priority scour critical bridge countermeasure plan of action …gis.dot.nh.gov/bridge_scour/pelham...
TRANSCRIPT
DocID_106
Attachment D: Bridge Elevation Summary Showing Existing Streambed, Foundation Depth(s) and Observed and/or Calculated Scour Depths
The Following Materials Are Being Submitted With This Report:
Attachment H: Plan View Showing Location of Scour Holes, Debris, etc,
Attachment B: Map Showing Detour Route(s)
Attachment E: Boring Logs and/or Other Subsurface Information
Attachment F: Survey Cross Sections From Current and Previous Inspection Reports
Attachment G: Supporting Documentation, Calculations, Estimates, and Conceptual Designs for Scour Countermeasures
Attachment A: Photos
Attachment C: Field Verification Card (FVC)
Feature Crossed: Beaver Brook
Feature Carried: Main Street
Owner: NHDOT
New HampshireDepartment of Transportation
Scour Critical BridgePlan of Action (POA) Report
Final Recommended Action:This bridge is an historic stone arch built 1900, with a 1929 steel multi-girder addition – no meaningful plans available. The foundations and corresponding embedment are therefore unknown. Latest underwater inspection (2006) noted no particular scour deficiencies. Currently this bridge is under a 6-month inspection frequency due to the poor condition of the substructure. This frequency should continue. This structure has experienced several significant flood event, most recently in 2006 and 2007. During CHA’s 2009 inspection it was noted that there was a scour hole on the downstream end under the newer portion of structure and large amounts of debris in the superstructure due to previous floods. Due to the extensive flood history at the bridge and the poor condition of the substructures, CHA recommends monitoring the bridge during and after significant storm events until it can be replaced. If replacement efforts are not currently defined then partially grouted riprap should also be installed at the pier. CHA recommends that the Item 113 and Item 60 both be rated 2.
Pelham 110/090
POA Report
Scour POA Priority:
Attachment I: Post Flood Inspection Documentation
Post Flood Inspection Tasks
Flood Monitoring Program
Conceptual Structural / Hydraulic Countermeasures
Fixed Monitoring Devices
Increased Inspection Frequency
Priority Countermeasure
PriorityMonitoring
Attachment J: Scour / H&H Backup Calculations
Attachment K: NHDOT Underwater Inspection Report
SCOUR CRITICAL BRIDGE - PLAN OF ACTIONPelham 110/090
1. GENERAL INFORMATIONStructure:
Year Built:
110/090
1900
City, County, State:
Pelham, Hillsborough, New Hampshire
State Highway or Facility Carried:
Main Street
Waterway Crossed:
Beaver Brook
Owner:
NHDOT
Year Rebuilt:
1929
Planned Bridge Replacement (if scheduled):
Anticipated Opening Date:
Original structure comprised of a two-span filled-spandrel split-stone arch. Structure widened on the downstream side with concrete deck on steel beams and substructure extensions. No meaningful plans available.
Structure Size and Description:
Foundation Details:
KNOWN UNKNOWN
Subsurface SoilInformation:
Bridge ADT Info:
Does the Bridge Provide Service to Emergency Facilities and/or an Evacuation Route (Y/N)?:
Elementary school adjacent, also used for emergency vehicles.If So, Describe:
WorstAbutment: Right
WorstPier: 1
(Looking Downstream L to R)
Channel Primary Bed Material:
Sand
Channel Secondary Bed Material:
Sand & Gravel
Embedment (feet): unknown Exposure: No Exposure
Embedment (feet): unknown Exposure: No Exposure
Scour Summary
The bridge was originally constructed in 1900 and reconstructed (widened with concrete deck on steel beams and substructure extensions) in 1929. The FEMA FIS does not provide specific flood history for the Town of Pelham or Beaver Brook, however photos from the NHDOT inspection reports indicate that the bridge experienced flooding in May of 2006 and April 2007. USGS Gage 10965852 located 6.5 miles upstream recorded a 100 year event in 2006 and a 10-50 year event in 2007. Also NHDOT WWII Card (1942) indicates the flood of record was in 1936.
Flood History:
Two-span masonry arch bridge originally constructed in 1900 and reconstructed (widened with concrete deck on steel beams and substructure extensions) in 1929. Both abutments are composed of stone masonry, located in the channel and have unknown footing embedments. The pier is composed of stone masonry, located in the channel and has an unknown foundation. The latest NHDOT underwater inspection report (2006) did not note any significant scour issues, however it did note several voids in the masonry at the abutments and pier and that a stone at the pier was misaligned. In addition, according to the NHDOT Inspection History the bridge has been on a 6-month frequency since 1999, and inspectors have consistently noted the poor condition of the substructure elements. Bridge opening data referenced from the NHDOT WWII Card (1942) is generally consistent with the drop-line readings taken in 2009, indicating there has been no long term aggradation or degradation of the streambed within the bridge reach. During the 2009 inspection downstream of the bridge on the right side, it was observed that there was a large scour hole. Although the bridge has experienced several significant flood events since it was reconstructed in 1929 (most recently in 2006 & 2007), the potential scour depth along with the unknown and unprotected footing at the pier indicate that this bridge should remain rated as scour critical.
Field Observation:
Hillsborough Countywide FIS provides flow and water surface elevation data at the bridge. This information was used along with a field soil classification (fine to coarse sand) in order to develop a pier scour estimate. The result of this computation indicates the potential for 13.4 feet of scour at the pier during the incipient overtopping (50-year) event. Although the bridge has experienced several significant flood events since it was reconstructed in 1929 (most recently in 2006 & 2007), the potential scour depth along with the unknown and unprotected footing at the pier indicate that this bridge should be rated scour critical and a POA should be implemented.
Scour Calculations:
Current Item 113 Code: 2 Source of Scour Critical Code: Assessment
Borings:
Yes No
Bridge Maintenance Division5
20064900 Year:Total:
Text9:6/9/2010 Text9:Scour Critical Bridge - Plan of Action: Pelham 110/090 Text9: Page 1 of 6
5. MONITORING PROGRAM RECOMMENDED5a. Regular Inspection Program
Riverbed Profile Readings
Items toWatch:
According to the NHDOT Inspection History the bridge has been on a 6-month frequency since 1999, and inspectors have consistently noted the poor condition of the substructure elements. Monitor channel elevations with riverbed profile readings, making note of any significant changes. Monitor displacement of stones. Use photo documentation. MAINTAIN 6 MONTH INSPECTION FREQUENCY.
5b. Fixed Monitoring Device(s)
Type of Instrument:
Installation Location(s):
Sample Interval: 30 min 1 hr. 6 hrs. 12 hrs. Other
Frequency of Data Download and Review: Daily Weekly Monthly Other:
Scour Critical Elevation(s) For Each Pier:
Criteria of Termination For Fixed Monitoring:
Standard 2 Year Interval
Underwater Inspection Required Items toWatch:
Monitor channel elevations with riverbed profile readings, making note of any significant changes.
Standard 5 Year Interval
2 Year Interval
1 Year Interval
5c. Flood Monitoring Program
Type:
Discharge
Visual Inspection
Instrument (check all that apply)
Portable Geophysical SonarOther
(check all that apply)
Flood Monitoring event defined by:
Stage (WSE)
Frequency of Flood Monitoring: 1 hr. 3 hrs. 6 hrs. Other
Notified By Public
Flood Warning Issued by NWS
Notified by Fixed Monitoring Device
USGS Gage Station #
1 Year Interval
Criteria to End Flood MonitoringConditions Stable / Water Receding
Recommended Post Flood Inspection
Action(s) Required if Scour Critical Elevation Detected: (See Section 7 and Section 8)
Not Applicable:
During PrecipitationEvent, Look For:
Water surface elevation at low chord (apex of arch on the upstream side).
Revisit Bridge
Close Bridge (See Section 7)
Placard Location: Placard not necessary.
Contact Person(s):NHDOT Bridge Design Bureau, Bridge Inspector1.
NHDOT Bridge Maintenance Divisional Superintendent Crew# 142.
NHDOT Bridge Maintenance Divisional Foreman Crew# 143.
NHDOT Bridge Design Bureau, Existing Bridge Section4.
NHDOT Bridge Design Bureau, Administrator5.
Stage (WSE)
NOAA Gage Station #
Scour Critical Riverbed Elevation(s) for Each Pier/Abutment: Pier and Abutments have unknown foundations - 1 ft below current streambed (See Attachment D)
NOTE: Additional Details for Action(s) Required May Be Included in Sections 7 and 8.
Action(s) Required if Scour Critical Riverbed Elevation Detected:
Assess changes in channel/riverbed profiles, possible footing exposure and overall stability. Consider closing bridge.
Agency and Department Responsible for Monitoring:
NHDOT
Contact Person:
NHDOT Bridge Design Bureau (603) 271-2731
Riverbed Profile Readings (See Attachment I)
Items toWatch:
According to the NHDOT Inspection History the bridge has been on a 6-month frequency since 1999, and inspectors have consistently noted the poor condition of the substructure elements. Monitor channel elevations with riverbed profile readings, making note of any significant changes. Monitor displacement of stones.
5d. Post-Flood Inspection Tasks Required
Visual Inspection (See Attachment I)
Profile at Substructure (See Attachment I)
Undermining (See Attachment I)
Text9:6/9/2010 Text9:Scour Critical Bridge - Plan of Action: Pelham 110/090 Text9: Page 3 of 6
6. COUNTERMEASURE RECOMMENDATIONS
Conceptual Structural / Hydraulic Countermeasures
Basis for the Selection of the Preferred Scour Countermeasure:
Include Information on Hydraulic, Structural or Monitoring Countermeasures.
(1) Interim action - Articulated Concrete Blocks at pier and both abutments
Estimated Cost
$ 320,000
(2) $
(3) $
Consider major rehabilitation for this bridge. Install articulated concrete block system until rehabilitation schedule is defined. Deep water, but minimal embedment.
Countermeasure Implementation Project Type:
Proposed Construction
Other
Bridge Maintenance
Programmed Construction - Project Lead Agency
Bridge Design
Highway Design
Recommended Countermeasures to be Performed by:
NHDOT
Contact Person:
NHDOT Bridge Design Bureau (603) 271-2731
Post Flood Inspection Tasks Required
Flood Monitoring Program
Fixed Monitoring Devices
Regular Inspection Program
Lead Agency:
Conceptual Cost Estimate:
H & H Summary Information:
129.5
132.5
2955
3515
5600
132.5
134
135
50 year
Flow (cfs) Elevation (ft)
100 year
500 year
Roadway
Low Chord
Flow Impacting Bridge Flow Overtopping Bridge
Yes
Yes
Yes
Yes
Yes
Yes
1545 13010 year No No
Text9:6/9/2010 Text9:Scour Critical Bridge - Plan of Action: Pelham 110/090 Text9: Page 4 of 6
7. BRIDGE CLOSURE PLAN
Scour Measurement Results / Monitoring Device (See Section 5)
Criteria For Consideration of Bridge Closure:
Observed Structure Movement / Settlement
Water Surface Elevation Reaches Low Chord
Overtopping Road or Structure
Other: Debris Accumulation Movement of RipRap/Other Armor Protection Loss of Road Embankment
Agency and Department Responsible for Closure:
Contact Person(s):
NHDOT Bridge Design Bureau, Bridge Inspector
(See Attachment C)
Water Reaches Critical Elevation:
NHDOT Municipality:Transportation Management Center
1.
NHDOT Bridge Maintenance Divisional Superintendent Crew# 142.
NHDOT Bridge Maintenance Divisional Foreman Crew# 143.
NHDOT Bridge Design Bureau, Existing Bridge Section4.
NHDOT Bridge Design Bureau, Administrator5.
Ice Jam
DischargeStage (WSE)USGS Gage Station #
Stage (WSE)NOAA Gage Station #
8. DETOUR ROUTEDetour Route Description: (See Attachment B)
Bridges on Detour Route:
Bridge NumberFeatureCrossed
Load Posting (tons) (Date)
Item 113Code
Traffic Control Equipment (detour signing and barriers) and storage location(s) (NHDOT/Town): NHDOT Bridge Maintenance Divisional Crew 14
Additional Considerations or Critical Issues (susceptibility to overtopping, limited waterway adequacy, lane restrictions, etc.):
NHDOT Bridge Design Bureau (603) 271-2731
News Release, Other Public Notice (include authorized person(s), information to be provided and limitations):
NHDOT Public Information Officer, NHDOT Bridge Design Bureau (603) 271-2731
FeatureCarried
VerticalClearance
(feet)
WidthRestrictions
(feet)
HighwayMaintenance
District: 05
NHDOT Bureauof Traffic
Pelham 109/081 BEAVER BROOK 14.7 (6/20/2002)UOLD BRIDGE STREET unrestricted 23.9
Text9:6/9/2010 Text9:Scour Critical Bridge - Plan of Action: Pelham 110/090 Text9: Page 5 of 6
9. BRIDGE REOPENING PLAN9a. Criteria for Consideration to Complete Interim Bridge Reopening:
Agency and Person Responsible for Re-Opening Bridge After Inspection:
NHDOT Bridge Design Bureau (603) 271-2731
Post Flood Inspection Completed
Critical Elevation Marker Is Visible
Reasons for Closure Have Abated
Water Surface Levels Dropping
Diving Inspection Completed within 7 calendar days
Verify Riverbed Elevation (drop line readings)
Streambed Elevation Drops Less than
Streambed Elevation 1.0 Feet
0.1 Feet
9b. Criteria for Completing Bridge Reopening Process:
Above Critical Footing Elevation. (See Section 5d)
Text9:6/9/2010 Text9:Scour Critical Bridge - Plan of Action: Pelham 110/090 Text9: Page 6 of 6
Bridge: Pelham 110/090
Date Taken: 5/21/2009 10:24:49 AM
Description: UPSTREAM FASCIA
Source: CHA
DocID_106
Bridge: Pelham 110/090
Date Taken: 5/21/2009 10:25:01 AM
Description: DOWNSTREAM FASCIA
Source: CHA
DocID_106
Text9:5/17/2010 Text9:Attachment A: Bridge Photos: Pelham 110/090 Text9: Page 1 of 3
Bridge: Pelham 110/090
Date Taken: 5/21/2009 10:25:03 AM
Description: DOWNSTREAM CHANNEL
Source: CHA
DocID_106
Bridge: Pelham 110/090
Date Taken: 5/21/2009 10:24:51 AM
Description: UPSTREAM FASCIA - OVERFLOW CULVERT
Source: CHA
DocID_106
Text9:5/17/2010 Text9:Attachment A: Bridge Photos: Pelham 110/090 Text9: Page 2 of 3
Bridge: Pelham 110/090
Date Taken: 5/21/2009 10:24:59 AM
Description: DOWNSTREAM FASCIA - OVERFLOW CULVERT
Source: CHA
DocID_106
Text9:5/17/2010 Text9:Attachment A: Bridge Photos: Pelham 110/090 Text9: Page 3 of 3
11 King Court
Keene, NH 03431-4648 Main: (603)-357-2445
New Hampshire Scour Investigation
Pelham 110/090
Attachment B: Detour Route
Pelham 110/090
DETOUR MAP
IF GOING EAST ON MAIN ST., REVERSE DIRECTIONS.
GOING WEST ON MAIN ST.
Bridge: Pelham 110/090
Detour (miles): Last ADT:
Foundation Details:
KNOWN
UNKNOWN Worst Abutment: Right
Worst Pier: 1(Looking Downstream L to R)
Embedment (feet): unknown Exposure: No Exposure
Embedment (feet): unknown Exposure: No Exposure
Diving Insp Reports: 6/6/2008
FIELD VERIFICATION CARD (POA Attachment C)
Owner: NHDOT
Feature Carried: Main Street
Feature Crossed: Beaver Brook
Town, County: Pelham - Hillsborough
Contact Person: NHDOT Bridge Design Bureau (603) 271-2731
BRIDGE INFORMATION
Superstructure Type: Arch-Deck
Superstructure Material: Masonry
Scour Critical Feature: Pier
Placard Location: Placard not necessary.
Red List: Yes
Number of Spans: 2
USGS Gage Station: 10965852 USGS Station Prox To Bridge: 6.5 miles upstream
GENERAL INFORMATION
Scour Measurement Results / Monitoring Device
CRITERIA FOR CONSIDERATION OF BRIDGE CLOSURE
Observed Structure Movement / Settlement
Water Surface Elevation Reaches Low Chord
Overtopping Road or Structure
Date/TimeNotified:
Completed ProperNotification
Close BridgeRevisit BridgePost-Flood Inspection Recommendation
POST-MONITORING VERIFICATION
ACTION TAKEN
REFERENCE PHOTOS
Dates:
Water Reaches Critical Elevation:
Agency:
What To Look For: Changes in streambed elevation of more than 0.1 ft or evidence of footing exposure.
(Left to Right Convention Looking Downstream)
CRITERIA FOR CONSIDERATION TO COMPLETE INTERIM BRIDGE REOPENING:
Agency and Person Responsible for Re-Opening Bridge After Inspection:
NHDOT Bridge Design Bureau (603) 271-2731
Critical Elevation Marker Is Visible
Reasons for Closure Have Abated
Water Surface Levels Dropping
Verify Riverbed Elevation
Above Critical Footing Elevation. (See Section 5d)
(Continued on Next Page)
Interim Reopening Date:Interim Reopening Approved By: Time:
INTERIM REOPENING COMMENTS
Traffic Control Equipment (detour signing and barriers) and storage location(s) (NHDOT/Town): NHDOT Bridge Maintenance Divisional Crew 14
HighwayMaintenance
District: 05
NHDOT Bureauof Traffic
Streambed Elevation Drops Less than
Streambed Elevation 1.0 Feet
0.1 Feet
Other: Debris Accumulation Movement of RipRap/Other Armor Protection Loss of Road Embankment Ice Jam
DischargeStage (WSE)USGS Gage Station #
Stage (WSE)NOAA Gage Station #
NOAA Gage Station: NOAA Station Prox To Bridge:
1 20064900 Year:Total:
Text9:5/17/2010 Text9:Attachment C: Field Verification Card: Pelham 110/090 Text9: Page 1 of 2
Upstream Low Water
DocID_10629.jpg
Upstream Low Water
DocID_10628.jpg
Downstream Elevation of Bridge at Low Water
DocID_10632.jpg
Text9:5/17/2010 Text9:Attachment C: Field Verification Card: Pelham 110/090 Text9: Page 2 of 2
ROADWAY
ELEVATION (FT)
LOW CHORD
ELEVATION (FT)
FOOTING ELEVATION (FT) STREAMBED ELEVATION (FT)
TOP BOTTOM
SUBSTR.
UNIT
2) THE SUBSTRUCTURE LABELING CONVENTION ESTABLISHED BY CHA DEFINES LEFT AND RIGHT LOOKING DOWNSTREAM.
1) UNLESS OTHERWISE SPECIFIED, ALL ELEVATIONS ARE REFERENCED TO NGVD 1929.
LEFT ABUT.
PIER 1
RIGHT ABUT.
INVESTIGATION
DDATE: 10/09
BRIDGE ELEVATION SUMMARY
NEW HAMPSHIRE BRIDGE SCOUR
4) BRIDGE 110/090 HAS AN OVERFLOW CULVERT (12FT SPAN X 8.5 FT RISE, PIPE ARCH) LOCATION APPROXIMATELY 30 FT EAST OF THE LEFT ABUTMENT.
PELHAM 110/090
132.5
132.5
132.5
129.5 (SPAN 1 APEX)
--
129.5 (SPAN 1 APEX)
UNK
UNK
UNK
UNK
UNK
UNK
NHDOT WW11
CARD (1942)
v--
120.3
v--
CHA FIELD
2009
FEMA FIS (1979)
COUNTRYWIDE (2005)
--
117.0
--
120.6
120.1
120.5
CHA 100-YEAR SCOUR
ELEVATION (FT)
v--
106.7
v--
UPSTREAM ELEVATION
N.T.S.
STREAMBED ELEVATION
(TYP)
LOW CHORD ELEVATION
(TYP)ROADWAY ELEVATION
(TYP)
RAP1LA
3) STREAMBED ELEVATIONS GIVEN ARE APPROXIMATE AT EACH SUBSTRUCTURE UNIT AND ALONG THE FASCIA INDICATED. vFOR DETAILED SUBSTRUCTURE RIVERBED PROFILE MEASUREMENTS SEE ATTACHMENT I. ATTACHMENT H PROVIDES THE LOCATION OF vSCOUR RELATED FEATURES AND OTHER MINOR STREAMBED VARIATIONS.
FIL
E N
AM
E =
DA
TE
/TIM
E =
US
ER
=
K:\
18457\C
AD
D\M
ST
N\B
rid
ge P
OA
fil
es P
art
A-2\P
elh
am
110-090\1
8457_cpb_gnt_
update
d.d
gn
5/1
7/2
01
0
3293
ATTACHMENT
CP-NORMAL
SUBTITLE TEXT SIZE
N.T.S.
www.chacompanies.comMain: (603) 357-2445
11 King Court Keene, NH 03431-4648
Drawing Copyright c 2009
RA
P1
LA
ANNOTATION SCALE 200
FOOTING ELEVATION (FT) STREAMBED ELEVATION (FT)
BOTTOM CHA FIELD (2009)
vUPSTREAM ELEVATIONv
CHA File No:
18925.2003.1510
11 King Court
Keene, NH 03431-4648
Main: (603)-357-2445
New Hampshire Scour Investigation
Pelham 110/090 Attachment G: Scour Countermeasures
Attachment G:
Supporting Documentation, Calculations,
Estimates, and Conceptual Designs for Scour
Countermeasures
NHDOT PROTECTIVE COUNTERMEASURES 4/14/2010
ESTIMATED COST OF POTENTIAL INTERIM COUNTERMEASURE - Articulated Concrete Block System:
110/090Pelham
4619 3'-5'36 3.1 ACB Width = 2.5 times pier ftg width14 37 ACB Length is along its center25 <= width at abutment = 25 ft (less than 2 x design flow)
SSU CM TYPE Length (ft) Width (ft) Depth (ft) No. Items Quantity Unit Unit Price Subtotal1 1 LS $10,000 $10,0001 1 LS $10,000 $10,0000 0 LS $0 $0
120.5 7.75 - 2 208 SY $31 $6,485120.5 7.75 - 2 208 SY $63 $12,970120.5 7.75 - 2 208 SY $213 $44,100
0 0 LS $0 $086 25 - 2 478 SY $31 $14,93186 25 - 2 478 SY $63 $29,86186 25 - 2 478 CY $213 $101,528
Proposed work: $25,000 - diversion of water not practical - minor excavate and level area $254,875 - place filter 25% $63,719 - place ACB system $318,594
$320,000
Assumptions:Environmental impact associated with the proposed work is judged to be: potentially significantGiven the estimated quantities for this item, the unit price is judged to be higher than average unit prices.
Notes:The cost of mitigating or eliminating potential environmental impacts is not included in this estimate. The cost of environmental permit preparation is also not included herein.
Provide and place ACB system
Pier 1 ACB
Both Abutments ACB
Water Diversion System
Low Flow Water Depth
Spans Protected N/ABridge No.
In light of the overall poor condition of this bridge, CHA recommends COMPLETE REPLACEMENT. As an interim action, this countermeasure could be installed to address known scour deficiencies of the foundations. Such action might allow increasing the FHWA Item 113 scour rating from 2 (CHA’s proposed rating for current conditions) to 3 (still scour critical due to potential substructure instability during flood events). The rating condition of the substructure (FHWA Item 60) should be reduced due to its linkage with Item 113 (CHA proposes rating Item 60 as 2 for current conditions – could be increased to 3 after such action). A more careful evaluation of substructure stability would be required as part of this potential action because the countermeasure would result in “mounding” of the streambed, thereby violating the intent of HEC-23 and not allow a rating of 7.
TownSSU's Protected Pier 1 and Both Abutments
Dist. Between Abutment Faces Approved Countermeasure Type Articulated Concrete Block SystemDist. Between abut and pier
ContingencyTotal Estimated Cost
Conceptual Budget
Bridge Width
barge rental
Design Flow DepthPier Width (ft)
Pier Length (ft)
Access to pier via bargeItem
Subtotal
Excavation and site prep
Note - in light of deeper "normal low" flow, PGR is considered unacceptable due to higher costs of dewatering/diversion of water. Accordingly, use ACB system with underwater placement. Narrow and long roadway embankment drives need for barge for work access.
Mobilization
Provide and place ACB systemProvide and place filter
Water Diversion SystemExcavation and site prep Provide and place filter
5/17/2010 Attachment G
INVESTIGATION
G
NEW HAMPSHIRE BRIDGE SCOUR
DATE: 4/10
PELHAM 110/090
CONCEPTUAL COUNTERMEASURE DRAWING
UPSTREAM ELEVATION
N.T.S.
RAP1LA
N.T.S.
PLAN VIEW
LA P1 RA
PLACE ARTICULATED CONCRETE
BLOCKS
FIL
E N
AM
E =
DA
TE
/TIM
E =
US
ER
=
K:\
18457\C
AD
D\M
ST
N\B
rid
ge P
OA
fil
es P
art
A-2\P
elh
am
110-090\1
8457_cpb_pln
.dgn
5/1
7/2
01
0
3293
ATTACHMENT
CP-NORMAL
SUBTITLE TEXT SIZE
N.T.S.
www.chacompanies.comMain: (603) 357-2445
11 King Court Keene, NH 03431-4648
Drawing Copyright c 2009
RA
P1
LA
ANNOTATION SCALE 200
FOOTING ELEVATION (FT) STREAMBED ELEVATION (FT)
BOTTOM CHA FIELD (2009)
vUPSTREAM ELEVATIONv
NHDOT POST FLOOD INSPECTION REPORT (POA Attachment I)
Bridge: Post Flood Inspection Date:Pelham 110/090GENERAL INFORMATION
Town: Pelham
Feature Carried: Main Street
Owner: NHDOT
Feature Crossed: Beaver Brook
Major Basin (HU8): Merrimack River
Functional Class: 09 - Rural Local
Detour Length: 1 (miles)
Year Built: 1900
Year ofReconstruction: 1929
ADT: 4900 Year of ADT: 2006
Overall Fed Sufficiency Rating: 15.8
RedList: Yes
Item 60: 2 Item 61: 6 Item 71: 7 Item 113: 2
Current:
HYDRAULIC INFORMATION
FEMA Study:
Whitman & Howard Information
USGS Report:
Tidal Influence: Other Hydrologic & Hydraulic Data:FEMA FIS provides flow and water surface elvation data. USGS Gage on Beaver Brook is too far away to provide flow info for bridge but was included to document flooding in the watershed. Merrimack River Watershed (Nashua River to Shawsheen River).
100-Yr Water Velocity (feet per sec): 8.9
Angle Of Attack 5
Watershed Area (sq. mi): 74.5
(Flood Flow)
BRIDGE INFORMATIONBridge Length (in feet): 46.00 Plans Available: Borings Available:
Abutment Foundation: Unknown Pier Foundation: Unknown
2005 2006 2007
Flood / Scour HistoryComments:
The bridge was originally constructed in 1900 and reconstructed (widened with concrete deck on steel beams and substructure extensions) in 1929. The FEMA FIS does not provide specific flood history for the Town of Pelham or Beaver Brook, however photos from the NHDOT inspection reports indicate that the bridge experienced flooding in May of 2006 and April 2007. USGS Gage 10965852 located 6.5 miles upstream recorded a 100 year event in 2006 and a 10-50 year event in 2007. Also NHDOT WWII Card (1942) indicates the flood of record was in 1936.
Flood History:
:
Bridge Width (in feet): 36.00
Substructure Channel Stability Hydraulic Adequacy Scour Risk
Posting 12.7 , E2
Bridge Plan File Loc: J-49
(scale of 1-9)(worst - best)
100-Yr Overtopping Relief: Right Approach
3/14/1980
Bridge Scour ReportNov 1992 :( )
RESULTS OF POST FLOOD INSPECTION
:(Actual Metric Tons, Signed)
Date of Interim Bridge Reopening:Date of Bridge Closure:
Date of Post Flood Inspection: Post Flood Inspection Completed By:
NA NA
Foundation Details:
KNOWN
UNKNOWN Worst Abutment: Right
Worst Pier: 1(Looking Downstream L to R)
Embedment (feet): unknown Exposure: No Exposure
Embedment (feet): unknown Exposure: No Exposure
Diving Insp Reports: 6/6/2008
Superstructure Type: Arch-Deck
Superstructure Material: Masonry
Scour Critical Feature: Pier
Placard Location: Placard not necessary.
Red List: Yes
Number of Spans: 2
USGS Gage Station: 10965852 USGS Station Prox To Bridge: 6.5 miles upstream
Dates:
What To Look For: Changes in streambed elevation of more than 0.1 ft or evidence of footing exposure.
NOAA Gage Station: NOAA Station Prox To Bridge:
Text9:5/17/2010 Text9:Attachment I: Post Flood Inspection Report: Pelham 110/090 Text9: Page 1 of 1
CHA File No: 18925.2003.1510
11 King Court Keene, NH 03431-4648 Main: (603)-357-2445 New Hampshire Scour Investigation
Pelham 110/090 Attachment J: Scour/H&H Backup
Calculations
Attachment J: Scour/H&H Backup Calculations
COMPLETED BY KKD DATE
CHECKED BY SVE PROJ. NO.
PROJ. NAME & LOCATION Pelham 110-090 SUBJECT Scour Calcs
Pier Scour Input
V1 (fps) 8.9 Average Velocity at Pier Continuity EquationY1 (ft) 11 Average Depth at Pier (134 - 123) 50-yr WSE Estimate (FEMA) / Field Measurements
θ (deg) 5 Angle of Attack Field Estimatea (ft) 3.1 Pier Width Field MeasurementL (ft) 37 Pier Length (Bottom) Field Measurement
Underlying Streambed
D95 (ft) 0.016 Sand-gravel bed Field EstimateD50 (ft) 0.008 Sand-gravel bed Field Estimate
Armoring Layer
D95 (ft) N/AD50 (ft) N/A
2/18/2010
18457
VARIABLE CALC / NOTES SOURCE
3/23/2010 Page 1 of 2 Appendix J
K4: ARMORING COEFFICIENT
PIER SCOUR COMPUTATIONSReference for methodology: HEC-18 Fourth Edition
Pelham 110-090 Incipient Overtopping (50-year) EventK4: PIER COMPONENT
Pier #1D95 (ft) = 0.0160 <---Field Estimate
D50 (ft) = 0.0080 <---Field Estimate
PIER SCOUR ANALYSIS V1: APPROACH VELOCITY (ft/s) = 8.90y: DEPTH (ft) = 11.00
Reference for methodology: HEC-18 Fourth Edition Chapter 6 a: PIER WIDTH (ft) = 3.10Ku = 11.17
PIER* Yes Vc95: CRITICAL VELOCITY FOR D95 (ft/s) = 4.20
Pier Number Pier #1 Vc50: CRITICAL VELOCITY FOR D50 (ft/s) = 3.33
V1: VELOCITY (fps) 8.9 ViC95: INITIAL SCOUR VELOCITY FOR D95 (ft/s) = 2.05Y1: DEPTH (ft) 11 ViC50: INITIAL SCOUR VELOCITY FOR D50 (ft/s) = 1.57
ATTACK ANGLE, Degrees 5 VR: VELOCITY RATIO (ft/s) = 5.71INDIVIDUAL PIER WIDTH (ft) 3.10 K4 = 1.00a: PIER WIDTH (ft) 3.10 Note: If D50 < 2mm (.007 ft) or D95 < 20mm (0.07 ft), then K4=1L: PIER LENGTH (ft) 37.00PIER SHAPE (S=SQUARE, C = CIRCULAR, SN = SHARP NOSE) SK1: SHAPE COEFFICIENT 1.10K2: ANGLE COEFFICIENT 1.59K3: BED COND. COEFFICIENT 1.10K4: BED AMORING COEFFICIENT 1.00
g: gravitational constant (ft/s2) 32.20FROUDE NUMBER, Fr 0.47LOCAL SCOUR DEPTH (ft), Yspier 13.4
Calc. By: KKD Date: 2/18/2010Check By: SVE Date: 2/20/2010
Notes: There is no foundation information for this bridge and the field visit did not indicate evidence of an exposed footing. As a result, for the purposes of this analysis CHA used the
general pier scour equation.
Sand-gravel bed
3/23/2010 Page 2 of 2 Attachment J