princeton force main condition assessment project1307b359... · 6. geologic assessment 7. external...
TRANSCRIPT
-
PRINCETON FORCE MAIN
CONDITION ASSESSMENT
PROJECT
SAM BOARD PRESENTATION - MAY 11, 2020
-
PRESENTATION OUTLINE1. Purpose
2. Condition assessment team
3. Overview of Princeton Force Main
4. Methodology
5. Hydraulic assessment
6. Geologic assessment
7. External inspection process
8. Metal thickness test results
9. Soil and groundwater test results
10. Recommendations
11. Questions/discussion
2
-
PURPOSE
• Assure reliability for next 60 years
• Determine current condition of the force main
• Proactively determine if the force main presents a risk of failure
• Settlement requirement with Ecological Rights Foundation Consent Decree
3
-
CONDITION ASSESSMENT
TEAM
4
Participant Role
SAM Operations and Collection System staff Pump station and force main operations, project
oversight, spill mitigation in emergency
SRT Consultants, San Francisco, CA Engineer of record, planning, logistics, coordination,
reporting
BAGG Engineers, San Jose, CA Logistics, planning, UT testing, soil and groundwater
sampling and analysis
Andrieni Brothers, Half Moon Bay, CA Permitting, construction support, utility locating, traffic
control, pit excavation, shoring, pipe coating
restoration, backfilling, and paving
Pipeline Inspection and Condition Analysis
Corporation (PICA)
Electromagnetic scanning, data processing, and
reporting
Ductile Iron Pipe Research Association (DIPRA) Technical assistance, observation, and guidance
-
OVERVIEW OF PRINCETON FORCE MAIN
• 8 inch diameter
• Ductile iron
• Age: 41 years
• Installed in 1979
• Part of the IPS
• Length: 4,200’
• Depth: +/- 4’-0”
5
-
METHODOLOGY• Hydraulic Assessment
• Desk top model was developed in WaterCAD to assess pressure and velocity as various flow rates
• Geology and Seismicity Assessment
• Desktop study to determine geologic risks due to earthquake, faults, and liquefaction
• Force Main Alignment and Appurtenances Inspection
• Visual inspection of force main alignment
• Visual inspection of surge chamber, air release valves, and blow offs
• Non-Intrusive Pipe Wall Thickness Inspection
• Ultrasonic pipe wall thickness testing
• Electromagnetic pipe wall thickness testing
• Pipeline Subsurface Inspection
• Soil sampling and analysis
• Groundwater sampling and analysis
Removing a segment of the pipeline for internal inspection was considered but not performed because the
capacity of the Princeton PS wet well is too small to accommodate regular flow and drain back of the force main
6
-
HYDRAULIC ASSESSMENT
Princeton Force Main
- Hydraulic modeling shows that the
force main is constantly pressurized
and there is no local high or low
points
- Hydrogen sulfide gas is not likely to
accumulate except at the high point
(connection to Montara Force Main)
- Two ARVs are installed along the
force main alignment
- One at California Avenue and Yale Avenue
- One at the high point, Princeton’s connection
to Montara Force Main
7
-
GEOLOGY AND SEISMICITY ASSESSMENTGeology Assessment
- Site is underlain by sand and gravel deposited on uplifted marine-abrasion
platform along the coast
Seismicity Assessment
- No earthquake faults crosses the force main alignment
- Probability of major earthquake is relatively low
8
FaultApproximate Distance to Site
(km)1Location with Respect to
Site
Probability of Mw>= 6.7
within 30 Years2
Hayward – Rodgers Creek 39 NE 32%
Hayward (SE Extension) 39 NE 8%
Calaveras 53 NE 25%
Monte Vista – Shannon 28 SE 1%
San Andreas (Entire) 10 NE 33%
San Andreas (Peninsula) 10 NE 9%
San Gregorio 0.3 SW 5%
-
SURFACE INSPECTION
9
Princeton Pump Station
Surge Tank
Princeton Pump Station Pig
Launching Station
Princeton Force Main Air
Release Valve at California
and Yale Avenue
Princeton Force Main Air
Release Valve at connection
to Montara Force Main
-
EXTERNAL INSPECTION PROCESS
• Locate pipeline
• Excavate test pits (three total)
• Clean exposed pipe
• Wire brush scale and bituminous coating
• Perform ultrasonic thickness testing
• Perform electromagnetic testing
• Sample groundwater and send to lab for analysis
• Sample soil and send to lab for analysis
• Backfill and pavement restoration
• Conducted March 9, 10, and 11, 2020
10
-
METAL THICKNESSClass 52 ductile iron pipe thickness for an 8-inch pipe is expected to be 0.33 inches
Manufacturing tolerance is +/- 0.05 inches
11
Ultrasonic Thickness Testing
Electromagnetic
Scanning using
Bracelet Probe
-
ULTRASONIC AND ELECTROMAGNETIC
THICKNESS TESTING RESULTS
12
Location No. Location (inches)* UT High Readings
by PICA (inches)
UT Low Readings
by PICA (inches)
Wall Loss UT Readings by BAGG
(inches)
1 (14.5, 0.0) 0.258 0.220 22% - 33% 0.248-0.261
2 (24.0, 0.0) 0.289 0.240 12% - 27% 0.252-0.259
3 (21.0, 10.0) 0.265 0.221 20% - 33% 0.251-0.253
4 (36.0, 0.0) 0.261 0.246 21% - 25% 0.259-0.261
Test Pit 1:
Location
No.
Location
(inches)*
UT High Readings
by PICA (inches)
UT Low Readings
by PICA (inches)
Wall Loss UT Readings by BAGG
(inches)
Bell Side
1 (2.2, 0.0) 0.280 0.222 15% - 33% 0.237 – 0.267
2 (11.0, 0.0) 0.250 0.168 24% - 49% 0.195 – 0.253
3 (15.0, 0.0) 0.263 0.243 26% - 28% 0.195 – 0.265
Spigot Side
4 (0.0, 0.0) 0.276 0.276 16% 0.230 – 0.303
5 (11.0, 0.0) 0.240 0.217 27% - 34% N/A
Test Pit 2:
-
ULTRASONIC AND ELECTROMAGNETIC
THICKNESS TESTING RESULTS CONTINUED
13
Location
No.
Location
(inches)*
UT High Readings by
PICA (inches)
UT Low Readings by
PICA (inches)Wall Loss
UT Readings by BAGG
(inches)
1 (6.0, 0.0) 0.268 0.255 18% - 23% 0.266 – 0.267
2 (15.0, 0.0) 0.267 0.200 19% - 39% 0.205 – 0.277
3 (24.0, 10.0) 0.274 0.196 17% - 41% 0.220 – 0.248
Test Pit 3:
-
SOIL AND GROUNDWATER
SAMPLING
14
Force Main Subsurface Profile in Test Pit 1 Groundwater in Test Pit 2
-
SOIL ANALYTICS
15
Soil Resistivity (ohm-cm) Degree of Corrosivity0-500 Very High
500-1,000 High
1,000-2,000 Moderate
2,000-10,000 Mild
Above 10,000 Negligible
Correlation between soil resistivity and degree of corrosion
Correlation between soil pH and degree of corrosion
pH Degree of Corrosivity
< 5.5 High
5.5 – 6.5 Moderate
6.5 – 7.5 Neutral
> 7.5 Negligible
-
SOIL ANALYTICS CONTINUED
16
Sulfate concentration (ppm) Degree of Corrosivity
> 2,000 Severe
1,000 – 2,000 Moderate
< 1,000 Negligible
Sulfate: Sulfate ion concentration and degree of corrosivity of soil
Chlorides: Chloride concentration and degree of corrosivity of soil
Chloride concentration (ppm) Degree of Corrosivity
> 5,000 High
1,500 – 5,000 Moderate
500 - 1,500 Mild
100 – 500 Threshold
< 100 Negligible
-
SOIL SAMPLING RESULTS
17
Analysis/Test
Test Pit 1 Test Pit 2 Test Pit 3
Corrosion
PotentialTP-1-1 @
2.25 ft
TP-1-2 @
5 ft
TP-1-4
@ 5 ft
TP-2-1 @
2.25 ft
TP-2-2 @
4.75 ft
TP-3-1
@ 3 ft
TP-3-2 @
5 ft
Resistivity @100%
Saturation (ohm-cm)3,795 9,070 9,255 1,566 3,147 3,374 3,808 Mild
pH 7.2 7.5 5.4 7.8 7.5 7.9 7.6Neutral to
negligible
ORP (Redox) (mV) 506 526 400 520 536 421 507
Chloride (mg/Kg) 23 8 32 29 22 12 21 Negligible
Sulfate (mg/Kg) 147 65 106 29 83 63 76 Negligible
Sulfide (Qualitative
by Lead)Negative Negative Negative Negative Negative Negative Negative
Moisture Content
(%)14.6 16.6 9.9 23.1 20.6 14.2 11.8
-
GROUNDWATER RESULTS
18
Analysis/Test
Test Pit 1 Test Pit 2 Test Pit 3
Corrosion Potential
TP-1-3 @ 5 ft TP-2-3 @ 4.75 ft TP-3-3 @ 5 ft
Resistivity (ohm-cm) 4,633 1,754 1,361 Moderate to mild
pH 7.3 7.2 7.2 Neutral
Chloride (mg/Kg) 41 84 159 Negligible
Sulfate (mg/Kg) 21 56 112 Negligible
-
CONCLUSIONS
• The Princeton Force Main appears to be in good condition and does not pose a threat of failure
• The pressure rating of the Force Main far exceeds the normal working pressure
• No hydraulic anomalies were observed
• There are no observed surface indications that the Force Main is leaking
• No development or other utilities are jeopardizing the Force Main
• No faults or geologic hazards pose a threat to the Force Main
• Soil and groundwater surrounding the Force Main are not corrosively aggressive
• Metal loss is moderate and does not pose of risk of failure
• There is no reason to believe the Force Main will have any less than a 100-year service life which is expected of a ductile iron pipeline
19
-
RECOMMENDATIONS
• Perform similar inspection in 10 years
• Air release valves and blow off should be on a regular maintenance schedule
• Replace deteriorated surge tank at Princeton Pump Station
• Replace the other ARV on the force main alignment
• Install emergency bypass capability at Princeton Pump Station
20
-
QUESTIONS &
DISCUSSION
21