it to the power outlet, and switch it on as described in the chapter „Completion“ on page 99.
a
a
12
U41601-J-Z156-1-76 Options Guide 57
Installing the PCI controller in the riser card PCI slots
9.2 Installing the PCI controller in the riser card
Ê Open the server as described in the chapter „Preparation“ on page 15.
Figure 43: Removing the riser card
Ê Open the knurled screws.
V CAUTION!!
Keep the rear cover of the PCI slot for future use. If you remove the controller again and do not replace it with a new one, the rear cover must be reinstalled to comply with EMC regulations and to satisfy cooling requirements and fire protection measures.
58 Options Guide U41601-J-Z156-1-76
PCI slots Installing the PCI controller in the riser card
Figure 44: Removing the riser card
Ê Remove the riser card upward.
Figure 45: Installing the controller
U41601-J-Z156-1-76 Options Guide 59
Installing the PCI controller in the riser card PCI slots
Ê Remove the screw and the slot cover of the associated connector
I To equip slot 8 with a full-length PCI controller it is necessary to remove slot cover of slot 7 too.
Figure 46: Installing controller
Ê Insert the controller into the PCI slot and push it down carefully.
Ê Fix the slot cover/s with the screw/s.
Ê If necessary connect the cables to the controller or other components.
Ê Insert the riser card and be careful with the cables.
Ê Close the server, connect it to the power outlet, and switch it on as described in the chapter „Completion“ on page 99.
60 Options Guide U41601-J-Z156-1-76
PCI slots Population of the PCI slots
9.3 Population of the PCI slots
Standard configuration with 5 low profile slots
Riser configuration with 3 standard profile slots
Adapter class Adapter priority Slot (order)
External SCSI interface 1 1
Parallel port 2 5
FC (QLA2340, LP9802) 3 5, 4
RSB 4 3, 4, 5
LAN Controller 5 5, 4, 3, 2, 1
RAID 6 5, 4, 3, 2, 1
SCSI 7 5, 4, 3, 2, 1
Adapter class Adapter priority Slot (order)
External SCSI interface 1 6
Parallel Port 2 8
RAID 3 8, 7, 6
FC (QLA2340, LP9802) 3 7, 6
RSB 4 6, 7, 8
LAN Controller 5 7, 6
SCSI 7 7, 6
U41601-J-Z156-1-76 Options Guide 61
10 RemoteView componentsV CAUTION!
Observe the safety instructions in the chapter „Safety notes“ on page 9.
10.1 Installing the chipDISK
Ê Open the server as described in the chapter „Preparation“ on page 15.
Figure 47: Installing the chipDISK
Ê Connect the chipDISK to the plug-in location on the system board.
V CAUTION
Note the coding of the chipDISK and plug-in location.
Ê Close the server, connect it to the power outlet, and switch it on as described in the chapter „Completion“ on page 99.
U41601-J-Z156-1-76 Options Guide 63
RemoteView Service Board S2 LP RemoteView components
10.2 RemoteView Service Board S2 LP
I How to install/remove and configure the RSB S2 LP is described in detail in the “RemoteView Service Board S2/ S2 LP 1.x, Mounting and Setting Up” manual.
Preferred mounting locations for RSB S2 LP are PCI slots 3, 4, and 5 in the standard configuration with only low profile PCI Slots. To configure ther RSB with a riser card you have to use RSB S2 LP 3HU. Any of the three slots can be used.
Ê Open the server as described in the chapter „Preparation“ on page 15.
Figure 48: Connecting cables to the system board
Ê Connect the data cable to the connector IPMB (1) and the power cable to the connector KVM Power (2) on the system board.
Figure 49: Connecting cables to the system board
Ausschnitt /section of D1889
1 2
2
1
64 Options Guide U41601-J-Z156-1-76
RemoteView components RemoteView Service Board S2 LP
Ê Connect the power cable (1) and the data cable (2) to the RSB S2 LP.
Ê Install the RSB S2 LP into PCI slot 3, 4 or 5 (described in „Installing a PCI controller in a low-profile slot“ on page 56) and RSB S2 LP 3 HU into PCI slot 6, 7or 8 (described in „Installing the PCI controller in the riser card“ on page 58) respectively.
Ê Close the server, connect it to the power outlet, and switch it on as described in the chapter „Completion“ on page 99.
U41601-J-Z156-1-76 Options Guide 65
11 External SCSI interfaceV CAUTION!
Observe the safety instructions in the chapter „Safety notes“ on page 9.
11.1 Installing the external SCSI interface
Ê Open the server as described in the chapter „Preparation“ on page 15.
I For standard configuration the external SCSI interface is to install with a low profile slot cover. If the optional riser card is used, a standard slot cover is necessary.
External SCSI interface in standard configuration
Figure 50: external SCSI cable with low-profile slot cover.
U41601-J-Z156-1-76 Options Guide 67
Installing the external SCSI interface External SCSI interface
Removing fan box
Figure 51: Unlocking fan box air duct
Ê Unlock the fan box air duct.
Figure 52: Removing fan box air duct
Ê Pull the fan box air duct out.
68 Options Guide U41601-J-Z156-1-76
External SCSI interface Installing the external SCSI interface
Figure 53: Removing the fan box
Ê Unlock all fans (1).
Ê Unlock the fan box (2).
Ê Push the fan box to the left side (3).
Ê Pull out the fan box in an angle (4).
1 1 1 12
3
4
U41601-J-Z156-1-76 Options Guide 69
Installing the external SCSI interface External SCSI interface
Removing cable channel cover
Figure 54: Remove the three-part cable channel cover.
Figure 55: Snap-fits of the three-part cable channel cover
Ê Remove the three-part cable channel. Press the upper and lower snap-fit on the outside together. Each part of the three-part cable chanel coverhas two snap-fits.
Ê Push the green PCI board holder of slot 1 backward.
Ê Remove the slot cover.
viewoutside
viewinside
70 Options Guide U41601-J-Z156-1-76
External SCSI interface Installing the external SCSI interface
Figure 56: Installing cable
Ê Insert the slot cover with the SCSI interface.
Ê Close the green PCI board holder.
Ê Route the SCSI cable, as shown in the picture.
Ê Insert the three-part cable channel cover.
U41601-J-Z156-1-76 Options Guide 71
Installing the external SCSI interface External SCSI interface
Figure 57: Connecting the SCSI cable to the system board
Ê Connect the SCSI cable to the connector SCSI B on the system board (see arrow).
Ê Install the fan box and the fan box air duct.
Ê Push the fans back.
Ê Close the server, connect it to the power outlet, and switch it on as described in the chapter „Completion“ on page 99.
72 Options Guide U41601-J-Z156-1-76
External SCSI interface Installing the external SCSI interface
External SCSI interface in the riser card
Figure 58: Cable for external SCSI interface (with low profile slot cover)
Ê Remove the two screws.
Ê Remove the low-profile slot cover from the SCSI-connector.
Figure 59: External. SCSI Interface with standard slot cover
Ê Insert the SCSI connector to the slot cover.
U41601-J-Z156-1-76 Options Guide 73
Installing the external SCSI interface External SCSI interface
Figure 60: Removing riser card
Ê Remove the riser card.
Figure 61: Removing slot cover of slot 6
Ê Remove the screw of the slot cover of slot 6.
Ê Remove the slot cover of slot 6.
Ê Remove the fan box, see „Removing fan box“ on page 68.
74 Options Guide U41601-J-Z156-1-76
External SCSI interface Installing the external SCSI interface
Figure 62: opening cable duct
Ê Open the cabel channel cover, see „Removing cable channel cover“ on page 70.
Figure 63: external SCSI interface
Ê Thread the cable in the cable channel.
V CAUTION
Leave an extra 6 cm cable protruding.
Ê Close the cable duct.
U41601-J-Z156-1-76 Options Guide 75
Installing the external SCSI interface External SCSI interface
Figure 64: Inserting riser card
Ê Lay the riser card into the server as shown above.
Ê Push the SCSI slot cover into Slot 6.
Ê Fix the slot cover with the screw.
Ê Insert the riser card completely.
Ê Fix the riser card with the two knurled screws.
76 Options Guide U41601-J-Z156-1-76
External SCSI interface Installing the external SCSI interface
Figure 65: Connecting the external SCSI cable to the system board
Ê Connect the SCSI cable to the connector SCSI B on the system board (see arrow).
Ê Insert the fan box and the fan box air duct.
Ê Press the fans firmly into position.
Ê Close the server, connect it to the power outlet, and switch it on as described in the chapter „Completion“ on page 99.
U41601-J-Z156-1-76 Options Guide 77
12 Parallel interfaceV CAUTION!
Observe the safety instructions in the chapter „Safety notes“ on page 9.
12.1 Installing a parallel interface
Ê Open the server as described in the chapter „Preparation“ on page 15.
I For standard configuration the parallel interface is to install into a low-profile slot cover. If the optional riser board is used, a standard slot cover is necessary.
Parallel interface in standard configuration
Figure 66: external parallel interface with low-profile slot cover
U41601-J-Z156-1-76 Options Guide 79
Installing a parallel interface Parallel interface
Figure 67: Removing the slot cover
Ê Push the PCI board holder backward.
Ê Remove the slot cover.
Figure 68: Routing the cable
Ê Insert the slot cover with the parallel interface.
Ê Connect the cable to the system board (see arrow).
Ê Route the cable as shown in the picture directly upon the system board.
Ê Close the server, connect it to the power outlet, and switch it on as described in the chapter „Completion“ on page 99.
80 Options Guide U41601-J-Z156-1-76
Parallel interface Installing a parallel interface
External Parallel-interface in slot cover with standard height
Figure 69: External parallel interface with low-profile slot cover
Ê Remove the two screws.
Figure 70: External parallel interface with standard slot cover
Ê Insert the connector of the parallel interface in the slot cover.
Ê Fix it with the two screws.
U41601-J-Z156-1-76 Options Guide 81
Installing a parallel interface Parallel interface
Figure 71: Removing the riser card
Ê Remove the riser card.
Figure 72: Removing the slot cover of slot 8
Ê Remove the slot cover of slot 8.
82 Options Guide U41601-J-Z156-1-76
Parallel interface Installing a parallel interface
Figure 73: Installing the slot cover with the connector of the parallel interface.
Ê Insert the slot cover with the parallel interface in slot 8 and fix the slot cover with the screw.
Ê Thread the flat cable between the riser board and the plastic side cover.
I Route the cable as shown in the photo.
U41601-J-Z156-1-76 Options Guide 83
Installing a parallel interface Parallel interface
Figure 74: Installing the riser card with parallel interface.
Ê Insert the riser card.
Ê Route the cable.
Ê Connect the cable to the system board.
Ê Close the server, connect it to the power outlet, and switch it on as described in the chapter „Completion“ on page 99.
84 Options Guide U41601-J-Z156-1-76
13 Converting from 1- to 2-channel version
V CAUTION!
Observe the safety instructions in the chapter „Safety notes“ on page 9.
I For the PRIMERGY RX300 S2 the SCSI backplane is separated into two parts. The 1st SCSI backplane can stay installed for both configurations. For upgrading you must change the second SCSI backplane. Die 1-channel backplane must be exchanged for a 2-channel SCSI backplane (which is the same as the SCSI backplane installed in the first SCSI backplane holder yet) and the SCSI cabling must be exchanged.
Figure 75: Second SCSI backplane for 1-channel configuration
U41601-J-Z156-1-76 Options Guide 85
Converting from 1- to 2-channel version
Figure 76: Second SCSI backplane 2-channel configuration (backplane is equal to the first SCSI backplane).
86 Options Guide U41601-J-Z156-1-76
Converting from 1- to 2-channel version Removing 2nd SCSI backplane
13.1 Removing 2nd SCSI backplane
Ê Open the server as described in the chapter „Preparation“ on page 15.
Ê Remove all hot-plug hard disks or/and the hot-plug tape drive on the left side (for a description see the Operating Manual).
Figure 77: Disconnecting the cables
Ê Pull out the connectors of the I2C cable (1), the power cable (2), and both SCSI cables (3) from the SCSI backplane.
1
2
3
3
U41601-J-Z156-1-76 Options Guide 87
Removing 2nd SCSI backplane Converting from 1- to 2-channel version
Figure 78: Loosening knurled screw
Ê Loosen the knurled screw.
Ê Twist the SCSI backplane holder out slightly. Do not damage the hooks.
Ê Pull the SCSI backplane holder out.
88 Options Guide U41601-J-Z156-1-76
Converting from 1- to 2-channel version Removing 2nd SCSI backplane
Figure 79: Removing the 2nd SCSI backplane (1-channel) from the holder
Ê Unlock the backplane from the snap-fits.
Ê Remove the SCSI backplane from the holder.
U41601-J-Z156-1-76 Options Guide 89
Installing 2nd SCSI backplane Converting from 1- to 2-channel version
13.2 Installing 2nd SCSI backplane
Figure 80: Inserting the 2nd SCSI backplane (2-channel) into the SCSI backplane holder
Ê Insert the 2-channel SCSI backplane in the hooks of the SCSI backplane holder (1).
Ê Press the SCSI backplane down.
Ê The backplane must engage under the green snap-fits (2).
1
2
90 Options Guide U41601-J-Z156-1-76
Converting from 1- to 2-channel version Installing 2nd SCSI backplane
Figure 81: Inserting second SCSI backplane
Ê Insert the assembled SCSI backplane holder. Be careful with the hooks. The angle may not be too great.
Ê Close the holder.
Ê Fasten it with the knurled screw.
U41601-J-Z156-1-76 Options Guide 91
Installing 2nd SCSI backplane Converting from 1- to 2-channel version
Figure 82: Cabling the second SCSI backplane
Ê Connect the I2C cable (1), the power cable (2) and the SCSI-cable (3) to the SCSI backplane.
I Do not insert the SCSI signal cable.
Ê Connect the SCSI cable to (4) and (5) of the system board.
Ê Reinstall the fan box and the fan box air duct.
Ê Reinstall the drives.
Ê Close the server, connect it to the power outlet, and switch it on as described in the chapter „Completion“ on page 99.
2 3
4
1
5
92 Options Guide U41601-J-Z156-1-76
14 Converting from low-profile to standard PCI Slots
V CAUTION!
Observe the safety instructions in the chapter „Safety notes“ on page 9.
14.1 Removing lp slot cage
Ê Open the server as described in the chapter „Preparation“ on page 15.
Figure 83: Removing hot-plug cable
Ê Release and remove the hot-plug cable from the system board.
U41601-J-Z156-1-76 Options Guide 93
Removing lp slot cage Converting from low-profile to standard PCI Slots
Figure 84: Removing the slot cage
Ê Remove the two screws.
Ê Pull the slot cage out.
94 Options Guide U41601-J-Z156-1-76
Converting from low-profile to standard PCI Slots Removing lp slot cage
Figure 85: Without slot cage
Ê Equip the riser card as described in part „Installing the PCI controller in the riser card“ on page 58.
Figure 86: Assembled Riser card
U41601-J-Z156-1-76 Options Guide 95
Installing Riser card Converting from low-profile to standard PCI Slots
14.2 Installing Riser card
Figure 87: Inserting the Riser card
Ê Install the riser card.
96 Options Guide U41601-J-Z156-1-76
Converting from low-profile to standard PCI Slots Installing Riser card
Figure 88: With riser card
Ê Fasten the two screws.
Ê Close the server, connect it to the power outlet, and switch it on as described in the chapter „Completion“ on page 99.
U41601-J-Z156-1-76 Options Guide 97
15 CompletionV CAUTION!!
Observe the safety instructions in the chapter „Safety notes“ on page 9.
15.1 Closing the server
Figure 89: Closing the cover
Ê Apply the cover.
Ê Push the cover to the front (1).
Ê Make sure that the locks engage.
1
1
U41601-J-Z156-1-76 Options Guide 99
Closing the server Completion
If you have not removed the server from the rack cabinet, please skip this page.
Figure 90: Installing the server in a rack cabinet
V CAUTION!
At least two people are required to install the server in the rack cabinet.Do not use the handles on the rack front cover to lift the server into the rack.
Ê Lower the server from above onto the extended telescopic rails.
Ê Push the server in the direction of the arrow (1) until the hooks of the telescopic rails engage.
Ê Release the telescopic rails’ locking mechanism (2) on both sides and push the server as far as it will go into the rack.
Ê Reconnect all the cables you disconnected beforehand on the rear of the server.
2
1
100 Options Guide U41601-J-Z156-1-76
Completion Closing the server
Figure 91: Fastening the knurled screws
Ê Fasten the server in the rack using the two knurled screws (1).
Ê Connect all power plugs to the power outlets.
Ê Press the on/off key to start up the server.
2
1
1
U41601-J-Z156-1-76 Options Guide 101
16 Appendix
16.1 Cabling
The following table gives you an overview of the cables:
Numbers in the drawings
Material number Designation
1 A3C40058008 Parallel Port cable
2 A3C40057192 SV cable PSU
3 A3C40057188 SV cable 24 pol
4 T26139-Y3697-V101 Power Backplane SMB cable
5 A3C40058003 Power cable CD-ROM
6 A3C40057191 SV cable PSU
7 A3C40057185 USB FRONTPANEL cable
8 A3C40057190 OPERATER PANEL cable
9 A3C40057187 ULTRA ATA cable
10 A3C40057186 FLEX FLAT cable
11 A3C40057385 SMB CABLE
12 A3C40058005 SCSI cable
13 A3C40057189 SCSI CTRL.CABLE
14 A3C40058004 SCSI cable
15 A3C40057182 FLEX FLAT CABLE
U41601-J-Z156-1-76 Options Guide 103
Cabling Appendix
Figure 92: Basic cabling with 1-channel SCSI
Fron
tpan
el
Loca
lVi
ewSCS
I-HD
ID2
SCS
I-HD
ID1
SCS
I-HD
ID0
SCS
I-HD
ID2
SCS
I-HD
ID1
SCS
I-HD
ID0
1" H
DD
SCSI
PowerLegend:
IDTE
MP
Com
bo
CD
-RO
M S
limlin
e
Flop
py S
limlin
e
PS Bpl
1" H
DD
Verkabelung RX300 S2 mit 1 Kanal SCSI
USB
BPL 0BPL 1
SMBusSCSIIDE/FDUSBSteuersignal
13
Power
SupplyR
SP-500
Power
SupplyR
SP-500
optionalerparallel Port
SCSI
System FAN
System FANredundant
CPU FAN3
CPU FAN3redundant
CPU FAN2 CPU FAN1
CPU FAN2redundant
CPU FAN1redundant
CPU1 CPU0D
IMM
3B
DIM
M 3
AD
IMM
2B
DIM
M 2
AD
IMM
1B
DIM
M 1
A
PCI S
lot
1
PCI S
lot
2
PCI S
lot
3
PCI S
lot 4
hot
plu
g
PCI S
lot 5
hot
plu
g
Com
pact
Flas
h
SCSI B SCSI A Floppy
Para
llel
12V1
Mai
n Po
wer
PC98
PanelIDEUSB
SMB
hot p
lug
hot p
lug
15
11 10 9 8 7
6
5
2
3
4
1
SCSI
14
12
DIM
M 0
BD
IMM
0A
104 Options Guide U41601-J-Z156-1-76
Appendix Cabling
Figure 93: Basic cabling with 2-channel-SCSI
Fron
tpan
el
Loca
lV
iewSC
SI-H
D ID
2
SCSI
-HD
ID1
SCSI
-HD
ID0
SCSI
-HD
ID2
SCSI
-HD
ID1
SCSI
-HD
ID0
1" H
DD
SCSI
PowerLegend:
IDTE
MP
Com
bo
CD
-RO
M S
limlin
e
Flop
py S
limlin
e
SCSI
PS Bpl
1" H
DD
Verkabelung RX300 S2 mit 2 Kanal SCSI
US
B
BPL 0BPL 1
SMBusSCSIIDE/FDUSBSteuersignal
Pow
erS
upplyR
SP
-500
Pow
erS
upplyR
SP
-500 optionalerparallel Port
SCSI
System FAN
System FANredundant
CPU FAN3
CPU FAN3redundant
CPU FAN2 CPU FAN1
CPU FAN2redundant
CPU FAN1redundant
CPU1 CPU0
DIM
M 3
BD
IMM
3A
DIM
M 2
BD
IMM
2A
DIM
M 1
BD
IMM
1A
PC
I Slo
t 1
PC
I Slo
t 2
PC
I Slo
t 3
PC
I Slo
t 4 h
ot p
lug
PC
I Slo
t 5 h
ot p
lug
Com
pact
Flas
h
SCSI B SCSI A Floppy
Par
alle
l12
V1
Mai
n P
ower
PC
98
PanelIDEUSB
SM
B
hot p
lug
hot p
lug
15
11 10 9 8 7
6
5
2
3
4
1
1412
DIM
M 0
BD
IMM
0A
U41601-J-Z156-1-76 Options Guide 105
Configuration diagram Appendix
16.2 Configuration diagram
Figure 94: part1 of the system configurator
board front sidemiddle
Bank I (2 Modules) Bay for LocalView LCDXeon DP or 3.5"x 0,5" Floppy disk
Bank II (2 Modules)
Bank III (2 Modules) Air channelXeon DP
Bank IV (2 Modules) Bay for 5,25"x 0,5" IDE-CD
or DVD-ROM Memory ( III ) Processor ( II )
Accessible drives ( V )rear side
Fan 1 - Fan 4 1. PSU 2. PSU Needs space for 2
hard disk drives!Fan 5 - Fan 8 3.5"x1,6"
Redundant system- Redundant power fans option Backup drive option supply option
Hard disk drives ( VI ) RAID 5 support Licence key + 128MB Cache channel 1 left side
onboard Licence key + 128MB Cache+BBU
Extension slots for 3.5"x1" ID 5
SCSI Controller ( VII )Disk Array ( VIII )Communication/Network ( IX ) 3.5"x1" ID 4Miscellaneous ( X )
HOT PLUG RISER optionSlot 5: PCI-X 64-Bit / 133MHz, Low Profile 3.5"x1" ID 3
Slot 6: Slot 7: Slot 8:HOT PLUG Standard configuration is
Slot 4: PCI-X 64-Bit / 133MHz, Low Profile single channelchannel 2 (optional) right side
PCI-X 64 PCI-X 64 PCI-X 64
133MHz with IOOP�Slot 3: PCI-X 64-Bit / 100MHz, Low Profile 3.5"x1" ID 2
100 MHz 100 MHz 100 MHz
Slot 2: PCI-X 64-Bit / 100MHz, Low Profile 3.5"x1" ID 1
Standard Standard Standard
Slot 1: PCI-X 64-Bit / 100MHz, Low Profile 3.5"x1" ID 0
short short long
Key:
Included in basic unit
Option
PCI-B
us
2nd
All
low
pro
file
slot
s ar
e co
vere
d, if
PC
I-ris
er c
ard
conf
igur
ed
3rd
1st
1st
1st
106 Options Guide U41601-J-Z156-1-76
Appendix Hard disk mirroring
16.3 Hard disk mirroring
Figure 95: part of the system configurator
The system is equipped with a two channel Utra 320 SCSI on-board controller and embedded "IME".IME (Integrated Mirroring Enhanced) offers the RAID levels 1, 1E witout any additional costs.IME is a RAID 1 implementation ( no RAID 0 support ), which also can operate with an odd number of hard disks( max. 1 RAID 1 set ). Up to 6 hard disks including one hot spare HD are possible depending on the system. Administration of IME is possible with the LSI Global Array Manager (GAM). Windows2000/2003 as well as SuSe and RedHat Linux are supported ( Restrictions refer to Software Configurator )
Example with 3 HD`s:
1-channel standard SCSI-cabling of a basic unit PRIMERGY RX300 S2 with on-board controller1. One channel of the Ultra 320 SCSI controller is connected to the 6 internal hard disks, if no additional HD controllers are configured for internal HDs. (Two backplanes with 3 HDs each cascaded to one SCSI channel with 6HD`s = standard cabling).2. The second channel of the Ultra 320 SCSI controller is available for external accessible SCSI drives with S26361-F3120-E12-channel SCSI cabling of a PRIMERGY RX300 S2 basic unit with on-board controller and "Conversion kit 6 HD 2-channel" For the order of a "Conversion kit 6 HD 2-channel (S26361-F2612-E4)", both channels of the Ultra 320 SCSI controller are connected to one backplane for 3 HDs each.All internal cables and adapters for the basic unit and for components are included. 1x per RX300 S2
U41601-J-Z156-1-76 Options Guide 107
Related publicationsPRIMERGY manuals are available as PDF files on the ServerBooks CD. The ServerBooks CD is part of the ServerView Suite delivered with each server system.
The current version of the necessary manuals can be downloaded free of charge from the Internet. The overview page showing the online documentation available in the Internet can be found via the URL:http://manuals.fujitsu-siemens.com (choose: intel based servers/PRIMERGY ServerBooks).
[1] Safety
[2] Warranty
[3] PRIMECENTER Rack Technical Manual
[4] DataCenter Rack Technical Manual
[5] 19 inch rack Technical Manual
[6] LocalView User Manual
[7] PRIMERGY ServerView Suite ServerStart
[8] ServerView Server ManagementUser Manual
[9] ServerView ExtensionServerView Extension for HP OpenView NNM
[10] ServerView/Plus for Tivoli
[11] RemoteView User Manual
U41601-J-Z156-1-76 Options Guide 109
Related Publications
[12] RemoteView Service Board S2/S2 LP 1.xMounting and Setting Up User’s Guide
[13] PRIMERGY RX300 S2 Operating Manual
[14] System Board D1889 Technical Manual
[15] BIOS-Setup Reference Manual
[16] Integrated Mirroring User’s Guide
[17] Global Array Manager Client Software User’s Guide
[18] Global Array Manager Server Software User’s Guide
[19] Configurator For partners and distributors only:http://extranet.fujitsu-siemens.com/cafe/products/primergy
110 Options Guide U41601-J-Z156-1-76
Index
Aaccessible drives 3, 37air duct 22Ccache module 35chipDISK 4, 63Controller 4, 56, 58conversion of SCSI 1-channel version
to 2-channel version 5converting form low profile to standard
slots 93converting from SCSI-1-channel to 2-
channel 85
Ddual operation 27, 32
EESD (electrostatic sensitive device)
13external SCSI interface 5, 67
HHard disk drives 4
IiButton 36information material 2
Llight-emitting diode (LED) 13Lithium battery 11LocalView module 3, 43
Mmain memory 3, 19meaning of the symbols 6multiprocessor operating system 27,
32
Nnotational conventions 6note about the laser 13
Pparallel interface 5, 79processor 27
RRemoteView 4RemoteView Service Board S2 LP 5,
64ROMB 3
Sslot cover 67
Ttarget group 1
U41601-J-Z156-1-76 Options Guide 111
Comments on PRIMERGY RX300 S2Server System
U41601-J-Z156-1-76
CommentsSuggestionsCorrections
✁
Submitted by
Fujitsu Siemens Computers GmbHUser Documentation81730 MunichGermany
Fax: (++49) 700 / 372 00000
email: [email protected]://manuals.fujitsu-siemens.com
Comments on PRIMERGY RX300 S2Server System
U41601-J-Z156-1-76
CommentsSuggestionsCorrections
✁
Submitted by
Fujitsu Siemens Computers GmbHUser Documentation81730 MunichGermany
Fax: (++49) 700 / 372 00000
email: [email protected]://manuals.fujitsu-siemens.com
Information on this document On April 1, 2009, Fujitsu became the sole owner of Fujitsu Siemens Compu-ters. This new subsidiary of Fujitsu has been renamed Fujitsu Technology So-lutions.
This document from the document archive refers to a product version which was released a considerable time ago or which is no longer marketed.
Please note that all company references and copyrights in this document have been legally transferred to Fujitsu Technology Solutions.
Contact and support addresses will now be offered by Fujitsu Technology So-lutions and have the format …@ts.fujitsu.com.
The Internet pages of Fujitsu Technology Solutions are available at http://ts.fujitsu.com/... and the user documentation at http://manuals.ts.fujitsu.com.
Copyright Fujitsu Technology Solutions, 2009
Hinweise zum vorliegenden Dokument Zum 1. April 2009 ist Fujitsu Siemens Computers in den alleinigen Besitz von Fujitsu übergegangen. Diese neue Tochtergesellschaft von Fujitsu trägt seit-dem den Namen Fujitsu Technology Solutions.
Das vorliegende Dokument aus dem Dokumentenarchiv bezieht sich auf eine bereits vor längerer Zeit freigegebene oder nicht mehr im Vertrieb befindliche Produktversion.
Bitte beachten Sie, dass alle Firmenbezüge und Copyrights im vorliegenden Dokument rechtlich auf Fujitsu Technology Solutions übergegangen sind.
Kontakt- und Supportadressen werden nun von Fujitsu Technology Solutions angeboten und haben die Form …@ts.fujitsu.com.
Die Internetseiten von Fujitsu Technology Solutions finden Sie unter http://de.ts.fujitsu.com/..., und unter http://manuals.ts.fujitsu.com finden Sie die Benutzerdokumentation.
Copyright Fujitsu Technology Solutions, 2009