princeton force main condition assessment project1307b359... · 6. geologic assessment 7. external...

21
PRINCETON FORCE MAIN CONDITION ASSESSMENT PROJECT SAM BOARD PRESENTATION - MAY 11, 2020

Upload: others

Post on 03-Feb-2021

0 views

Category:

Documents


0 download

TRANSCRIPT

  • PRINCETON FORCE MAIN

    CONDITION ASSESSMENT

    PROJECT

    SAM BOARD PRESENTATION - MAY 11, 2020

  • PRESENTATION OUTLINE1. Purpose

    2. Condition assessment team

    3. Overview of Princeton Force Main

    4. Methodology

    5. Hydraulic assessment

    6. Geologic assessment

    7. External inspection process

    8. Metal thickness test results

    9. Soil and groundwater test results

    10. Recommendations

    11. Questions/discussion

    2

  • PURPOSE

    • Assure reliability for next 60 years

    • Determine current condition of the force main

    • Proactively determine if the force main presents a risk of failure

    • Settlement requirement with Ecological Rights Foundation Consent Decree

    3

  • CONDITION ASSESSMENT

    TEAM

    4

    Participant Role

    SAM Operations and Collection System staff Pump station and force main operations, project

    oversight, spill mitigation in emergency

    SRT Consultants, San Francisco, CA Engineer of record, planning, logistics, coordination,

    reporting

    BAGG Engineers, San Jose, CA Logistics, planning, UT testing, soil and groundwater

    sampling and analysis

    Andrieni Brothers, Half Moon Bay, CA Permitting, construction support, utility locating, traffic

    control, pit excavation, shoring, pipe coating

    restoration, backfilling, and paving

    Pipeline Inspection and Condition Analysis

    Corporation (PICA)

    Electromagnetic scanning, data processing, and

    reporting

    Ductile Iron Pipe Research Association (DIPRA) Technical assistance, observation, and guidance

  • OVERVIEW OF PRINCETON FORCE MAIN

    • 8 inch diameter

    • Ductile iron

    • Age: 41 years

    • Installed in 1979

    • Part of the IPS

    • Length: 4,200’

    • Depth: +/- 4’-0”

    5

  • METHODOLOGY• Hydraulic Assessment

    • Desk top model was developed in WaterCAD to assess pressure and velocity as various flow rates

    • Geology and Seismicity Assessment

    • Desktop study to determine geologic risks due to earthquake, faults, and liquefaction

    • Force Main Alignment and Appurtenances Inspection

    • Visual inspection of force main alignment

    • Visual inspection of surge chamber, air release valves, and blow offs

    • Non-Intrusive Pipe Wall Thickness Inspection

    • Ultrasonic pipe wall thickness testing

    • Electromagnetic pipe wall thickness testing

    • Pipeline Subsurface Inspection

    • Soil sampling and analysis

    • Groundwater sampling and analysis

    Removing a segment of the pipeline for internal inspection was considered but not performed because the

    capacity of the Princeton PS wet well is too small to accommodate regular flow and drain back of the force main

    6

  • HYDRAULIC ASSESSMENT

    Princeton Force Main

    - Hydraulic modeling shows that the

    force main is constantly pressurized

    and there is no local high or low

    points

    - Hydrogen sulfide gas is not likely to

    accumulate except at the high point

    (connection to Montara Force Main)

    - Two ARVs are installed along the

    force main alignment

    - One at California Avenue and Yale Avenue

    - One at the high point, Princeton’s connection

    to Montara Force Main

    7

  • GEOLOGY AND SEISMICITY ASSESSMENTGeology Assessment

    - Site is underlain by sand and gravel deposited on uplifted marine-abrasion

    platform along the coast

    Seismicity Assessment

    - No earthquake faults crosses the force main alignment

    - Probability of major earthquake is relatively low

    8

    FaultApproximate Distance to Site

    (km)1Location with Respect to

    Site

    Probability of Mw>= 6.7

    within 30 Years2

    Hayward – Rodgers Creek 39 NE 32%

    Hayward (SE Extension) 39 NE 8%

    Calaveras 53 NE 25%

    Monte Vista – Shannon 28 SE 1%

    San Andreas (Entire) 10 NE 33%

    San Andreas (Peninsula) 10 NE 9%

    San Gregorio 0.3 SW 5%

  • SURFACE INSPECTION

    9

    Princeton Pump Station

    Surge Tank

    Princeton Pump Station Pig

    Launching Station

    Princeton Force Main Air

    Release Valve at California

    and Yale Avenue

    Princeton Force Main Air

    Release Valve at connection

    to Montara Force Main

  • EXTERNAL INSPECTION PROCESS

    • Locate pipeline

    • Excavate test pits (three total)

    • Clean exposed pipe

    • Wire brush scale and bituminous coating

    • Perform ultrasonic thickness testing

    • Perform electromagnetic testing

    • Sample groundwater and send to lab for analysis

    • Sample soil and send to lab for analysis

    • Backfill and pavement restoration

    • Conducted March 9, 10, and 11, 2020

    10

  • METAL THICKNESSClass 52 ductile iron pipe thickness for an 8-inch pipe is expected to be 0.33 inches

    Manufacturing tolerance is +/- 0.05 inches

    11

    Ultrasonic Thickness Testing

    Electromagnetic

    Scanning using

    Bracelet Probe

  • ULTRASONIC AND ELECTROMAGNETIC

    THICKNESS TESTING RESULTS

    12

    Location No. Location (inches)* UT High Readings

    by PICA (inches)

    UT Low Readings

    by PICA (inches)

    Wall Loss UT Readings by BAGG

    (inches)

    1 (14.5, 0.0) 0.258 0.220 22% - 33% 0.248-0.261

    2 (24.0, 0.0) 0.289 0.240 12% - 27% 0.252-0.259

    3 (21.0, 10.0) 0.265 0.221 20% - 33% 0.251-0.253

    4 (36.0, 0.0) 0.261 0.246 21% - 25% 0.259-0.261

    Test Pit 1:

    Location

    No.

    Location

    (inches)*

    UT High Readings

    by PICA (inches)

    UT Low Readings

    by PICA (inches)

    Wall Loss UT Readings by BAGG

    (inches)

    Bell Side

    1 (2.2, 0.0) 0.280 0.222 15% - 33% 0.237 – 0.267

    2 (11.0, 0.0) 0.250 0.168 24% - 49% 0.195 – 0.253

    3 (15.0, 0.0) 0.263 0.243 26% - 28% 0.195 – 0.265

    Spigot Side

    4 (0.0, 0.0) 0.276 0.276 16% 0.230 – 0.303

    5 (11.0, 0.0) 0.240 0.217 27% - 34% N/A

    Test Pit 2:

  • ULTRASONIC AND ELECTROMAGNETIC

    THICKNESS TESTING RESULTS CONTINUED

    13

    Location

    No.

    Location

    (inches)*

    UT High Readings by

    PICA (inches)

    UT Low Readings by

    PICA (inches)Wall Loss

    UT Readings by BAGG

    (inches)

    1 (6.0, 0.0) 0.268 0.255 18% - 23% 0.266 – 0.267

    2 (15.0, 0.0) 0.267 0.200 19% - 39% 0.205 – 0.277

    3 (24.0, 10.0) 0.274 0.196 17% - 41% 0.220 – 0.248

    Test Pit 3:

  • SOIL AND GROUNDWATER

    SAMPLING

    14

    Force Main Subsurface Profile in Test Pit 1 Groundwater in Test Pit 2

  • SOIL ANALYTICS

    15

    Soil Resistivity (ohm-cm) Degree of Corrosivity0-500 Very High

    500-1,000 High

    1,000-2,000 Moderate

    2,000-10,000 Mild

    Above 10,000 Negligible

    Correlation between soil resistivity and degree of corrosion

    Correlation between soil pH and degree of corrosion

    pH Degree of Corrosivity

    < 5.5 High

    5.5 – 6.5 Moderate

    6.5 – 7.5 Neutral

    > 7.5 Negligible

  • SOIL ANALYTICS CONTINUED

    16

    Sulfate concentration (ppm) Degree of Corrosivity

    > 2,000 Severe

    1,000 – 2,000 Moderate

    < 1,000 Negligible

    Sulfate: Sulfate ion concentration and degree of corrosivity of soil

    Chlorides: Chloride concentration and degree of corrosivity of soil

    Chloride concentration (ppm) Degree of Corrosivity

    > 5,000 High

    1,500 – 5,000 Moderate

    500 - 1,500 Mild

    100 – 500 Threshold

    < 100 Negligible

  • SOIL SAMPLING RESULTS

    17

    Analysis/Test

    Test Pit 1 Test Pit 2 Test Pit 3

    Corrosion

    PotentialTP-1-1 @

    2.25 ft

    TP-1-2 @

    5 ft

    TP-1-4

    @ 5 ft

    TP-2-1 @

    2.25 ft

    TP-2-2 @

    4.75 ft

    TP-3-1

    @ 3 ft

    TP-3-2 @

    5 ft

    Resistivity @100%

    Saturation (ohm-cm)3,795 9,070 9,255 1,566 3,147 3,374 3,808 Mild

    pH 7.2 7.5 5.4 7.8 7.5 7.9 7.6Neutral to

    negligible

    ORP (Redox) (mV) 506 526 400 520 536 421 507

    Chloride (mg/Kg) 23 8 32 29 22 12 21 Negligible

    Sulfate (mg/Kg) 147 65 106 29 83 63 76 Negligible

    Sulfide (Qualitative

    by Lead)Negative Negative Negative Negative Negative Negative Negative

    Moisture Content

    (%)14.6 16.6 9.9 23.1 20.6 14.2 11.8

  • GROUNDWATER RESULTS

    18

    Analysis/Test

    Test Pit 1 Test Pit 2 Test Pit 3

    Corrosion Potential

    TP-1-3 @ 5 ft TP-2-3 @ 4.75 ft TP-3-3 @ 5 ft

    Resistivity (ohm-cm) 4,633 1,754 1,361 Moderate to mild

    pH 7.3 7.2 7.2 Neutral

    Chloride (mg/Kg) 41 84 159 Negligible

    Sulfate (mg/Kg) 21 56 112 Negligible

  • CONCLUSIONS

    • The Princeton Force Main appears to be in good condition and does not pose a threat of failure

    • The pressure rating of the Force Main far exceeds the normal working pressure

    • No hydraulic anomalies were observed

    • There are no observed surface indications that the Force Main is leaking

    • No development or other utilities are jeopardizing the Force Main

    • No faults or geologic hazards pose a threat to the Force Main

    • Soil and groundwater surrounding the Force Main are not corrosively aggressive

    • Metal loss is moderate and does not pose of risk of failure

    • There is no reason to believe the Force Main will have any less than a 100-year service life which is expected of a ductile iron pipeline

    19

  • RECOMMENDATIONS

    • Perform similar inspection in 10 years

    • Air release valves and blow off should be on a regular maintenance schedule

    • Replace deteriorated surge tank at Princeton Pump Station

    • Replace the other ARV on the force main alignment

    • Install emergency bypass capability at Princeton Pump Station

    20

  • QUESTIONS &

    DISCUSSION

    21