proco’s line stopping methods do not stress the pipes · pdf fileen 13480-3 metallic...

1
Proco Services AB (Head Office) Västberga Allé 26 SE-126 30 Hägersten Tel +46 8 734 05 80 Fax +46 8 734 05 81 E-mail [email protected] Proco Services AB (South Sweden) Brovägen 12 SE-266 97 Hjärnarp Tel +46 43 147 80 20 www.proco.se/en Before the repair or maintenance work of pipelines in large dimen- sions with high pressure, it is important to affect the system as little as possible. Too large branch connection on the main pipe at line stopping in this type of system results in unnecessary stress, which increases the risk of future leakage. Obviously, it is important to minimize this risk in the district heating system, a crucial part of the infrastructure and a system with an expected life-span of 30 years. With a patented solution, Proco Services can perform line stopping in pressurized piping systems without drilling unnecessary large holes in the pipes. This will ensure the strength of the connection on the main pipe and the system is leak proof the expected life time. Proco Line Stopping DN300 from below. Do=323,9mm, dborehole=168mm. Strength Proco Services places great emphasis on safety when engaging on pressu- rized piping systems. This is especially important when working on the district heating system. Pressure vessel steel P235GH or better are used in all con- nections to district heating pipes. Strength calculations are the basis for the engagement and connections which are left on the pipes after the the work. It meets the requirements of the following European standards and are approved for 16 bar and 120° C. Pressure tests are always preformed on both connections and tools before work starts. EN 13480-3 Metallic industrial piping– Design and calculation. EN 13941 Design and installation of pre- insulated bonded pipe system for district heating. Proco’s Line Stopping methods do not stress the pipes Requirement:

Upload: vobao

Post on 28-Mar-2018

219 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Proco’s Line Stopping methods do not stress the pipes · PDF fileEN 13480-3 Metallic industrial piping– Design and calculation. EN 13941 Design and installation of pre-insulated

Proco Services AB (Head Office)Västberga Allé 26 SE-126 30 Hägersten Tel +46 8 734 05 80 Fax +46 8 734 05 81E-mail [email protected]

Proco Services AB (South Sweden)Brovägen 12 SE-266 97 HjärnarpTel +46 43 147 80 20www.proco.se/en

Before the repair or maintenance work of pipelines in large dimen-sions with high pressure, it is important to affect the system as little as possible. Too large branch connection on the main pipe at linestopping in this type of system results in unnecessary stress, which increases the risk of future leakage. Obviously, it is important to minimize this risk in the district heating system, a crucial part of theinfrastructure and a system with an expected life-span of 30 years.

With a patented solution, Proco Services can perform line stopping inpressurized piping systems without drilling unnecessary large holes in the pipes. This will ensure the strength of the connection on the main pipe and the system is leak proof the expected life time.

Proco Line Stopping DN300 from below. Do=323,9mm, dborehole=168mm.

StrengthProco Services places great emphasis on safety when engaging on pressu-rized piping systems. This is especially important when working on the districtheating system. Pressure vessel steel P235GH or better are used in all con- nections to district heating pipes. Strength calculations are the basisfor the engagement and connections which are left on the pipes after thethe work. It meets the requirements of the following European standards and are approved for 16 bar and 120° C.Pressure tests are always preformedon both connections and tools beforework starts.

EN 13480-3

Metallic industrial piping–

Design and calculation.

EN 13941

Design and installation of pre-

insulated bonded pipe system for district heating.

Proco’s Line Stopping methodsdo not stress the pipes

Requirement: