private sector expectations in the ppp project structure

14
Private Sector Expectations In the PPP project structure

Upload: marissa-wiley

Post on 27-Mar-2015

214 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Private Sector Expectations In the PPP project structure

Private Sector Expectations

In the PPP project structure

Page 2: Private Sector Expectations In the PPP project structure

To make project attractive to the private sector (1)

PPP project must be in line with strategic public sector goals

Unquestionable necessity of the project Political approval by cross-parties Analysis of alternative schemes and PPP

scenarios shows better value for money than traditional methods

Qualified approach to potential partners

Page 3: Private Sector Expectations In the PPP project structure

To make project attractive to the private sector (2)

Good information to all parties (public and private) that may be concerned

Equal conditions of access to project information to all prospective bidders

Strong Institutions with appropriate resources

Mitigation and flexibility in managing macro-risks

Page 4: Private Sector Expectations In the PPP project structure

Problems with the PPP process

Lack of legislation and laws governing PPP process and protecting both partners

Lack of knowledge and approval of the process by the civil service

Inappropriate project selection Poorly prepared project Private partner’s interests and risk

mitigation are not taken under consideration

Lack of effective public marketing of the PPP projects

Absence of alternative analysis Inappropriate risk sharing

Page 5: Private Sector Expectations In the PPP project structure

Private partner’s expectation

Fair return Compensation for assumed risk Risk mitigation mechanism Clear legal and regulatory structure Ongoing dialogue and involvement of

the public sector Political stability Political support

Page 6: Private Sector Expectations In the PPP project structure

Lender’s expectations

Thorough financial analysis Conservative cost and revenues

assumptions Guarantee of state funding and/or

support Clear legal regulatory structure Technical ability of the private

partner Political stability

Page 7: Private Sector Expectations In the PPP project structure

Risks implication in PPP projects

Page 8: Private Sector Expectations In the PPP project structure

Unavoidable Risks

Ideological differences between Public and Private partners• Public sector focused on

public goods• Private sector focused on

profitability Project specific risks Lack of flexibility

Page 9: Private Sector Expectations In the PPP project structure

Avoidable Risks

Unfair competition during the bidding process

Unclear partner selection procedure Inadequate Risks and Liabilities transfer Sustainability of profits Loss of control by the public sector Public resistance Develop simple and common

communication “language” between partners

Page 10: Private Sector Expectations In the PPP project structure

Selected mechanisms of Risk Mitigation

Page 11: Private Sector Expectations In the PPP project structure

Revenue guarantee

Failure to achieve the minimum revenue level triggers compensation from the public sector. Often the lower limit is set with an upper limit to mitigate risk for the public sector (i.e.; the private sector does not get to have downside protection along with unlimited upside potential)

Page 12: Private Sector Expectations In the PPP project structure

Modification of the contract’s economic balance

The goal is to re-establish economic balance of the concession when IRR is below a minimum IRR stipulated in the contract. Compensation can include changes in toll or charge levels, adjusting contract’s lengths, public subsidies.

Page 13: Private Sector Expectations In the PPP project structure

Contract duration

This matches contract duration to the pre-defined revenue target. If full revenue is realized earlier than planned, the concession will end earlier. When revenue is lower than planned – the concession will end later. This evens out the risk profile of the project. Both the concessionaire and public bear the risk of higher or lower than projected revenues. This also reduces the risk of hard-to-forecast revenue streams in certain sectors.

Page 14: Private Sector Expectations In the PPP project structure

Thank you

Wojtek KsiazkiewiczSEE Business Advisory Council (BAC)

Email: [email protected]