process improvement in a physiotherapy outpatient setting · design. the terminology used to...

199
Process Improvement in a Physiotherapy Outpatient Setting Marie Byrne 2013 A Dissertation submitted to the University of Dublin, in partial fulfilment of the requirements for the Degree of Masters in Science in Health Informatics

Upload: others

Post on 12-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

Process Improvement in a Physiotherapy Outpatient

Setting

Marie Byrne

2013

A Dissertation submitted to the University of Dublin, in partial

fulfilment of the requirements for the Degree of Masters in Science in

Health Informatics

Page 2: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

i

Declaration

I declare that the work described in this dissertation is, except where

otherwise stated, entirely my own work, and has not been submitted as an

exercise for a degree at this or any other university.

Signed: _____________________

Marie Byrne

Date: _______________________

Page 3: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

ii

Permission to lend and/or copy

I agree that the School of Computer Science and

Statistics, Trinity College may lend or copy this

dissertation upon request.

Signed: ___________________

Marie Byrne

9th August 2013

Page 4: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

iii

Acknowledgements

I would like to take this opportunity to say thank you to all those who

encouraged and helped me in a variety of ways to complete this research.

I would first like to thank all participants. A special thank you goes to all of

the physiotherapy and the information technology staff for facilitating and

supporting me.

I am also very grateful to my supervisor Lucy Hederman for all her queries

and suggestions and to all the lecturers who guided me throughout the two

years of the course.

I would like to give my special thanks to the two most important men in my

life; my husband Stuart and son Jack who with their love, sense of fun and

unending patience enabled completion of this dissertation and kept me

focused on the important things in life.

A huge thank you to my sister Briege for the extremely valuable feedback

along the way both on my dissertation and on keeping focused on life’s

priorities. Finally, to my parents; Mary and Frank and all other family

members and friends for their encouragement.

Page 5: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

iv

Summary

The requirement to do more with less in the current healthcare environment

has led healthcare professionals to look at the potential opportunities

provided by process improvement methodologies. In the main, these

methodologies have their origins in the manufacturing industry and provide

an alternative way to look at healthcare, away from profession or disease

specific initiatives and toward the processes of the patient journey. Rather

than doing more with less process improvement can lead to the elimination

of unnecessary processes and measurable improvements in quality.

The question this research wished to answer was how processes could be

improved in a physiotherapy outpatients setting. The first phase of

answering this question involved carrying out a literature review to

determine current prevalent process improvement methodologies in use in

healthcare and how processes have been improved at other sites through

the application of such methodologies. The literature also outlined some

potential benefits and perceived challenges. From the literature the

researcher determined that a process improvement methodology based on

the principles of Lean Thinking was appropriate for use in the case under

study. In conjunction with the literature review baseline data was collected

by the researcher. Next the process improvement methodology was applied

in the physiotherapy outpatient department. This was done in three stages:

process mapping through observation, interviews with key physiotherapy

informants and a staff focus group. These three stages pinpointed which

parts of the process should be improved and how, the potential benefits

these improvements could have on the quality of the patient journey and

some possible challenges.

While the scope of this research was not to implement the suggested

process improvements some of the suggested improvements have been

Page 6: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

v

progressed and others are planned. Those progressed have had a significant

impact on the baseline data whereby no patient waited for an orthopaedic

or rheumatology appointment for the three months following clarification of

the booking policy (I1)1 (figures 5.2 to 5.4). A possible future process map

and key repositories are also presented based on the improvements

suggested (figure 5.7 and 5.8). As can be seen, figure 5.8 shows the

potential for a dramatic reduction in the reliance on paper. This has already

begun with the elimination of the printing of 5,500 front sheets each year

(section 5.4.1).

The literature emphasises the need to begin by reviewing processes, and to

use data to determine the focus of improvement, and to highlight if any

change is indeed an improvement. The literature also recommends that

processes are improved in so far as possible before the introduction of

health information technology (IT) to avoid automation of outdated

processes. At the same time, the role of IT in simplifying and standardising

processes and ultimately in sustaining improvement is also acknowledged.

This research demonstrated that the staff who participated clearly

acknowledged the role IT has in this regard. Highlighting the benefits

realised elsewhere and the baseline data had a noticeable impact on staff

engagement. Challenges outlined in the literature and through the

interviews are important to be aware of to allow for change management

strategies to be put in place.

The literature also highlights, that while there are case studies outlining

various methodologies, the tools and methodologies used are sometimes

not clearly stated and some authors have called for more rigorous study

design. The terminology used to describe Lean Thinking interventions also

varies as some organisations have adapted Lean Thinking principles to their

local context.

1 I1,2,3 etc. refer to the suggested improvements/point in the workflow outlined in Chapter 5.

Page 7: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

vi

In conclusion, the use of process improvement and information technology

in physiotherapy has not been cited extensively. However, numerous case

studies are available elsewhere in healthcare. This research demonstrates

that a process improvement methodology based on Lean Thinking principles

can be applied in a physiotherapy outpatient setting to determine how

processes could be improved. Data collection and staff engagement at all

stages have been and will continue to be crucial.

Page 8: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

vii

Table of Contents

Declaration .......................................................................................... i

Permission to lend and/or copy ............................................................. ii

Acknowledgements .............................................................................. iii

Summary .......................................................................................... iv

Table of Contents ............................................................................... vii

List of Tables ..................................................................................... xii

List of Figures ................................................................................... xiii

Abbreviations ....................................................................................xv

Glossary of Terms ............................................................................. xvi

CHAPTER 1 ......................................................................................... 1

INTRODUCTION .................................................................................. 1

1.1 Study Context ............................................................................ 1

1.1.1 National Context ................................................................... 5

1.1.1.1 HSE CompStat................................................................. 6

1.1.1.2 HSE National Clinical Programmes (NCP) ............................ 6

1.1.1.3 Health Information and Quality Authority Standards ............. 7

1.2 Research Questions ..................................................................... 7

1.3 Motivation for the Research .......................................................... 8

1.4 Overview of the Research ............................................................ 8

1.5 Overview of the Dissertation ........................................................ 9

CHAPTER 2 ....................................................................................... 10

LITERATURE REVIEW ......................................................................... 10

2.1 Introduction ............................................................................. 10

2.1.1 Literature Search Strategy ................................................... 12

Page 9: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

viii

2.2 Process Improvement in Healthcare ............................................ 13

2.2.1 What is Process Improvement in Healthcare? .......................... 14

2.2.2 Levers for Process Improvement in Healthcare ........................ 16

2.3 Methodologies in Process Improvement in Healthcare .................... 17

2.3.1 Lean Thinking ..................................................................... 18

2.3.2 Six Sigma ........................................................................... 21

2.3.3 Plan-Do-Study-Act (PDSA) ................................................... 22

2.4 Measurement in Process Improvement in Healthcare ..................... 23

2.5 Tools used to Understand and Improve Processes ......................... 24

2.5.1 Process Mapping ................................................................. 25

2.5.2 Focus Groups and Interviews ................................................ 28

2.5.3 Fishbone Diagrams .............................................................. 29

2.5.4 Data Check Sheets .............................................................. 30

2.5.5 Statistical Control Chart ....................................................... 30

2.5.6 Summary ........................................................................... 31

2.6 Case Studies ............................................................................ 32

2.7 Process Improvement based on the introduction of Information

Technology .................................................................................... 36

2.8 Process Improvement and the introduction of Information Technology

for Physiotherapists ........................................................................ 38

2.9 Challenges to Process Improvement ............................................ 42

2.10 Change Management ............................................................... 45

2.11 Conclusion ............................................................................. 46

CHAPTER 3 ....................................................................................... 48

RESEARCH METHODOLOGY ................................................................ 48

3.1 Introduction ............................................................................. 48

Page 10: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

ix

3.2 Background .............................................................................. 49

3.3 Study design ............................................................................ 49

3.4 Methodology ............................................................................ 50

3.4.1 Stage 1: Process mapping .................................................... 51

3.4.2 Stage 2: Semi-structured interviews ...................................... 54

3.4.3 Stage 3: Focus group ........................................................... 55

3.5 Participants and recruitment methods ......................................... 58

3.6 Ethics application ...................................................................... 58

3.7 Conclusion ............................................................................... 58

CHAPTER 4 ....................................................................................... 60

RESULTS .......................................................................................... 60

4.1 Introduction ............................................................................. 60

4.2 Baseline data ........................................................................... 60

4.2.1 Throughput ........................................................................ 61

4.2.2 Retrieval and filing of physiotherapy notes ............................. 62

4.2.3 Phone calls ......................................................................... 62

4.2.4 Costs of paper and storage ................................................... 63

4.3 Process Maps ........................................................................... 63

4.4 Semi-structured interviews ........................................................ 92

4.4.1 Suggested Improvements arising from interviews ................... 93

4.4.2 Potential Benefits as identified by interviews ........................... 96

4.4.3 Perceived Challenges as identified by interviews ...................... 97

4.5 Focus Group ............................................................................. 98

4.6 Conclusion ..............................................................................102

Page 11: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

x

CHAPTER 5 ......................................................................................104

ANALYSIS AND DISCUSSION .............................................................104

5.1 Introduction ............................................................................104

5.2 Research questions ..................................................................104

5.3 Findings ..................................................................................104

5.3.1 What process improvement methodology is appropriate to apply

in the physiotherapy outpatient setting? (SQ1) ..............................105

5.3.2 Which processes should be improved? (SQ2) .........................106

5.3.3 How can processes be improved in a physiotherapy outpatients

setting? (SQ3)............................................................................109

5.3.4 What are the potential benefits of any suggested improvements?

(SQ4) ........................................................................................112

5.3.5 What are the perceived challenges of any suggested

improvements? (SQ5) .................................................................113

5.3.6 Conclusion to Research Questions ........................................113

5.4 Progress and Plans for Suggested Improvements .........................114

5.4.1 Progress made to date ........................................................114

5.4.2 Plans for the future .............................................................118

5.4.3 Suggested improvements that cannot be progressed or have not

been progressed to date ..............................................................123

5.4.4 Proposals to address challenges ...........................................125

5.5 Conclusion ..............................................................................125

CHAPTER 6 ......................................................................................126

CONCLUSION ..................................................................................126

6.1 Introduction ............................................................................126

6.2 Recommendations for Future Research .......................................126

Page 12: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

xi

6.3 Study limitations ......................................................................127

6.4 Conclusion ..............................................................................128

References ......................................................................................130

Bibliography ....................................................................................151

Appendices ......................................................................................153

Appendix A: Overview of physiotherapy ........................................154

Appendix B: Protocol for semi-structured interviews with experts .....158

Appendix C: Consent Form ..........................................................159

Appendix D: Participant Information Sheets ...................................162

Appendix E: Ethics ......................................................................169

Appendix F: Key to notations on process maps ...............................172

Appendix G: Stakeholder Analysis.................................................179

Appendix H: Draft Benefits Realisation Plan ...................................180

Page 13: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

xii

List of Tables

Table 4.1 Throughput (average per month in 2012)............................... 61

Table 4.2 Physiotherapy notes retrieval and filing (average per month) ... 62

Table 4.3 Phone calls (average per month in 2012) ............................... 62

Table 4.4 Documents created ............................................................. 88

Table 4.5 Data created ...................................................................... 90

Table 4.6 Information Accessed .......................................................... 91

Table 4.7 Top Ten Suggested improvements identified at the focus group

100

Table 5.1 Which processes should be improved? ..................................106

Table 5.2 Suggested Improvements not yet progressed ........................123

Page 14: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

xiii

List of Figures

Figure 1.1 Body chart anterior and posterior view ................................... 3

Figure 2.1 Six aims for improvement outlined by the IOM ...................... 11

Figure 2.2 Principles of Lean Thinking .................................................. 19

Figure 2.3 PDSA cycle ........................................................................ 22

Figure 2.4 High-level flowchart for ischaemic heart disease patient ......... 26

Figure 2.5 Fishbone diagram .............................................................. 29

Figure 2.6 Check Sheet ...................................................................... 30

Figure 2.7 Control chart ..................................................................... 31

Figure 4.1 High level process map ....................................................... 66

Figure 4.2 Key Data Repositories ........................................................ 68

Figure 4.3 Data storage and access ..................................................... 69

Figure 4.4 Referral Management and Triage ......................................... 70

Figure 4.5 Waiting list Management and Appointment Booking ................ 72

Figure 4.6 Waiting List Reporting and Queries ....................................... 75

Figure 4.7 Patient Attendance ............................................................. 77

Figure 4.8 Registration ...................................................................... 80

Figure 4.9 Patient Non-Attendance ...................................................... 81

Figure 4.10 Discharge ........................................................................ 83

Figure 4.11 Retrieval and Filing of Physiotherapy Notes ......................... 85

Figure 4.12 Clinical Documentation and Information Access .................... 87

Figure 5.1 Venn diagram of suggested improvements from interviews and

focus group .....................................................................................111

Figure 5.2 Number of patients waiting for a rheumatology physiotherapy

appointment Jan 2012 – July 2013 .....................................................115

Page 15: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

xiv

Figure 5.3 Number of patients waiting for an orthopaedic physiotherapy

appointment Jan 2012 – July 2013 .....................................................115

Figure 5.4 Number of weeks patients waited for a rheumatology

physiotherapy appointment Jan 2012 – July 2013 ................................116

Figure 5.5 Number of weeks patients waited for an orthopaedic

physiotherapy appointment Jan 2012 to July 2013 ..............................116

Figure 5.6 Body Chart in Cerner Millenium EPR ....................................118

Figure 5.7 Possible Future Process Map ...............................................121

Figure 5.8 Possible Future Key Repositories .........................................122

Page 16: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

xv

Abbreviations

AHP Allied Health Professional

AHRQ Agency for Healthcare Research and Quality

ARCHI Australian Resource Centre for Healthcare Innovations

ASQ American Society for Quality

DoH&C Department of Health & Children

DNA Did Not Attend

ED Emergency Department

EHR Electronic Health Record

EMR Electronic Medical Record

EPR Electronic Patient Record

HIMSS Healthcare Information and Management Systems Society

HIQA Health Information and Quality Authority

HSE Health Service Executive

IHI Institute for Healthcare Improvement

MeSH Medical Subject Headings

NCP National Clinical Programmes

PAS Patient Administration System

SOAP Subjective, Objective, Analysis, Plan

TQM Total Quality Management

VAS Visual Analogue Scale

VMMC Virginia Mason Medical Centre

Page 17: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

xvi

Glossary of Terms

Bottleneck

Part of the system where patient flow is obstructed, causing waits

and delays e.g. waiting for an appointment

Capacity

Resources available to do the work

Demand

All the referrals/requests coming in from all sources

Flow

The progressive, uninterrupted movement of products, information

and people through a sequence of processes

Functional bottleneck

Service that has to cope with demand from several sources e.g.

physiotherapy, radiology, pathology

Hand-offs

The number of times work is passed from one person to another

person

Kaizen Event

An improvement tool that brings together employees to examine a

problem, propose solutions, and implement changes. Kaizen events

usually take place over several days

Map of Medicine

The Map of Medicine supports the optimisation of care by providing

access to a web-based visual representation of evidence-based

patient care journeys covering 28 medical specialties and 390

pathways and clinical decision support at the point of care

Page 18: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

xvii

New slot

An appointment slot in the outpatient booking module on the PAS

which is specifically for a new patient appointment

PhysioTools

Software used to produce personalised exercise hand-outs

Return slot

An appointment slot in the outpatient booking module on the PAS

which is specifically for a return patient appointment

Triage

The practice of sorting patients into categories of priority for

treatment

Page 19: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

1

CHAPTER 1

INTRODUCTION

1.1 Study Context

This dissertation describes research carried out in the physiotherapy

outpatients department of a large acute teaching hospital. The research

investigated how processes could be improved in the study setting. The

research also explored the potential benefits and perceived challenges of

any suggested improvements.

The overall aim of any process improvement in the department under study

was improvement to the patient’s journey and staff morale. The focus for

this study was the orthopaedic and rheumatology patients referred to the

department. Focussing on this cohort of patients would give a

comprehensive outline of the patient journey through the department as

they go through the complete range of processes. The physiotherapists who

treat this cohort are also based solely in the main outpatients department.

Patients from other specialties such as oncology, cardiology, neurology,

women’s health and plastics are also managed as outpatients but are

treated by physiotherapists who are also based on the acute wards. Some

of these specialities would not follow the full extent of the processes e.g.

oncology patients would not go through the triaging process as they do not

go on to a waiting list as they are booked directly into an outpatient

appointment on discharge from their inpatient stay.

The department under study sees over 2,000 new orthopaedic and

rheumatology patients per annum. There are 5.5 physiotherapists and 2

clerical staff serving these patients. Of note, the clerical staff complement

has reduced from 3 in 2010 due to the Irish Health Service Executive (HSE)

early redundancy scheme at the end of 2010.

In theory, there appears to be sufficient physiotherapy capacity to prevent a

waiting list but there continues to be several weeks of waiting for patients.

Page 20: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

2

The view of the clerical staff is that they are unable to book patients into

appointments in a timely manner due to lack of time. The clerical staff do

spend a significant amount of their working day making and receiving calls

from patients while many calls to the department are unanswered – see

baseline data in section 4.2.

The current workflow through the department is heavily dependent on

paper and a few separate information systems. The workflow can be broadly

divided into the following sections; referral management, waiting list

management, clinical documentation and discharge and/or onward referral.

All referrals, assessments, outcome measures and treatment plans are

paper based. The patient is reassessed each time they are referred as

accessing physiotherapy notes for previous attendances is difficult due to

reduced clerical capacity to retrieve them. There are manual processes for

referral and waiting list management. Referrals outward to the community

and other hospitals are paper-based via the general postal service. This

results in delays in referral onwards to community physiotherapy. An

internal audit carried out in 2010 showed an average delay from referral to

date stamp in the community of 6 days but in some cases up to 8.5 days.

This is before the patient goes on the community physiotherapy waiting list.

Due to all clinical documentation including outcome measures and protocols

being paper based there is a lack of easily accessible information. This

makes it difficult and time consuming to determine if (1) physiotherapists

are using outcome measures consistently, (2) if patient outcomes are

sufficient, (3) to carry out research and audit and so determine where

improvements are required clinically.

There are three main information systems in use; (1) the Cerner EPR

(Electronic Patient Record) which is used only for referrals to the outpatient

physiotherapy service and to look up test results and imaging, (2) the PAS

(Patient Administration System) for all patient appointment bookings and

registration of patient attendance and (3) PhysioTools which is a software

Page 21: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

3

application used to generate paper based exercise programmes for patients

to carry out at home. Microsoft Excel is used for referral and waiting list

management. There is also some information saved in electronic format,

patient correspondence (to consultants), protocols, outcome measures and

relevant articles and presentations.

The following section gives an overview of key steps where information is

collected and accessed during a patient attendance in the outpatient

physiotherapy department under study. For further background on the

physiotherapy outpatient setting see Appendix A.

In the outpatient physiotherapy setting (following consent from the patient

for treatment) the patient receives an initial assessment from an individual

physiotherapist. All information from this initial assessment is recorded on a

standardised assessment for, which includes a body chart. Clinical

information for follow-up appointments is recorded in the form of a SOAP

note (Subjective, Objective, Assessment and Plan). The standardised

assessments and SOAP notes are paper-based.

Figure 1.1 Body chart anterior and posterior view

(Reproduced from Whitman, J., Flynn, T., Wainner R and Magle J., 2002. Orthopaedic Manual

Physical Therapy Management of the Lumbar Spine, Pelvis, and Hip Region. Fort Collins, CO:

Manipulations, Inc.)

At the initial visit the presenting complaint is recorded on a body chart.

Figure 1.1 above is a standard view of a body chart. Physiotherapists use

Page 22: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

4

symbols to describe the location of symptoms, nature of any pain (sharp,

ache), the frequency of the pain (intermittent, constant) and whether the

pain radiates. The notations used are not currently standardised among the

physiotherapists in the department under study.

Assessment of red flags is a key part of the physiotherapist’s examination to

alert the physiotherapist to the possibility of a more serious underlying

condition. While most patients will have musculoskeletal conditions as an

explanation of their symptoms, a small number will have a more serious

condition such as malignancy. These patients need to be identified and

referred urgently to a medical specialist. Going through the list of red flags

systematically greatly reduces risk. An example of a red flag in a patient

with low back pain would be a change in bladder habit e.g. incontinence.

The physiotherapists should use an outcome measure at the initial

assessment and intermittently thereafter to determine patient progress.

Many of these outcome measures are self-reported questionnaires.

However, due to time constraints and difficulties with analysing the

resulting data they are not used consistently.

Advice and education are a very important part of the physiotherapist’s role,

and the patient will be given further educational material such as an

exercise sheet or information on their condition. These exercise sheets are

pre-printed or generated from PhysioTools. When treatment is complete the

patient is discharged back to the referring consultant and previously a

discharge summary was written to the consultant outlining the treatment

undertaken and the progress to date. This discharge summary was not in a

standardised format. Due to a shortage of clerical staff discharge letters are

no longer written.

Physiotherapists refer to the evidence base for the most relevant outcome

measures, clinical pathways and the latest evidence. This occurs outside

patient treatment times due to time constraints and issues with access to

Page 23: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

5

this information. This information is accessed on the department’s shared

drive or via the internet.

Management reports are available from the information inputted on the PAS

and are downloaded monthly e.g. DNAs (Did Not Attends), cancellations and

number of new and return patients. However, other metrics such as waiting

time (required by the Health Service Executive (HSE)) continue to be

determined through inefficient manual processes. Manual collation of

numbers waiting and waiting times is necessary as the referral comes

through the EPR (date stamped on EPR) and the booking occurs separately

in the PAS and there is currently no link between date of referral and date

of appointment to allow for calculation of waiting time.

In summary, there are a number of issues:

Reduction in clerical capacity

Dependency on paper

Disparate IT systems

Some of the reports required locally and nationally generated

manually

Delays in patient referrals reaching the community services

Lack of standardisation in use of notations on the body chart

Lack of easy access to information to review previous attendances,

analyse outcomes and carry out research and audit

Discharge letters not sent to the referrer to complete patient journey

1.1.1 National Context

At a national level there are some key initiatives that are driving the need

to improve the processes of the patient journey and how data is collected

and reported along that journey. Three of these are outlined below; (1) the

requirement for physiotherapy departments to submit data to the HSE each

month, (2) the work of the National Clinical Programmes (NCP) and (3) the

Page 24: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

6

Health Information and Quality Authority (HIQA) publication the “National

standards for Safer, Better, Healthcare”. It remains to be seen if the work

around “money follows the patient” (Department of Health & Children

(DoH&C), 2013) will include the money following the input provided by

physiotherapists but the drive from the HSE is certainly to keep waiting lists

low and the work of the NCP and HIQA is focussed on improving the quality

of the patient journey.

1.1.1.1 HSE CompStat

Each month physiotherapy departments nationally, submit a report of

clinical activity (including the number of patients seen, waiting times and

numbers waiting) to CompStat (formerly HealthStat2). This is the public

health services performance dashboard and is published online by the HSE.

HealthStat was devised to provide ‘reliable, timely and comprehensive

information about how our services are delivered to those who use them’

(HSE, 2011). CompStat compares the monthly performance of twenty nine

public hospitals. Actual performance is then compared with a target of the

average of the top three best performing hospitals. The aim is to have no

patient waiting for outpatient physiotherapy for more than 6 weeks. It is

therefore, imperative that the data submitted is collected accurately.

1.1.1.2 HSE National Clinical Programmes (NCP)

The objectives of the NCPs are to improve quality, improve patient care and

access and ensure value for money. The new clinical director of the NCP has

outlined that patient flow should be embedded in all NCPs and that all

programmes have a dependency on data to understand demand/capacity

issues and to measure patient outcomes. All NCP programmes are

developing clinical decision making support tools such as guidelines,

algorithms, referral templates, data sets, bundles and models of care (HSE

NCP). Physiotherapists are involved in all programmes either as therapy

2http://www.hse.ie/eng/staff/Healthstat/about/

Page 25: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

7

leads or support to the therapy lead and the work of all programmes

impacts the care provided by physiotherapists.

1.1.1.3 Health Information and Quality Authority Standards3

The Health Information and Quality Authority (HIQA) published the ‘National

Standards for Safer Better Healthcare’ in June 2012. The standards focus on

patient-centred, effective, safe and reliable services and outline how

accurate and timely information is key to driving improvements in patient

care. The department under study will be accredited according to these

standards.

1.2 Research Questions

This research will attempt to answer the following questions:

Main Question (MQ):

How can processes be improved in a physiotherapy outpatient

setting?

Sub questions (SQs):

What process improvement methodology is appropriate to apply in

the physiotherapy outpatient setting? (SQ1)

Which processes should be improved? (SQ2)

How should processes be improved? (SQ3)

What are the potential benefits of any suggested improvements?

(SQ4)

What are the perceived challenges of any suggested improvements?

(SQ5)

3http://www.hiqa.ie/standards/health/safer-better-healthcare

Page 26: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

8

1.3 Motivation for the Research

The main motivation for this research is to add to the limited body of

research in this area. Despite the vast and ever expanding body of literature

on process improvement and electronic records, physiotherapy specific

literature makes up a very small percentage. Use of a specific process

improvement methodology will allow for the structured identification of

possible improvements, where paper could be reduced, inefficiencies could

be eliminated and information technology could add value.

Some of the issues with the current processes that the researcher was

aware of before commencing the research are summarised at the end of

section 1.1, all are motivators for the research.

Local motivation factors include the announcement that the proposed new

children’s hospital will be based on the site. This is significant as it will

involve the knocking down of the physiotherapy building within 12 months.

It would be advantageous to move to a new location with inefficiencies

ironed out and new ways of working standardised in so far as possible.

In addition, one of the eight areas of focus of the organisation’s corporate

strategy is paperless systems and to move to a higher level on the HIMSS

(Healthcare Information and Management Systems Society) European EHR

Adoption Model4.

1.4 Overview of the Research

A literature review was carried out to gain a clear understanding of process

improvement methodologies prevalent in healthcare and the tools

commonly used. Process improvement based on the principles of Lean

Thinking was selected by the researcher as the best fit for the case under

study. This methodology was then applied in three stages of process

mapping through observation, semi-structured interviews with key

physiotherapy informants and a staff focus group. This methodology

4 http://www.himssanalytics.eu/emr.asp

Page 27: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

9

assisted in identifying how processes could be improved in the department.

The use of data and staff engagement were noted as key building blocks.

1.5 Overview of the Dissertation

This chapter presented the background to the research, the research

questions, motivation for the research and an outline of the dissertation.

Chapter 2 presents the literature review. The literature review addresses

the area of process improvement, methods and tools used in healthcare,

case studies in healthcare, process improvement and information

technology, process improvement and information technology in

physiotherapy.

Chapter 3 presents the research methodology. The literature review and

collection of baseline data was followed by the application of the process

improvement methodology; process mapping, interviews with key

informants and the focus group.

Chapter 4 presents the quantitative data from the process mapping stage

(stage 1) outlining how the data was collected and the time spent in

observation. The process maps are presented in this chapter. This chapter

also presents the qualitative data from the interviews, and focus group

(stages 2 and 3).

Chapter 5 presents an analysis of the data in chapter 4 and a discussion of

the findings and how the research questions have been answered.

Chapter 6 presents the study limitations, recommendations for future work

and the conclusion.

Page 28: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

10

CHAPTER 2

LITERATURE REVIEW

2.1 Introduction

This chapter gives an overview of process improvement in healthcare.

Prevalent improvement methodologies are outlined along with an

introduction to the importance of measurement and some tools used. The

importance of data to highlight priorities for improvement and to determine

if any change results in improvement is illustrated.

Some case studies and benefits realised are outlined followed by a summary

of information technology (IT) used to drive improvement in the

physiotherapy setting. Some challenges to improvement are then

highlighted and the importance of staff engagement and change

management to assist in overcoming these challenges is emphasised.

Of relevance to this research is the emphasis in the literature on the

importance of reviewing processes, involving staff and using data to

determine the focus of improvement and to highlight if any change is indeed

an improvement. The case studies also give ideas for improvement and the

benefits realised. Regarding the introduction of IT for process improvement

the literature acknowledges the role of IT in the simplification,

standardisation and ultimately in sustainability of improvement (Hughes,

2008; Bell, 2013).

Information technology in healthcare is viewed by many as a way to reduce

costs, improve quality and safety and optimize operational efficiencies

(Institute of Medicine (IOM), 1999). However, others call for these claims to

be further substantiated (Himmelstein, Wright and Woodlander, 2009;

Black, et al., 2011).

It is acknowledged that many of the processes in healthcare can be

inefficient and complicated. Therefore, the introduction of IT without first

improving processes could result in doing the same inefficient, complicated

Page 29: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

11

activities electronically. The allocation of current limited resources to IT

without first tackling inefficient healthcare processes will be unlikely to

generate benefits. Therefore, the need to simplify and eliminate wasteful

activities in hospital processes should be a prerequisite to implementing any

IT system. In fact, Trinity Health, a large U.S. multi-hospital healthcare

organisation, attributes much of its successful implementation of an

organisation-wide Electronic Health Record (EHR) to carrying out process

improvement initiatives prior to implementation (Brokel and Harrison,

2009).

Before looking at “process” we need to look at “quality” in health care.

Quality is a complex concept. The IOM identified six specific aims for

improvement in its report “Crossing the Quality Chasm”, 2001 (IOM, 2001;

Berwick, 2002). The six aims are depicted in Figure 2.1.

Figure 2.1 Six aims for improvement outlined by the IOM

(Institute of Medicine, 2001. Crossing the Quality Chasm: A New Health System for the 21st

Century.Washington, DC: National Academies Press)

More than 40 years ago, Donabedian (1966) proposed measuring the

quality of health care by the observation of structure, process, and

outcome. Structure measures assess the accessibility, availability, and

quality of resources; having the right things. Process measures assess the

delivery of health care by all providers; doing the right things right.

Page 30: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

12

Outcome measures indicate the final result of health; having the right

things happen.

Process improvement, particularly in the name of quality, has been around

for a long time. Back in 1950 W. Edwards Deming spoke to Japanese

business leaders, outlining a roadmap for total quality management (TQM).

Deming outlined how most quality issues are caused by process, policy and

procedure issues rather than by people. A more recent advocate of process

improvement, Spear (2011) a senior fellow at the Institute for Healthcare

Improvement (IHI) concurs outlining that inadequately designed and

operated systems of care delivery are the cause of many quality issues.

Batalden (2006) also emphasises that poorly designed systems lend

themselves to inefficiency and poor quality.

“Every system is perfectly designed to get the results that it gets”

Paul Batalden, 2006, p. 32

The IOM report (1999) “To Err Is Human” also outlined how the majority of

errors in healthcare are the result of faulty systems and processes, not

individuals. This report also suggests that IT must play a central role in the

redesign of healthcare if a substantial improvement in quality is to be

achieved.

2.1.1 Literature Search Strategy

An initial requirement in the research process is a review of relevant

literature (Creswell, 2009). Some of the MeSH terms that were used for

this literature review included process improvement AND physiotherapy,

quality improvement AND physiotherapy, Lean Thinking AND physiotherapy,

electronic patient record AND physiotherapy, electronic documentation AND

physiotherapy, information technology AND physiotherapy, computer use

AND physiotherapy, process improvement AND healthcare and Lean

Thinking AND healthcare. For each search using “physiotherapy” a duplicate

search was also conducted using “physical therapy” as both titles are used

interchangeably.

Page 31: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

13

The literature was searched using the electronic database Pubmed initially

followed by, ProQuest Nursing and Allied Health Source database, the BMJ

group database and others that specific journal articles led the researcher

to such as Science Direct, SpringerLink, Wiley Library, JSTOR and Academic

Search Complete.

While there is a sufficient number of articles and grey literature published

on the topics of process improvement in healthcare and Lean Thinking in

healthcare no articles were found that described process improvement

methodologies in physiotherapy. A general search was carried out to seek

out presentations or other source material related to the topic of

physiotherapy and process improvement with limited success. Therefore,

the reader will note there is reference made to health service reports and

blogs in the literature review (section 2.8).

The references of all key articles found in the initial stages were reviewed

for further relevant articles and specific leads pursued (snowballing). Alerts

were set up from the databases outlined above.

The search strategy for the literature review was a challenge. There was

limited literature on the subject of process improvement in

physiotherapy/physical therapy. The quality improvement literature is

extensive. Lean Thinking principles have been adapted to local contexts and

are applied in many settings under various guises, for example, VMPS

(Virginia Mason Production System), BICS (Bolton Improving Care System)

and Redesigning Care Programme in Australia.

This chapter will now introduce process improvement in health care,

prevalent methodologies, measurement and tools, outline some interesting

case studies and finally take a brief look at some challenges to process

improvement.

2.2 Process Improvement in Healthcare

Many countries have national healthcare quality improvement agencies

which are highlighting the importance of using process improvement

Page 32: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

14

methodologies; the Institute of Healthcare Improvement (IHI) in the US,

the NHS Institute for Innovation in the UK, the Dutch Institute for

Healthcare Improvement (CBO) and the Australian Council for Safety and

Quality in Healthcare (Locock, 2003 (a)).

2.2.1 What is Process Improvement in Healthcare?

In healthcare, a process is a set of steps, each of which must be

accomplished properly in the proper sequence at the proper time to create

value for the customer (patient and/or staff). So invariably in order to look

at improving what the organization does, the focus must be on reviewing

and improving the process (Batalden, 2006; Victorian government report on

streaming care, 2008; Holden, 2011). Batalden (2006) outlines that trying

to change things without first understanding how things are working won’t

lead to sustainable change.

The activities that make up a process are not equal. Some activities add

value to a process and other activities fail to add value. Therefore, one way

to think about process improvement is to think in terms of reducing non-

value added activities. To understand the concepts of value-added and non-

value added processes (waste) it is important to look in more detail at

process improvement based on the principles of Lean Thinking. This will be

discussed further in section 2.3.1.

Once it is understood what processes exist in a healthcare environment

options for improvement of processes can be explored. This definition of

improvement

“An improvement is anything that brings about a measurable benefit

against a stated aim”

(NHS Institute for Innovation and Improvement Leaders Guide 1.1, 2005,

p.40)

emphasises the importance of defining aims prior to making any changes

and of using measurement to determine if a change is indeed an

Page 33: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

15

improvement. Measurement to define priorities and determine if a change is

an improvement will be explored further in section 2.4.

An important aspect of improving processes is that it is not about cutting

people. It’s about cutting waste and inefficiency so people can carry out

their work more efficiently (Ben-Tovim, et al., 2008). Process improvement

gives staff clear ways of working and so allows them greater job satisfaction

as they are able to get on with their job without process distractions. It also

aims to ensure patients get faster and more predictable treatment

(Australian Resource Centre for Healthcare Innovations (ARCHI))5.

Some suggestions for improvement in healthcare include:

Eliminating duplication and redundant processes

Reducing time taken to complete tasks

The introduction of information technology

(NHS Institute for Innovation, 2007; Bolton Improving Care System (BICS),

2007; Campbell, 2009; Page, 2010).

Simplification and standardisation are key to sustainability of any

improvement (Ben-Tovim, et al., 2008). Once the most simple, effective

and efficient way of undertaking a process has been developed it can

become standard work. Spear (2005) also highlights the importance of

reducing ambiguity and work arounds by standardising processes and the

time taken to carry out each step in the process. McGrath, et al. (2008) also

highlight that standard processes are robust, less prone to error and are

easy to teach to new staff. However, Mazzocato, et al. (2012) caution

against over standardisation as staff can begin to find their work

monotonous.

5 http://www.archi.net.au/

Page 34: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

16

In section 2.6 some case studies outline further examples but first we will

look at levers for process improvement followed by the process

improvement methodologies and tools prevalent in health care.

2.2.2 Levers for Process Improvement in Healthcare

The main lever for process improvement in health care should always be the

patient as the customer. The Agency for Healthcare Research and Quality

(AHRQ)6 highlights that rising demands in healthcare, increasing costs,

workforce shortages and the requirement for quality outcomes have all led

healthcare organisations to look for opportunities through process

improvement.

According to NHS Institute for Innovation (2005) and Fillingham (2008) the

main levers for process improvement are:

• To improve the journey for the patient leading to better outcomes

and experiences for patients

• To increase staff morale

• To improve overall performance in terms of efficiency, quality and

safety

• To improve the flow of information

• To reduce waiting lists

• To avoid mistakes

• To develop a business case

• To understand the culture we work in

The IHI also emphasises patient-centred care as a key lever for process

improvement and other authors outline how the patient as the customer

must remain as the central focus and that the patient’s experience should

be improved at every opportunity (Philips and Hughes, 2008).

6http://www.ahrq.gov/qual/toolkit/toolkit3.htm

Page 35: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

17

In Virginia Mason Medical Centre (VMMC), Kaplan (Albright, 2008) outlines

that the board challenged staff to take a closer look at their processes to

make sure everything they did was for the benefit of the patient.

Mazzocato, et al. (2012) outline a similar directive from the hospital board

at Lindgren’s children’s hospital in Sweden for the initiation of process

improvement.

Other levers include:

A crisis (the Emergency Department in the newspaper due to long

waits), The need to transform the organisation

A general desire to improve processes

A need to demonstrate improved operational or financial results

A need to exploit strategic events such as an information technology

implementation, integration of care and building a new facility

(Fine, Golden, Hannam, and Morra, 2009; The Philips Healthcare white

paper, 2009).

Overall the requirement to do more with less highlights an opportunity to

step back and determine if process steps actually need to be done at all

(Locock, 2003 (b)).

2.3 Methodologies in Process Improvement in Healthcare

As outlined, quality issues are generally a result of system or process

failures. Like any other business, healthcare requires a framework built

upon best practices in process improvement and innovation (Bell, 2006;

Hughes, 2008).

In recent years healthcare organisations are turning to quality improvement

methodologies with origins in the manufacturing world such as Lean

Thinking, Six Sigma, Business Process Re-engineering, Theory of

Constraints, Queuing and TQM (total quality management)/CQI (continuous

quality improvement) (Albright, 2008; Murray, 2009). Healthcare, like

manufacturing, is a complex system with multiple processes that must be

Page 36: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

18

aligned to deliver optimal services of high quality at reasonable cost.

Another methodology outlined in the literature which does not have its

origins in manufacturing is the IHI’s Plan-Do-Study-Act (PDSA) cycle.

The use of methodologies and tools for process improvement in healthcare

has expanded in recent years and some can be quite complex to understand

and apply. However, fundamental concepts can be applied to improve

processes and a basic understanding of methodologies and tools is a

starting point for any process improvement project. According to Locock

(2003 (b)) much of it is common sense and accessible to all.

In healthcare, models are not always clearly outlined and in fact healthcare

settings often pull on a range of methodologies and apply them in a

piecemeal fashion (Powell, Rushmer and Davies, 2009).

However, all of the process improvement methodologies outlined involve

mapping out the current workflow, establishing baseline data (how long

process takes, cost), validating that the workflow accurately reflects the

existing processes, applying improvement techniques and use of

improvement tools, implementing change and driving continuous

improvement (ARCHI, NHS Institute for Innovation, 2005).

There follows an outline of the three methodologies most commonly used in

healthcare. There are others in the literature and the reader is referred to

the work of Murray (2009) and the Powell, Rushmer and Davies (2009) NHS

confederation report for further review.

2.3.1 Lean Thinking

Lean thinking, as the name implies is a mind-set. Macleod, Bell, Dean and

Baker (2008) suggest that Lean Thinking is becoming a critical tool for

healthcare. Lean Thinking was developed by Toyota in the 1950s and its

application in healthcare began in the early 2000s (Young and McClean,

2009). Lean Thinking in healthcare is largely based on the work of Deming

at the IHI. It emphasises streamlining processes and standardisation to

provide what the internal (staff) and external (patient) customer wants with

Page 37: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

19

minimal waste (Dickson, et al., 2009). This methodology uses a range of

tools to identify blockages in process flow and then looks at removing

unnecessary steps in the process. It is a different way of looking at

healthcare, moving away from the work of specific clinicians or body

systems towards processes (Ben-Tovim, et al., 2008).

There are five principles of Lean Thinking (see figure 2.2) (Ben-Tovim,

Dougherty, O’Connell and McGrath, 2008; Campbell, 2009):

Identifying value. This involves identifying anything that adds value

to the customer

Mapping the value stream. This involves mapping the complete set of

process steps

Making value flow. This involves eliminating non-value added

activities and simplifying and standardising the remaining steps that

do add value. This also involves the elimination of batching and

queuing. Ultimately for the patient this means giving them just what

they need when they need it without waiting

Establishing pull. This allows for work to be pulled to the next step

(rather than pushed, for example, on to a waiting list)

Seeking perfection. This requires continuous improvement and the

sustaining of any improvements made

Figure 2.2 Principles of Lean Thinking

(Lean Enterprise Institute, Principles of Lean Available at:

http://www.lean.org/whatslean/principles.cfm)

Page 38: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

20

To identify non-value added activities Lean Thinking assigns non-value

added activities (waste) into seven categories:

1. Overproduction – incompatible IT systems or dual paper and IT-based

systems can lead to duplication of data entry

2. Waiting – time spent where resources are idle or time spent waiting for a

service

3. Transportation – moving resources (paper or staff or equipment) from

one location to another which introduces delay and inefficiency

4. Nonessential activity – performing an activity that makes no contribution

to the service provided to the customer

5. Inventory – holding resources until they can be used

6. Variation – changes or deviations from the expected outcome or the

expected standard

7. Defects – errors produced during the process

The idea in Lean Thinking is to squeeze non value activities out of a process

(Mazzocato, et al., 2012). Fine, Golden, Hannam and Morra (2009) give

examples of waste as test results that are never read, staff walking miles

daily and repeating tests as forms of waste. Fillingham (2008) adds staff

searching for equipment, staff recording information many times and staff

not having important information to hand when needed.

In summary, Lean Thinking views any non-value added activity as waste,

focuses on process and the tools used are all related to visualising where

there is waste. Value is always defined from the customer’s viewpoint

(patients and staff in healthcare). Data is key to the identification and

prioritisation of improvement initiatives (see section 2.4) and staff

involvement is crucial for success and sustainability. Lean Thinking as a

methodology is often selected where an organisation values a visual

improvement along with positive changes in speed and efficiency (ARCHI).

Page 39: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

21

A review of projects using Lean Thinking by Hughes (2008) reported that

health care organizations improved patient safety and the quality of health

care by systematically defining the problem; setting goals, removing

workarounds and clarifying responsibilities. Team members in the

improvement projects developed action plans that improved, simplified, and

redesigned work processes. In contrast to this Holden (2011) found in his

review of Lean Thinking in emergency departments studies did not report

on patient safety outcomes or on quality aspects. Research on Lean

Thinking is limited with studies lacking clear research designs, limited

metrics, a variation in terminology/definitions, tools and methods used and

there is a knowledge gap regarding how and why Lean Thinking may work

in healthcare making it difficult to determine which aspects work best

(Young and McClean, 2009; Mazzocato, et al., 2012). In 2010, Mazzocato,

et al., outlined that 33 articles they reviewed all reported positive results

suggesting a bias towards reporting of successful implementations. In

summary, there is scope for methodological development (Young and

McClean, 2008). Further challenges are outlined in section 2.5.

2.3.2 Six Sigma

Six Sigma is the newest of the methodologies prevalent in healthcare. It

originated in Motorola in the mid-1980s and has been used in

manufacturing since then but in healthcare only in the last 15 years.

Six Sigma uses a five-phased structured approach and is a very rigorous

statistical measurement methodology. The five-phased approach is known

as the define, measure, analyse, improve, and control (DMAIC) approach.

Statistical tools, for example, statistical process control charts, are used to

identify variation in processes. Six Sigma recognises that variability can

prevent the delivery of a consistent quality service (Eitel, et al., 2010). This

Page 40: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

22

method requires statistical expertise and reliable data collection and usually

requires intensive technical training (ARCHI7; NHS8; IHI9).

Albright (2008) highlights that Lean Thinking and Six Sigma share some

similarities. However, Six Sigma is a problem-solving methodology focused

primarily on reducing process variation while lean focuses more on

improving process flow. Lean Thinking also allows for more holistic decisions

to be made about opportunities for process improvement with the emphasis

on involvement of staff and observation of the workflow in situ whereas Six

Sigma tends to look at disembodied facts and statistics. Six Sigma as a

methodology is often selected where an organisation values analytics and

precision (ARCHI).

2.3.3 Plan-Do-Study-Act (PDSA)

Figure 2.3 PDSA cycle

(Langley, G.J., Moen, R., Nolan, K.M., Nolan, T.W., Norman, C.L. and Provost,

L.P., 2009. The Improvement Guide: A Practical Approach to Enhancing Organizational Performance.

2nded. San Francisco: Jossey-Bass)

The Plan-Do-Study-Act (PDSA) cycle depicted in figure 2.3 above has been

widely used by the IHI for rapid improvement in healthcare. One of the

unique features of this model is the cyclical nature of assessing change

7 http://www.archi.net.au/

8http://www.institute.nhs.uk/

9 http://www.ihi.org/Pages/default.aspx

Page 41: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

23

through small and frequent PDSA cycles before changes are made system

wide. In this way this methodology turns ideas into action and connects

action to learning (Varkey, Reller and Reser, 2007).

Langley, et al. (2009) propose a model for improvement which poses three

questions before using the PDSA cycles: (1) what are we trying to

accomplish? (Aim) (2) how will we know that a change is an improvement?

(Measures) (3) what change can we make that will result in improvement?

(Change). The PDSA cycle starts by determining the problem, what changes

can be made, a plan, who should be involved and what should be measured

to understand the impact. The change is implemented and data and

information are collected. Results from the implementation study are

assessed and interpreted by reviewing key measurements that indicate

success or failure. Finally, action is taken on the results by implementing

the change or beginning the process again. PDSA cycles allow low risk tests

of change based on proposals of frontline staff and so encourages staff

engagement. As outlined by Powell, Rushmer and Davies (2009) there is

only limited evidence in the peer-reviewed literature of changes in

outcomes from this approach.

The next section outlines the importance of data and measurement in

process improvement.

2.4 Measurement in Process Improvement in Healthcare

The literature outlines some of the measures used to monitor the impact of

any process improvement initiative. These include counting the number of

steps in the process, the time to carry out each step in the process, the

waiting time at each step, the total cycle time, throughput, capacity and

demand, the number of errors, staff numbers involved and customer

satisfaction.

One of the universal principles for a sustained approach to improving a

process is to measure the process. Data helps to identify problems,

prioritise problems and determine if improvement has occurred (Chyna,

Page 42: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

24

2002). In Lean Thinking terms data can “push” improvement by identifying

problems and “pull” improvement by identifying opportunities (Victorian

Government report on using data for quality improvement, 2008). Once the

process is measured there is an opportunity to get control over it. McGrath,

et al. (2008) highlight that data must be used to determine if a change is an

improvement and so any solution can become more evidence based. Some

authors also emphasise that data used for measurement needs to be

simple, clearly visible and available in real time (McGrath, et al., 2008;

Eitel, et al., 2010).

The establishment of a baseline position for measuring and communicating

the improvements can also be an exciting and motivating factor for teams

(Fillingham 2008; NHS Institute for Innovation, 2005; ARCHI). However,

Holden (2011) in his review of Lean Thinking in 15 EDs (Emergency

Departments) points out that pre and post metrics were often not measured

and no numeric data was given to support the reported improvements.

A weakness in the literature on improvement methods is that there is

minimal discussion on the costs of implementation and while many

initiatives state a reduction in cost through increased efficiency as one of

their objectives there is a lack of evidence to suggest reductions have

occurred (Powell, Rushmer and Davies, 2009). However, it is acknowledged

that measuring and analysing cost savings from these initiatives presents

complex challenges (Brennan, Sampson and Deverill, 2005).

2.5 Tools used to Understand and Improve Processes

This section outlines some of the tools used in process improvement. Some

tools are used to collect data on processes in order to visual where issues

are occurring, for example a process map; others are used to further

explore problems to examine their cause and effect, for example a fishbone

diagram; and others work with numbers to monitor progress.

Page 43: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

25

“If you can’t describe what you’re doing as a process, you don’t know what

you’re doing,”

The father of the quality revolution, W. Edwards Deming 1900-1993

2.5.1 Process Mapping

Process Maps are a visual representation of the steps that make up a

process and are a key first step when using process improvement

methodologies. They can describe process steps, timing, and frequencies at

the highest level and work downward. High level process maps give an

overview of the process. Lower level maps help analyse the process in

greater detail and can assist in highlighting priority areas for improvement

(ARCHI; IHI, 2004; NHS, 2005). Of note, attention to detail in the lower

level maps is important to determine how best to integrate healthcare IT

into workflow (Crandall, et al., 2007). Attention to detail at bottlenecks is

also important (NHS Scotland Quality Improvement Hub, 2008). It is

important to define the beginning and end (the scope). As process mapping

is a key step in process improvement it is outlined here in more detail than

the other tools. Figure 2.4 below outlines a high-level process map for an

ischaemic heart disease patient. The diamonds in the map are decision

points where the patient journey can take one of two paths depending on

the decision-making process.

Page 44: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

26

Figure 2.4 High-level flowchart for ischaemic heart disease patient

(Institute for Healthcare Improvement (IHI), Process Improvement Tools, Flowcharts, 2004. [pdf]

http://nnphi.org/CMSuploads/Flowcharts%20Guide.pdf)

There is little guidance in the literature regarding the most effective type of

process map to use (Colligan, Anderson, Potts and Berman, 2010). Patient

orientated approaches to process mapping put the patient at the centre and

remind staff of why process improvement is needed. This method may be

preferable to more clinician orientated workflow with each clinician depicted

in parallel “doing” things to the patient. Ozkaynak, et al. (2013) outline how

clinician orientated workflow, unlike patient orientated, can lose sight of the

cooperative work that prevails in healthcare and that a more patient

orientated approach can help characterise the gap between clinical and non-

clinical practices and inform the IT that can bridge the gap. However, it

should be emphasised that a review of clinical workflow and integration of

any process improvement (including IT) into such workflow is crucial to get

buy-in from staff (Kawamoto, Houlihan, Balas and Lobach, 2005; Bowens,

Frye and Jones, 2010). Therefore, in many cases more than one type of

map may be appropriate.

Process mapping is used to depict the flow of steps within a process. In

order to map a process the activities need to be understood, what triggers

Page 45: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

27

these activities (inputs), who is involved, the sequential steps, and the

outputs associated with the steps (Fine, Golden, Hannam and Morra, 2009).

Where possible, it is also recommended that time consumed at each step or

at some key steps is documented (Holden, 2011). The Victorian

Government report on Process Mapping (2007) recommends keeping

process maps simple by not using complex symbols and shapes that are not

easily understood.

Once completed the process map can be used to answer certain critical

questions:

1. Can we eliminate or reduce certain activities?

2. Can we complete the process in less time by changing the process?

3. Can we improve how we meet customer requirements by changing the

process?

The importance of process mapping by on the ground observation is

emphasised by Bell (2006). This is a Lean Thinking concept of “Gemba” or

“going where the action is”.

Summarised below are some of the benefits of process mapping

• Once workflow is mapped opportunities for improvement can be

identified

• Mapping assists in the understanding of all the processes involved in

the patient journey. Sometimes staff are seeing the complete patient

journey for the first time and this increases their understanding of

the journey and its complexity. Mapping makes all stages visible to

all involved and engages staff in owning any problems that emerge.

In short, mapping can generate permission to change from all

involved (Victorian Government report on Process Mapping, 2007;

Ben-Tovim, Dougherty, O'Connell, and McGrath, 2008; Eitel, et al.,

2010).

Page 46: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

28

• Mapping promotes collaboration and improved communication

between staff members. It provides an opportunity to bring people

together and boosts team morale. Mapping has also been shown to

really assist in understanding capacity and demand problems (NHS,

2005).

In Lean Thinking process maps called value stream maps can be used to

take process mapping a step further by establishing the steps but also

outlining which steps do and don’t add value (waste).

2.5.2 Focus Groups and Interviews

Focus groups and interviews are common methods of gaining qualitative

data to guide improvement initiatives. They can provide valuable input in

terms of diagnosing any issues and gaining an understanding of the

perspectives of various stakeholders in a short amount of time. They are

also useful for identifying and exploring challenges (Victorian Government

report on using data for quality improvement, 2008).

Focus groups are important for ideas generation. One of the key elements

of any improvement work is getting staff views on what could be improved

(section 2.9). Appropriate representation of stakeholders is also an

important consideration and Bell (2012) recommends IT department

involvement (section 2.7). It is important to be clear about goals, roles and

what will happen, to stick to the start and finish time and allow each person

present to have their views heard. If there are dominant people in the

group, a method whereby each person has an opportunity to write

down/express their views is preferable. The NHS Leaders Guide on “Working

with Groups” gives some useful ideas on how to conduct these groups. Once

all ideas are outlined by participants ideas can be prioritised (NHS, 2005).

Interviews are used to garner more in-depth information from a limited

number of experts. These experts can give their valuable insight and

recommend solutions. Interviews tend to be more objective as those

interviewed do not have any affiliation with the organisation and can lead to

Page 47: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

29

more frank discussions whereas the larger number in a focus group can

limit or bias discussion. The interviewees can help direct towards similar

work or other experts. Interviews are commonly guided by a script and can

be face to face or on the telephone (NHS, 2005; Victorian Government

report on using data for quality improvement, 2008).

2.5.3 Fishbone Diagrams

Ishikawa, Fishbone, or Cause and Effect Diagrams visually represent the

causes of a problem/effect and help determine the ultimate source of the

problem (IHI; NHS).

Figure 2.5 Fishbone diagram

(NHS Institute for Innovation and Improvement Quality and Service Improvement Tools)

http://www.institute.nhs.uk/quality_and_service_improvement_tools/quality_and_service_improvement

_tools/cause_and_effect.html)

This tool invented by Ishikawa is called a “fishbone” diagram because of its

appearance. The cause-and-effect diagram can be used for further analysis

to determine why a particular problem/effect occurs. Once a problem/effect

is identified as a priority for improvement all causes are listed by the team.

The causes can then be listed in order of priority as a focus for

improvement work. In Figure 2.5 the causes are broken down in 4 sections;

environment, methods, equipment and people. Causes in terms of methods

outlined include lack of automation, too much paperwork and the process

taking too long.

Page 48: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

30

2.5.4 Data Check Sheets

Data check sheets, or recording tables are used to collect observational data

which can be analysed to identify opportunities for improvement. They are

usually used to collect data repeatedly at the same location or by the same

person (ASQ, 2004; Victorian Government report on using data for quality

improvement, 2008). Figure 2.6 below shows a check sheet used to collect

data on telephone interruptions. The tick marks were added as data was

collected over several weeks. These interrupt the staff workflow and an

analysis would determine if they are valued added or non-value added.

Figure 2.6 Check Sheet

(To collect data on telephone interruptions from the American Society for Quality (ASQ)

http://asq.org/learn-about-quality/data-collection-analysis-tools/overview/check-sheet.html)

2.5.5 Statistical Control Chart

The control chart is a type of statistical process control tool. Process

performance is plotted over time against upper (UCL) and lower control

limits (LCL). This chart helps to readily identify process variations over time.

Control charts are used both during and after process improvement

implementations. Variations evidenced on a control chart can highlight a

focus for process improvement and once improvements have been

implemented control charts can be used to ensure that processes are

maintained within pre-determined control limits (Varkey, Reller and Resar,

2007).

Page 49: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

31

Figure 2.7 Control chart

(Control chart of falls per 1,000 patient days from Quality Digest

http://www.qualitydigest.com/june08/articles/03_article.shtml)

Figure 2.7 outlines the number of falls per 1,000 patient days. The UCL is

set at 4.5 and if the control chart shows a peek above this UCL further

investigation is carried out and the necessary improvements implemented.

2.5.6 Summary

To achieve the best results in process improvement the literature

recommends the following strategies (Locock, 2003 (b); Hughes 2008;

Holden, 2011):

Draw a process map to understand the process flow

Document the time consumed at each or key steps

Use check sheets if observing the process to collect repetitive data

Analyse the process map and identify which problems to focus on

Develop a cause-effect diagram if the cause of problems is not easily

identified

Prioritise improvement opportunities

Page 50: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

32

Following the introduction of a process improvement initiative a

control chart can be used to ensure that the process is staying within

process control limits

Some improvement opportunities will be easily identified once the process

map is drawn and can be implemented immediately. This is often referred

to as “Just do it!” in Lean Thinking.

2.6 Case Studies

Some healthcare organisations are using process improvement

methodologies to target improvements in a wide range of departments both

clinical and administrative: laboratories, emergency departments, wards

and stock are the areas most commonly targeted. Improvements in

emergency departments are frequently cited in the literature (Dickson, et

al., 2009; Mazzocato, et al., 2010; Holden, 2011). Process improvement

methodologies are also applied to achieve improvements in such areas as

diagnostics, patient records, operating rooms, outpatient services,

pharmacy, quality assurance, IT and accounts. Middleton, et al. (2009)

outlines clearly the reduced workload, time spent and cost of improving

processes through the introduction of IT in a radiotherapy department.

Many of these sites use process improvement methodologies based on the

principles of Lean Thinking.

From a review of improvement work by thousands of clinical teams across

the UK in 2004, the NHS Institute for Innovation (2005) outlined the 10

improvements with the highest impact and benefit. They outline that the

work to match capacity and demand and reduce variation particularly at

bottlenecks has led to some of the most exciting improvements in

healthcare processes. The 10 high impact improvements are outlined below.

1. Day surgery being the norm

2. Improving flow through access to diagnostic tests

3. Managing variation in patient discharge thereby reducing length of

stay

Page 51: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

33

4. Managing variation in the patient admission process

5. Avoiding unnecessary follow-ups and ensuring any follow-ups occur in

the right care setting

6. Care bundle packages to increase reliability of performing therapeutic

interventions

7. A systematic approach to care for people with long term conditions

8. Improve access by reducing the number of queues

9. Optimise patient flow through service bottlenecks using process

templates

10. Redesign extended roles in line with efficient pathways

However, success depends on what is done correctly at the outset of any

improvement effort. Identifying opportunities through process mapping and

measures to be used are essential pre-requisites for the delivery of benefit

(Fillingham, 2008).

Some specific case studies of process improvement now follow. The

majority have used a methodology based on the principles of Lean Thinking

and they were chosen as they are leaders in the field and/or have

introduced process improvements that could be applicable to the study

setting.

Gary Kaplan (Kenney, 2011), CEO of Virginia Mason Medical Centre (VMMC)

in the USA, emphasises that at VMMC “Lean” is not just an improvement

system; it is a culture. VMMC was the first health centre to integrate the

Toyota Manufacturing (Lean) philosophy back in 2000 (Holden, 2011;

Kenney, 2011; Mazzocato, et al., 2012). Process improvements include a

patient alert system, nurses using computers on wheels (COWs) for change

of shift handovers to take them away from the nurses’ station and be more

visible to patients which also reduced the number of steps they took daily

by up to 90%. They also introduced contemporaneous documentation and

order entry by portable wireless computer and computer access in all

Page 52: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

34

outpatient rooms. All of these improvements were achieved through the

introduction of IT.

The VMMC outline benefits of improvements in terms of reduced costs,

decreased time to report test results and a decrease in the amount of

walking for staff. Now patients get to spend more time with healthcare

providers, patients have less delays, more timely results and treatments,

staff have less duplication and when best practices are introduced they

become the standard (Womack, et al., 2005; Kaplan and Patterson 2008;

Kenney, 2011).

Intermountain healthcare is recognised internationally as a pioneer in both

quality improvement and health information technology. Intermountain uses

a system called HELP2 which provides clinical decision support to clinicians

through automated clinical tools, gives a longitudinal view of patient records

and collects aggregate data for use in quality improvement. While similar

paper-based tools (protocols, infection control tools, guidelines and

summary worksheets) have been used at other organisations, the use of

more than a few of these tools has been shown to require information

technology (Intermountain briefing report, 2013; Thompson, Classen and

Haug, 2007).

At the Flinders Medical Centre in Australia (Ben-Tovim, et al., 2008) the

redesign of care (as it is known there) using Lean Thinking began in 2003.

They concentrated on improving the processes for the Emergency

Department (ED) and medical and surgical patients, standardisation of work

and sustainability of improvements. By rearranging the order in which

patients were seen during ward rounds patients ready for discharge were

seen first and this meant discharge summaries were completed more

efficiently and the authors reported that over 80% were completed within

24hours. The Australian experience also highlights the importance of

suitable IT systems as a key enabler of process improvement.

Page 53: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

35

Thedacare in the USA, the nation’s “most wired” hospital10, also uses Lean

Thinking principles. Improvements ensured all patients were visited by the

multidisciplinary team (MDT) on admission and a care plan devised which

was documented in the electronic medical record (EMR) so that it could be

accessed by all providers and orders could be generated. They had reduced

errors, length of stay and greatly improved customer satisfaction (Womack

et al., 2005; Thoussaint, 2007)11.

Bolton Improving Care System (BICS), which is a Lean Thinking approach

has been implemented throughout Bolton hospital. This led to a reduction in

the steps for routine bloods from 309 to 57 steps (70%) and fewer staff

were required to carry out these tasks and there was a 90% reduction in

the time taken (Jones and Mitchell, 2006).

In Canada, Lean Thinking began in 2005 within 5 hospitals initially. They

reported reduced ED wait times, reduced length of stay, improved operating

room usage, increased radiology procedures per time period and better

infection control measures as a result (Fine, Golden, Hannam and Morra,

2009).

In Sweden, Lean Thinking led to the introduction of a data board in a

paediatric ED which was used to highlight if the flow of patients was slowing

down with patient names turning red if target timeframes were surpassed

(Mazzocato, et al., 2012).

Some primary care practices in California are adopting touchscreen tablets,

kiosks or patient portals that automate the registration process which

results in shorter waiting times, a reduction in errors and lower staff costs

(Rhoads and Drazen, 2009). At Vanguard urologic institute in Houston a

self-service patient check-in kiosk has enabled patients to enter their

personal health information and consent to treatment (Webster, 2011).

10http://www.thedacare.org/News%20and%20Events/Company%20News/ThedaCare%20Ag

ain%20Ranks%20Among%20Most%20Wired.aspx

11 http://www.innovations.ahrq.gov/content.aspx?id=3355

Page 54: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

36

This initiative has reduced the number of errors and lost charts and

provides an opportunity to assess the patient experience. Patients at

Vanguard wait an average of 2.44 minutes only (the national average wait

being 21.3 minutes (ASQ)).

“It lessens the work that I wouldn’t consider high value and the patients can

do it better. I think job satisfaction is higher when you are doing more

interesting work”

Kevin Slawin, MD, Vanguard Urologic Institute p. 2

In a review of Lean Thinking in EDs Holden (2011) looked at 15 EDs in the

USA, Australia and Canada. Improvements included reduced length of stay

and proportion of patients leaving the EDs without being seen, fast tracking

of patients of low complexity, eliminating or combining steps in the process

and registration conducted using mobile workstations.

However, despite the benefits outlined, a survey carried out in 2009 by the

American Society for Quality (ASQ, 2009) highlighted that only 4% of U.S.

hospitals reported full deployment of Lean. However, 53% of the hospitals

did outline some level of Lean. Some challenges to the deployment of

process improvement will be outlined further in section 2.6.

A discussion of process improvement through the introduction of

information technology now follows in section 2.5. It is important at this

point to note that the application of a process improvement methodology

such as, Lean Thinking without introducing IT, as seen in some of the case

studies above, demonstrates the value that can be added by changes to

process alone.

2.7 Process Improvement based on the introduction of

Information Technology

As outlined in the introduction, the IOM (1999) suggests that IT must play a

central role in the redesign of healthcare to achieve substantial

improvements in quality. IT is an enabler and allows for the automation of

routine tasks which in turn, gives providers more time to spend with

Page 55: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

37

patients. The connectivity provided by IT allows for better communication

among providers. Decision support assists providers with the analysis of

ever-growing amounts of information and ensures the right information is

delivered to the right people at the right time and in the right format which

aids decision making (IOM, 1999; NHS Institute for Innovation, 2007;

Victorian government report on streaming care, 2008). In this way, health

IT such as electronic records, digital technology for x-rays, mobile

technology, telecare, access to Map of Medicine can be extremely powerful

tools for improvement (NHS Institute for Innovation, 2007; Victorian

government report on streaming care, 2008). Bates (2002) states that IT

and high-quality healthcare are closely linked and that excellent clinical

outcomes at some healthcare organisations have been achieved in part due

to their information systems.

As outlined previously (section 2.4) measurement is a key component of

improvement. Data for improvement, generated from information systems

is often more accessible, timely, accurate and reliable than that created

manually. Finally, data mining allows providers to carry out statistical

analysis to determine outcomes of care, if processes need to be improved

and to carry out more extensive research (Hynes, et al., 2004).

In the context of process improvement Hughes (2008) advises that IT

should be used cautiously. IT exists to add value to a business, so that a

business in turn can add value to the customer. Bell (2006) outlines that IT

can be used effectively to simplify processes and add value, but if it is used

badly it can ingrain the very waste that should be eliminated. Automation

for automation sake is poor practice. Computers are amplifiers and if

inefficiencies are not first removed, the addition of IT will just lead to the

system becoming more inefficient faster (Diamond and Shirky, 2008).

Trinity Health and others outlined in the case studies above (2.6) have

demonstrated that process improvement prior to implementation of IT can

provide a solid foundation for IT implementation rather than simply

Page 56: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

38

modelling existing, possibly problematic processes (Brokel and Harrison,

2009).

Bell and Orzen (2011) recommend that IT staff are active participants in

process improvement activities. Business and IT sections must integrate

and keep focused on delivering value to the customer. The authors

acknowledge that there can be misalignment between the business

processes and IT; IT can be seen as inflexible and resistant to change and

continuous improvement by the business side. Bell (2012) highlights the

need for guidance on how business and IT can integrate and suggests this

guidance may be found in the principles of Lean Thinking.

Bell (2013) tells us that the key to creating effective IT systems is engaging

employees in the simplification and standardisation of business processes

before investing in information systems. Bell (2006) indicates that

previously IT was often seen as waste to be removed rather than a tool to

help achieve improvement. Now IT is seen as a requirement for sustainable

improvement and he outlines that it is no longer possible to exclude IT from

the Lean Thinking approach. IT can make it difficult to revert to old ways of

working so can assist with sustainability of improvements (NHS, 2007).

Some examples of process improvements through the introduction of IT

were highlighted in section 2.6. There follows an outline of process

improvements based on the introduction of IT in physiotherapy.

2.8 Process Improvement and the introduction of Information

Technology for Physiotherapists

Physiotherapy specific literature makes up a very small percentage of the

growing body of literature on process improvement and health information

technology.

In Lean terminology physiotherapy can be seen as a functional bottleneck

as often physiotherapy is the last point in the patient journey and due to

waiting lists the flow stops and the patient waits. In a lean process the

patient would not have to wait but instead would be “pulled” from the

Page 57: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

39

referring service to see a physiotherapist directly (NHS Institute for

Innovation, 2005; NHS Scottish Quality Improvement Hub, 2008).

In the UK the Department of Health commissioned service improvement in

Allied Health Professional (AHP) services in 2011, the aim of which was to

enhance quality and productivity through better outcomes and experience

for patients and carers. One of the main learning points from this initiative

was the importance of AHPs (Allied Health Professional) taking sufficient

time to first understand clearly the processes of the business they work in

and the importance of using data. In Barnet physiotherapy community

services wait times and Did Not Attends (DNAs) were reduced and a new

referral process was implemented. This was achieved through a demand

and capacity analysis, development of clear protocols and the use of

evidence based clinical outcome measures (Department of Health, 2011).

In Flinders Medical Centre in Australia, a similar initiative based on Lean

Thinking principles resulted in a reduction in waiting times and DNA rates in

two AHP services, physiotherapy and podiatry (Kitch, Crane, Ben-Tovim and

Daebeler, 2007).

The literature outlines how quality improvements can be achieved by

reviewing processes and introducing information technology in

physiotherapy, for example, by use of structured forms to improve data

accuracy and allow for the right information to be in the right place at the

right time, screening for contra-indications to treatments, improved

communication with the multidisciplinary team and improved research

capabilities (Barry, Jones and Grimmer, 2006; Vreeman, Taggard, Rhine

and Worrell, 2006; Buyl and Nyssen 2009). Shields, et al. (1994) found that

electronic documentation took 30% less time than paper documentation.

However, Vreeman, Taggard, Rhine and Worrell (2006) point out that apart

from the analysis by Shields, et al. (1994) few studies provide any

quantitative assessment of the impact of electronic recording in

physiotherapy.

Page 58: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

40

Despite the benefits there have been limited examples of process

improvement through the introduction of IT in physiotherapy. In fact,

Vreeman, Taggard, Rhine and Worrell (2006) state that a 2004 review in

the USA showed only 26.4% of healthcare providers with EHR functionality

had implemented any components for AHPs and there were no plans to do

so in the future.

Through informal correspondence with physiotherapy managers the

researcher determined that there has been limited progress in the area of

process improvement based on the introduction of IT for physiotherapy in

acute hospitals in Ireland. Private hospitals in Ireland have made some

progress but there are still some outstanding issues such as duplication of

data entry into paper charts. Private practice physiotherapy services have

made most progress in this area but they are single service, stand-alone

systems with no necessity for the integration that would be required in an

acute hospital. These practices are at somewhat of a disadvantage in not

having access to on-line scan or x-ray results. However, some have

managed to achieve an integrated body chart, incorporated VAS (Visual

Analogue Scales) and % improvement scales into their electronic notes.

Physiotherapists can enter physiotherapy discharge status and are using

PCs and tablets.

Some physiotherapists overseas have made significant progress. Nitin

Chhoda is a physiotherapist in the USA and an early adopter of EMRs.

Chhoda (2012) outlines the benefits of EMRs which he believes should allow

clinicians to spend much less time on paper work and much more time with

patients. Chhoda (2012) also outlines a new innovation in physiotherapy

management that he calls self-intake technology. This is similar to the

initiative outlined previously in Vanguard urologic institute and allows

Page 59: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

41

patients to carry out pre-visit registration saving time at a first

attendance12.

Choose and Book is in use by some physiotherapy services in the UK since

2008. The GP and patient can review waiting lists in their local area on line

and choose which location to refer to. Patients can leave their GP or

consultant knowing their referral has gone directly to their location of choice

which increases patient satisfaction. Physiotherapists can then triage

referrals on line and contact the patient with an appointment. The benefits

in terms of referral response times, improved communication, improved

access and reduction in time spent storing and retrieving referrals is well

established (Choose and Book, 2013).

Richardson (2011) outlines in his book how computerised clinical decision

support can be leveraged within physiotherapy electronic records to set up

computerised alerts and reminders to physiotherapists and their patients,

integrate clinical practice guidelines, condition-specific order sets, and

documentation templates and can give context and person specific

diagnostic support to the physiotherapist. The author suggests benefits in

terms of improved quality and productivity and patient outcomes, and

highlights that there is clear evidence that the use of evidence based clinical

decision rules allow physiotherapists to make decisions that are safer and

more efficient. One example outlined is the Virginia Mason low back

screening process which originated in the VMMC spinal clinic (Bisognano and

Kenney, 2012).

Work by Swinkels, et al. (2007) outlines that electronic clinical databases

for physiotherapy are in place in a few countries and are being used for

research, quality improvement and performance management. Clinical

outcome measures and numbers of patients was the main data collected.

12http://www.prweb.com/releases/PT-management/physical-therapy-

software/prweb10162237.htm

Page 60: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

42

Many physiotherapy-specific challenges that have been cited include the

need for a body chart to allow for profession specific notations to be

documented (see figure 1.1) and access to laptop PCs or tablets to allow for

documentation at the point of care, both of which would match the current

workflow of physiotherapists in the out-patient setting (Buyl and Nyssen,

2009; Unertl, Weinger, Johnson and Lorenzi, 2009).

Chapman (2010) demonstrated how the challenge of the body chart could

be resolved through his work with SystmOne UK and a digital pen. The

initial implementation of SystmOne added 40 minutes to the time taken for

the physiotherapist to complete one patient’s notes. Using the digital pen

reduced this time dramatically and increased consultation time with patients

by 15 per cent. More time spent with patients meant a reduction in the

number of attendances for each patient as more could be achieved in a

single appointment. Chapman’s (2010) work demonstrated overall

productivity gains of 35 per cent as a direct result of using the digital pen13.

Further challenges are explored in the next section.

2.9 Challenges to Process Improvement

The characteristics of healthcare have been extensively outlined in the

literature as a challenge to any change initiative. These characteristics

include complexity, multiple standards of care, multiple stakeholders, intra-

professional boundaries, reluctance to engage and varying standards of

infrastructure.

With specific reference to process improvement, some authors outlined

further challenges: (Fine, Golden, Hannam and Morra, 2009; Powell,

Rushmer and Davies, 2009; Dixon-Woods, McNicol and Martin, 2012)

(1) staff concerns about jobs

(2) staff believing that the initiative is the current flavour of the month

13http://www.ubisys.co.uk/news/detail/digital-pen-and-paper-increases-

productivity-of-physiotherapists-by-35

Page 61: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

43

(3) the difficulty with sustainability of some initiatives

(4) convincing staff of the need for change

(5) convincing staff that the solution is viable

(6) ability to access and continuously collect and monitor data preferably

through easily usable IT systems

(7) preventing unintended consequences at another point in the care

system

Fillingham (2008) highlights the difficulties with overcoming cultural barriers

and John Toussaint of Thedacare suggests the importance of being open

and honest about such cultural problems in any organisation14.

The importance of leadership as a success factor, and also as a challenge if

not clearly present and visible, is highlighted extensively in the literature

(Chyna, 2002; Fillingham, 2008; O’Connell, et al., 2008; ASQ, 2009;

Bowens, Frye and Jones, 2010).

Similar challenges to the introduction of health information technology have

been identified by some authors; lack of leadership, funding, buy-in from

staff, training or loss of expert personnel have also been cited in the

literature (Lapointe and Rivard, 2006; Vreeman, Taggard, Rhine and

Worrell, 2006; Buyl and Nyssen, 2009; Lluch, 2011; Rozenblum, et al.,

2011).

Fillingham (2008) suggests it is important to recognise the existence of

challenges and develop strategies to overcome them. With regard to staff

engagement Fine, Golden, Hannam and Morra (2009) put emphasis on

addressing “what’s in it for me?” for all staff involved. Staff involvement can

shift employees from merely carrying out the steps in a process to looking

14 http://www.lean.org/common/display/?o=1578

Page 62: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

44

for ways to improve and feel empowered to suggest and implement change

(Scott, et al., 2011; Spear, 2005). `

When we acknowledge the link between structure (including staff roles and

responsibilities), process and outcomes the critical importance of engaging

with staff; those who are at the frontlines and will be impacted by any

change initiative cannot be overlooked (Berwick, 1992). Batalden (2006)

outlines how the greatest power for change lies at the front lines.

Virginia Mason Medical Centre (VMMC) believes that the key to

accomplishing the perfect patient journey is understanding that the staff

who do the work know what the problems are and have the best awareness

of process improvement opportunities (Kenney, 2011). Other authors

concur with the idea of learning about possibilities for improvement through

problem solving with staff rather than telling staff what to do (Berwick,

2002; Ben-Tovim, Dougherty, O’Connell and McGrath, 2008; Brokel and

Harrison, 2009; Mazzocato, et al., 2010; Holden, 2011).

However, while some studies in his review outline the positive effects of

involving staff Holden (2011) suggests that this positive effect may be due

to the Hawthorne effect, the phenomenon that change efforts bring about

positive effects in staff merely because more interest is paid to staff. Brokel

and Harrison (2009) also suggest that the release of clinical staff to

participate in process improvement can be a challenge and therefore,

involvement of clinicians should be done in a manner that meets their needs

(McGrath, et al., 2008).

The use of data to convince staff of the need for change and to demonstrate

that a change is indeed an improvement is reiterated at this point (see

section 2.2.1.4).

In summary the critical importance of frontline staff involvement, data

collection and easily usable IT systems and leadership is emphasised

(Batalden, 2006; Ben-Tovim, Dougherty, O’Connell and McGrath, 2008;

O’Connell, et al., 2008; Dickson, et al., 2009; Holden, 2011).

Page 63: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

45

The importance of referring to the organisational change literature in more

depth prior to implementation of any process improvement is highlighted. A

brief overview of change management for process improvement is outlined

in the next section.

2.10 Change Management

“All improvement requires change but not all change is an improvement”

Don Berwick, IHI; 1996, p. 619

The link between improvement and change is indisputable as outlined by

Berwick (1996). Fillingham (2008) in the NHS outlines how process

improvement is as much about an understanding of culture and beliefs as it

is about techniques and tools. Crandall, et al. (2007) suggests change

management for implementation of IT in healthcare is one part technology

and two parts work processes and culture. Lorenzi (2000) takes this further

suggesting an 80/20 split between culture and IT implementation. Kaplan of

the VMMC recommends a clear commitment to change and very open

communication about expectations of any process improvement (Kenney,

2011). However, even with strong and committed leadership, some people

within the organization may be hesitant to participate in quality

improvement efforts because previous attempts to create change were

hindered by system factors; a lack of organization-wide commitment, poor

relationships, and/or ineffective communication (Eitel, et al., 2010). The

impact of these challenges was found to reduce if the organization

embraced the need for change.

The importance of identifying potential benefits and perceived challenges

cannot be overemphasised. These are important aspects of the change

management process as is the involvement of key stakeholders at each step

as outlined in the previous section. As emphasised by the Change

Management Framework of the Canada Infoway (2011), if stakeholders are

not engaged and cannot see potential benefits, change is less likely to be

successful. Therefore, any process improvement technique should have an

Page 64: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

46

associated benefit for the key stakeholders; the patients and staff (Buyl and

Nyssen, 2009). However, it is acknowledged that sustaining change is a

continuous challenge but once processes are simplified and standardised IT

can assist hugely in the quest for sustainability (Bell, 2006; Brokel and

Harrison, 2009). IT systems, if designed and implemented appropriately can

make it difficult if not impossible to revert to old ways of working (NHS,

2007).

The Australian literature on Lean Thinking suggests the 8 steps for change

devised by Kotter in the 1990s offers a framework for the change

management process (Philips and Hughes, 2008).

2.11 Conclusion

Healthcare is embracing methodologies from manufacturing to improve

processes. Key areas of focus to date have been emergency departments,

laboratories, the admission and discharge processes through hospitals and

waiting times and numbers waiting for outpatient clinics. Some suggestions

for improvement are highlighted in the literature which are very relevant to

physiotherapy and include reduction in duplication of processes, elimination

of redundant processes, avoiding unnecessary follow-ups to improve

throughput, improving flow of patients and reducing unnecessary staff

motion. Once processes are simplified and as near to perfection as they can

be these processes should become standard work. There are some

examples of process improvement based on the introduction of IT while the

emphasis is on improving the processes and flow in the first instance.

Information Technology has a huge role to play in standardisation and

sustainability of any process improvement.

Improvement requires some essential elements for success: fostering a

culture of change, involving key stakeholders, leadership commitment,

standardising care processes, appropriate use of information technology and

allocating sufficient resources.

Page 65: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

47

Physiotherapists have not been extensively involved in process

improvement and/or the introduction of IT to date so an awareness of the

various approaches and an acknowledgement of the key challenges and

success factors is very much a first step.

Through this literature review and the case studies outlined therein, the

researcher identified process improvement methodology and tools based on

the principles of Lean Thinking are appropriate for use in the physiotherapy

outpatient setting. Lean Thinking principles are simple, yet powerful. The

focus is on the process rather than specific problems and the customer is

always at the centre. Staff engagement is crucial. Data to highlight where

processes could be improved and if a change is indeed an improvement is a

key factor. This data needs to be meaningful to all and not involve complex

statistical analysis. The next chapter outlines the methodology used in this

research in further detail.

Page 66: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

48

CHAPTER 3

RESEARCH METHODOLOGY

3.1 Introduction

This chapter outlines the methodology used to assist in answering the

research questions.

Main Question (MQ):

How can processes be improved in a physiotherapy outpatients

setting?

Sub questions:

What process improvement methodology is appropriate to apply in

the physiotherapy outpatient setting? (SQ1)

Which processes should be improved? (SQ2)

How should processes be improved? (SQ3)

What are the potential benefits of any suggested improvements?

(SQ4)

What are the perceived challenges of any suggested improvements?

(SQ5)

A mixed methods exploratory case study design was employed. Baseline

quantitative data was collected and a literature review carried out. Through

the literature review the researcher identified a process improvement

methodology and tools based on the principles of Lean Thinking as an

appropriate methodology for use in the physiotherapy outpatient setting.

Following baseline data collection and the literature review, the three stages

of applying the process improvement methodology took place: process

mapping, semi-structured interviews and a focus group. Further

quantitative data was collected at the process mapping stage. This process

improvement methodology and the tools chosen closely resemble those

Page 67: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

49

used by the redesigning care programme in Australia (Ben-Tovim, et al.,

2008; Victorian Government Department on streaming care, 2008).

As outlined previously (section 2.5.6) the first step is to map the process.

Next the map should be analysed and improvement ideas prioritised. Before

starting and during the observation stage data is collected to assist

prioritisation and to determine after implementation if a change is indeed an

improvement. Keeping the patient at the centre and the engagement of

staff is crucial. Armed with this knowledge the first stage of applying the

process improvement methodology was to map the process of the patient

journey while involving staff in the clarification and validation of the process

maps. Following this mapping, potential process improvements and

associated benefits and challenges were garnered from the literature,

interviews and the focus group. While the scope of this research did not

involve the implementation all improvements some initial changes have

been made and the impact on the baseline data and other measures will be

closely monitored going forward.

3.2 Background

The location of this research study was the physiotherapy outpatient

department of a large acute teaching hospital. The department is not

located in the main hospital outpatients department and is at the very edge

of the campus.

The focus for this study was the orthopaedic and rheumatology patients

referred to the service as they make up the highest percentage (71%) of

referrals that go through the complete range of processes and so they were

a useful sample (see further explanation of local context in section 1.1).

3.3 Study design

The approach to this research was that of a case study concentrating on the

specific case of the physiotherapy outpatients department of a large acute

teaching hospital but it is hoped that the process improvement methodology

identified and results of applying this methodology can be leveraged for use

Page 68: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

50

by other departments, physiotherapy and other allied health professional

settings.

3.4 Methodology

A literature review was completed to identify (1) an appropriate process

improvement methodology for the study setting (SQ1) (2) process

improvements carried out elsewhere (SQ3) (3) potential benefits (SQ4) and

(4) perceived challenges (SQ5). Referring back to the research questions,

the literature review assisted with answering the questions on the most

appropriate process improvement methodology, how processes were

improved elsewhere and the resulting benefits and challenges. It also gave

the researcher some improvement ideas that could be applied in the

setting.

As outlined in section 2.3.1 Lean Thinking as a methodology is often

selected where an organisation values a visual improvement along with

positive changes in efficiency. Referring back to the issues identified by the

researcher (section 1.1) before commencing this research, the principles of

Lean Thinking were deemed the best fit for the department under study.

Section 1.1 identified waste from use of paper and disparate IT systems,

lack of standardisation for some processes and the need for improved

efficiency due to reduced clerical capacity.

Baseline data was collected. This data was used to assist in determining

which processes should be improved (SQ2) and will be used to determine if

any future change is an improvement. The baseline data gives an indication

of the department throughput; number of notes filed and retrieved, phone

usage and costs and is outlined in section 4.2.

As outlined in section 1.1.1 the waiting times and throughout data is

requested by the HSE each month. Waiting does not add value to the

patient experience and can lead to conditions moving from an acute to a

chronic phase and inability to work. Patients want to have access to a

service without a delay, not when the system determines this for them

Page 69: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

51

(Campbell, 2009; Murray, 2009). Patients also want to have access to any

appliances they require; this is not always possible due to non-pay budget

constraints, a budget which is also used for the purchase of paper and

printing components. Unanswered phone calls from patients are not

providing a patient-centred service.

Application of the process improvement methodology addressed sub-

questions SQ2, SQ3, SQ4 and SQ5 (to a lesser extent) and was made up of

three distinct stages:

3.4.1 Stage 1: Process mapping

As outlined in section 2.5.6 the first step towards improvement should

always be to map the process. Referring to figure 2.2, this stage is in line

with the Lean Thinking principles of all steps adding value for the customer

(patients and staff), mapping, creating flow and establishing pull.

Mapping allows all staff involved in the patient journey to visualise the

complete journey and can clearly highlight which processes need to be

improved (SQ2). Steps may not add value and timing of steps can assist

staff to realise the time taken to complete steps some of which may not add

value. Therefore, the processes were documented at a high level and in

detail through observation of all processes. The scope of the process

mapping and observation was the complete patient journey through the

physiotherapy outpatients department from the patient’s referral to the

service to discharge and/or onward referral. Many studies focus on the

patient journey from the point of arrival for a service (Dickson, et al.,

2009). However, the researcher was also interested in a more detailed

review of the processes involved in the period from referral to actual

appointment to determine what if any value was added. The observation

was carried out by the researcher and included measuring the time taken to

carry out some key steps in the process, for example; to retrieve and file

physiotherapy paper notes and to access relevant patient information. Time

was measured with a stopwatch mobile phone app. In parallel to the

Page 70: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

52

process mapping, information flow in terms of documents and data

generated and information accessed was also documented.

Ten participants made up of 8 physiotherapy and 2 clerical staff were

recruited for observation. Participants were drawn from the staff of the

physiotherapy department and were a convenience sample dependent on

which staff members were available and willing to volunteer at the time the

study was taking place. Consent was received from all participants. There

are three grades of physiotherapy staff working in the outpatients

department and one clinical specialist, two seniors and five staff grade

physiotherapists were recruited. The staff grade physiotherapists rotate

through the hospital to a different area every four months and this

happened midway through the observation stage. Therefore, staff at each

grade and staff grades with different levels of experience in the area were

observed.

An initial pilot of data collection took place in early January 2013 to finalise

the data collection sheet and determine the best way to randomise the

observations. Following this it was decided that observing the complete

patient journey from referral to discharge in sequence was not realistic as

the process steps occur at different times and some processes were a bit

adhoc. Therefore, this approach would not be an efficient use of the

researcher’s time and would not yield sufficient data.

For patient interactions such as patient registration, booking of

appointments and the patient being alone in a cubicle while the

physiotherapist accesses relevant information the researcher decided to

observe a maximum of one patient every 15 minutes. Other steps that took

place during the observation were documented and timed as they occurred.

A total of 7.49 hours observation was carried out on various days (Monday

to Friday) and at various times. Various days and times ensured

documentation of a representative process map of both busy and quiet

periods and ensured an even distribution of staff were observed.

Page 71: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

53

The researcher was positioned at a desk in the reception area to allow

visibility of the clerical staff while blending in in so far as possible. The

researcher would have a presence at the reception area in any case and did

not announce every time she was carrying out the observations. This was

an attempt to reduce performance bias.

Throughout the observation, the researcher recorded notes on observations

and anything that required clarification.

To acquire further detail on some of the process steps it was sometimes

necessary for the researcher to request clarification at the time from the

observed staff member.

The process map was documented in Microsoft Visio after each observation

session. Standard process map symbols were used as these are easily

understood and currently used at the site under study. Value stream maps

were not used as the researcher did not wish to make any assumptions at

the observation stage about which steps did or did not add value as

determined by the customer (patients and staff).

In between observations, a reflection session and iterative construction of

process maps was used to highlight gaps in knowledge about the processes

and guide subsequent observations. The level of detail outlined in the

process maps was determined by what was observed during the observation

sessions and what clarifications were gained within the timeframe of the

study. It is acknowledged that some gaps remain which were highlighted to

some extent through the interviews and focus group. Timings of steps and

reflections on the observations were recorded in Microsoft Excel after each

observation session. Descriptive statistical analysis was carried out on these

timings and mean times documented on the Visio process maps. Following

observation and documentation of the process maps in Visio the maps were

validated by those observed. This added credibility to this stage of the study

(Wallace and Savitz, 2008). The resultant process maps are presented in

section 4.3.

Page 72: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

54

3.4.2 Stage 2: Semi-structured interviews

As outlined in section 2.5.2 interviews and focus groups are ways of

gathering qualitative data to aid process improvement initiatives.

Referring to figure 2.2, this stage is in line with the Lean Thinking principles

of all steps adding value for the customer (patients and staff), creating flow

and establishing pull.

Three semi-structured interviews with key physiotherapy informants who

have implemented process improvements and/or health information

technology were undertaken. The interviewees assisted with answering the

research questions as they reviewed the process maps in the study setting,

outlined where improvements could be made (SQ2), gave clear suggestions

as to what those improvements would look like (SQ3) and their potential

benefits (SQ4) and finally they gave some advice about challenges and how

to manage them (SQ5).

Five experts were originally identified through the literature and word of

mouth and were asked for their voluntary participation. Four agreed to

participate but one subsequently had to withdraw for personal reasons. All

three were physiotherapists, one has a diploma in Lean healthcare, and the

other two participants have implemented process improvements through

the introduction of IT; one in an Irish private practice and the other at a

UK-based acute /community trust.

Once consent had been received from participants they were e-mailed some

background information on the department under study, some of the

baseline data and the detailed process maps. This information was sent a

minimum of 3 weeks prior to interview to allow the participants sufficient

time to review the detailed maps. Interviews were by telephone and took

approximately one hour (total time spent interviewing was just over 3

hours) and written notes were taken by the researcher during the interview.

Interviews were conducted as per the protocol outlined in Appendix B.

Page 73: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

55

The interviewee was encouraged to talk about the process maps and the

questions were not necessarily asked in sequence but before ending the

interview the researcher asked if the interviewee wished to add anything to

each of the questions as outlined in the protocol by going through each

question systematically. Each set of individual interview notes were sent to

the interviewees for validation. While the conversation of the interviews did

not flow from one question to the next the researcher’s notes were

organised according to the questions outlined in the protocol. Similar

comments and ideas emerged from these interviews and it was felt that

further interviews were unlikely to yield additional insights.

3.4.3 Stage 3: Focus group

A focus group with key stakeholders was carried out. Eight participants

were involved in the focus group which included physiotherapists (n=5),

clerical staff (n=1) and IT staff (n=2). Participants were a convenience

sample dependent on which staff members were available and willing to

volunteer at the time. Eleven people expressed an interest in participating

but due to work demands 2 IT staff and 1 clerical staff member had to

withdraw. The final group was made up of one clerical staff member, two IT

staff, three physiotherapists from the out-patient area and two

physiotherapists who previously worked in the area and have a keen

interest in IT and/or quality improvement.

The focus group assisted with answering the research questions as staff

reviewed some of the baseline data and the process maps with timings and

identified which processes could be improved (SQ2) and how (SQ3).

Following this they prioritised the improvements and outlined what they felt

the benefits of each improvement could be (SQ4).

The focus group took place from 11:30 a.m. as this time was most

convenient for participants and had the least impact on patient contact

time. The venue was on the site of study but in a location very much

Page 74: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

56

separate from the physiotherapy outpatients department where staff would

have space to give their full participation with no interruptions.

At the focus group the process maps from stage 1 were displayed on A1

size posters at four stations. The documents, data and information accessed

tables and the outline of repositories were also displayed in a separate area

of the room on A1 size posters for participants to refer to.

The session began with a brief introduction to the purpose of the focus

group, an outline of findings from the literature and the goals of any

suggested improvements. Participants were encouraged to add to the goals

throughout the session or to remove any they did not agree with. The goals

were displayed throughout the focus group and reiterated again prior to the

regroup and discussion session. There was agreement to maintain them as

they were.

Goals:

Improve patient journey and the importance of keeping the patient at

the centre

Boost staff morale

Reduce non-value added activities, for example, waiting, duplication

and movement

Reduce non-clinical steps for the physiotherapists

Improve ease of access to information – both when the patient is

present (patients with multiple attendances) and to review service

outcomes and carry out research

Referring to figure 2.2, these goals are in line with the Lean Thinking

principles of adding value for the customer (patients and staff), creating

flow and establishing pull.

From the department’s “comment cards” process; of note, patients have

very few complaints but access to the service and waiting times are

commented on. Therefore value from the patient’s viewpoint is access to

Page 75: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

57

the service when they need it and not when their problem is chronic, to

have their queries answered and to have the therapist spend time with

them and explain their condition.

Some of the baseline data was also presented (see section 4.2).

Following collection of consent forms from all participants they were divided

into groups of two and asked to review the process maps to identify where

improvements could be made. Each group of two had 12 minutes to review

each station. Each group of two had at least one member currently working

in the physiotherapy outpatients department. Each group had a flip chart

and a specific colour pen on which they documented their ideas for process

improvement. After 12 minutes the groups rotated clockwise to the next

station, reviewed what the previous group had documented, ticked the

ideas they agreed with and added to this list. This method of group work is

one of the suggested activities outlined in the NHS leaders’ guides (2005)

section “Working with groups”.

When each pair had visited each station the full group took a break for

lunch. Following lunch the full group came together to discuss the ideas

presented and to outline potential benefits and perceived challenges of any

suggestions. The focus group took 2.5 hours in total. In all 19 items were

listed as improvement opportunities. The number of ticks allowed clear

visibility of the opportunities highlighted most frequently.

Notes from the focus group were transcribed into a table by the researcher,

listing each item against any benefits and challenges outlined at the focus

group and were distributed to each participant by e-mail. Participants were

asked to state whether they agree/not agree that each item should be

explored and to prioritise the items for which they said “yes”, giving 1 to

their highest priority. All responses were amalgamated into a master

priority list and an average score was assigned to each item (total assigned

to item/number of responses to the item). If average scores were equal for

Page 76: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

58

two items the item that received the higher number of “Yes” responses was

given the higher priority.

3.5 Participants and recruitment methods

All participants were asked to sign a consent form (Appendix C) before

participating. The same consent form was used for all three stages. For

semi-structured interviews (stage 2) consent forms were sent by e-mail and

confirmation of agreement to participate was received by e-mail.

Participants in each stage of this research study were given a [stage

specific] information sheet a minimum of two weeks in advance of the study

stage outlining the purpose of the study and requesting their voluntary

participation (Appendix D). Each information sheet includes a statement

“Your participation is voluntary and you are free to withdraw at any time

without providing a reason”. One participant who had agreed previously to

participate in a semi-structured interview had to withdraw for personal

reasons.

3.6 Ethics application

Ethics was sought from the ethics committee at the acute hospital site and

was deemed unnecessary. An application to the Trinity College Dublin

(TCD), School of Computer Science and Statistics Research Ethics

Committee was then submitted and approval received following one

requested change. This study conformed to the conditions of the ethical

approval obtained (Appendix E).

3.7 Conclusion

This chapter has detailed the design of the research study and its

implementation. The methodology outlined assisted in answering the

research questions as described in the text.

The Mixed Methods approach (Creswell, 2009) used, allowing for the

collection of both quantitative and qualitative data and also data from a

variety of sources increased the validity of the data and findings.

Page 77: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

59

The results of all three stages are presented in the following chapter. While

the scope of this research did not involve the implementation of all

improvements some initial changes have been made and the impact on the

baseline data and other measures will be closely monitored going forward

(section 5.4).

Page 78: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

60

CHAPTER 4

RESULTS

4.1 Introduction

This chapter presents the quantitative and qualitative data collected by the

researcher. Baseline data and the process maps including a brief narrative

of each map are presented initially. Thereafter, data from the semi-

structured interviews and focus group are presented.

As outlined in chapter 3 data from all three stages of applying the process

improvement methodology; process mapping, semi-structured interviews

and the focus group was reviewed and validated by participants which

added to its validity given that one researcher carried out each stage

independently.

Throughout this chapter numbers I1,2,3 etc. refer to the suggested

improvements and/or the point in the process map to which the suggested

improvement applies, as identified in this research. These numbered

suggested improvements are listed in table 5.1 in section 5.3.2. They are

ordered in the table starting with the suggestions whose implementation is

complete or further advanced. This is an attempt to add clarity for the

reader regarding which suggested improvement/point in the process the

researcher is referring to.

4.2 Baseline data

As outlined in Chapter 3, as part of this study baseline data was collected.

The baseline data gives an indication of department throughput, numbers

waiting and time to wait, unanswered calls and estimated paper and storage

costs and is outlined in the tables and text below. As outlined by Ben-

Tovim, et al. (2008) data is an important part of any process improvement

initiative and the measures used need to be important to patients, the

organisation and the health service in general. The data chosen impacts all

three aspects with the patient at the centre.

Page 79: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

61

Table 4.1 illustrates the number of referrals, number of new and return

patients seen and the waiting time and number of patients waiting per

month for each of the two specialties under study. The DNA for both

specialties is also outlined.

4.2.1 Throughput

Table 4.1 Throughput (average per month in 2012)

Orthopaedic Rheumatology

Referrals 170 46

New patients seen 140 27

Return patients seen 422 104

New to Return ratio 1 : 3 1 : 4

Number of patients on

the waiting list

46 38

Waiting time for

patients

6 weeks 5 weeks

Did Not Attend (DNA)

rate

9% 7%

As illustrated in table 4.2 the clerical staff retrieve the physiotherapy notes

and make up and file away the notes of patients attending for the first time

(new patients) each day. The physiotherapists file away the notes of all

patients returning for a second or subsequent appointment (return

patients). See process map 4.11 in the next section for timings on this

section of the process.

Page 80: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

62

4.2.2 Retrieval and filing of physiotherapy notes

Table 4.2 Physiotherapy notes retrieval and filing (average per month)

Number of physiotherapy notes

clerical staff retrieve monthly

526

Number of physiotherapy notes

physiotherapy staff file monthly

526

Number of physiotherapy notes

clerical staff file monthly

167

Number of new sets of

physiotherapy notes made up by

the clerical staff monthly

167

Table 4.3 illustrates the high volume of calls that the clerical staff have to

deal with and highlights that 20% of calls are unanswered (I3). Calls to the

department are mainly from patients to (1) cancel their appointment (2) to

book an appointment (3) to determine where they are on the waiting list

and (4) how long they will wait.

4.2.3 Phone calls

Table 4.3 Phone calls (average per month in 2012)

Number of calls in and out of the

physiotherapy outpatient’s main

reception

2760

Average time per call 63 seconds

% of calls that were unanswered 20.46%

Page 81: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

63

4.2.4 Costs of paper and storage

Each set of physiotherapy notes has an average of 8 pages. This

includes the referral, a front sheet, a pre-printed assessment sheet, a

database and blank sheets for SOAP notes (see figure 4.3).

This paper along with printing components costs an average of

€2,220 per annum.

Appointment cards cost an average of €145 per annum.

Text messaging has no on-going cost (Ref. IT department)

Active physiotherapy notes are stored in a shelving unit with a

tambour door. Each set of physiotherapy notes has its own cardboard

file which is recycled so there is a negligible cost involved.

Physiotherapy notes that have been discharged are filed in the

current and then old archive. Notes are destroyed after 8 years and

the filing cabinets are recycled so there is a negligible cost involved.

Source of baseline data:

Phone usage data is automatically generated

Numbers of new and return patients is a monthly report generated by

the IT department based on data inputted to the PAS at the point of

patient registration

Paper costs; actual price comes from the SAP requisitioning system

and the overall cost was manually calculated

Number of referrals is counted manually

Waiting numbers and times are counted manually

4.3 Process Maps

The methodology used for the observation and process mapping stage is

outlined previously in section 3.4.1. The researcher believes that

documentation of the processes through observation by the researcher

rather than staff outlining the processes was an accurate representation. As

outlined by Unertl, Weinger and Johnson (2006), staff may have difficulty in

Page 82: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

64

providing a complete description of their processes because they are

immersed in the work. Use of a single researcher also eliminated intra

observer bias. As outlined previously by Crandall, et al. (2007) attention to

detail in the lower level maps is important to determine how to improve

existing processes and how best to integrate healthcare IT into processes.

The outputs of the observation stage are depicted in the process maps on

the following pages. Overall the process maps clearly indicate that this is a

very busy department with very complex processes producing a high

volume of documents and data which are accessed from a variety of

repositories (see figure 4.3 and tables 4.4, 4.5 and 4.6). When the maps

were documented some opportunities for improvement were visible to the

researcher; the need to simplify, standardise and make better use of

existing IT systems.

The process maps presented are those based on the observations that the

researcher carried out. As outlined in sections 4.4 and 4.5 some

clarifications were sought on steps in the process maps, both during the

semi-structured interviews and at the focus group, but the researcher did

not adjust the maps accordingly but did take note of all clarifications

requested (see section 4.5).

During the observation and process mapping stage some opportunities for

improvement emerged and it was agreed that these changes should be

carried out (Just do it! in Lean Thinking which might be more akin to action

learning than a case study). These opportunities included the need to clarify

the policy of booking new patients into return patient slots for all staff (I1)

and standardisation of the notations for the body chart diagram (I2). These

changes are not reflected in the initial background information or the

process maps as the researcher thought it best to clearly demonstrate the

starting point of the study.

The process maps are now outlined. Figure 4.1 outlines the high level

process map broken down into the key blocks that make up the patient

Page 83: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

65

journey from referral to discharge. The separation into blocks emerged

naturally with the iterative construction of the process maps between each

observation session. Blocks A-D are detailed in figures 4.4 through 4.10.

Figure 4.2 is an overview of key repositories of patient information. Figures

4.4 to 4.10 are lower level process maps of the blocks outlined in the high

level map (4.1). Figure 4.11 outlines the process for filing and retrieval of

physiotherapy notes and figure 4.12 clinical documentation and information

access during the patient attendance. Tables 4.4, 4.5 and 4.6 outline

documents and data created and information accessed. Each is described in

the following sections. More detail on each of the notations outlined on the

process maps is available in Appendix F.

Page 84: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

66

A Referral Triage and

Management

Internal Referrals from Hospital Consultants

External Referrals from Other

Hospitals and GPs

BWaiting List

Management and Appointment

Booking

CPatient Attendance

DPatient Discharge &

Referral Onwards

Internal Referrals from Hospital

physiotherapists attending

consultant clinics

1 Documents

3 Information

Accessed

2 Data

Documents, Data and Information Flow

Patient Non-Attendance

Community or Local Hospital

RescheduleAppointment

DNA first appointment or appointment not rescheduled within 2 weeks

Follow-up appointmentneeded

Figure 4.1 High level process map

Page 85: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

67

As illustrated in Figures 4.2 and 4.3 information is stored in a number of

locations many of which do not join up together leading to multiple points of

data entry (some of which are paper-based and some electronic) and

storage and much duplication. Access to the IT systems is limited by the

number of computers available and accessing any information involves

movement of staff and/or paper.

Page 86: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

68

PAS

PhysiotherapyNotes

EPR

Monday

New Referrals Box

PhysiotherapyReferral

PhysiotherapyReferral

PT REF

Referrals database

Old Archive

Waiting List folders

Lists for each clinic

Active Notes

Clinic Name Alphabetically

Current Year Archive

DNAs Box

YellowAppointment

card

ConsultantCorrespondence to GP

PT NOTES

APPTCARD

WLFOLDER

Community database

COMM DB

REFSDB

NEW REF BOX

ACTIVE

DNA

CORR

CLIN LIST

OLD

CURRENT

KEY REPOSITORIES

Waiting ListNumbers

WL NUMBERS

DB

Figure 4.2 Key Data Repositories

Page 87: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

69

PAS

EPR

Monday

New Referrals Box

EPRPhysio

Referral

Referrals database

Old Archive

INTERNALEXTERNAL

PaperPhysio

Referral

PaperPhysio

Referral

Physio Notes

Physio triage trayTransport

Transport

Clerical tray

Triage &Transport

Data entry

Waiting List folders

Referrals in

Appointmentbooking

ReferralsPut in Patient

Paper AssessSheet

PaperDatabase& blank sheets

Print off PAS

FrontSheet

Physio Referral

Physio Referral

Remove

Clinic Lists

New file made up and file

Active Notes

Clinic Name

Alphabetically

Notes of patients per clinic

Current Year Archive

DNAs Box

Retrieve

Retrieve

After 8 years Destroy

Research or audit

Retrieve

Cancelled andNo contact in 2 weeks

discharge

Transported toPhysiotherapist’s desk

File

PatientDNA

No contact in 2 weeks

discharge

No further treatment required discharge

For community

Into Area Envelope

AccessedFor scans and blood results

Register

Handed

Appointment card

File

PlaceReferral

Complete

Discharge or update

letter

Entry

Printed

Retrieve

Outcome Measures

PhysioTools package for HEPs

ConsultantCorrespondence to GP

Accessed for more detail Accessed, completed

And put into notes

Accessed, printed And handed

to patient

Physio Notes

Figure 4.3 Data storage and access

Page 88: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

70

A6

Referral reviewed for triage

A5

Referral transported to main out-patient department

A9

Referral transported to main out-patient reception

Resource: Clerical staff

Av Task Time to complete steps A3, A4 and A5 for each referral = 10.5 seconds

Done in batches

Resource: Physiotherapist

Av Task Time to complete steps A6, A7, A8 and A9 for each referral = 39.38 seconds

Done in batches

A3

Referral lifted from printer

A4

Referral completed on EPR

A10

Referral data entered into Excel spread sheet

A11

Referrals separated

Resource: Clerical staff

Av Task Time to complete steps A10 and A11 for each referral =38.7seconds

Done in batches

AREFERRAL MANAGEMENT

AND TRIAGE

A2

Paper referral from external source

arrives

A1

Referral placed on EPR

A7

Triage category written on referral

A8

Code written on referral

A12

Community or local hospital referral?

YES

NO

To D Discharge

To B Booking

PhysiotherapyReferral

PhysiotherapyReferral

PT REF

Referrals database

Referrals database

REFSDB

Community database

Community database

COMM DB

Figure 4.4 Referral Management and Triage

Page 89: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

71

The process for referral management and triage (I4) was mapped in detail.

As outlined in section 2.5 it is important to map in detail at any bottlenecks.

This stage is an obvious bottleneck in the patient journey as referrals arrive

and patients wait for an appointment. As illustrated in Figure 4.4 referral

management and triage involves 9 steps, takes a mean of 88.6 seconds per

referral (n=35) and entails a lot of walking about for staff and movement of

paper from one place to another. The 9 steps in the process are purely to

determine the patient’s priority and to decide a physiotherapy diagnostic

code. This process takes up to 16 minutes (for orthopaedic and rheumatology

referrals only) of staff time each day and adds little value to the patient

journey apart from ensuring that those patients who are in urgent need of

physiotherapy are seen first. Referrals are triaged daily in batches which

causes a delay between receipt of each individual referral and the referral

going on to the waiting list and the patient actually receiving an appointment.

However, the researcher acknowledges that due to the significant amount of

movement, carrying out this process on each individual referral would

actually add to the time taken to complete the steps. An example illustrates

this clearly and highlights the amount of time wasted on movement of staff

and referrals. The mean time it took one of the clerical staff to complete

steps A2, A3 and A4 for 5 referrals was 20.71 seconds per referral whereas

this mean time reduced to 8.3 seconds per referral for a batch of 30 referrals.

Page 90: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

72

B (a) 5Ring the next patient

B (a) 2PAS reviewed to determine what free new slots are

available

B (a) 3Free new slots written on paper

B (a) 8Clinic lists reviewed to determine what

return slots are not filled

NEW APPOINTMENT BOOKING

B (a) 10Return appointment

booked

Resource: Clerical staffAv Task Time per appointment = 60.64 seconds

FOLLOW UP APPOINTMENT

BOOKING

B (a) – WAITING LIST MANAGEMENT AND APPOINTMENT BOOKING

B (a) 1 Manual waiting list folders reviewed

simultaneously with PAS

OR

From A

B (a) 9Follow-up

Appointment Required?

To D Discharge

B (a) 4Manual waiting list folders reviewed

B (a) 7Patients booked in to

all of the available clinic slots on the PAS

To C (a) Patient

Attendance

YES

NO

PAS

Waiting List folders

WLFOLDER

To C (a) Patient

Attendance

B (a) 6Patient self-

dischargeNO

YES

From C (a) Patient

Attendance

Figure 4.5 Waiting list Management and Appointment Booking

Page 91: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

73

The process map for waiting list management and appointment booking

(figure 4.5) shows a waiting list folder (WL folder). This is where all paper

referrals are stored. This manual folder exists despite most referrals

(internal consultant referrals make up 95%) already being on the EPR

system. This process follows on from figure 4.4 triage. As outlined

previously in table 4.1 (section 4.2) the timeframe from referral received to

appointment booking can be up to 6 weeks.

With regard to taking patients off this manual waiting list and ringing them

to book an appointment it is not clear who is responsible for this; all clerical

staff or one or if done on all or specific days? During the observation the

researcher noted that both clerical staff took on this duty while carrying out

multiple other tasks with multiple interruptions. As seen in the process map

there were two ways that the two clerical staff carried out this process one

of which appears more efficient than the other (B (a) 1 directly to B (a) 5)

(I12).

Staff did not seem to be clear on the expectation that all new slots were to

be filled 3 weeks in advance or what the guidelines are for booking new

patients into return slots (if they are vacant). The booking policy states all

new slots in the clinic templates should be filled 3 weeks in advance. It is

not in the booking policy but clerical staff understand that return slots can

only be filled with new patients 1 day in advance so they do this following

printing of clinic lists which leads to the patients getting an appointment at

very short notice. On the other hand, the physiotherapists said they are

happy for new patients to be booked into return slots 3 days in advance. As

the understanding of expectations and clarification on the policy was

required a decision was made to meet with staff and seek agreement on the

policy (Just do it!) (I1).

Clerical staff also said they could ring 20 patients and manage to make only

4 appointments and the question must be asked if this is an efficient use of

their time or if an alternative time or method for making appointments

needs to be considered. The time taken to book new appointments was not

Page 92: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

74

recorded as there were so many variations in understanding of the booking

policy and the process for booking that time did not allow for this to be fully

assessed and timed.

There was significant variation in the time taken to book a return

appointment; ranging from 28.7 to 124.9 seconds (mean 60.64 seconds

SD+/- 35.38 seconds) per patient (n=15). There were some reasons noted

for this variation including interruptions from other staff and interruptions

from phone calls. While the stopwatch was stopped while interruptions were

dealt with the staff member was obviously distracted on returning to finish

the booking.

Page 93: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

75

B (b) 13PAS checked to see

when patient was with consultant?

B (b) - WAITING LIST REPORTING AND QUERIES B (b) 6

Patient phones re referral status

B (b) 7Patient queried when

with consultant?

B (b) 8EPR reviewed

Referral placed?B (b) 11

Patient advised referral received

NO

B (b) 12Patient advised

no referral received and

patient referred back to

consultant

B (b) 8EPR reviewed

Referral placed?

YES

YES

B (b) 9Waiting list folders

reviewedReferral in there?YES

NO

B (b) 10Spread sheet checked

Referral entered?

NO

OR

B (b) 10Spread sheet checked

Referral entered?

NO

NO

YES

YES

To B (a) Booking

B (b) 3Numbers waiting manually counted

B (b) 1Management request

report of numbers waiting and waiting

time

B (b) 2Manual waiting list folders reviewed

B (b) 4Waiting time calculated for urgent and routine

referrals

B (b) 5Data entered on Excel

waiting list spread sheet

Waiting List folders

Waiting List folders

WLFOLDER

Waiting ListNumbers

Waiting ListNumbers

WL NUMBERS

PAS

EPR

Referrals database

Referrals database

Waiting List folders

Waiting List folders

WLFOLDER

REFSDB

Figure 4.6 Waiting List Reporting and Queries

Page 94: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

76

Figure 4.6 illustrates the process followed for calculation of numbers waiting

and waiting time. This process is completely manual.

An observation from this process map is to query why the manual process

of data collection occurs given that all of the data is inputted in to the PAS?

As explained in section 1.1 the referral is date stamped on the EPR system

and the appointment then booked on the PAS and these two systems do not

link up. As will be seen in the next sections (4.4 and 4.5) the question as to

why waiting list data cannot be calculated automatically was asked by some

participants at the focus group and by two of the interviewees (I5).

Figure 4.6 also illustrates that the process for answering a patient query is

not standardised and involves the checking of multiple systems storing

similar information (I13).

Page 95: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

77

C (a) 2

Patient arrives

C (a)PATIENT

ATTENDANCE

C (a) 4

Patient is registered as

a NEW attendance

C (a) 6

A front sheet is printed out

C (a) 8

Physiotherapy notes are made up

C (a) 3First

attendance?

YES

NO

C (a) 9Patient is

registered as a RETURN

attendance

C (a) 10Patient is

treated by the physiotherapist

C (a) 11Further treatment required

[based on clinical need]?

C (a) 1

Patient receives appointment

reminder

To C (c) Registration

YES

To B (a) Booking

To D Discharge

NO

From B (a) Booking

C (a) 7Department policies and

appointment card issued

PAS

PhysiotherapyNotes

PT NOTES

APPTCARD

From B (a) Booking

Monday

NEW REF BOX

C (a) 5

Referral is retrieved from

the new referrals box

Figure 4.7 Patient Attendance

Page 96: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

78

The process that occurs when the patient attends the department for a new

or return appointment is outlined in figure 4.7. Information gathered and

accessed by the physiotherapist at step C (a) 10 is illustrated further in

figure 4.12. Similar to the triage process outlined in figure 4.4 there is

much movement and gathering of pieces of paper for a new patient

attendance (I11). The physiotherapy notes are not made up in advance of a

new patient attendance to avoid time wasting in the case of non-

attendance. However, as can be seen some of the steps, for example,

registration at C (a) 4 (new) and C (a) 9 (return) do not add value to the

patient’s journey while this step does allow for automatic calculation of

numbers attending. Step C (a) 6, leads to the printing of a front sheet and

it is unclear what this is actually used for (Table 4.4) (I6).

Registration is mapped in more detail in figure 4.8. The researcher

acknowledges that there is more than one step in each box and would like

to state that this section of the process map was represented

diagrammatically purely to demonstrate the time taken to complete patient

registration of a new and return patient. The mean time taken to register a

new patient was 62.36 seconds (SD +/- 23.23 seconds) with an extra 41.52

seconds (SD +/- 12.32 seconds) on average to gather up the pieces of

paper needed to make up the physiotherapy notes (n=7).

The mean time taken to register a return patient (I10) was 12.6 seconds

(SD +/- 16.47 seconds) (n=13). Therefore, a significant amount of time is

taken to register patients and as stated above this adds no value to the

patient as it purely acknowledges their arrival but it does allow for

automatic calculation of the number of attendances. Of note, if a patient

arrived without their yellow appointment card for a return appointment this

caused delays in the registration process as there are important details such

as the clinic code, consultant’s name and physiotherapist’s name written on

the yellow card and these details are required by the clerical staff to register

the patient (I7). One example clearly illustrates this where the patient had

no yellow card, was unclear who their consultant or physiotherapist were

Page 97: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

79

leading to the registration taking 56.4 seconds to complete. The

physiotherapist/consultant details are currently not in the text message

reminder sent to patients (step C (a) 1).

During patient attendance clerical staff are engaged in multiple

simultaneous tasks which can lead to many interruptions. As seen in the

study by Chand, et al. (2009), any external disruption while registering a

patient lengthened the registration time. A consistent example of this was

interruption by phone calls, whereby the registration process was

interrupted and the phone call answered and then put on hold while the

registration process was completed.

Page 98: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

80

Each time the patient attends they are registered on the PAS

When the patient arrives in for their appointment they are registered to the relevant clinic on the PAS with

the clerical staff confirming the patient’s details (e.g. mobile phone

number for text reminders) and outlining the department policies.

Resource: Clerical staff

Av Task Time for return patient registration = 12.6 seconds

Resource: Clerical staff

Av Task Time for new patient registration = 62.36 secondsNew Reg

Return Reg

A front sheet is printed out on the first registration (outline of appointments in

hospital and personal details) and physiotherapy notes are made up which

include the referral, a peripheral or spinal assessment sheet and continuation sheets

for progress notesThe clerical staff then walk to deposit the

notes in the main physiotherapy outpatient department

Resource: Clerical staff

Av Task Time for each set of new notes = 41.52 seconds

From C (a) Patient

Attendance

PAS

PhysiotherapyNotes

PT NOTES

C (c) REGISTRATION

Figure 4.8 Registration

Page 99: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

81

C (b) 2DNA automatically registered on the

PAS

C (b) 1Patient does not

attend

C (b) 3First

appointment

YES

C (b) 4The patient makes

another appointment within

two weeks

NO

NO

YES

C (b)PATIENT NON-ATTENDANCE

C (b) 5Patient rings to cancel

C (b) 8This is the third

consecutive cancellation recorded

on the PAS

C (b) 7Immediate

rescheduling

To D Discharge

To C1 Patient

Attendance

YES

NO

YES

NO

From B (a) Booking

PAS

C (b) 6Patient self-

discharge

NO

YES

Figure 4.9 Patient Non-Attendance

Page 100: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

82

Figure 4.9 illustrates the process for non-attendance. Overall the patient

non-attendance block of the process seems to work well with the

department receiving automatic reports from the IT department on the

number of cancellations and DNAs on a monthly basis and actions taken to

try to improve the rates. Of note, when it comes to retrieving the notes of

patients who have cancelled and not made subsequent appointments the

process involves the physiotherapist going through all of his/her active

notes and subsequently removing the notes of these patients; a manual

process (see step E7 in figure 4.11) (I11).

Page 101: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

83

D - DISCHARGE AND REFERRAL ONWARDS

From ATriage and

Referral Management

D1Community Referral?

D5Identify community care area

D6The patient is

informed

YESD3

Print off relevant details from EPR

D2Local Hospital Referral?

NO NO

To A Triage Or B (a) Booking

YES

D4Post

To D Discharge

To D Discharge

From C (a)Patient

Attendance

From C (b)Patient Non-Attendance

D9Referrals/

physiotherapy notes are filed away in the current year archive

NOTE THERE IS NO ENTRY

MADE ON THE PAS OR EPR THAT THE

PATIENT HAS BEEN

DISCHARGED

D8Patient Discharged is

written on the referral/

physiotherapy notes

PhysiotherapyNotes

EPR

PhysiotherapyReferral

PhysiotherapyReferral

PT REF

PT NOTES

D7Details entered into community

databaseCommunity

database

Community database

COMM DB

Figure 4.10 Discharge

Page 102: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

84

Figure 4.10 illustrates the process carried out when the patient is to be

discharged from physiotherapy. The patient may be referred to their local

hospital or community care area at the point of triage. This is a paper-based

process (I9). The patient is informed that they have been referred to their

community care area but not if referred to their local hospital so there is no

standard process. There is no entry made on the EPR or PAS that the

patient has been discharged. This is only written on the physiotherapy

referral/notes which are stored in the physiotherapy department and not

accessed by others. An entry on the PAS or EPR would allow internal

referrers to see that the patient has completed their physiotherapy (I11).

Page 103: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

85

E 1Physiotherapists file away return patient

notes daily

E 2Clerical staff file away

new patient notes daily

E 3Clerical staff retrieve

notes for patients due to attend the next day

daily

E 4Clerical staff archive notes that have been

discharged as time allows

Resource: Clerical staff

Av Task Time for one set of notes = 10.44 seconds

Done in batches

Resource: Clerical staff

Av Task Time for one set of notes = 16.3 seconds

Done as batches

E RETRIEVING AND

FILING PHYSIO NOTES SEE DOCUMENTS

E 5Notes are retrieved for medico legal reasons

from active files, current year and/or old

archives when requested

E 6Notes of DNAs held in DNA box for 2 weeks

then discharged if appointment not made

E 7If appointment

cancelled and no follow-up needed notes are

removed from the active notes

immediately and discharged

E 8Notes of Cancels left in

active files and then discharged if

appointment not made within 2 weeks

To C (b) Patient Non-Attendance

To C (b) Patient Non-Attendance

To C (b) Patient Non-Attendance

Active notes are stored by clinic code alphabetically

Active notes are stored by clinic code alphabetically

PhysiotherapyNotes

PT NOTES

Lists for each clinic

CLIN LIST

Current Year Archive

CURRENT

DNAs BoxDNAs Box

DNA

Old Archive

OLD

Active Notes

Clinic Name Alphabetically

ACTIVE

Resource: Physiotherapist

Av Task Time for one set of notes = 10.4 seconds

Done in batches

Figure 4.11 Retrieval and Filing of Physiotherapy Notes

Page 104: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

86

As outlined in Figure 4.11 a significant amount of time is spent by both the

clerical and physiotherapy staff on the retrieval and filing of notes on a daily

basis (I11). Each set of notes takes approximately 10 seconds to retrieve

(n= 18) and 10 seconds (n = 21) to file away. Archiving notes takes over

16 seconds per set of notes (n = 12).

In figure 4.12 we see that a significant amount of time is taken up

accessing information during the patient attendance; more than 99 seconds

(n = 7) of the physiotherapist’s time each visit is taken up searching for

information to assist the decision-making process or give to the patient to

aid recovery; exercise sheets, outcome measures, x-ray and scan results

and other correspondence (see table 4.6 for further details) (I11). During

the time the physiotherapist accesses this information the patient waits

alone in the cubicle. While it is acknowledged that all steps in this process

add value to the patient in terms of treatment planning and goal setting,

information could be more easily and efficiently accessed.

Page 105: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

87

On their first attendance the physiotherapist

takes an extensive history from the

patient

Red flag questions are used to assist in

decision-making/alert the physiotherapist to

extra/particular precautions

Each time the patient attends the physiotherapist documents in the paper physiotherapy notes in the

form of a SOAP (Subjective, Objective, Analysis and Plan) note

Home exercise programmes (HEPs)

are printed off a separate PhysioTools

package if individualised for a

patient or taken from a filing cabinet where they have been pre-

printed

If the Physiotherapists wants to show the patient their x-

ray/scan result as part of management they must leave

the cubicle where they are treating the patient and log

on to the EPR to print this off

A body chart is used to document pain site and

intensity

For Rheumatology patients there is a correspondence

section on the Rheumatology G Drive

where relevant letters and referrals can be viewed to

aid decision making

Outcome measures are often used at the initial visit and subsequently to review

the patient’s progressThose used are mainly patient self-reported

questionnaires and are retrieve in paper based copies from the filing

cabinet as needed

Resource: Physiotherapist

Av Task Time to gather information per patient visit = 99.54 seconds

CLINICAL DOCUMENTATION AND INFORMATION RETRIEVAL

From C1 Patient

Attendance

To D Discharge

To B Booking

CORR

PhysioTools package for HEPs

PhysioTools package for HEPs

EPR

Outcome Measures

Figure 4.12 Clinical Documentation and Information Access

Page 106: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

88

The following tables outline the documents and data created and information accessed by the clerical and physiotherapy staff

during the patient’s journey.

Table 4.4 Documents created

Document Daily work list Physiotherapy Referral

Yellow Appointment

Card

Front sheet Physiotherapy Notes including file

made up to hold them

Discharge Letters Report to referrer

Type

Paper EPR Cardboard Paper Paper File is cardboard

Paper E-mail for Rheumatology patients (internal

referrals) Paper to all referrers Telephone calls to all

referrers (?data)

When accessed?

Daily print from PAS for next day

Lifted from printer on referral

Reviewed by physiotherapist

Every attendance

On first attendance

Each time patient attends

Not routinely done Completed once on discharge

Written by physiotherapist and posted internally to

medical records chart room for filing

As needed

Where stored?

Paper is discarded once the clinic date

has passed

In standard folders until appointment

booked In “new patients” box

when appointment booked until patient

arrives in In physiotherapy

notes

With patient In the front of the physiotherapy

notes

In notes storage area as long as

patient continues to attend

In filing cabinets on discharge for 8

years Notes holders are

recycled

Original filed in medical chart Copy filed in physiotherapy

notes

Copy of letters kept in physiotherapy notes

Note made of phone call E-mails kept separately

Page 107: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

89

Document Daily work list Physiotherapy Referral

Yellow Appointment

Card

Front sheet Physiotherapy Notes including file

made up to hold them

Discharge Letters Report to referrer

What

used for?

For each physio

to know which patients (whether new or return) are arriving on a given

day. The physiotherapists document any

DNAs or Cancels on the paper worklist?

Details on referral used to decide clinical

priority (triage)

Details from referral transcribed into Excel

spread sheet

Appointment Time

Clinic Code

Physiotherapist’s name

All written on it

Unclear All clinical documentation relating to the

patient

Retrieved for research, audit and

medico legal purposes

To update referrer on patient’s status on discharge

from physiotherapy

No discharge letters sent since Nov 2012 due to

reduced clerical capacity

To highlight concerns to referrer

To give update

Page 108: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

90

Table 4.5 Data created

Data

created

Waiting List Excel Spread Sheet -

database of patients waiting

Waiting List Excel Spread Sheet -

of numbers waiting and time waiting

Reports from the PAS

Number of new, return, DNAs and cancels

New and returns per consultant/specialty

Excel spread sheet outlining all

community referrals

Type

Excel

Excel

On-line report run by the IMS

department

Excel

When accessed?

All referrals manually transcribed

into database Accessed if patient rings department

Numbers counted manually and

inserted monthly

Monthly

Monthly

Where stored?

On department drive

On department drive

On department drive

On department drive

What

used for?

To profile patients attending

To confirm referral received and possible length of wait for patients

phoning the department If referral sent on to community or local hospital this is recorded here

To give number of referrals and

numbers in each category of wait to HSE

New and returns needed for HSE

CompStat New, returns, DNAs and cancels needed

at corporate level Used for annual reports, service plans,

business cases

Knowledge of referrals sent out

and demand for community services

To show patient seen in most appropriate setting

Page 109: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

91

Table 4.6 Information Accessed

Information Accessed

Home exercise programmes (HEPs)

X-ray/scan result

Further correspondence relating to the patient

Outcome measures

The Evidence Base or clinical guidelines

Type

Paper

EPR Report and image

Scanned letters or letters saved electronically

Paper or soft copy

Paper or soft copy

When accessed?

While the patient is attending

Prior to or while the patient is attending

While the patient is attending

While the patient is attending

In between the first and second patient attendances

Where

stored?

Pre-printed or in most cases individualised and printed from a PhysioTools package

EPR

EPR and specialty drive

Paper based in filing cabinet or electronic on department drive

On-line or paper based in filing cabinet

What

used for?

To give to patient to carry out independent exercise

To aid decision making and treatment planning

To aid decision making and treatment planning

To aid goal setting and determine progress

To aid decision making and treatment planning

Page 110: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

92

4.4 Semi-structured interviews

As previously outlined in section 3.4.2 three semi-structured interviews of

key physiotherapy informants who have implemented process

improvements and/or health information technology were undertaken. The

interviewees reviewed the detailed process maps, outlined where

improvements could be made, gave clear suggestions as to what those

improvements would look like and their potential benefits and finally they

gave some advice about possible challenges and how to manage them.

The three experts interviewed confirmed that they were familiar with

process maps. All found the diagrams and notations very clear. The

overview/high level workflow and the documents, data and information

accessed tables were found to be very useful.

Prior to outlining the process improvements suggested at the interviews an

overview of opinions expressed by the interviewees on the process maps

and methodology used is presented.

It was suggested that the diagrams could be used to explain the workflow

to others who do not work in the department under study. They could also

be used in another area or across disciplines as a good starting point for

similar work.

With regard to the methodology used to map the workflow i.e. observation

and validation with staff observed; it was suggested by one of the

interviewees that staff could have been asked to input directly into the

workflow. This is known as a “Kaizen event” in Lean terminology and would

usually involve freeing staff up for 3-5 days to map the process. However, it

was acknowledged that this would be hard to do while maintaining a

service. It was also suggested that ideally the patient’s viewpoint should

be included.

All clarifications that were sought related to the department’s activity and

definitions; the definition of a new patient, the number of new and return

Page 111: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

93

patients seen by each therapist daily, the monthly demand and an

understanding of possible reasons that there is a waiting list.

4.4.1 Suggested Improvements arising from interviews

There follows an outline of suggestions for improvement which emerged

from the interviews. These are grouped in the blocks (A-D) outlined in the

high level process map (see figure 4.1).

There was an emphasis on using the functionality in existing systems to

their fullest extent and in particular the use of simple IT methods of

communication such as text messaging and e-mail.

A – Triage and Referral management (Figure 4.4)

In general, comments were that there is too much movement of paper and

people and too many “hand-offs”. There is duplication of work when

transcribing patient details from the printed referrals to the Excel spread

sheet as all details are already contained in the electronic referral. There

could also be a clinical risk in transcribing data from the referral to the Excel

file. The risk of storing all of the referral and waiting list data on a general

drive in Excel was also highlighted. It was queried if this was safe and

secure, how many staff had access and could the file be accidentally

deleted? It was also stated that an Excel file could become corrupt over

time, with many changes being made leading to loss of data. Other issues

with Excel and having several individuals accessing and updating a file is

that there is no way of knowing who updated which parts and there is no

audit trail; this is after all patient data.

Suggested Improvements:

Upgrading the current EPR to allow for everything to be done on one

system (Not Possible).

Clerical staff triaging by giving clerical staff clear guidelines on how to

triage. This would eliminate the movement of paper and people and

reduce the time taken for this part of the workflow even if this

Page 112: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

94

continued to be done on paper. However, ideally triaging should be

done electronically (I4).

The accuracy of coding at this point in the workflow was queried and

it was suggested that this should be done at a later point, ideally

discharge. To make improvements to patient outcomes it is important

to look back at the input each patient was given. If coding were to

happen at discharge the input for each of the discharge codes could

be reviewed and this could be used to determine changes required to

service provision or to improve outcomes (I14).

Use of formulae in the Excel file to assist with calculation of waiting

times (see B (b) below).

B (a) – Appointment Booking (Figure 4.5)

The booking of appointments needs to be standardised to ensure efficiency

in the process and so reduce unnecessary waiting for patients. A lot of time

is wasted phoning patients with appointments and in many cases staff do

not received an adequate response.

Suggested Improvements:

The appointment booking process should be standardised (I12).

Clarification of the booking policy regarding booking new patients into

return slot (I1).

Sending an appointment by text and giving the patient an option of

Yes/No to accept should be explored. This still gives the patients the

option to look for an alternative yet eliminates the need for the

clerical staff to do so much ringing (Not Possible).

A short waiters list – of patients who are happy to be contacted at

short notice for those last minute appointments [next day

appointments] could be explored (I15).

Page 113: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

95

B (b) – Waiting list data (Figure 4.6)

This involves too much manual counting and too much paper. It was

queried why this process is manual when all of the information needed to

calculate waiting times gathered in the Excel referrals spread sheet and so a

formulae could be used to assist. It was also queried why if the bookings

are carried out in the PAS why this information couldn’t be drawn down

from there? The researcher explained that the referrals are generated in the

EPR (and date stamped with the date of referral) but there is no connection

between the EPR and the PAS that would allow for date of referral (EPR) to

date appointment booked (PAS) to be calculated.

Suggested Improvements:

Waiting list data should be generated electronically. This would

increase the reliability and accuracy of the data. An electronic system

works off an algorithm therefore; there is consistency with calculation

(I4).

C (a) – Patient attendance (Figure 4.7)

Suggested Improvements:

Use a self-registration booth (I10).

Electronic documentation would get rid of make-up of notes (I11).

Self-appointment making booth for return appointments (I16).

Return appointments could be confirmed by text one day in advance

as the current 5 days is too long (I8). The patient should have the

option of replying to this text. The reply can be set up to go to the

department’s e-mail and be checked each morning. Text speak can

be used if characters limited. All texts could be embedded in each

individual patient’s record.

Text messaging for mass cancellation of appointment, for example if

a clinician is sick (Not possible).

Page 114: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

96

Stop using appointment cards as patients receive a text message

(I8).

Draw a body chart diagram and scan it in to the EPR to attach to the

patient record (I11).

Take photos for certain evaluations to engage patients and as a

motivator for patients. A photo taken with a mobile phone which can

be uploaded and attached to the patient’s record on the system has

huge advantages (I17).

Using the camera in a tablet or laptop would be very helpful. The

photo could then be uploaded to the patient’s record (I17).

Simple outcome measures could be embedded into the patient’s

record. This is motivating for the patient and helps the

physiotherapist to review progress (I18).

D – Discharge and onward referral (Figure 4.10)

Suggested Improvements:

Clarity around what services are actually available in the HSE is a

challenge. There should be one national database of services. It is

acknowledged that this is a wider issue for the health services than

the department under study (I19).

Have an agreement with referrers that a discharge summary is only

sent if requested (I20).

Links with hospitals and other agencies could be by secure e-mail

communication (taking into account data protection issues) (I9).

4.4.2 Potential Benefits as identified by interviews

The interviewees were then asked to identify the potential benefits of their

suggested process improvements. The benefits are not broken down by

block in the process map (as in many cases they apply across the

continuum of the process map) but rather how they relate back to the

Page 115: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

97

quality aims outlined by the IOM (2001) and those outlined by the HIQA

standards (2012) whereby the patient is at the centre and the care provided

is safe, timely, effective, efficient and equitable with IT and information

enabling improvements.

Overall the benefits of electronic recording were identified as

enormous.

The electronic record gives a much better holistic view of patients.

The ability to look back and see the records of patients who

consistently attend assists greatly. If the usual “recipe” doesn’t work

for these patients this may be a good indicator that the patient needs

to be referred onwards.

• Mass cancellation by text saving significant admin time

Reduce hand-offs between staff

Reduce duplication of effort

Clarity of process, roles and responsibilities

Reduce risk of data loss and errors of data entry

Savings on postage – one interviewee said she used to buy 100

stamps per month now she wouldn’t use 100 stamps in 4 months

Savings on purchase of appointment cards - purchased 10,000 cards

about 2.5 years ago and hasn’t used very many of them

Making the most of functionality and systems already available

reduces cost

Stats can be available as needed

Improve accuracy and safety of data

4.4.3 Perceived Challenges as identified by interviews

During the interviews very few challenges were highlighted and in fact the

two interviewees who have undertaken implementation of IT projects were

very positive about this change but did stress the importance of change

management and staff buy-in. The main exception to this was the challenge

Page 116: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

98

in determining what services are actually available in the HSE. As outlined

above this impacts more than the department under study.

Two challenges that were specifically mentioned were finding the correct

solutions to electronic triage and documentation and the possibility of

asking staff to take on non-traditional roles such as the suggestion that

clerical staff could triage.

Some key success factors that were highlighted were:

Staff buy-in

A phased approach making small changes

Clarity on benefits

Selecting a clinical champion who is “aware of the mood on the

ground”

The necessity to carry out a stakeholder analysis which should

include patients and referrers

Administration staff may be threatened by any changes so again stressing

the importance of change management. It is important to state the

positives to those who feel threatened; improved throughput of patients,

ensuring the patient is at the centre and reducing/eliminating risks in the

process (for patient and staff).

Finally it is important to understand that there will always be an element of

discord and that sometimes it’s important to just keep focussed.

4.5 Focus Group

Before presenting the results of the focus group the researcher would like to

outline again the overall goals, of any process improvement, that were

agreed at the focus group. As outlined in section 3.4.3 these goals were

presented as a starting point by the researcher at the beginning of the focus

group and participants were encouraged to add/remove any they didn’t

agree with. No changes were made.

Page 117: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

99

Goals:

Improve the patient journey and the importance of keeping the

patient at the centre

Boost staff morale

Reduce non-value added activities, for example, waiting, duplication

and movement

Reduce non-clinical steps for the physiotherapists

Improve ease of access to information – both when the patient is

present (to review previous notes) and to review outcomes and carry

out research

The methodology used for the focus group is outlined in section 3.4.3.

Nineteen improvements were suggested which the participants

subsequently prioritised. The top 10 items are outlined in table 4.7 on the

following page.

Page 118: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

100

Table 4.7 Top Ten Suggested improvements identified at the focus group

Suggested improvements identified at the focus group

1. Automatic printing of the "Front sheet" from the PAS for new patients should stop as the information contained therein is not used for anything (I6)

2. Clerical staff to give physiotherapy notes directly to new patients and ask the patient to give them to the physiotherapist to avoid excessive walking (I21 )

3. Edit the text message for each clinic (on OPRS) to ensure the essential details required by the clerical staff at registration are on the text (I8 )

4. Triaging of referrals on the PAS (I4 )

5. Standardisation of the process of actually ringing the patients and booking their appointments on the PAS (I12)

6. Filtering of patient calls by extending the functionality used on the current phone system (I3)

7. Using the PAS for triage would allow for direct booking of appointments from the waiting list (I4 )

8. Electronic clinical documentation on the EPR (I11)

9. If a patient rings looking for an appointment and no physiotherapy referral has been received in the physiotherapy department but the patient has obviously had a recent appointment with the consultant (this can be seen on the PAS) generate a physiotherapy referral and offer the patient an appointment (I13 )

10. Electronic community/local referral (I9)

As outlined in table 4.7 there was an emphasis on (1) simplifying (2)

reducing steps staff need to take and (3) steps in the process that don’t add

value to the customer (4) standardising processes and (5) more extensive

use of the current IT systems.

During the focus group an unexpected energy among the staff involved was

observed, with much discussion and teasing out of ideas. Of interest, it was

not specifically the IT staff that suggested the possibilities of more

extensive use of existing IT systems.

During the regrouping session there was a significant amount of discussion

and some healthy conflict about some suggestions and their feasibility. For

example, the idea that the referring consultant could refer directly to the

Page 119: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

101

community, suggested by one participant, rather than referring to the

internal physiotherapy department was discussed at length. This would

reduce the steps the referral (and the patient) goes through to get to the

community physiotherapy services and would ensure the patient is seen in

the most appropriate setting. It was suggested that this would involve

significant training, change management and the group determined it was

best to stay within the locus of control initially.

Perceived benefits outlined at the focus group involved reducing the number

of steps and hence the time frame to complete processes all of which would

indirectly impact on the time patients have to wait for an appointment and

the time the physiotherapist spends in the cubicle with the patient on direct

patient care. Other benefits related to the introduction of electronic clinical

documentation and included (1) access to the patient’s previous records (2)

data accuracy and more reliable profiling of patients (3) reduction in paper

with associated costs and environmental impact.

All benefits relate back to the quality aims outlined by the IOM (2001) and

those outlined by the HIQA standards (2012) whereby the patient is at the

centre and the care provided is safe, timely, effective, efficient and

equitable and IT and information are used to enable improvement.

Some fear was expressed about getting rid of all paper when electronic

clinical documentation was discussed and the importance of having a

contingency plan in the event of systems going down. Otherwise no other

challenges were highlighted.

Some ideas that were not suggested during the focus group but were noted

as possible improvements by the researcher during the observation phase

were: (1) a system similar to “Choose and Book” in the UK whereby the

referrer can book the patient directly into a physiotherapy appointment slot

(I22), (2) asking patients to complete outcome measures prior to seeing the

physiotherapist (as many are self-reported) (I23) and (3) the use of

Page 120: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

102

computerised clinical decision support (I24) with electronic clinical

documentation.

Some comments were made by participants when they returned their

prioritised list; one participant stressed that she didn’t believe that

electronic clinical documentation would reduce time the physiotherapist

spent on documentation, some participants prioritised what they felt were

“quick wins” for staff and the patients.

A few gaps were noted in the workflow by the researcher and by

participants at the focus group. These are outlined as follows:

Time spent calculating waiting list times

Time spent by clerical staff ringing and booking patients

Is community or local referral recorded on the referrals spread sheet?

YES

Is the fact that an appointment is given to a patient ever recorded on

the referrals spread sheet? NO this is captured as an appointment

allocated on the PAS

If the patient is late what happens? One participant suggested it

depends on many factors; clinical need, how late, clinical staff on the

particular day

4.6 Conclusion

The methodology used in this study assisted in answering the research

questions. The question of which process improvement methodology to use

was answered through the literature review with the researcher identifying

a process improvement methodology and tools based on the principles of

Lean Thinking. The baseline data, process mapping, interviews and focus

group all answered the questions as to which processes should be improved

and what those improvements could look like. The literature review,

interviews and focus group outlined the potential benefits and some

perceived challenges of the suggested improvements.

Page 121: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

103

A more detailed discussion on how this methodology assisted in answering

the research questions will be outlined in the next chapter. As will be seen

there was significant overlap in the suggested improvements that emerged

from the interviews and focus group.

Page 122: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

104

CHAPTER 5

ANALYSIS AND DISCUSSION

5.1 Introduction

This chapter will now revisit the research questions and give more detail on

answers this research has provided. It must again be acknowledged that the

scope of this research did not involve implementation of the suggested

improvements. However, some suggested improvements have been

progressed and others are planned (section 5.4). Measurement of the

impact of improvements that have been progressed (Figures 5.2 to 5.4) and

those that will take place in the future will need to be continuous.

5.2 Research questions

Main Question (MQ):

How can processes be improved in a physiotherapy outpatients

setting?

Sub questions:

What process improvement methodology is appropriate to apply in

the physiotherapy outpatient setting? (SQ1)

Which processes should be improved? (SQ2)

How should processes be improved? (SQ3)

What are the potential benefits of any suggested improvements?

(SQ4)

What are the perceived challenges of any suggested improvements?

(SQ5)

5.3 Findings

As outlined in chapter 4 the methodology used in this study assisted in

answering the research questions posed. The answers to the sub-questions

will be presented first before returning to the main research question.

Page 123: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

105

5.3.1 What process improvement methodology is appropriate

to apply in the physiotherapy outpatient setting? (SQ1)

In order to answer the overall research question, the researcher needed to

first look to the literature to determine which process improvement

methodologies are prevalent in healthcare and which methodology and tools

would be appropriate for use in the study setting.

From the literature review the researcher identified a process improvement

methodology and tools based on the principles of Lean Thinking as the best

fit for the study setting. Lean Thinking principles are simple to understand,

yet are very powerful at exposing waste. Before commencing this research,

issues of waste, lack of standardisation and the need for improved efficiency

due to reduced clerical capacity (section 1.1) were identified by the

researcher. In section 2.3.1 we learned that Lean Thinking as a

methodology is often selected where an organisation values visual

improvement along with positive changes in speed and efficiency. The focus

of Lean Thinking is the process and visualisation of the process. The

customer (patient and staff) is placed at the centre and the emphasis is on

the elimination of any steps that do not add value (waste) from the

customer’s perspective. Data which is practical and meaningful and does

not require complex statistical analysis is used. Staff engagement is crucial.

The researcher then chose the tools from the literature that appeared to be

the most applicable to the research questions and context; process

mapping, interviews and focus group. All of these aspects fit clearly with the

aims of quality outlined by the IOM (2001) and those outlined nationally in

the HIQA standards (2012).

The Six Sigma methodology focusses on problem solving and involves more

extensive statistical analysis than was required for the study context and

the researcher did not think this methodology was appropriate in the study

setting (section 2.3.2). The PDSA cycles are learning cycles and are

appropriate for use for small tests of change (section 2.3.3). As

improvements progress through various iterations the PDSA methodology

Page 124: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

106

will be applied to continuously improve any solutions implemented. It was

not, however, identified as an appropriate methodology to answer the

research questions and determine how processes could be improved in the

first instance.

5.3.2 Which processes should be improved? (SQ2)

The recommendation to collect baseline data (Fillingham, 2008; McGrath, et

al., 2008) both to highlight, where improvements are required and to

determine, if any change is indeed an improvement assisted in answering

the question of which processes need to be improved. With implementation

of improvements it would be hoped that there would be an improvement in

throughput, waiting times, paper costs, notes retrieved and filed and the

number of calls unanswered and this will be closely monitored. It would also

be hoped that the time taken to complete processes and the number of

steps involved could be reduced.

Process mapping, the interviews and the focus group also assisted in

answering the question of which processes should be improved (SQ2). Table

5.1 outlines the processes that should be improved as identified from the

process mapping, interviews and focus group.

Table 5.1 Which processes should be improved?

Which process? Relevant process map and

narrative

Suggested

Improvement Code

There is no agreement as to

when new patients can be

booked in to return slots.

Clerical staff say 1 day in

advance whereas

physiotherapists say 3 days in

advance

4.5

Step B(a)8

I1

No standardisation in use of

notations on body chart

4.12 I2

Unanswered phone calls Across full patient journey I3

Page 125: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

107

Paper trail and staff

movement involved in Referral

Management & Triage

4.4

Steps A1 to A11

I4

Counting waiting list manually 4.6

Steps B(b)1 to B(b)5

I5

Printing front sheet which is

not used for anything

4.7

Step C(a)6

I6

Use of yellow card for

registration

4.7 I7

Text message reminder sent 5

days in advance of

appointment

4.7

Step C(a)1

I8

Paper based referral onwards

on discharge

4.10 I9

Registration process 4.8 & 4.7

(Steps C (a) 4 & C (a)9)

I10

Paper based documentation,

specifically the retrieval and

filing of notes and access to

information

4.11 and 4.12 I11

No standardisation of the

actual process carried out by

clerical staff when ringing

patients and booking an

appointment on the PAS.

4.5

Steps B(a)1 to B(a)5

I12

Process for dealing with

patient queries is not

standardised or patient

centred

4.6

Steps B(b)6 to B(b) 12

I13

Coding at point of triage 4.4

Step A8

I14

Page 126: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

108

Process mapping highlighted the complexity of the processes, that there are

multiple repositories of patient information (figure 4.2) and a significant

number of documents and data are produced in the department (tables 4.4,

4.5 and 4.6). The processes need to be simplified and the number of

repositories could be reduced (I11).

Process mapping also demonstrated the need for standardisation of some

processes and this was further highlighted by the interviews and focus

group. Examples are the use of notations on the body chart (I2), the policy

for booking new patients into return slots (I1), the actual process for

ringing patients and booking appointments (figure 4.5) (I12) and the

process that occurs when a patient rings the department with a query

(figure 4.6) (I13).

In particular, capturing the existing process of booking new patients into

return slots showed up inconsistencies in the implementation of the current

booking policy (I1), and allowed it to be corrected immediately. The effect

of this on waiting lists was significant and immediate – see section 5.4.

The three stages of application of the process improvement methodology

showed without a doubt that the concurrent use of paper-based systems (I9

& I11) and disparate IT systems is resulting in duplication of effort (I5) and

inefficiencies (Unertl, Weinger and Johnson, 2006).

The referral management and triage process (figure 4.4) (I4) and patient

attendance (figure 4.7) involve a significant amount of transportation of

people and paper and some non-essential activity (I6) and duplication.

The text message reminder was sent 5 days in advance of an appointment

which was felt to be too early (I8). Clerical staff rely heavily on the details

written on the yellow appointment card to complete the registration process

and if the patient misplaces this card the registration process takes much

longer (I7).

During the observation the researcher witnessed a significant number of

interruptions from phones yet 20% of calls remain unanswered and many

Page 127: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

109

calls were put on hold (waiting) (I3). These interruptions led to variation in

the time taken to complete some processes, for example, registration

(figure 4.8) (I10).

As outlined in section 2.3.1 in Lean Thinking all steps should add value to

the customer’s journey. Referring back to the 7 types of waste we can see

there is substantial waste in terms of overproduction, waiting,

transportation, nonessential activity and variation.

Finally these three stages also suggested that the current processes in use

for the IT systems could be improved and lead to more extensive use of the

systems.

5.3.3 How can processes be improved in a physiotherapy

outpatients setting? (SQ3)

This section looks at the “how” or in other words what improvements might

look like.

The case studies in the literature review (section 2.6) outlined some

improvements that have been implemented elsewhere. Section 2.8 outlined

process improvements through the introduction of IT in physiotherapy. The

literature review gave the researcher several ideas of what improvements

might look like, which included

More efficient referral pathways

Self-registration kiosks

Electronic clinical documentation

and associated clinical decision support

Through the semi-structured interviews with key informants and through

the focus group several ways to improve processes also emerged. All ideas

outlined had a focus on the patient and staff as customers of the service

either directly or indirectly. An overview of suggestions that emerged from

the interviews and focus group is presented in figure 5.1 in the form of a

Venn diagram to demonstrate where there was overlap.

Page 128: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

110

Some of the suggested improvements are outlined a little further here.

Electronic triage refers to changing the current paper-based process of

triaging referrals to on-line triaging (I4). This would eliminate the excessive

movement of paper and staff in the current process. Text messaging refers

to a suggested change to the current text message patients get from a

reminder 5 days in advance to 2 days in advance and also to change the

message to include details that would be useful for the registration process

in cases where the patient misplaces their yellow card (I7&8). Gathering

waiting list data electronically would increase the accuracy and reliability of

the data (I5). Electronic referral onwards to community care or other

hospital via secure e-mail would improve the efficiency of the current

process and ensure necessary information is received at the receiving site

(I9). Standardisation of the policy for booking new patients into return slots

(I1) and the process for actually booking appointments ensures all patients

are treated in an equitable manner and there are no unnecessary delays

(I12).

Page 129: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

111

Figure 5.1 Venn diagram of suggested improvements from interviews and focus group

Electronic Triage I4

Text Messaging I8

Electronic wait list data I5

Electronic Documentation I11

Electronic Referral onwards I9

Standardise process of ringing patients with

appointment s and booking

on PAS I12

Self-Registration I10

Page 130: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

112

5.3.4 What are the potential benefits of any suggested

improvements? (SQ4)

The literature review, interviews and focus group all outlined the potential

benefits of implementing improvements.

An overview of the benefits highlighted from the literature review includes:

Patients getting more time with providers

More timely results

Improved staff morale

Improved customer satisfaction

Reduction in errors

Improvement in outcomes

Throughout

Safety

Overall quality of care

Those highlighted through the interviews and focus group were more

specific to the context of the study. For the focus group an attempt was

made by participants to stick to the overall goals outlined. The benefits are

summarised below in no particular order:

Easier access to patient information and previous physiotherapy

notes

Reduced time to triage referrals

Reduced time from referral received to waiting list to appointment

Reduced paper – cost and environmental

Improved data accuracy as not manually collated

Reduced delays for patients

Improved customer service – patient and staff

Page 131: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

113

All benefits impact on the quality of care provided: effectiveness, timeliness,

efficiency, equity, safety and most importantly patient centeredness. A draft

benefits realisation plan is outlined in Appendix H.

5.3.5 What are the perceived challenges of any suggested

improvements? (SQ5)

Challenges outlined in the literature (section 2.9) were summarised as the

general characteristics of healthcare, the need for staff involvement,

importance of data to demonstrate the need for improvement and if a

change is indeed an improvement and visible leadership. These or other

significant challenges did not emerge during the interviews and focus group

except for the need for staff buy-in from start to finish (interviews) and the

fear of a completely paperless department (focus group). However, those

highlighted in the literature review must be acknowledged and the need for

a clear change management strategy is evident. How some of these

challenges have been or will be addressed will be discussed in section 5.4.4.

Perhaps these methods were not the most appropriate way of determining

possible challenges despite the literature suggesting them as a methodology

and further context specific challenges will most likely arise as

improvements are progressed (Victorian Government report on using data

for quality improvement, 2008).

5.3.6 Conclusion to Research Questions

The main research question of how processes can be improved in

physiotherapy outpatients setting has been answered through the sub-

questions which have determined which process improvement methodology

could be used (SQ1), which process should be improved (SQ2) and what

this could look like (SQ3), the potential benefits (SQ4) and challenges of

making any suggested improvements (SQ5).

There is more detail on the proposed improvements and their

implementation in section 5.4.

Page 132: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

114

5.4 Progress and Plans for Suggested Improvements

In this section some detail of the progress to date and plans for the

improvements outlined is provided.

5.4.1 Progress made to date

As noted in section 4.3, when process mapping the booking of new patients

into return slots, misunderstandings became apparent, the policy was

clarified and agreement reached to adopt the clarified policy. This occurred

in the 3rd week in January 2013. By getting an agreement on the booking

policy (I1) an improvement in numbers waiting and waiting times was

immediately evident – see figures 5.2 and 5.3 which show no patients

waited for the 3 months following the improvement in the two specialties

under study. Figures 5.3 and 5.4 show the number of weeks waiting for the

same patient cohort. These changes occurred with no increase in staff

resources or decrease in referrals to the physiotherapy outpatient service.

Comments from patients on the “comment cards” have also outlined that

patients who attended in the past have been surprised that they were called

for their appointment so quickly. If this short waiting list continues there will

be no need to look at “the short waiters” option (I15).

The number of new and return patients seen per month has also increased

with the clarification of the booking policy. The average number of new

rheumatology patients seen per month increased to 38 (from 27) and the

average number of return patients to 132 (from 104). The average number

of new orthopaedic patients seen per month increased to 162 (from 140)

and the average number of return patients to 452 (from 422) (see table

4.1).

Page 133: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

115

0

10

20

30

40

50

60

70

80

Jan

-12

Feb

-12

Mar

-12

Ap

r-1

2

May

-12

Jun

-12

Jul-

12

Au

g-1

2

Sep

-12

Oct

-12

No

v-1

2

De

c-1

2

Jan

-13

Feb

-13

Mar

-13

Ap

r-1

3

May

-13

Jun

-13

Jul-

13

Figure 5.2 Number of patients waiting for a rheumatology physiotherapy appointment Jan 2012 – July 2013

0

10

20

30

40

50

60

70

80

Jan

-12

Feb

-12

Mar

-12

Ap

r-1

2

May

-12

Jun

-12

Jul-

12

Au

g-1

2

Sep

-12

Oct

-12

No

v-1

2

De

c-1

2

Jan

-13

Feb

-13

Mar

-13

Ap

r-1

3

May

-13

Jun

-13

Jul-

13

Figure 5.3 Number of patients waiting for an orthopaedic physiotherapy appointment Jan 2012 – July 2013

The reason for there being 23 patients on the orthopaedic waiting list in

June (figure 5.3) with a 2 week wait (figure 5.5) was due to this service

being reduced by one member of staff due to a period of annual leave with

no backfill. Once the staffing level was restored there was no waiting.

Booking

Policy

Clarified

Booking

Policy

Clarified

Page 134: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

116

2

1

4 4

5 5

8

6

8

7 7

6

4

0 0 0 0

2

1

0

1

2

3

4

5

6

7

8

9

Jan

-12

Feb

-12

Ma

r-12

Ap

r-1

2

Ma

y-1

2

Jun

-12

Jul-

12

Au

g-1

2

Sep

-12

Oct

-12

No

v-1

2

De

c-12

Jan

-13

Feb

-13

Ma

r-13

Ap

r-1

3

Ma

y-1

3

Jun

-13

Jul-

13

Figure 5.4 Number of weeks patients waited for a rheumatology physiotherapy appointment Jan 2012 – July 2013

Figure 5.5 Number of weeks patients waited for an orthopaedic physiotherapy appointment Jan 2012 to July 2013

6 week HSE target

6 week HSE target

Page 135: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

117

The body chart notations are now standardised in preparation for

electronic clinical documentation (I2)

The script for the answering machine message and how phone calls

can be filtered has been implemented (I3). This has led to a

reduction in unanswered calls. This has, however, led to an

unintended consequence of a small number of patient queries being

filtered to the manager’s phone as this can be chosen as one of the

options.

The IT department has given a demonstration to clerical and

physiotherapy staff of an on-line triaging system in the EPR and PAS

(I4). This system will allow for on-line triage, direct booking of

appointments and automatic reporting of waiting list data (I5). The

current format needs to be changed somewhat but the initial

response from staff was very positive. When this is implemented

triaging and the booking of appointments will be standardised by the

introduction of IT

The front sheet is no longer printed which means the elimination of

printing of 5,500 sheets of paper each year (across all the

physiotherapy outpatient services). This has also allowed the

reception area to amalgamate their printer use into one printer with

two trays (previously there was two printers with two trays in each)

which was an unexpected benefit and will reduce toner costs (I6)

The text message has been updated to include the therapist’s name,

information that is useful to the clerical staff at the point of

registration and which could eliminate the need for the yellow

appointment card in the future (I7)

The text message reminder has been changed (in line with the

changes to the booking policy) from 5 to 2 days and the patients will

also get a text message as confirmation when their initial

appointment is made (I8)

Page 136: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

118

The IT staff have given a demonstration to physiotherapy staff of a

body chart embedded in the current EPR and the initial response is

that it is a very good solution – see screenshot in figure 5.6 below

This improvement relates to (I11) or the preparation for Electronic

documentation (see section 5.4.2 below)

Figure 5.6 Body Chart in Cerner Millenium EPR

5.4.2 Plans for the future

There are plans to pilot an electronic community referral with one

community area in the coming months – the community referral form

is already built in the EPR and a feasible secure e-mail solution has

been identified (I9)

A self-registration pilot is taking place in another section of the

hospital but it is unclear at this stage if this will be rolled out to other

departments. A similar project has been successfully piloted in

another large acute teaching hospital (I10)

A. 4 notations

1. Numbness = dots

2. Paraesthesia = xxx

3. Pain = shading

4. Tick (to clear joints ie denotes no symptoms at ticked joint)

B. Free text pain descriptor (e.g. agonising, aching - limit to 25 characters)

C. Drop down menu for 2 items

1. NRS (numerical rating scale = 0 - 10) (i.e. pain intensity)

2. intermittent/constant (i.e. frequency of pain)

Page 137: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

119

Complete electronic clinical documentation on the EPR is progressing

and all forms currently used are gathered, common fields across all

forms identified and conditional logic outlined (I11)

A future process map might look something like Figure 5.7 and key

repositories like Figure 5.8

ALL referrals are placed on the EPR and referrals do not print so

there is no waiting list folders or new referrals box

Triage occurs on-line on the EPR /PAS and there is no requirement for

a separate referrals database

Appointment booking occurs directly on to the PAS by having EPR

and PAS open simultaneously

Waiting list data required for HSE CompStat is retrieved electronically

Community referrals are completed on the EPR and are e-mailed to

the relevant community care service via a secure e-mail solution

There is no need for a separate database to be maintained of all

patients referred to the community as this information will be

available electronically

Text message reminders are used for appointment confirmation as

well as reducing the need for (while not eliminating) the need for

yellow appointment cards

Patients self-register their attendance for all appointments – there is

some debate about whether this could be used for new appointments

or only return. It is also likely that not all patients will be happy to

use the self-registration system

Electronic clinical documentation on the EPR and available on a

mobile device allows for clinical decision support to be embedded and

for the clinician to view the patient’s results without leaving the

cubicle/in conjunction with the patient

Page 138: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

120

Patients can complete self-reported outcome measures prior to

seeing their physiotherapist

Audit and research are more easily carried out

DNA and cancellation reports will continue each month but there will

be no need for the physiotherapists to retrieve the notes of patients

who cancelled and did not make another appointment as all notes will

be on-line

Discharge summaries will be available on the EPR to close the loop

and as a reference point for repeat referrals

The archive of physiotherapy paper notes will need to be maintained

in the interim

The EPR and PAS will become the main repositories leading to a

significant reduction in paper use

Page 139: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

121

The clerical staff view the EPR “triaged patients” screen and the PAS booking screen simultaneously on the

computer

Referrals triaged on EPR (online) by the physiotherapist

(no paper prints)

ALL Referrals placed on EPR

Patients are phoned and their appointments are booked on PAS

simultaneouslyCommunity or local hospital

referral?

YES

Online community referral is completed

and e-mailed to relevant area by secure

e-mail

Text sent to patient on the evening their appointment is booked and again 2 days in advance of their appointment

as a reminder

Waiting List data is retrieved automatically from the PAS

When the patient attends they self-register for all appointments

While the patient attends the physiotherapist all clinical documentation is recorded on a mobile tablet device which

has embedded clinical decision support and also allows access to blood results, x-rays, scans in the cubicle with the

patient

When the patient attends they complete self-reported outcome measures on a mobile device when in the waiting

room before they see the therapist

NO

Audit and Research are more easily carried out as all relevant information is in a structured format on the EPR and is retrievable

Community referral data is retrieved

automatically from the EPR

DNA and cancellation reports are available as before based on no registration on PAS

When the patient is discharged a discharge summary is completed to close the loop from referral to discharge

Figure 5.7 Possible Future Process Map

Page 140: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

122

PAS

PhysiotherapyNotes

EPR

Monday

New Referrals Box

PhysiotherapyReferral

PhysiotherapyReferral

PT REF

Referrals database

Referrals database

Old Archive

Waiting List folders

Waiting List folders

Lists for each clinicLists for each clinic

Active Notes

Clinic Name Alphabetically

Current Year Archive

DNAs BoxDNAs Box

YellowAppointment

card

ConsultantCorrespondence to GP

ConsultantCorrespondence to GP

PT NOTES

APPTCARD

WLFOLDER

Community database

Community database

COMM DB

REFSDB

NEW REF BOX

ACTIVE

DNA

CORR

CLIN LIST

OLD

CURRENT

KEY REPOSITORIES

Waiting ListNumbers

Waiting ListNumbers

WL NUMBERS

DB

Figure 5.8 Possible Future Key Repositories

Page 141: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

123

5.4.3 Suggested improvements that cannot be progressed or

have not been progressed to date

Through discussions with the IT department it has emerged that allowing a

reply to the text messages is not possible and there are no plans to

introduce this functionality (suggestion from interviews).

The suggestion by one of the interviewees that adding a physiotherapy code

to the patient’s record at the point of discharge rather than as it currently

happens at the point of triage is an interesting one (I14). The European

Core standards of physiotherapy15 do specify that a physiotherapy diagnosis

should be added to the patient record but they do not specify at which point

this should be done. However, it is acknowledged that to use clinical

decision support and aid treatment planning adding the physiotherapy

diagnostic code early on in the process would be advised.

Table 5.2 outlines some of the other suggested improvements outlined at

the focus group and interviews that have not been progressed to date.

Table 5.2 Suggested Improvements not yet progressed

Suggested Improvement

Relevant process map

and narrative

Suggested

Improvement Code

Have a short waiter’s list Figure 4.5 I15

Install a self-appointment making

booth

Figure 4.5 I16

Take photos over time to

demonstrate patient progress

Figure 4.12 I17

Embed outcome measures in the

patient’s record (links to electronic

clinical documentation)

Figure 4.12 I18

Clarity around what services are

actually available in the HSE

Figure 4.10 I19

15 http://www.physio-europe.org/download.php?document=71&downloadarea=6

Page 142: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

124

Agreement with referrers to give a

discharge summary only if

requested

Figure 4.10 I20

Clerical staff to give notes to the

patient to avoid excessive walking

Figure 4.7 I21

A process similar to Choose and

Book

Figure 4.5 I22

Patients completing self-reported

outcome measures prior to

attendance

Figure 4.7 I23

Computerised Clinical Decision

Support

Figure 4.12 I24

Page 143: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

125

5.4.4 Proposals to address challenges

As outlined previously staff involvement, a focus on the customer and data

are key to the success of process improvement. Improvements are more

likely to be sustained if staff have been involved and change has been

successfully managed. As has been seen in this research, data can be used

to convince staff that improvement is needed and that a change is indeed

an improvement. To date physiotherapy department and IT department

staff involved in the focus group will be key to the realisation of any

improvements and the associated benefits and it will be important to

engage with them on a continuous basis. A continued focus on the customer

and how any change impacts is essential, both now and in the future.

5.5 Conclusion

This chapter outlined how the methodology used answered the research

questions. Which processes should be improved was highlighted along with

suggestions as to how this could be done. The benefits of any suggestions

were then outlined along with some challenges to any implementation. The

next chapter outlines recommendations for future research and some of the

limitations of this study.

The mixed methods approach applied in this research, with collection of

quantitative and qualitative data, adds to the validity of the results. When

improvements are carried out in the future having all of this data would

assist greatly in monitoring improvement.

Page 144: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

126

CHAPTER 6

CONCLUSION

6.1 Introduction

A process improvement methodology and tools based on Lean Thinking

principles was successfully used to determine how processes could be

improved in a physiotherapy outpatients department. Ample opportunities

for process improvement in the physiotherapy outpatients department

under study emerged. Staff engagement in determining opportunities for

process improvement and the priority in which these opportunities should

be explored has assisted greatly with staff buy-in. It will be important that a

phased approach is used going forward as too many changes can exhaust

staff (Azad, 2012). Availability of data on an on-going basis, preferably

electronically (for accuracy and credibility) will be crucial.

6.2 Recommendations for Future Research

Any future work should involve continuous review of the baseline data as

the suggested changes are implemented. It will be necessary to monitor

patient throughput, which has already increased, and the impact this

change has on the number of notes that require retrieval and filing on a

daily basis and the impact on storage facilities.

As outlined in the literature, patient engagement and involvement is

important in any process improvement and any change should be seen as

valuable to the patient (Locock, 2003 (b); Ben-Tovim, Dougherty, O’Connell

and McGrath, 2008; Azad, 2012). McGrath, et al. (2008) outline how often

the most innovative solutions come from patients so engagement of

patients with process improvement initiatives through focus groups or

surveys would be a good idea for future work. It is acknowledged that the

department under study does have a comment card system and makes

changes suggested by patients as appropriate. However, the patient

Page 145: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

127

experience of any improvements will need to be assessed further

(Mazzocato, et al., 2010).

Staff satisfaction should also be assessed and has not been extensively

measured (Holden, 2011).

Communication flows and methods of communication – to community, to

other referral sources, to patients, to referrers should be looked at more

thoroughly. It will also be useful to look at any unintended consequences of

improved processes e.g. more efficient referral onwards to the community

could lead to a backlog in that system. Finally, if processes are streamlined

and information technology is introduced there will be possibilities for

further research into other quality aspects such as patient outcomes from

various treatments.

6.3 Study limitations

This study had a few limitations.

This was a single case study and a comparative study with another

similar department may have been useful and may have increased

the scalability of the results to other physiotherapy departments.

There was no external expert guiding the process (Mazzocato, et al.,

2012). However, as can be seen from the study by Scott, et al.

(2011) process improvements led internally are often more

successful. Also the literature was reviewed, guidance was received

from the researcher’s supervisor and experts were consulted. Since

January 2013 the researcher has also undertaken a 6 day course on

leadership and quality improvement. However, the main focus of the

course was PDSA cycles.

It must be acknowledged that the department under study has

limited experience in this area. Trinity Health spent seven years

training physicians and other staff in the use of improvement tools,

data use and process maps (Brokel and Harrison, 2009). Despite this,

Page 146: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

128

as outlined by Locock (2003 (b)) much of it is common sense and as

highlighted extensively in the literature having the staff who work on

the frontline and best know the processes and where improvements

can be made is key. Staff easily understood the process maps at the

focus group and embraced the challenge of seeking out opportunities

for improvement with significant enthusiasm.

As outlined in section 2.5.1 consideration should be given to using

more than one type of process mapping.

The Hawthorne effect needs to be acknowledged as the researcher is

one of the managers in the department under study and there is

always the possibility of performance bias in such a situation.

Enthusiasm and the buy-in for the process improvement initiatives

outlined which has been witnessed to date could be down to the fact

that the focus has been on the staff. Some of the comments made at

the focus group and in e-mails to the researcher afterwards would

give some credence to this theory.

“We always knew it was a busy department but it is great to have

this information documented objectively and acknowledged”

“It's great that someone is doing their Masters on this as otherwise

there would never be the time to look at it” This comment concurs

with the comment made by one of the interviewees that a 3-5 day

“Kaizen event” would have been worthwhile but would it have been

possible with service demands as they are?

“It's great to be a part of a group that is willing to look at a problem

and try and conjure some ideas that will improve the patient

experience – it’s very inspiring”.

6.4 Conclusion

This research demonstrated that a process improvement methodology and

tools based on the principles of Lean Thinking can be applied in a

Page 147: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

129

physiotherapy outpatient setting to determine how processes can be

improved. Data and staff engagement, including IT department staff, have

to date, and will continue to be key to the success of any initiative.

Page 148: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

130

References

American Society for Quality (ASQ), 2004. Check Sheet. [online]

Available at:

http://asq.org/learn-about-quality/data-collection-analysis-

tools/overview/check-sheet.html

[Accessed 5 October 2012]

American Society for Quality (ASQ), 2009. Hospitals see benefit of Lean and Six

Sigma. [online]

Available at:

http://asq.org/qualitynews/qnt/execute/displaySetup?newsID=5843

Accessed 10 October 2012]

Albright, B., 2008. Lean and Mean, Healthcare Informatics, [online]

Available at:

http://www.healthcare-informatics.com/article/lean-and-mean

[Accessed 4 January 2013]

Australian Resource Centre for Healthcare Innovations (ARCHI).

[online] Available at: http://www.archi.net.au/

[Accessed 20 November 2012]

Azad, K.H., 2012. Transformational Patient Care Redesign Project, Journal of the

Society for Healthcare Improvement Professionals, [online] pp. 1-8.

Available at:

http://www.jship.org/wp-content/uploads/2012/06/Transformational-

Patient-Care-Redesign-Project-V2.pdf

[Accessed 22 February 2013]

Barry, C., Jones, M. and Grimmer, K., 2006. Electronic Clinical records for

Physiotherapists, The Internet Journal of Allied Health Sciences and Practice,

[online] vol. 4, No. 1, pp. 1- 8.

Available at:

http://ijahsp.nova.edu/articles/vol4num1/Barry.pdf

[Accessed 7 June 2012]

Page 149: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

131

Batalden, P., 2006. What System?, Dartmouth Medicine, Summer 2006.

[online] pp. 28-35

Available at:

http://dartmed.dartmouth.edu/summer06/pdf/what_system.pdf

[Accessed 30 January 2013]

Bates, D.W., 2002. The quality case for information technology in healthcare,

BMC Medical Informatics and Decision Making,

[online] vol 2, No.7, pp. 1-9.

Available at:

http://www.biomedcentral.com/1472-6947/2/7

[Accessed 6 July 2013]

Bell, S.C., 2006. Lean Enterprise Systems: Using IT for Continuous Improvement.

New Jersey: John Wiley & Sons, Inc.

Bell, S.C., 2012. Lean Business-IT Integration. Lean.org blog [blog] August 2011 to

August 2012. Available at:

https://www.lean.org/search/Default.aspx?e=0&sec=0&mf=2097151&role=

0&func=0&cp=2&sc=Bell%2C+Stephen&s=publishdate

[Accessed 6 July 2013]

Bell, S.C., 2013. Run, Grow, Transform. Integrating Business and Lean IT.

Boca Raton: Taylor & Francis Group.

Bell, S.C. and Orzen, M.A., 2011. What is Lean IT and why is it important?

[online] Available at:

http://www.lean.org/admin/km/documents/2F8FF00A-E509-4680-9A69-

832123F1E933-leanit_ch1.pdf

[Accessed 5 January 2013]

Ben-Tovim, D.I., Bassham, J.E., Bennett, D.M., Dougherty, M.L., Martin, M.A.,

O'Neill, S.J., Sincock, J.L..and Szwarcbord, M.G., 2008.

Redesigning care at the Flinders Medical Centre: clinical process redesign

using "lean thinking", Medical Journal of Australia, [e-journal] vol. 188, no. 6

Suppl, pp. S27-31.

Page 150: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

132

Available through ProQuest Nursing and Allied Health Source database:

http://search.proquest.com.elib.tcd.ie/nursing/docview/235705755/fulltextP

DF/13CFEAF8A8D7136F2D3/1?accountid=14404

[Accessed 13 December 2012]

Ben-Tovim, D.I., Dougherty, M.L., O'Connell, T.J. and McGrath, K.M., 2008.

Patient journeys: the process of clinical redesign, Medical Journal of

Australia, [e-journal] vol. 188, no. 6 Suppl, pp. S14-7.

Available through ProQuest Nursing and Allied Health Source database:

http://search.proquest.com.elib.tcd.ie/nursing/docview/235705755/fulltextP

DF/13CFEAF8A8D7136F2D3/1?accountid=14404

[Accessed 13 December 2012]

Berwick, D.M., 1992. The clinical process and the quality process, Quality

Management in HealthCare, [e-journal] vol. 1, no. 1, pp. 1-8.

Available through Ovid database:

http://library.catalogue.tcd.ie/search~S6?/tQuality+management+in+healt

hcare/tquality+management+in+healthcare/-

3%2C0%2C0%2CB/frameset&FF=tquality+management+in+health+care&1

%2C1%2C/indexsort=-

[Accessed 23 January 2013]

Berwick, D.M., 1996. A primer on leading the improvement of systems, British

Medical Journal, [online] vol. 312, no. 7031, pp. 619-22.

Available at:

http://www.ncbi.nlm.nih.gov/pmc/articles/PMC2350403/pdf/bmj00532-

0035.pdf

[Accessed 23 January 2013]

Berwick, D.M., 2002. A user's manual for the IOM's 'Quality Chasm' report,

Health Affairs (Millwood), [online] vol. 21, no. 3, pp. 80-90.

Available at:

http://content.healthaffairs.org/content/21/3/80.long

[Accessed 23 January 2013]

Bisognano, M., and Kenney, C., 2012. Pursuing the Triple Aim.

San Francisco: John Wiley & Sons Inc.

Page 151: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

133

Bolton Improving Care System (BICS), Royal Bolton Hospital NHS Foundation

Trust, 2007. [online]

http://www.boltonft.nhs.uk/about-us/bics/

[Accessed 20 November 2012]

Black, A.D., Car, J., Pagliari, C., Anandan, C., Cresswell, K., Bokun, T., McKinstry,

B., Procter, R., Majeed, A. and Sheikh, A., 2011. The impact of eHealth on

the quality and safety of health care: a systematic overview, PLoS Medicine,

[online] vol. 8, no. 1, p. e1000387.

Available at:

http://www.ncbi.nlm.nih.gov/pmc/articles/PMC3022523/pdf/pmed.1000387.

pdf

[Accessed 26 January 2013]

Bowens, F.M., Frye, P.A. and Jones, W.A., 2010. Health information technology:

integration of clinical workflow into meaningful use of electronic health

records, Perspective in Health Information Management, [online] vol. 7, p.

1d.

Available at:

http://www.ncbi.nlm.nih.gov/pmc/articles/PMC2966355/pdf/phim0007-

0001d.pdf

[Accessed 29 December 2012]

Brennan, A., Sampson, F. and Deverill, M., 2005.Can we use routine data to

evaluate organizational change? Lessons from the evaluation of business

process re-engineering in a UK teaching hospital, Health Service

Management Research, [e-journal] vol. 18, no. 4, pp. 265-76.

Available through ProQuest Nursing and Allied Health Source database:

http://search.proquest.com.elib.tcd.ie/nursing/docview/236459600/fulltextP

DF/13CFEBF80D85A4258E/1?accountid=14404

[Accessed 13 February 2013]

Brokel, J.M., and Harrison, M.I., 2009. Redesigning Care processes using an

Electronic Health Record: A System’s experience, The Joint Commission

Journal on Quality and Patient Safety, [online] vol. 35, No. 2, pp.82-92.

Available at:

http://www.trinityhealth.org/documents/News%20Coverage/CPORTAL_0031

89.pdf

Page 152: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

134

[Accessed 20 December 2012]

Buyl, R. and Nyssen, M., 2009. Structured electronic physiotherapy records,

International Journal of Medical Informatic, [e-journal] vol. 78, no. 7, pp.

473-81.

Available through Science Direct database:

http://ac.els-cdn.com/S138650560900032X/1-s2.0-S138650560900032X-

main.pdf?_tid=d7fc26a0-9405-11e2-a9a3-

00000aacb35d&acdnat=1364076539_9d617909827481a1840b12f57a6d2c1

0

[Accessed 29 October 2012]

Campbell, R.J., 2009. Thinking Lean in Healthcare, Journal of AHIMA.

[online] vol. 80, no.6 pp. 40-43.

Available at:

http://library.ahima.org/xpedio/groups/public/documents/ahima/bok1_0437

53.hcsp?dDocName=bok1_043753

[Accessed 21 November 2012]

Canada Health Infoway, 2011. Change Management Guide. [online]

Available at:

https://www.infoway-inforoute.com/index.php/progress-in-

canada/managing-change

[Accessed 11 November 2012]

Chand, S., Moskowitz, H., Norris, J.B., Shade, S. and Willis, D.R., 2009.

Improving patient flow at an outpatient clinic: study of sources of variability

and improvement factors, Health Care Management Science, [e-journal] vol.

12, no. 3, pp. 325-40.

Available through SpringerLink database:

http://download.springer.com.elib.tcd.ie/static/pdf/552/art%253A10.1007%

252Fs10729-008-9094-

3.pdf?auth66=1365373332_19a537bf641533eb419fd50184b83c1f&ext=.pdf

[Accessed 6 February 2013]

Chapman, P., 2010. A digital pen and paper increases productivity of

physiotherapists. [online]

Available at:

Page 153: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

135

http://www.ubisys.co.uk/news/detail/digital-pen-and-paper-increases-

productivity-of-physiotherapists-by-35

[Accessed 3 September 2013]

Chhoda, N., 2012. Self-Intake Technology allows physical therapists to focus on

what’s most important, patient care. Prweb.com blog [blog] 1 December.

Available at:

http://www.prweb.com/releases/PT-management/physical-therapy-

software/prweb10162237.htm

[Chhoda’s Blog was Accessed from July 2012]

Choose and Book, 2013.

[online] Available at:

http://www.chooseandbook.nhs.uk/staff/communications/studies

[Accessed 3 January 2013]

Chyna, J.T., 2002. Wait reduction: improving operational and financial

performance in outpatient services, Healthcare Executive,

[e-journal] vol. 17, no. 4, pp. 14-9.

Available through ProQuest Nursing and Allied Health Source:

http://search.proquest.com.elib.tcd.ie/docview/200292510/fulltextPDF/13CF

EE412E87DCC0FE6/1?accountid=14404

[Accessed 6 February 2013]

Colligan, L., Anderson, J.E., Potts, H.W. and Berman, J., 2010. Does the process

map influence the outcome of quality improvement work? A comparison of a

sequential flow diagram and a hierarchical task analysis diagram, BMC

Health Services Research, [online] vol. 10, no. 7, p. 7.

Available at:

http://www.ncbi.nlm.nih.gov/pmc/articles/PMC2822834/pdf/1472-6963-10-

7.pdf

[Accessed 23 March 2013]

Crandall, D.K., Brokel, J.M., Schwichtenberg, T., Henderson, S., Haskins, R.,

Wakefield, D., Ward, M. and Dixon, B.E. 2007. Redesigning care delivery

through health IT implementation. Exploring Trinity Health's IT model,

Journal of Healthcare Information Management, [online] vol. 21, no. 4, pp.

41-8.

Page 154: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

136

Available at:

http://www.himss.org/files/HIMSSorg/Content/files/jhim/21_4/10_caseStud

y1.pdf

[Accessed 23 October 2012]

Creswell, J.W., 2009. Research design: qualitative, quantitative, and mixed

methods approaches. 3rd ed. London: Sage.

Department of Health, 2011. Allied Health Professionals Service Improvement

Project. [pdf] London: Department of Health.

Available at:

http://www.dh.gov.uk/prod_consum_dh/groups/dh_digitalassets/documents

/digitalasset/dh_126838.pdf

[Accessed 2 December 2012]

Department of Health and Children, 2013. Money Follows the Patient.

[pdf] Dublin:Department of Health and Children.

Available at:

http://www.dohc.ie/publications/pdf/MoneyFollowsthePatient_HFPP.pdf?dire

ct=1

[Accessed 31 May 2013]

Diamond, C. C., and Shirky, C., 2008. Health information technology: a few years

of magical thinking? Health Affairs (Millwood), [online] vol. 27, no. 5

pp.w383-90.

Available at:

http://content.healthaffairs.org/content/27/5/w383.full.pdf+html

[Accessed 3 July 2013]

Dickson, E. W., Singh, S., Cheung, D.S., Wyatt C.C., and Nugent, A.S., 2009.

Application of lean manufacturing techniques in the Emergency Department,

Journal of Emergency Medicine, [e-journal] vol. 37, no. 2, pp. 177-182.

Available through Science Direct database:

http://ac.els-cdn.com/S0736467908002163/1-s2.0-S0736467908002163-

main.pdf?_tid=78ca1318-cab0-11e2-92bb-

00000aab0f27&acdnat=1370087186_64e4f4a73f82a737c574c494af999c81

[Accessed 1 May 2013]

Page 155: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

137

Dixon-Woods, M., McNicol, S., Martin, G., 2012. Ten challenges in improving

quality in healthcare: lessons from the Health Foundation's programme

evaluations and relevant literature, British Medical Journal Quality & Safety,

[online] vol. 21, no. 10, pp. 876-84.

Available at:

http://www.ncbi.nlm.nih.gov/pmc/articles/PMC3461644/pdf/bmjqs-2011-

000760.pdf

[Accessed 8 July 2012]

Donabedian, A., 1966. Evaluating the quality of medical care, Milbank Memorial

Fund Quarterly, [e-journal] vol. 44, no.3, pp. S166-206.

Available through JSTOR database:

http://www.jstor.org.elib.tcd.ie/stable/pdfplus/3348969.pdf?acceptTC=true

[Accessed 5 October 2012]

Eitel, D.R., Rudkin, S.E., Malvehy, M.A., Killeen, J.P. and Pines, J.M., 2010.

Improving service quality by understanding emergency department flow: a

White Paper and position statement prepared for the American Academy of

Emergency Medicine, Journal of Emergency Medicine, [e-journal] vol. 38,

no. 1, pp. 70-9.

Available through Science Direct database:

http://ac.els-cdn.com/S0736467908003910/1-s2.0-S0736467908003910-

main.pdf?_tid=ac0de4c4-9474-11e2-8f11-

00000aab0f02&acdnat=1364124139_c86ede1e8cef015bad9d8f7195496409

[Accessed 29 December 2012]

Fillingham, D., 2008. Lean Healthcare Improving the patient's experience.

Norfolk: Biddles Ltd.

Fine, B.A., Golden, B., Hannam, R. and Morra, D., 2009.

Leading Lean: a Canadian healthcare leader's guide, Healthcare Quarterly,

[online] vol. 12, no. 3, pp. 32-41.

Available at:

http://www.healthsectorstrategy.ca/downloads/HQ_vol12_no3_Fine.pdf

[Accessed 3 January 2013]

Page 156: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

138

Health Information and Quality Authority (HIQA), 2012.

National Standards for Safer Better Healthcare.

[pdf] Dublin: HIQA.

Available at: http://www.hiqa.ie/standards/health/safer-better-healthcare

[Accessed 2 September 2012]

Health Services Executive (HSE).

HealthStat: Improving Performance

Available at: http://www.hse.ie/eng/staff/Healthstat/about/

[Accessed 2 July 2012]

Health Services Executive (HSE).

National Clinical Programmes

Available at: http://www.hse.ie/eng/about/Who/clinical/natclinprog/

[Accessed 2 July 2012]

Himmelstein, D.U., Wright, A. and Woolhandler, S., 2009.

Hospital computing and the costs and quality of care: a national study,

American Journal of Medicine, [e-journal] vol. 123, no. 1, pp. 40-6.

Available through Science Direct database:

http://ac.els-cdn.com/S000293430900816X/1-s2.0-S000293430900816X-

main.pdf?_tid=c8205e94-9479-11e2-907f-

00000aab0f26&acdnat=1364126334_fdf9505f66bbe5922dcf4ea83dc93796

[Accessed 29 December 2013]

Holden, R.J., 2011. Lean Thinking in emergency departments: a critical review,

Annals of Emergency Medicine, [e-journal] vol. 57, no. 3, pp. 265-78.

Available through Science Direct database:

http://ac.els-cdn.com/S0196064410013223/1-s2.0-S0196064410013223-

main.pdf?_tid=23e224b4-947b-11e2-bd01-

00000aab0f01&acdnat=1364126917_f69596fa47648860468ac3f6522f70ba

[Accessed 3 November 2012]

Hughes, R., 2008. In: Patient Safety and Quality: An Evidence-Based Handbook

for Nurses, Chapter 44. Tools and Strategies for Quality Improvement and

Patient Safety

[pdf] Rockville: Agency for Healthcare Research and Quality (AHRQ)

Page 157: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

139

Available at:

http://www.ahrq.gov/professionals/clinicians-

providers/resources/nursing/nurseshdbk/HughesR_QMBMP.pdf

[Accessed 30 December 2012]

Hynes, D. M., Perrin R. A., Rappaport S., Stevens J. M., and Demakis J. G., 2004.

Informatics resources to support health care quality improvement in the

Veterans health administration, Journal of the American Medical Informatics

Association, [online] vol. 11, no.5, pp.344-50.

http://www.ncbi.nlm.nih.gov/pmc/articles/PMC516240/pdf/344.pdf

[Accessed 1 July 2013]

Institute for Healthcare Improvement (IHI)

[online] http://www.ihi.org/Pages/default.aspx

[Accessed from October 2012]

Institute for Healthcare Improvement (IHI), 2004.

Process Improvement Tools, Flowcharts. [pdf]

http://nnphi.org/CMSuploads/Flowcharts%20Guide.pdf

[Accessed 3 October 2012]

Institute of Medicine (IOM), 1999. To Err is Human: Building a Safer Health

System.

Washington, DC: National Academies Press

Available at:

http://www.iom.edu/Reports/1999/To-Err-is-Human-Building-A-Safer-

Health-System.aspx

[Accessed from July 2012]

Institute of Medicine (IOM), 2001. Crossing the Quality Chasm: A New Health

System for the 21st Century.

Washington, DC: National Academies Press

Available at:

http://www.iom.edu/~/media/Files/Report%20Files/2001/Crossing-the-

Quality Chasm/Quality%20Chasm%202001%20%20report%20brief.pdf

[Accessed from July 2012]

Page 158: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

140

Intermountain Healthcare, 2013. Intermountain Healthcare Briefing Notes.

[pdf] Utah: Intermountain Healthcare.

http://intermountainhealthcare.org/about/overview/trustees/fortrustees/Doc

uments/briefingnotes.pdf

[Accessed 5 July 2013]

Jones, D. and Mitchell, A., 2006. Lean Thinking for the NHS.

[pdf] London: NHS Confederation.

Available at:

http://www.nhsconfed.org/Publications/Documents/Lean%20thinking%20for

%20the%20NHS.pdf

[Accessed 3December 2012]

Kaplan, G.S. and Patterson, S.H., 2008. Seeking perfection in healthcare. A case

Study in adopting Toyota Production System methods, Healthcare Executive,

[e-journal] vol. 23, no. 3, pp. 16-8, 20-1.

Available through ProQuest database:

http://search.proquest.com.elib.tcd.ie/docview/200305546/fulltextPDF/13D

01E0758B287A9094/1?accountid=14404

[Accessed 6 February 2013]

Kawamoto, K., Houlihan, C. A., Balas, E. A. and Lobach, D.F 2005.

Improving clinical practice using clinical decision support systems: a

systematic review of trials to identify features critical to success, British

Medical Journal, [online] Vol. 330, No. 7494, pp. 765-768

Available at:

http://www.ncbi.nlm.nih.gov/pmc/articles/PMC555881/pdf/bmj33000765.pd

f

[Accessed 2 January 2012]

Kenney, C., 2011. Transforming Health Care Virginia Mason Medical Center’s

Pursuit of the Perfect Patient Experience.

New York : Taylor & Francis Group

Kitch, J., Crane,B., Ben-Tovim, D., Daebeler, R., 2007. Redesigning Allied Health

Outpatients. In: NAHC (National Allied Health Conference), 7th National

Allied Health Conference: No profession is an island. Hobart, Australia 18-20

July 2007.

Page 159: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

141

Available at: http://www.proceedings.com.au/nahc/

[Accessed 23 February 2013]

Langley, G.J., Moen, R., Nolan, K.M., Nolan, T.W., Norman, C.L. and Provost,

L.P., 2009.

The Improvement Guide: A Practical Approach to Enhancing Organizational

Performance. 2nded. San Francisco: Jossey-Bass

Lapointe, L. and Rivard, S., 2006. Getting physicians to accept new information

technology: insights from case studies, Canadian Medical Association

Journal, [online] vol. 174, no. 11, pp. 1573-8.

Available at:

http://www.cmaj.ca/content/174/11/1573.full.pdf+html

[Accessed 3 October 2012]

Lean Enterprise Institute, Principles of Lean

Available at: http://www.lean.org/whatslean/principles.cfm

[Accessed 3 November 2012]

Lluch, M., 2011. Healthcare professionals' organisational barriers to health

information technologies-a literature review, International Journal of Medical

Informatics, [e-journal] vol. 80, no. 12, pp. 849-62.

Available through Science Direct database:

http://ac.els-cdn.com/S1386505611001961/1-s2.0-S1386505611001961-

main.pdf?_tid=a2ecfe2e-9489-11e2-aa2a-

00000aab0f26&acdnat=1364133143_b58dcfc92a93544b7235aec8605e479d

[Accessed 3 October 2012]

Locock, L., 2003a. Healthcare redesign: meaning, origins and application,

Quality & Safety in Health Care, [online] vol. 12, no. 1, pp. 53-7.

Available at:

http://www.ncbi.nlm.nih.gov/pmc/articles/PMC1743671/pdf/v012p00053.pd

f

[Accessed 29 December 2012]

Locock, L., 2003b. Redesigning health care: new wine from old bottles?, Journal

of Health Service Research Policy, vol. 8, no. 2, pp. 120-2.

Page 160: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

142

Only available in hard copy Trinity College Dublin, John Stearne Library.

Lorenzi, N.M. and Riley, R.T., 2000. Managing change: an overview, Journal of

American Medical Informatics Association, [online] vol. 7, no. 2, pp. 116-24.

Available at:

http://www.ncbi.nlm.nih.gov/pmc/articles/PMC61464/pdf/0070116.pdf

[Accessed 6 February 2013]

Macleod, H., Bell, R.S., Deane, K. and Baker, C., 2008.

Creating sustained improvements in patient access and flow: experiences

from three Ontario healthcare institutions, Healthcare Quarterly,

Abstract only [online] vol. 11, no. 3, pp. 38-49.

Available at:

http://www.longwoods.com/content/19855

[Accessed 5 January 2013]

Mazzocato, P., Holden, R.J., Brommels, M., Aronsson, H., Bäckman, U., Elg, M.

and Thor, J. 2012. How does lean work in emergency care? A case study of

a lean-inspired intervention at the Astrid Lindgren Children's hospital,

Stockholm, Sweden, BMC Health Services Research,

[online] vol. 12, no. 28, pp. 1-13.

Available at:

http://www.ncbi.nlm.nih.gov/pmc/articles/PMC3298466/pdf/1472-6963-12-

28.pdf

[Accessed 23 March 2013]

Mazzocato, P., Savage, C., Brommels, M., Aronsson, H. and Thor, J., 2010.

Lean thinking in healthcare: a realist review of the literature, Quality &

Safety in Health Care, [e-journal] vol. 19, no. 5, pp. 376-82.

Available through British Medical Journal database:

http://qualitysafety.bmj.com.elib.tcd.ie/content/19/5/376.full.pdf+html

[Accessed 23 March 2013]

McGrath, K.M., Bennett, D.M., Ben-Tovim, D.I., Boyages, S.C., Lyons, N.J. and

O'Connell, T.J., 2008. Implementing and sustaining transformational change

in health care: lessons learnt about clinical process redesign, Medical Journal

of Australia, [e-journal] vol. 188, no. 6, Suppl, pp. S32-5.

Page 161: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

143

Available through ProQuest Nursing and Allied Health Source database:

http://search.proquest.com.elib.tcd.ie/nursing/docview/235680495/fulltextP

DF/13D02555E836C68D3B8/1?accountid=14404

[Accessed 13 December 2012]

Middleton, M., Bradford, C., Frantzis, J., Ambler, A., Sisson, T., Montgomerie, D.

and Martin, J. 2009. Paperless and paper-based processes in the modern

Radiotherapy department, Radiography, [e-journal] vol. 15, no. 4, pp. 300-

5.

Available through Science Direct database:

http://ac.els-cdn.com/S1078817409000054/1-s2.0-S1078817409000054-

main.pdf?_tid=27db1d9a-949a-11e2-907f-

00000aab0f26&acdnat=1364140238_6fc645f466dbe478d2beb828b22ce205

[Accessed 3 November 2012]

Murray, M., 2009. Process improvement and supply and demand: the elements

that underlie integration, Healthcare Quarterly, [online] vol. 13, Special

Issue, pp. 37-42.

Available at: http://www.longwoods.com/content/21095

[Accessed 3 January 2013]

National Health Service (NHS), Institute for Innovation and Improvement.

[online]

Available at:

http://www.institute.nhs.uk/quality_and_service_improvement_tools/quality

_and_service_improvement_tools/process_mapping_-_an_overview.html

[Accessed 21 November 2012, closed 31st March 2013]

National Health Service (NHS) Institute for Innovation and Improvement, 2005.

Improvement Leaders Guides. [pdf] Coventry: NHS Institute for Innovation

and Improvement.

Available at:

1.1 Improvement Knowledge and skills

http://www.clahrc-

northwestlondon.nihr.ac.uk/inc/files/documents/improvement-methodology-

resources-section/ilg_1.1_improvement_knowledge_and_skills.pdf

1.2 Process mapping, analysis and redesign

Page 162: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

144

http://www.clahrc-

northwestlondon.nihr.ac.uk/inc/files/documents/improvement-methodology-

resources-section/ilg_1.2_process_mapping_analysis_and_redesign.pdf

1.3 Working with groups

http://www.clahrc-

northwestlondon.nihr.ac.uk/inc/files/documents/improvement-methodology-

resources-section/ilg_1.3_working_with_groups.pdf

1.4 Involving patients and carers

http://www.clahrc-

northwestlondon.nihr.ac.uk/inc/files/documents/improvement-methodology-

resources-section/ilg_1.4_involving_patients_and_carers.pdf

1.5 Evaluating Improvement

http://www.clahrc-

northwestlondon.nihr.ac.uk/inc/files/documents/improvement-methodology-

resources-section/ilg_1.5_evaluating_improvement.pdf

2.1 Measuring for Improvement

http://www.clahrc-

northwestlondon.nihr.ac.uk/inc/files/documents/improvement-methodology-

resources-section/ilg_2.1_measuring_for_improvement.pdf

2.2 Matching Capacity and Demand

http://www.clahrc-

northwestlondon.nihr.ac.uk/inc/files/documents/improvement-methodology-

resources-section/ilg_2.2_matching_capacity_and_demand.pdf

2.3 Improving Flow

http://www.clahrc-

northwestlondon.nihr.ac.uk/inc/files/documents/improvement-methodology-

resources-section/ilg_2.3_improving_flow.pdf

2.4 Working in systems

http://www.clahrc-

northwestlondon.nihr.ac.uk/inc/files/documents/improvement-methodology-

resources-section/ilg_2.4_working_in_systems.pdf

[Accessed from October 2012]

National Health Service (NHS) Institute for Innovation and Improvement, 2007.

Improvement Leaders Guides. [pdf] Coventry: NHS Institute for Innovation

and Improvement.

Available at:

1.6 Use of Technology to improve service

http://www.clahrc-

northwestlondon.nihr.ac.uk/inc/files/documents/improvement-methodology-

resources-section/ilg_1.6_use_of_technology_to_improve_services.pdf

Page 163: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

145

1.7 Sustainability

http://www.clahrc-

northwestlondon.nihr.ac.uk/inc/files/documents/improvement-methodology-

resources-

section/ilg_1.7_substainability_and_its_relationship_with_spread_and_adoption

.pdf

[Accessed from October 2012]

NHS Scotland Quality Improvement Hub, 2008. [online]

Available at: http://www.qihub.scot.nhs.uk/home.aspx

[Accessed 14 January onwards]

O'Connell, T.J., Ben-Tovim, D.I., McCaughan, B.C., Szwarcbord, M.G. and

McGrath, K.M., 2008. Health services under siege: the case for clinical

process redesign, Medical Journal of Australia, [e-journal] vol. 188, no. 6

Suppl, pp. S9-13.

Available through ProQuest Nursing and Allied Health Source database:

http://search.proquest.com.elib.tcd.ie/nursing/docview/235699684/fulltextP

DF/13D02A638D81637ACCA/2?accountid=14404

[Accessed 13 December 2012]

Ozkaynak, M., Brennan, P.F., Hanauer, D.A., Johnson, S., Aarts, J., Zheng, K. and

Haque, S.N., 2013. Patient-centered care requires a patient-oriented

workflow model, Journal of the American Medical Informatics Association,

[e-journal] June Vol 20, Issue e1 pp. e14-e16.

Available through British Medical Journal group:

http://jamia.bmj.com.elib.tcd.ie/content/20/e1/e14.full.pdf+html

[Accessed 29 March 2013

Page, S., 2010. The Power of Business Process Improvement - 10 Simple Steps

to Increase Effectiveness, Efficiency, and Adaptability. [e-book] American

Management Association.

Available through Knovel database:

http://www.knovel.com.elib.tcd.ie/web/portal/basic_search/display?_EXT_K

NOVEL_DISPLAY_bookid=4951

[Accessed 19 November 2012]

Page 164: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

146

Philips, P. and Hughes, C., 2008. Clinical Process Redesign – Can the Leopard

change its spots? Medical Journal of Australia, [online] vol. 188, no. 6,

Suppl, pp. S7-8.

Available at: https://www.mja.com.au/journal/2008/188/6/clinical-process-

redesign-can-leopard-change-its-spots

[Accessed 13 December 2012]

Philips Healthcare white paper, 2009. Deploying Lean in Healthcare.

[pdf] Available at:

http://www.healthcare.philips.com/pwc_hc/main/shared/Assets/Documents/

About/News/Articles/Deploying_Lean.pdf (paste link into browser)

[Accessed 28 December 2012]

Powell, A.E., Rushmer, R.K. and Davies, H.T.O., 2009. A systematic narrative

review of quality improvement models in health care. [pdf]

Dundee: NHS Quality Improvement Scotland

Available at:

http://www.healthcareimprovementscotland.org/previous_resources/hta_re

port/a_systematic_narrative_review.aspx

[Accessed 6 February 2013]

Rhoads, J. and Drazen, E., 2009. Touchscreen check-in: Kiosks Speed Hospital

Registration. [pdf]

California: California Healthcare Foundation

Available at:

http://www.chcf.org/~/media/MEDIA%20LIBRARY%20Files/PDF/T/PDF%20

TouchscreenCheckInKiosks.pdf

[Accessed 1 March 2013]

Richardson, T., 2011. Bullet Proof Expert Systems: Clinical Decision Support for

Physical Therapists in the outpatient setting.

Summary Available at: http://bulletproofpt.com/

[Accessed July 2012]

Rozenblum, R., Jang, Y., Zimlichman, E., Salzberg, C., Tamblyn, M., Buckeridge,

D., Forster, A., Bates, D.W. and Tamblyn, R., 2011. A qualitative study of

Canada's experience with the implementation of electronic health

information technology, Canadian Medical Association Journal,

Page 165: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

147

[online] vol. 183, no. 5, pp. E281-8.

Available at:

http://www.cmaj.ca/content/early/2011/02/22/cmaj.100856.1.full.pdf+html

[Accessed 2 June 2012]

Scott, I.A., Wills, R.A., Coory, M., Watson, M.J., Butler, F., Waters, M. and

Bowler, S., 2011. Impact of hospital-wide process redesign on clinical

outcomes: a comparative study of internally versus externally led

intervention, British Medical Journal of Quality & Safety,

[e-journal] vol. 20, no. 6, pp. 539-48.

Available through BMJ Journals database:

http://qualitysafety.bmj.com.elib.tcd.ie/content/20/6/539.full.pdf+html

[Accessed 20 March 2013]

Shields, R.K., Leo, K.C., Miller, B., Dostal, W.F. and Barr, R., 1994.

An Acute Care Physical Therapy Clinical Practice Database for Outcomes

Research, Physical Therapy, [online] vol. 74, no. 5, pp. 463-70.

Available at: http://ptjournal.apta.org/content/74/5/463.full.pdf+html

[Accessed 3 July 2012]

Spear, S.J., 2011. Why Best Practices Haven’t fixed Healthcare. HBR Blog

Network blog, [blog] 3 January.

Available at:

http://blogs.hbr.org/cs/2011/01/why_best_practices_havent_fixe.html

[Accessed 5 October 2012]

Spear, S.J., 2005. Fixing health care from the inside, today, Harvard Business

Review, [online] vol. 83, no. 9, pp. 78-91, 158.

Available at: http://hbr.org/2005/09/fixing-health-care-from-the-inside-

today/ar/1

[Accessed 5 October 2012]

Swinkels, I.C., van den Ende, C.H., de Bakker, D., Van der Wees, P.J., Hart, D.L.,

Deutscher, D., van den Bosch, W.J. and Dekker, J., 2007.

Clinical databases in physical therapy, Physiotherapy Theory and Practice,

[e-journal] vol. 23, no. 3, pp. 153-67.

Available through Academic Search complete database:

Page 166: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

148

http://web.ebscohost.com.elib.tcd.ie/ehost/pdfviewer/pdfviewer?vid=3&sid

=02215c42-5a2c-4d45-ae55-d1aa97a57833%40sessionmgr104&hid=108

[Accessed 3 August 2012]

Thompson, D. I., Classen, D. C. and Haug, P.J., 2007.

EMRs in the fourth stage: the future of electronic medical records based on

the experience at Intermountain Health Care, Journal of Healthcare

Information Management, [online] vol. 21, no. 3, pp. 49-60.

Available at:

http://www.himss.org/files/HIMSSorg/content/files/jhim/21_3/12_features_

EMR.pdf

[Accessed 5 July 2013]

Thoussaint, J., 2007. Redesigned Inpatient Care Model Increases Quality and

Patient Satisfaction, Reduces Costs and Length of Stay. [online] Wisconsin:

Thedacare.

Available at: http://www.innovations.ahrq.gov/content.aspx?id=3355

[Accessed 10 February 2013]

Unertl, K.M., Weinger, M.B. and Johnson, K.B., 2006. Applying direct observation

to model workflow and assess adoption, AMIA Annual Symposium

Proceedings. [online] pp. 794-8.

Available at:

http://www.ncbi.nlm.nih.gov/pmc/articles/PMC1839698/pdf/AMIA2006_079

4.pdf

[Accessed 3 January 2013]

Unertl, K.M., Weinger, M.B., Johnson, K.B. and Lorenzi, N.M., 2009. Describing

and modeling workflow and information flow in chronic disease care, Journal

of the American Medical Informatics Association, [online] vol. 16, no. 6, pp.

826-36.

Available at:

http://www.ncbi.nlm.nih.gov/pmc/articles/PMC3002133/pdf/826.S10675027

09001686.main.pdf

[Accessed 29 October 2012]

Varkey, P., Reller, M.K. and Resar, R.K., 2007. Basics of quality improvement in

health care, Mayo Clinic Proceedings. [online] vol. 82, no. 6, pp. 735-9.

Page 167: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

149

Available at:

http://download.journals.elsevierhealth.com/pdfs/journals/0025-

6196/PIIS0025619611611944.pdf

[Accessed 23 March 2013]

Victorian Government Department of Human Services, 2007. Process Mapping, A

guide for health service staff. [pdf] Melbourne: Victorian Government

Department of Human Services.

Available at:

http://www.health.vic.gov.au/qualitycouncil/downloads/process_mapping.pd

f [Accessed 21 March 2013]

Victorian Government Department of Human Services, 2008. Streaming care:

Fast track services in hospital emergency departments. [pdf] Melbourne:

Victorian Government Department of Human Services.

Available at:

http://www.health.vic.gov.au/emergency/fasttrack_discussion_paper.pdf

[Accessed 21 March 2013]

Victorian Government Department of Human Services, 2008. A guide to using

data for health care quality improvement. [pdf] Melbourne: Victorian

Government Department of Human Services.

Available at:

http://www.health.vic.gov.au/qualitycouncil/downloads/vqc_guide_to_using

data.pdf

[Accessed 21 March 2013]

Vreeman, D.J., Taggard, S.L., Rhine, M.D. and Worrell, T.W., 2006. Evidence for

electronic health record systems in physical therapy, Physical Therapy,

[online] vol. 86, no. 3, pp. 434-46.

Available at:

http://ptjournal.apta.org/content/86/3/434.full.pdf+html

[Accessed 29 October 2012]

Wallace, C.J. and Savitz, L., 2008. Estimating waste in frontline health care

worker activities, Journal of Evaluation in Clinical Practice, [e-journal] vol.

14, no. 1, pp. 178-80.

Available through Wiley Library database:

Page 168: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

150

http://onlinelibrary.wiley.com.elib.tcd.ie/doi/10.1111/j.1365-

2753.2007.00828.x/pdf

[Accessed 7 February 2013]

Webster, A., 2011. Patient Check-In Technologies Cut Cost, Wait Times.

[online] Available at:

http://www.healthleadersmedia.com/page-1/LED-263095/Patient-CheckIn-

Technologies-Cut-Cost-Wait-Times

[Accessed 4 February 2013]

Whitman, J., Flynn, T., Wainner R and Magle J., 2002. Orthopaedic Manual

Physical Therapy Management of the Lumbar Spine, Pelvis, and Hip Region.

Fort Collins, CO: Manipulations, Inc.

Womack, J., Byrne, A., Flume, O., Kaplan, G. and Toussaint, J., 2005.

Going Lean in Health Care. IHI Innovation Series white paper. [pdf]

Cambridge, MA: Institute for Healthcare Improvement

Available at:

http://www.ihi.org/knowledge/Pages/IHIWhitePapers/GoingLeaninHealthCar

e.aspx

[Accessed 6 February 2013]

Young, T. and McClean, S., 2009. Some challenges facing Lean Thinking in

healthcare, International Journal of Quality in Health Care, [online] vol. 21,

no. 5, pp. 309-10.

Available at:

http://www.ncbi.nlm.nih.gov/pmc/articles/PMC2742395/pdf/mzp038.pdf

[Accessed 6 February 2013]

Young, T.P.and McClean, S.I., 2008. A critical look at Lean Thinking in healthcare,

Quality and Safety in Health Care, [e-journal] vol. 17, no. 5, pp. 382-6.

Available through British Medical Journal database:

http://qualitysafety.bmj.com.elib.tcd.ie/content/17/5/382.full.pdf+html?sid

=146cd2ad-c3e5-48de-a202-4ef3ac4ea0d3

[Accessed 6 February 2013]

Page 169: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

151

Bibliography

Berwick, D.M., Nolan, T.W. and Whittington, J., 2008. The triple aim: care, health,

and cost, Health Affairs (Millwood), vol. 27, no. 3, pp. 759-69.

Brand, C.A., Cameron, P.A., Greenberg, P.B. and Scott, I.A., 2008. Health services

under siege: the case for clinical process redesign, Medical Journal of

Australia, vol. 189, no. 4, pp. 239; author reply -40.

Brand, C.A., Tropea, J., Ibrahim, J.E., Elkadi, S.O., Bain, C.A., Ben-Tovim, D.I.,

Bucknall, T.K., Greenberg, P.B. and Spigelman, A.D., 2008. Measurement

for improvement: a survey of current practice in Australian public hospitals,

Medical Journal of Australia, vol. 189, no. 1, pp. 35-40.

Clague, J.E., Reed, P.G., Barlow, J., Rada, R., Clarke, M. and Edwards, R.H., 1997.

Improving outpatient clinic efficiency using computer simulation,

International Journal of Health Care Quality Assurance, vol. 10, no. 4-5, pp.

197-201.

Clemmer, T.P., Spuhler, V.J., Berwick, D.M. and Nolan, T.W., 1998. Cooperation:

the foundation of improvement, Annals of Internal Medicine, vol. 128, no. 12

Pt 1, pp. 1004-9.

De Mast, J., Kemper, B., Does, R.J., Madnjes, M. and van der Bijl, Y., 2011.

Process Improvement in Healthcare: Overall Resource Efficiency, Quality and

Reliability Engineering International, no. 27, pp. 1095 - 106.

Grimson, J., 2009. EHR Workshop, viewed 12th November 2012

<http://www.hiqa.ie/system/files/workshop_HI_EHR_Jane_Grimson_23100

9.pdf>.

Hardacre, J., Cragg, R., Shapiro, J., Spurgeon, P. and Flanagan, H. What's

Leadership got to do with it? Exploring links between Quality Improvement

and Leadership in the NHS.

Hart, M., 1995. Improving out-patient clinic waiting times: methodological and

substantive issues, International Journal of Health Care Quality Assurance,

vol. 8, no. 6, pp. 14-22.

Jette, D.U., Halbert, J., Iverson, C., Miceli, E. and Shah, P., 2009.

Page 170: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

152

Use of standardized outcome measures in physical therapist practice:

perceptions and applications, Physical Therapy, vol. 89, no. 2, pp. 125-35.

Kaplan, H.C., Brady, P.W., Dritz, M.C., Hooper, D.K., Linam, W.M., Froehle, C.M.

and Margolis, P., 2010. The influence of context on quality improvement

success in health care: a systematic review of the literature, Milbank

Quarterly, vol. 88, no. 4, pp. 500-59.

Leading Edge Group, 2012. Adding Value to Irish Community Pharmacy [pdf]

Macleod, H, Bell, RS, Deane, K & Baker, C 2008, 'Creating sustained improvements

in patient access and flow: experiences from three Ontario healthcare

institutions', Healthc Q, vol. 11, no. 3, pp. 38-49.

Schreiber, J., Stern, P., Marchetti, G. and Provident, I., 2009. Strategies to

promote evidence-based practice in pediatric physical therapy: a formative

evaluation pilot project, Physical Therapy, vol. 89, no. 9, pp. 918-33.

Scottish Executive, 2004. Improving outpatient waiting times: What matters, what

works, what next? [pdf] Edinburgh: Scottish Executive

van der Wees, PJ, Jamtvedt, G, Rebbeck, T, de Bie, RA, Dekker, J & Hendriks, EJ

2008, 'Multifaceted strategies may increase implementation of

physiotherapy clinical guidelines: a systematic review', Aust J Physiother,

vol. 54, no. 4, pp. 233-41.

Vreeman, D.J., 2006. Clinical prediction rules, Physical Therapy, vol. 86, no. 5, pp.

761-2.

Williams, H., and Duray, R., 2013. Making IT Lean.

Boca Raton: Taylor & Francis Group.

Page 171: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

153

Appendices

Appendix A: Overview of physiotherapy

Appendix B: Protocol for semi-structured interviews

Appendix C: Consent form

Appendix D: Participant information sheets

Appendix E: Ethics

Appendix F: Key to notations on process maps

Page 172: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

154

Appendix A: Overview of physiotherapy

Outpatient physiotherapists treat patients residing at home and aim to achieve the

best possible outcome and provide advice to increase and maintain the patient’s

quality of life and independence.

The main focus of physiotherapy is movement, which is essential for everyday

function. Outpatient physiotherapy involves the assessment and treatment of

muscles, tendons, ligaments, bones, spinal discs, nerves and other structures in

order to restore normal movement. A large part of physiotherapy also focuses on

health promotion.

In the outpatient physiotherapy setting (following consent from the patient for

treatment) the patient receives an initial assessment from an individual

physiotherapist. Depending on the condition or reason for referral the patient may

continue to see the physiotherapist individually, or may be referred on to an

exercise class within the outpatients department or referred to their local

community physiotherapy service (for follow-up in a more appropriate setting).

All information from the initial and follow-up assessments is usually recorded on a

standardised assessment form. Clinical information is recorded in the form of a

SOAP note (Subjective, Objective, Assessment and Plan) and adheres to the

European Core Standards for Physical Therapy, standard 14. The SOAP note was

developed by Dr. Laurence Weed in 1968 as part of the problem oriented medical

record (POMR).

The first stage of an outpatient’s assessment is a subjective examination. During

this exam the physiotherapist will observe the patient’s gait. The physiotherapist

will then take a medical history, followed by a history of the present complaint. This

will involve asking about how the present complaint started, the cause, whether it

has progressed, and whether the patient has had any treatment to date.

The presenting complaint is usually recorded on a body chart. Figure 1.1 is a

standard view of a body chart. It shows an anterior and posterior view of the body

(some charts have left and right views as well). Physiotherapists use symbols to

describe the location and the nature of the pain (sharp, ache), the frequency of the

pain (intermittent, constant) and whether the pain radiates and to where. The

symbols used are not currently standardised among physiotherapists.

Page 173: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

155

A number of more specific questions may follow depending on what the presenting

complaint is in order to provide the physiotherapist with as much information as

possible from which to draw up a treatment plan. In addition social history will be

investigated.

Assessment of red flags is a key part of the physiotherapist’s examination to rule

out a more serious condition. While most patients will have musculoskeletal

conditions as an explanation of their symptoms, a small number will have a more

serious underlying issue. These people need to be identified and referred urgently

to a medical specialist. Going through the list of red flags systematically greatly

reduces the risk of missing anything important. There is no substitute for going

through a checklist. An example of a red flag in a patient with a presenting

complaint of low back pain would be a change in bladder and/or bowel. Any

incontinence not previously present or an inability to pass water (retention) is

important and should be immediately reported.

The final question a physiotherapist will ask is what the patient wants from their

treatment; what goals they would like to achieve. Patient involvement is important

to achieve the best possible outcome.

Following this rigorous questioning the physiotherapist will conduct an objective

assessment. The first step of this stage is to observe any discolouration, swelling,

bruising, or scar tissue around the site of injury; this is followed by the

physiotherapist checking for any heat or tenderness in the same region.

The next stage is an observation of movement, both active (patient carrying out the

movement) and passive (physiotherapist manipulating the movement), allowing for

a better understanding of which specific structures are involved in the injury.

Resistive movements are the next stage where movement against resistance is

studied. Based on their findings, the physiotherapist will decide whether there is a

need for a neurological assessment based on reflexes and sensation, in particular

looking for areas of numbness, increased sensitivity, or muscular weakness.

Sometimes the physiotherapist will conduct joint manipulations for more

information. Next, balance and posture might also be observed.

There are many other specialised tests that may be performed for a more specific

study of affected structures, but these vary and are dependent on the findings

throughout the initial stages of assessment.

Page 174: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

156

Physiotherapists generally use an outcome measure at the initial assessment and

intermittently at treatment sessions to determine patient progress. An example of

such an outcome measure is the Roland and Morris Questionnaire for patients with

low back pain. However, due to time constraints and difficulties with analysing the

resulting data they are often not used consistently. Standardized outcome

measures have been advocated for use by physiotherapists for many years. They

assist the direction of the treatment plan and enhance communication with patients

(Jette, et al., 2009).

After assessment the physiotherapist will use the information gathered during the

assessment to formulate a treatment plan based on the problems identified and the

objectives the patient wants to achieve through physiotherapy. The problem will be

discussed along with treatment options and recommendations.

Treatment may include some or all of the following: Exercise, mobilisation,

manipulation, soft tissue techniques, electrical modalities and acupuncture. Advice

and education are very important parts of a physiotherapist’s role, and they will

give further resources to the patient such as an exercise sheet or information on

their condition to give the patient some level of control over the management of

their complaint. Further appointments, if necessary, will be arranged according to

the plan, the physiotherapist and the severity of the condition.

When treatment is complete the patient is discharged back to the referring

consultant and a discharge summary is written to the consultant outlining the

treatment undertaken and the progress to date. This discharge summary is often

manually written and is usually not in a standardised format.

Physiotherapists refer to the evidence base for advice on the most relevant

outcome measures, clinical pathways and the latest evidence. This usually occurs

outside patient treatment times due to time constraints and issues with access to

this information.

Some outpatient physiotherapy departments in Ireland do have electronic referral

systems and outpatient scheduling systems. However, these systems are often not

linked together and there can be duplication of effort with parallel paper based

systems.

Currently in Ireland outpatient physiotherapy departments in acute hospitals have

paper based clinical documentation, referrals onwards, discharge summaries,

Page 175: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

157

outcome measures and audit and research processes. In fact, audit and research

can be a long winded paper-based exercise in many physiotherapy departments

due to the lack of adequate electronic databases. This makes it extremely

challenging to review patient outcomes and make improvements. Determining the

profile of patients referred is also a difficulty and this causes problems in

determining staff training needs and service needs e.g. group versus individual

treatment requirements.

Management reports may be possible in the acute hospital outpatient departments

with electronic referral systems and scheduling systems e.g. DNAs (Did Not

Attends), cancellations and number of new and return patients. However, other

metrics such as waiting time (required by the Health Service Executive (HSE) often

continue to be determined through inefficient manual processes.

Page 176: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

158

Appendix B: Protocol for semi-structured interviews with

experts

Title of research study

Opportunities for, potential benefits of and challenges to Process Improvement

(based on the introduction of information technology) in an Outpatient

Physiotherapy Department

Lead Researcher

Marie Byrne Date:

Time start: Time finish:

Thank participant for accepting the invitation to participate

So the purpose of this research is determine what if any are the opportunities for

process improvement in the physiotherapy out-patients department, what the

benefits of any improvement initiative would be and what could be the perceived

challenges

Ask participants not to name third parties

You received an e-mail which outlines the detail of the current workflow in the

Physiotherapy out-patients department at St. James’s hospital, Dublin

Where there any steps in the workflow that were unclear?

If yes, please outline

From your review of the workflow please highlight the steps were you believe

processes could be improved

What changes would you suggest to improve the process at each of these steps?

What would the potential benefits be of improving the process at each of these

steps?

What challenges could prevent the realisation of such benefits?

Please outline any key people that you are aware of that have expert knowledge in

this area and who may be willing to participate (snowballing).

Page 177: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

159

Appendix C: Consent Form

TRINITY COLLEGE DUBLIN

INFORMED CONSENT FORM

LEAD RESEARCHER: Marie Byrne

BACKGROUND OF RESEARCH:

The purpose of this research study is to carry out a detailed review of opportunities

for, potential benefits of and challenges to process improvement (based on the

introduction of information technology) in the outpatient physiotherapy department

at St. James’s Hospital.

PROCEDURES OF THIS STUDY:

The researcher will carry out a literature review. The research methodology will be

to document a detailed workflow using observation, confirm this workflow with the

physiotherapists and clerical staff involved, carry out semi-structured interviews

with experts in the area and a focus group with key stakeholders to evaluate

potential benefits of automating key points in the workflow and highlight any

possible challenges.

A comprehensive information sheet will be made available to all potential

participants.

PUBLICATION:

The results of the research will be submitted in partial fulfilment of the Masters in

Health Informatics at Trinity College, Dublin. The work may be further developed

with the intention of publication in a peer reviewed journal. The research may be

used by others for academic research. In addition the research outcomes are likely

to be presented at selected conferences, seminars or workshops in Ireland.

The results will be made available to all research participants on completion of the

research study.

DECLARATION:

I am 18 years or older and am competent to provide consent.

Page 178: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

160

I have read, or had read to me, a document providing information about this

research and this consent form. I have had the opportunity to ask questions

and all my questions have been answered to my satisfaction and understand

the description of the research that is being provided to me.

I agree that my data is used for scientific purposes and I have no objection

that my data is published in scientific publications in a way that does not

reveal my identity.

I understand that if I make illicit activities known, these will be reported to

appropriate authorities.

I understand that I may stop electronic recordings at any time, and that I

may at any time, even subsequent to my participation have such recordings

destroyed (except in situations such as above).

I understand that, subject to the constraints above, no recordings will be

replayed in any public forum or made available to any audience other than

the current researcher.

I freely and voluntarily agree to be part of this research study, though

without prejudice to my legal and ethical rights.

I understand that I may refuse to answer any question and that I may

withdraw at any time without penalty.

I understand that no personal details about me will be recorded.

I have received a copy of this agreement.

PARTICIPANT’S NAME: PARTICIPANT’S SIGNATURE:

Date:

______________________ _____________________________

Statement of investigators’ responsibility: I have explained the nature and

purpose of this research, the procedures to be undertaken and any risks that may

be involved. I have offered to answer any questions and fully answered such

Page 179: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

161

questions. I believe that the participant understands my explanation and has freely

given informed consent.

RESEARCHERS CONTACT DETAILS: [email protected] or by phone: 01

4162486

INVESTIGATORS’ SIGNATURE: Date:

_________________________________________________________

Marie Byrne

Page 180: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

162

Appendix D: Participant Information Sheets

TRINITY COLLEGE DUBLIN

INFORMATION SHEET FOR PARTICIPANTS – OBSERVATION OF WORKFLOW

Dear Colleague,

I would like to invite you to take part in a research study entitled “Opportunities

for, potential benefits of and challenges to process improvement (based on the

introduction of information technology) in the outpatient physiotherapy department

at St. James’s Hospital”. This research is being undertaken as part fulfilment of an

MSc in Health Informatics in Trinity College Dublin (TCD).

Please read the following information carefully and ask if you do not understand

any part of it or would like more information.

Who is organising the research study?

This research study is being undertaken by Ms. Marie Byrne as part of an MSc in

Health Informatics in Trinity College, Dublin.

The study will be completed between January and May 2013.

Why have I been chosen?

We are inviting you to participate in this study as you are familiar with the current

processes in the outpatient physiotherapy department at St. James’s Hospital.

Background of research:

This research study is concerned with a detailed review of the workflow in an

outpatient physiotherapy setting to seek out opportunities for, potential benefits of

and challenges to process improvement (based on the introduction of information

technology).

The overall aim of this research is to provide a roadmap to process improvement in

outpatient physiotherapy and similar settings as there is a very limited research

base in this area.

Objectives:

• To outline the goals of process improvement

• To map out the current workflow from patient referral to discharge and/or

onward referral

• To validate this workflow with relevant team members to ensure the current

situation is accurately reflected in the workflow

• To collect baseline data to allow for benefit realisation studies to take place

in the future

• To highlight process improvement opportunities

• To determine potential benefits of any process improvements

Page 181: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

163

• To outline possible challenges

What is the purpose of the research study?

The purpose of this study is to review opportunities for process improvement

(based on the introduction of information technology) along the physiotherapy out-

patient pathway, to outline potential benefits of any change and to highlight any

challenges that may exist to prevent realisation of such benefits.

What will happen to me if I take part?

You will be observed carrying out your work in order to clearly document the

current workflow/processes and you will be asked to confirm the workflow

documented by the researcher afterwards

What will happen to the results of the research study?

The results of the research will serve to inform the researcher of opportunities for

the introduction of IT, the benefits of such an introduction and the possible

challenges to realization of such benefits.

The results of the study will be submitted as part of the TCD masters programme.

The work may be further developed with the intention of publication in a peer

reviewed journal. The research may be used by others for academic research. In

addition the research outcomes are likely to be presented at selected conferences,

seminars or workshops in Ireland.

The results can be made available to all research participants on completion of the

research study.

Confidentiality - who will know I am taking part in the research study?

All information, which is collected during the course of the research, will be kept

strictly confidential.

Conflict of interest:

The main researcher is a physiotherapy manager in the physiotherapy department

in which the research will be undertaken.

Expected duration:

It will take approximately 45 minutes for the researcher to complete each

observation.

Confirmation of workflow will take a further 15 minutes.

Procedure to be used if assistance or advice is needed

In the event that you require further information about this study please contact

Marie Byrne who will be happy to answer your questions. Marie can be contacted by

email: [email protected] or by phone: 01 4162486.

Page 182: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

164

Voluntary Participation

Your participation in this study is voluntary and you are free to withdraw at any

time without providing a reason. If you are happy to participate please complete

the attached consent form and return to Ms. Marie Byrne before taking part. Thank

you for taking the time to read this correspondence and for considering taking part

in this research.

Yours sincerely

Marie Byrne

TRINITY COLLEGE DUBLIN

INFORMATION SHEET FOR PARTICIPANTS – SEMI-STRUCTURED

INTERVIEWS

Dear Colleague,

I would like to invite you to take part in a research study entitled “Opportunities

for, potential benefits of and challenges to process improvement (based on the

introduction of information technology) in the outpatient physiotherapy department

at St. James’s Hospital”. This research is being undertaken as part fulfilment of an

MSc in Health Informatics in Trinity College Dublin (TCD).

Please read the following information carefully and ask if you do not understand

any part of it or would like more information.

Who is organising the research study?

This research study is being undertaken by Ms. Marie Byrne as part of an MSc in

Health Informatics in Trinity College, Dublin.

The study will be completed between January and May 2013.

Why have I been chosen?

We are inviting you to participate in this study as you have carried out a process

improvement initiative in a physiotherapy or another similar setting.

Background of research:

This research study is concerned with a detailed review of the workflow in an

outpatient physiotherapy setting to seek out opportunities for, potential benefits of

and challenges to process improvement (based on the introduction of information

technology).

The overall aim of this research is to provide a roadmap to process improvement in

outpatient physiotherapy and similar settings as there is a very limited research

base in this area.

Objectives:

Page 183: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

165

• To outline the goals of process improvement

• To map out the current workflow from patient referral to discharge and/or

onward referral

• To validate this workflow with relevant team members to ensure the current

situation is accurately reflected in the workflow

• To collect baseline data to allow for benefit realisation studies to take place

in the future

• To highlight process improvement opportunities

• To determine potential benefits of any process improvements

• To outline possible challenges

What is the purpose of the research study?

The purpose of this study is to review opportunities for process improvement

(based on the introduction of information technology) along the physiotherapy out-

patient pathway, to outline potential benefits of any change and to highlight any

challenges that may exist to prevent realisation of such benefits.

What will happen to me if I take part?

You will be e-mailed the detail of the current workflow in the outpatient

physiotherapy department at St. James’s Hospital to review. The researcher will

then carry out a semi-structured telephone interview with you where you will be

asked to highlight opportunities for, benefits of and challenges to process

improvement as you see them. The researcher will take written notes of the

interview, transcribe these notes into a soft copy format and e-mail the notes to

you to confirm their accuracy.

What will happen to the results of the research study?

The results of the research will serve to inform the researcher of opportunities for

the introduction of IT, the benefits of such an introduction and the possible

challenges to realization of such benefits.

The results of the study will be submitted as part of the TCD masters programme.

The work may be further developed with the intention of publication in a peer

reviewed journal. The research may be used by others for academic research. In

addition the research outcomes are likely to be presented at selected conferences,

seminars or workshops in Ireland.

The results can be made available to all research participants on completion of the

research study.

Confidentiality - who will know I am taking part in the research study?

All information, which is collected during the course of the research, will be kept

strictly confidential.

Conflict of interest:

Page 184: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

166

The main researcher is a physiotherapy manager in the physiotherapy department

in which the research will be undertaken.

Expected duration:

It will take approximately one hour to complete each interview.

Procedure to be used if assistance or advice is needed

In the event that you require further information about this study please contact

Marie Byrne who will be happy to answer your questions. Marie can be contacted by

email: [email protected] or by phone: 01 4162486.

Voluntary Participation

Your participation in this study is voluntary and you are free to withdraw at any

time without providing a reason. If you are happy to participate please complete

the attached consent form and return to Ms. Marie Byrne before taking part. Thank

you for taking the time to read this correspondence and for considering taking part

in this research.

Yours sincerely

Marie Byrne

TRINITY COLLEGE DUBLIN

INFORMATION SHEET FOR PARTICIPANTS – FOCUS GROUP

Dear Colleague,

I would like to invite you to take part in a research study entitled “Opportunities

for, potential benefits of and challenges to process improvement (based on the

introduction of information technology) in the outpatient physiotherapy department

at St. James’s Hospital”. This research is being undertaken as part fulfilment of an

MSc in Health Informatics in Trinity College Dublin (TCD).

Please read the following information carefully and ask if you do not understand

any part of it or would like more information.

Who is organising the research study?

This research study is being undertaken by Ms. Marie Byrne as part of an MSc in

Health Informatics in Trinity College, Dublin.

The study will be completed between January and May 2013.

Why have I been chosen?

Page 185: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

167

We are inviting you to participate in this study as you are familiar with the current

processes in the outpatient physiotherapy department at St. James’s Hospital or

have an interest in information technology in this or another setting.

Background of research:

This research study is concerned with a detailed review of the workflow in an

outpatient physiotherapy setting to seek out opportunities for, potential benefits of

and challenges to process improvement (based on the introduction of information

technology).

The overall aim of this research is to provide a roadmap to process improvement in

outpatient physiotherapy and similar settings as there is a very limited research

base in this area.

Objectives:

• To outline the goals of process improvement

• To map out the current workflow from patient referral to discharge and/or

onward referral

• To validate this workflow with relevant team members to ensure the current

situation is accurately reflected in the workflow

• To collect baseline data to allow for benefit realisation studies to take place

in the future

• To highlight process improvement opportunities

• To determine potential benefits of any process improvements

• To outline possible challenges

What is the purpose of the research study?

The purpose of this study is to review opportunities for process improvement

(based on the introduction of information technology) along the physiotherapy out-

patient pathway, to outline potential benefits of any change and to highlight any

challenges that may exist to prevent realisation of such benefits.

What will happen to me if I take part?

You will be involved in a focus group to review the workflow with approximately five

other participants. Participants will be asked to highlight opportunities for process

improvement along with potential benefits and challenges. The focus group will be

recorded on a Dictaphone and the researcher will take written notes.

What will happen to the results of the research study?

The results of the research will serve to inform the researcher of opportunities for

the introduction of IT, the benefits of such an introduction and the possible

challenges to realization of such benefits.

The results of the study will be submitted as part of the TCD masters programme.

The work may be further developed with the intention of publication in a peer

Page 186: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

168

reviewed journal. The research may be used by others for academic research. In

addition the research outcomes are likely to be presented at selected conferences,

seminars or workshops in Ireland.

The results can be made available to all research participants on completion of the

research study.

Confidentiality - who will know I am taking part in the research study?

All information, which is collected during the course of the research, will be kept

strictly confidential.

Conflict of interest:

The main researcher is a physiotherapy manager in the physiotherapy department

in which the research will be undertaken.

Expected duration:

The focus group will take a maximum of two hours.

Procedure to be used if assistance or advice is needed

In the event that you require further information about this study please contact

Marie Byrne who will be happy to answer your questions. Marie can be contacted by

email: [email protected] or by phone: 01 4162486.

Voluntary Participation

Your participation in this study is voluntary and you are free to withdraw at any

time without providing a reason. If you are happy to participate please complete

the attached consent form and return to Ms. Marie Byrne before taking part. Thank

you for taking the time to read this correspondence and for considering taking part

in this research.

Yours sincerely

Marie Byrne

Page 187: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

169

Appendix E:

Ethics

Page 188: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

170

Page 189: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

171

Page 190: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

172

Appendix F: Key to notations on process maps

A-REFERRAL MANAGEMENT AND TRIAGE

A1 Referral to physiotherapy is placed on the EPR (Cerner Electronic Patient Record) by an

internal consultant or physiotherapist (at fracture clinics)

A2 An EPR referral is not currently generated for external referrals (GP referrals for staff

and patient referrals from other hospitals) so the paper referral for these categories

arrives in the post or is handed in by the patient (make up less than 5% of referrals)

A3 Paper referrals are lifted from the printer by the clerical staff

It takes an average of 10.5 seconds to complete steps A3, A4 and A5 for each referral.

These are steps are carried out on a batch of referrals rather than individual referrals.

A4 Clerical staff log on to the EPR, enter the patient’s MRN and “complete” in message

centre list. This indicates to the referrer that the referral has been received in

physiotherapy

A5 Paper referrals that have been “completed” on the EPR by the clerical staff are carried

from reception and put in a tray in the main physiotherapy out-patient department

A6 The paper referrals (from external source and internal (EPR)) are triaged by a senior

physiotherapist

A7 The physiotherapist decides whether the referral is “Urgent”, “Routine” or “Fracture”

or to be referred locally/to community (note there are 4 triaging categories) and writes

this on the paper referral

A8 Using a physiotherapy coding system the physiotherapist determines the anatomy and

pathology of the reason for referral and writes this on the paper referral. Each referral

will have a 2 or 3 character code written on it

A9 Paper referrals that have been triaged by the physiotherapist are carried from the

main physiotherapy outpatients area and put in a tray in the physiotherapy reception

It takes an average of 39.38 seconds to complete steps A6, A7, A8 and A9 for each

referral. These are steps are carried out on a batch of referrals rather than individual

referrals. As for steps A3, A4 and A5 one referral would involve as much walking as 10

or 20. Some referrals are difficult to triage and code due to the limited amount of

Page 191: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

173

information on them and so further background information on the patient is sought

from the EPR (scans, x-rays, correspondence)

A10 The clerical staff enter the referral details on an Excel waiting list spread sheet. This

involves transcribing all of the details on the paper referral in to the spread sheet. The

spread sheet is saved on the physiotherapy department G Drive and is a list of all

referrals to physiotherapy out-patients

A11 Once entered on the spread sheet the paper referrals are separated into routine and

urgent and those to be referred to community/locally. The routine and urgent referrals

are put into separate manual folders. Fracture (#) clinic referrals get a new file made

up for each of them as they don’t go on the waiting list as have return appointments.

Fracture clinic patients are patients that are seen by a physiotherapist attending a

consultant orthopaedic clinic where the patient is seen directly by the physiotherapist

for advice and exercise and given a follow-up appointment in the main physiotherapy

out-patients department before they leave the # clinic

It takes an average of 38.7 seconds to complete steps A10 and A11 for each referral.

These are steps are carried out on a batch of referrals rather than individual referrals.

A12 If a patient is referred onwards to the community services or their local hospital they

exit the workflow at this point and are discharged

B (a)-WAITING LIST MANAGEMENT AND APPOINMTENT BOOKING

There is some variation between the clerical staff as to what happens when the appointment is

allocated

B (a) 1 The manual waiting list folders (paper referrals in standard folders) are reviewed by

the clerical staff in conjunction with free new patient slots on the PAS

OR

B (a) 2 The clerical staff review all of the new patient slots in all clinics on the PAS for the

coming 3 weeks. This involves going into each clinic individually then each day

individually

B (a) 3 Any new slots that are free are documented on a piece of paper

B (a) 4 The manual waiting lists are then reviewed to determine which patients are next in

line for appointments

Page 192: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

174

B (a) 5 The clerical staff ring the next patient on the manual waiting list

B (a) 6 The patient tells the clerical staff member they no long need physiotherapy or they

wish to be referred locally

B (a) 7 The clerical staff book patients in to all of the available clinic slots on the PAS

B (a) 8 Following the printing of all clinic lists and pulling of physiotherapy notes [ which

happens on a daily basis for the following day] the clerical staff review the clinic lists

and determine which return slots are free. Return slots are set up on creation of a

clinic template to allow patients returning to physiotherapy out-patients to be booked

in as needed

B (a) 9 The need for a follow-up appointment at the end of a scheduled appointment is based

on clinical need which is determined by the physiotherapist

B (a) 10 Patients book another appointment as required before leaving the department

The average time to carry out this task is outlined as 60.64 seconds (range 20.25 – 124.9

seconds).

B (b) – WAITING LIST DATA

B (b) 1 Each month physiotherapy management request data on the length of the waiting list

and the numbers waiting in various categories 0-2 weeks, 3-6 weeks, 7-10 weeks. This

information is manually calculated from the manual waiting list folders that store the

paper referrals. The information on the length of the waiting list and the numbers

waiting is entered into an Excel waiting list spread sheet. This spread sheet divides the

waiting list up per consultant, per specialty and outlines the numbers waiting in each

of the HSE categories. This information is required for HSE CompStat and is

benchmarked against 29 hospitals nationally

B (b) 2 The manual waiting list folders are reviewed. This is a completely manual process

B (b) 3 The number of referrals in each of the folders is manually counted

B (b) 4 Waiting time is calculated for urgent and routine referrals. This is done by calculating

the time of referral to today for the longest person waiting in each of the triage

categories

Page 193: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

175

B (b) 5 Data on numbers in each category and time to routine and urgent appointment are

entered on the Excel waiting list spread sheet

B (b) 6 A patient phones the department asking when they will receive an appointment

B (b) 7 The clerical staff ask the patient when they were seen at the consultant clinic

B (b) 8 The clerical staff review the EPR to determine if a referral was placed

B (b) 9 The clerical staff check the manual waiting list folder to determine if the referral is

there

B (b) 10 The clerical staff review the spread sheet with all the referral details to ensure a

referral was received

B (b) 11 Patient advised that their referral has been received and is told length of waiting list

B (b) 12Patient advised no referral received and they need to go back to their consultant

B (b) 13The clerical staff refer to the PAS to determine when the patient was at the

consultant’s clinic if the patient does not know

C (a)-PATIENT ATTENDANCE

C (a) 1 The patient receives a reminder text message for all appointments 5 days in advance.

This reminder is set up in an Outpatient Reminder System (ORPS) which is linked to the

PAS

C (a) 2 The patient arrives in to the physiotherapy out-patient department

C (a) 3 The clerical staff determine if this is the patient’s first appointment

C (a) 4 The patient is registered to the relevant clinic on the PAS as a NEW attendance with

the clerical staff confirming the patient’s details (e.g. mobile phone number)

C (a) 5 The clerical staff retrieve the patient’s referral from the new referrals box

C (a) 6 A front sheet is printed from the PAS. This sheet outlines the patient’s personal details

including GP, medical card number and attendances at consultant out-patient clinics

C (a) 7 Department policies are outlined to the patient and a copy given to the patient with a

yellow appointment card

Page 194: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

176

C (a) 8 The clerical staff make up physiotherapy notes which include the referral, front sheet,

an assessment sheet, a database and continuation sheets and walk through to the

main department to give the notes to the physiotherapist

C (a) 9 The patient is registered to the relevant clinic on the PAS as a RETURN attendance

C (a) 10 The physiotherapist treats the patient for the duration of their scheduled appointment

C (a) 11 A decision is made by the physiotherapist based on the patient’s clinical need that

further treatment is or is not require

C (b) PATIENT NON-ATTENDANCE

Did Not Attends (DNA)

C (b) 1 Patient does not attend (DNA) for their scheduled physiotherapy out-patient

appointment so they are not registered on the PAS

C (b) 2 This DNA is automatically registered on the PAS 24 hours after the scheduled

appointment time

C (b) 3 The physiotherapist determines if this is the patient’s first appointment – if it is they

are discharged as per policy.

C (b) 4 If it is not the patient’s first appointment they are given two weeks to make a further

appointment before they are discharged

Cancellations

C (b) 5 Patient rings to cancel a scheduled appointment

C (b) 6 Patient determines no further treatment is required so they self-discharge

C (b) 7 The patient makes another appointment directly at the time of cancelling

C (b) 8 The physiotherapist determines if this is the third consecutive cancellation recorded

on the PAS and if so the patient is discharged

Page 195: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

177

D-DISCHARGE

D1 The physiotherapist decides if a referral to community is most appropriate

D2 The physiotherapist decides if a referral to the patient’s local hospital is most

appropriate

D3 The physiotherapist prints off any relevant x-ray/scan results from the EPR and

attaches these to the referral

D4 The referral with all relevant details attached is posted to the patient’s local

hospital/community care area

D5 Community care area is based on the patient’s address and it is necessary to look up a

street index to determine the correct area. This is a manual process which involves

accessing a separate PDF document. This is carried out by the physiotherapist

D6 The patient is informed by posted letter that they have been referred to their

community service

D7 Details of all referrals to the community are entered into the community referrals

Excel database

D8 Patient Discharged is written on the referral/physiotherapy notes

D9 Referrals/physiotherapy notes are filed away in the current year archive

The physiotherapist does not routinely write a discharge letter or update letter to the referrer

(since Nov ’12 due to lack of clerical capacity)

Exceptions:

If the physiotherapist feels the patient needs to access further investigations (MRI) or

needs further interventions (Injections)

If the patient is unsuitable for physiotherapy

E-RETRIEVING AND FILING NOTES

E1 Each day the physiotherapists file away return patient physiotherapy notes

Page 196: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

178

E2 Each day the clerical staff file away new patient physiotherapy notes (a new file needs

to be made up for these patients)

E3 Each day the clerical staff retrieve physiotherapy notes for all of the patients due to

attend the next day. This is based on the clinic list for each clinic which is printed off

the PAS. The notes are stored in the main reception area and are filed by clinic,

alphabetically. It takes an average of 10.44 seconds to retrieve each file (an average of

25 files are retrieved daily)

E4 As time allows the clerical staff archive physiotherapy notes of patients who have been

discharged. The current year notes are stored in an office beside the main reception

area. It takes an average of 16.3 seconds to file each set of notes

E5 Medico legal requests including; Freedom of Information (FOI), Routine Access and

Medico legal reports require the clerical staff to retrieve the relevant patient notes.

These notes might be filed in the current year archive or old archive

E6 If a patient DNAs their appointment the physiotherapist does not file the notes away.

These notes are kept for 2 weeks in a DNA box and then discharged if the patient has

not made another appointment within that time frame

E7 If a patient Cancels their appointment and does not wish/need to make another

appointment the physiotherapist removes these notes from the active notes

immediately and they are discharged

E8 If a patient Cancels their appointment and does not make another appointment for 2

weeks their notes are removed from the active notes by the physiotherapist as time

allows and they are filed away with the discharged notes. When they are removed

from the active files is adhoc and involves the physiotherapist going through their

clinic files one by one

Page 197: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

179

Appendix G: Stakeholder Analysis

Stakeholder

Patient

Physiotherapists

Clerical Staff

Physiotherapy Managers internal

Physiotherapy Managers external (29 acute hospitals compared)

Senior Management

HSE staff

IT staff

Finance staff

Community

Other hospitals

All consultants currently referring and who may refer in the future

Page 198: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

180

Appendix H: Draft Benefits Realisation Plan

Benefits Measures

Decrease in waiting time for patients

Improved patient outcomes as

patients don’t become chronic while

waiting

Reduced time to triage referrals for

physiotherapists and clerical staff

Decreased cost of paper and printing

components

Decreased time spent retrieving and

filing notes

Reduction in number of unanswered

calls

Easier access to information

Numbers waiting

Waiting times

Throughput (new patients seen and

New: Return ratios)

New: Return ratios

Reduction in number of steps in

process and actual time to complete

triaging

Total cost

Number of notes filed and retrieved

Time spent

% of calls unanswered

Staff satisfaction with information

access

Staff presentation of data retrieved

Page 199: Process Improvement in a Physiotherapy Outpatient Setting · design. The terminology used to describe Lean Thinking interventions also varies as some organisations have adapted Lean

181

Improved staff satisfaction

Improved Patient satisfaction

Close off of patient attendance

Decreased non-clinical activity for

physiotherapists

for annual reports/audits

Survey

Survey

Discharge summaries

Review of process steps and timings