Procurement Reform – LEAN Sourcing
A new approach that requires us to change the way we work
UNCLASSIFIED
Briefing for policy staff & project managers
The Procurement Reform Agenda
• The Coalition Government has set out the requirement to support the implementation of the Growth Agenda and to ensure that more Small & Medium Sized Enterprises win government contracts. The requirement includes a new approach to the way central government departments carry out procurement.
• This requires departments to think very differently about how procurements are planned and delivered.
• Subsequently, this will require a much closer working relationship between procurement staff and colleagues from policy areas and project management functions than has previously been the case.
• The new approach has been endorsed by Francis Maude, the Minister for the Cabinet Office and all central government departments and their arms length bodies are required to adopt it.
The new policy requirements
• The new approach comprises the following new government policy requirements:
– Adoption of a LEAN sourcing approach that strips out waste and reduces costs
– A requirement to carry out significant levels of pre-procurement market engagement with diverse range of prospective suppliers, including SMEs in order to warm-up the market, test our thinking and generate ideas for innovation as part of the development of outcome-based specifications.
– Contracts should be broken down into lots where appropriate, and requirements that are below the value of £100K should be rapidly sourced through the new Government Dynamic Market place.
– All Government procurements are strongly encouraged to use the Open Procedure.
– There is now a presumption against the use of the Competitive Dialogue procedure which has often resulted in slowing things up unnecessarily and typically incurs huge costs on both sides.
– There is an expectation that all but the most complex procurements are completed with 120 working days (publication of the advert to the contract award decision date).
What this means for our department• Collectively, we need to develop:
– A detailed understanding of what the pipeline of potential procurements is so that these can be planned and resourced effectively
– Strong recognition within business areas that early engagement and joint working with the procurement function (as part of a multi-disciplined procurement team) is a critical success factor
– A full understanding of the key principles of the LEAN sourcing process and how engagement with suppliers in the market before establishing a formal procurement process has to become standard practice (we can no longer rush out with an advert)
– Strong acceptance that large complex contracts with large suppliers are no longer going to be permitted (in the vast majority of cases) and that increasing the number of contracts awarded to SMEs (through breaking requirements into lots) is the new way forward (where appropriate).
– Strong recognition that departmental performance in delivering procurements within 120 days will be subject to ongoing scrutiny by ERG and No10 and that we can only achieve this by working together.
– More efficient and effective approaches to taking business decisions to ensure that we do not incur any unnecessary delays.
7 key principles of the new approach
5
1. Establish a clear understanding of required business outcomes
2. Engage with the market in order to shape and confirm that the business requirement is attractive to a diverse range of suppliers
4. Do not commence formal procurement until thorough engagement with suppliers has taken place.
6. Use e-sourcing tools to support the procurement and follow the LEAN Standard Operating Procedures (SOPs)
7. Measure and manage performance through continued focus on turnaround times and costs. Advert to contract award decision date should be completed within 120 working days
3. Use LEAN thinking and visual tools to set up and run a well planned and efficient process
5. Streamline any engagement with suppliers and stakeholders by using a ‘boot camp’ approach to make best use of limited time
Strong focus on preparing to go to market
This is a key activity that takes time and careful
planning
Strong focus on running a fast procurement process
This is a key activity that requires collective effort and
is dependant on effective preparation
Route Key Features Use
Open All interested suppliers may respond to the advertisement in the OJEU by tendering for the contract.Well defined, outcome-based requirements will help ensure a manageable number of bid responses from good quality and capable suppliers.
There is a government commitment towards greater use of the Open procedure.
Restricted A two stage process where a selection of suppliers who respond to the advert is made and only they are invited to submit a tender for the contract. The selection (pre-qualification) questionnaire (PQQ) must only contain proportionate and relevant criteria
Use in limited circumstances where pre qualification is essential.. The use of a standardised , stripped back ‘core’ PQQ is mandatory across central Government, and not used at all of sub £100k work.
Competitive Dialogue
Following an advert and a selection process potential suppliers are invited to enter into dialogue to develop one or more suitable solutions before chosen suppliers are invited to tender.
The Government has set a presumption against the use of competitive dialogue.
Negotiated One or more potential suppliers are selected to negotiate the terms of the contract. An advert is usually required.
Only to be used in extremely limited circumstances described in the Regulations, for example, where a previous procurement was discontinued because of unacceptable/irregular tenders.
6
Procurement routes – our choice has become limited
The new LEAN sourcing approach – the 5 Stage Process
7
1. Business need & baselining
2. Market analysis & sourcing strategy
3. Supplier identification4. Execution of
sourcing strategy5. Finalise contract
Mobilisation
Pre-Procurement Market Engagement Sourcing and Contracting
Talk to potential suppliers, publicise requirement (preferably by using a project specific PIN) to warm the market up and advertise the industry engagement event
Establish a project planning and performance hub in the mobilisation phase and use visual management and e-sourcing tools to drive the process and to measure and manage performance including turnaround times in line with the 120 day target.
Industry boot camp to capture the suppliers’ views on your requirement, on the viability, and on possible delivery options and where appropriate to facilitate meetings between suppliers to explore the potential for the establishing consortia, partnering arrangements and / or subcontracting opportunities.
Pre-OJEU readiness - the preparation and subsequent publication of a bidders pack at OJEU including requirements, draft terms and conditions, selection criteria, evaluation strategy and criteria and procurement timescales. This transparency allows suppliers to make informed decisions as to whether they wish to bid.
Execution of sourcing strategy through structured workshops, boot camps and tightly managed project plans
Use standstill period to prepare for publication of the contract documentation and to finalise delivery and contract management plans
Driven by visual management tools
The new approach requires more work to be carried out before going to market
8
6. LEAN Sourcing Process Overview – General
2. Mobilisation
The sourcing team is set up for success, all associated stakeholders are clear on requirements of the business need
22 to 66 calendar days from issue of
OJEU
10 days
1. Business Need Identification, Baselining & Market Analysis
Ensure identification & clear articulation of the business need
2. Sourcing Strategy
Setup the procurement & develop the most efficient sourcing strategy
4. Supplier Identification (OJEU)
Publish requirements through a contract notice in the supplement to the Official Journal of the European Union
5. Supplier clarification
Respond to all questions & clarifications simultaneously
6. Evaluation of Tenders
The best solution is established through evaluation of tenders
7. Contract Award
Notify the supplier and finalise the contract
8. Contract Signature
Formal signature of contract
Business need, baselining & market
analysisSourcing strategy Supplier identification Execution of sourcing strategy Finalise contract
Mobilisation
Use e-sourcing
tools
Talk to suppliers
Talk to business
stakeholders
Establish a strong PPM discipline
approach and deploy visual management
techniques
Ensure that you are
ready to go to market
Drive continuous improvement in
turnaround times by measuring performance
The new LEAN sourcing approach – overview
To be completed within 120 working days
The Standard Solution enables the execution of the LEAN sourcing process. It provides a suite of tools that you can use to execute the sourcing process from business need identification and baselining through to contract award & signature.
The LEAN sourcing tools that have been developed to help us
Team Implementation Plan (TIP)An action plan showing who will do what and when in specific functions and processes
Policy Business Need & Baselining Market Analysis & Sourcing Strategy Supplier Identification Execution of Sourcing Strategy Finalise Contract Managing the contract & Supplier
Handing off to contract & supplier management
Activity: Outputs: Activity: Outputs: Activity: Outputs: Activity: Outputs: Activity Output: Activity: Output: Activity Outcome:Analyse business needs (SOP 1.1)
Intial make or buy consderations and intial thinking on approach to market (Covered by SOP 1.1)
Sound understanding of business outcomes required
Run an Industry boot camp to conduct Market Analysis to identify requirements and what is available, using market specialists if appropriate (SOP 3.1)
MI updated Create OJEU notice and gain approval (SOP 4.1)
OJEU notice is published
Bidders pack published via web / e-sourcing system
Complete evaluation of responses and agree ranked list (SOP 6.1)
Undertake assurance to ensure the team are ready to progress to dialogue (SOP 6.2)
Appropriate suppliers shortlisted Hold Dialogue Boot Camps (the number of dialogues will depend on the complexity of the specified outcome, number of bidders, workstreams) (SOP 7.1)
Conduct immediate Evaluation & Feedback (SOP 7.1)
Mutual understanding of final solution
Evaluate BAFOs / tenders (SOP 8.1)
Finalise terms & conditions of contract (SOP 8.2)
Final tenders / BAFOs received & evaluatedSuccessful bidder chosen
Contract finalised
Sign Contract (SOP 9.1) Contract signed
Operational Imperatives e.g. Expiring Contracts
Conduct initial market research (SOP1.2)
Conduct benchmarking vs current provision (SOP 1.3)
Baseline of current provision and cost Internal decision to make or buy (SOP 3.2)If 'Buy' then use decision tool to identify the most appropriate procurement route
MI updatedFinalise & issue the invitation to participate in dialogue (ITPD) (SOP 6.3)
Dialogue invite issued (ITPD) including:~ Requirement~ Outline Solution Template~ Draft joint statement of intent & revised project plan ~ Refined T&Cs with draft schedules
Negotiation of contract (key terms and principles)( SOP 7.1)
Facilitate the undertaking of due diligence (SOP 7.2)
Draft final contract issued (including finally agreed solution).
Gain approval to award decision (SOP 8.3)
Issue alcatel letter (notify of standstill period) (SOP 8.4)
Debrief Suppliers
Update Full Business Case
Standstill (Alcatel) letter issued
Suppliers receive feedback
Approved Full Business Case updated
Publish contract award notice on TEDPublish contract on Contracts Finder
Contract published unredacted on e-sourcing system or stored in appropriate document management systemContract published on Contracts FinderMI Updated
Write 1st draft of the strategic outline business case (SOP 1.4)
First draft Strategic Outline Business Case (SOBC) including draft of outcomes and first draft of project plan.
Write procurement strategy and get approval (SOP 3.3)
Procurement strategy agreed including:~ Outcomes defined~ Procurement procedure~ Standard T&Cs
Conduct supplier feedback (SOP 6.4)
All suppliers receive feedback where requested / appropriate
Formerly close dialogue & invite Best & Final Offers (BAFOs) / nvitation toSubmit Tender (ITST) (SOP 7.3)
Dialogue Closed & invitation to submit Best and Final Offers (BAFOs) issued
Write and publish a project specific Prior Information Notice (SOP 1.5) & check pipeline of sourcing projects has been updated & published
Project Specific Prior Information Notice (PIN) published (Requirements, scale & contract value)Updated pipeline of sourcing projects published on departmental website
Understand & agree requirements, scale & value
~ Initial negotiation strategy (what is in and out of dialogue)~ Scale and Value~ Contract Management Strategy~ Selection Criteria & Methodology
Refine project plan
Finalise bootcamp logistics (SOP 6.5)
Plan dialogue sessions (SOP 6.6)
MI updated
Bootcamp logistics finalised
Dialogue plan in place
Draft Full Business Case (SOP 7.4) Full Business Case drafted
Update Business Case (From Stategic Outline Business Case to Outline Business Case) (SOP 3.4)
Create Bidders Pack (SOP 3.5)
Outline Business Case updated
Bidders Pack agreed including:~ Standard selection criteria~ Extended selection criteria (tech/prof capability)
~ Prospectus (inc. requirements)~ First draft Ts&Cs~ Evaluation strategy & criteria~ Explicit guidelines on timelines, security~ Timescales / Project Plan
Carry out assurance & obtain approval to proceed (SOP 3.6 )
Approval to proceed
Activity: Outputs:Set up and run web-based Q&A facility (SOP 5.1)
Suppliers have increased understanding of requirementWeb pages recording all clarifications with suppliers
Real time evaluation of supplier returns (SOP 5.2) against selection criteria:1) Pass / Fail2) Qualitative Scored
Incomplete ranked list based on responses received before deadline
Create an Invitiation to Participate in Dialogue (ITPD) (SOP 5.3)
1st draft ITPD created including:~ Requirement~ Outline Solution Template~ Draft joint statement of intent & revised project plan ~ Refined T&Cs with draft schedules~ Evaluation stratgey & criteria
10 days
Approvals plan in place
Create project performance hub (SOP 2.2)Complete team skills assurance (SOP 2.3)Establish & brief Project Board (SOP 2.4)
Establish dialogue boot camp logistics (SOP 2.7)
Establish industry boot camp logistics (SOP 2.6)Venues secured
6) Finalisation of Supplier Identification
Activity: Establish a cross disciplined team (SOP 2.1)
Purpose - Choose the supplier and finalise the contract
Room, plan, communication strategy etc in place
1 week1 week
Project Board in place & understand objectives, evaluation Strategy agreed with end participantsMI updated
Purpose - To identify a potential list of qualified suppliers
Purpose - To identify a potential list of qualified suppliers
Dedicated team in place
2 weeks
Purpose: To have an agreed outcome focused contract in place at the best possible price from the chosen supplier
4) Supplier Identification (OJEU)
Policy Decision - Perception of Need
Date set for contract renewal
8) Finalisation of Contract
Purpose - Formal signature of contract
Purpose - To publish requirements through a contract notice in the
supplement to the Official Journal of the European Union
30 days
SCOPE
9) Contract Signature7) Execution of Sourcing Strategy through Competitive Dialogue
2 weeks
Purpose - Licensed sourcing team is set up for success, all associated stakeholders are clear on requirements
5) Supplier Identification
4 - 6 weeks
Outputs:
Establish what approvals will be required & when (SOP 2.5)
Proposed Future State map for Government Sourcing Process (Competitive Dialogue)
3) Market Analysis & Sourcing Strategy
Harmonious Relationship
Contract Management
Delivery plan & governance
0 days
2) Mobilisation
1) Business Need Identification & Baselining
Purpose - To ensure identification & clear articulation of the business need
Purpose - To understand what the market can provide & identify sourcing strategy
6 weeks1 week2 weeks
Purpose - The best outcome based solution established through fact based negotiations
System allowing potential bidders to access bidders pack (e-sourcing System )Govt/Dept.
30 Days
30 days from issue of OJEU
10 Days
10 days from Contract Aw ard to Contract signature
BIQ
BIQ
BIQ
KEY
BIQ= Built in quality
= Specialist Legal support
= Treasury
Govt/Dept.
E-sourcing tools OJEU compliant
System allowing department to evaluate returns from bidder (e-sourcing System)
E-soucing tools OJEU compliant
Log interest electronically in the sourcing opportunity
complete Selection criteria electronically
Receive timely feedback and invitation to attend dialogue
Attend dialogue boot camps and receive transparent & timely feedback & issue solutions
Agree and sign contract
BIQ
System updated detailing the final details and contract published
E-sourcing tools OJEU compliant
What - The M ake/Buy/Internal decision w as correct - and procurem ent approach correctly identified
What - OJEU , Bidder aw areness, technical evaluation all m eet agreed standard
What - Evaluation results ready to proceed to dialogue
What - The team are in place and ready to proceed
ActivityOpportunity to refine delivery plan and complete contract management plan, with briefing slides including rationale for negotiation
BIQ
What - Dialogue boot cam ps are standard, ready for contract negotiations
Database advertising all sourcing opportunities (Contracts Finder & Tenders Electronic Daily)
E-sourcing tools OJEU compliant
TimelineThe timeline is dependant upon the size, the complexity and the risk of the procurement.
A depiction of the supplier journey, the touch points with the department and the places where deselection occurs.
What - Productive use of 30 day OJEU period Bidders fully understand the requirem ents enabling them to subm it optim um bid or dese lect
BIQ
e-sourcing System
E-sourcing tools OJEU compliant= Business
Case
E-sourcing tools OJEU compliant
Database advertising sourcing opportunities (Contracts Finder & Tenders Electronic Daily)Departmental website
Govt/Dept.
BIQ
What - Contract, final business case and evaluation to agreed standard
Lean Procurement Project Key Performance Indicators
September 2011V2.0
UNCLASSIFIED
0
50
100
150
200
250
300
350
400
450
500
Turnaround time working days - OJEU to contract signature
Planned
Actual
Competitve Dialogue Average
Visual ManagementA way of displaying information to drive the performance of the process & specific parts of the process
KPIsPerformance indicators to measure turnaround times and cost of running procurements.
Standard Operating Procedures (SOPs) A set of high level desk instructions describing the best known method for carrying out the activities described in the value stream map
Procurement Route Decision Tree
A tool to assist procurement
professionals to think through and identify the most appropriate procurement route for their requirement.
Visual Management in Procurement
Project Performance Hub Guidance V3.0
Use for the duration of Project
Visual Management in Procurement
Project Performance Hub Guidance V3.0
Use for the duration of Project
Value Stream Map The route map which sets out the LEAN sourcing process.
7. Procurement Route Decision Tree
8
COMPETITIVE DIALOGUE PROCEDURE
Government presumption against its use
Use of Competitive Dialogue may be challenged by ERG
Follow the Competitive Dialogue Standard Operating Procedures (SOPs).
RESTRICTED PROCEDURE
Confirmed by Commercial Director / Head of Procurement
Follow the Restricted Procedure LEAN sourcing Standard Operating Procedures (SOPs)
Use mandatory standardised PQQ and ensure it contains proportionate and relevant criteria, and not at all for sub £100k work
Yes but there is strong evidence the market is very large and the pre-qualification is the only option
NOYES
OPEN PROCEDURE
Use the Open Procurement Route following the Standard Operating Procedures (SOPs)
There is a government commitment to move towards
greater use of the Open Procedure, see:Cabinet Office
YES
You have been approached with a new requirement
ORyou have an operational imperative
– e.g. an expiring contract
1. Analyse the requirement to ensure that you have a sound understanding of business outcomes required and engage the market
StartIs your requirement covered
by Government's Central Procurement Programme for
common goods and services?
Refer to the Government
Procurement Service.
Is your requirement covered by an existing departmental or cross government contract?
Use pre-existing departmental or cross
government arrangement
YES
NO
YES2. Engage the market to sound out ideas on the best way to shape, and where possible, simplify and breakdown the requirement
Now that you have completed pre procurement market engagement (including publication of a project specific PIN and Industry Bootcamp) can you define and specify in accordance with the appropriate EU Regulations:
1. How the project outcome will be delivered, and2. How the contract and commercial deal will be structured
NO
Routinely challenge your sourcing strategies to ensure enough consideration has been given to whether the requirement can be simplified or broken up to allow for greater competition in the marketplace, including SMEs
Key specific differences in practice
Typical as-is New approach
1. Used rarely, and only when requirements are so specific and the target supply base is known to be small
1. More efficient requirements capture through stakeholder bootcamp, followed by full and comprehensive pre-procurement market engagement
2. Publish OJEU, Bidders pack (ITT including Ts &Cs) at same time, with a clear statement of requirement and evaluation criteria
Problems with this:
• Inevitable tendency to avoid using the Open route because of the lack of control over the number of bidders.
Benefits
• Provides full clarity to market and opportunity for supplier self de-selection
• Helps to ensure the widest possible market is aware of and understands the opportunity to compete pre-OJEU
Open – Standard Operating Procedures (SOPs)
Key specific differences in practiceTypical as-is New approach
1. Publish OJEU & PQQ 1. Publish OJEU, PQQ & Bidders pack (including Ts &Cs) at same time
2. Evaluate PQQ
3. Use time between 1& 2 to develop ITT (full bidders pack)
4. Issue ITT to those who get through pre- qualification
5. Evaluate responses to ITT
Problems with this: Benefits
•Suppliers may get through PQQ and not like Ts & Cs and then cause delays in timescales - waste
• Inefficient supplier self de-selection - they may not have entered the competition if they had seen full pack
•Provides full clarity to market and opportunity for supplier self de-selection
• Helps to ensure that requirement are crystal clear before going to market.
• Helps to ensure the widest possible market is aware of and understands the opportunity to compete pre-OJEU
•Helps consortia and other partnerships to form
Restricted – Standard Operating Procedures (SOPs)
Key points
1. The more quality time that is spent on pre-OJEU activities the more efficient the procurement is likely to be.
2. Reduced turnaround times (OJEU to contract award decision date) = reduced costs and improved resource utilisation
3. LEAN sourcing is not about cutting corners it is about improving efficiency, and quality as part of a repeatable approach that is subject to continuous improvement
Pipeline of known
procurements
Pre-OJEU
Setting up for success - readiness
1.Developing a clear understanding of requirement business outcomes
2.Engaging with suppliers in the market and identifying opportunities for innovation and/ or breaking requirements into more attractive lots
3.Developing a detailed understanding of the business requirement and constructing it in a way that will be clear and attractive to the market
4.Getting a team in place with the right capabilities and a clear delivery plan (that takes into account approval and assurance points)
Procurement: OJEU to Award
Execution
1.Operating a highly efficient process in line with the plan, which focuses on reducing turnaround times and costs to both the client and the suppliers within the competition but maintains quality
Risk
1. Failure to complete the pre-OJEU activities is likely to result in three things occurring:
1. A protracted procurement incurring significant costs2. A business outcome that is sub-optimal3. Dissatisfaction of key business stakeholders
The pool of scarce resources
In summary......
New policy imperatives that
may require procurement
What we need to do next......
• Business stakeholders will need to:
– Familiarise themselves with the policy requirements set out in this briefing
– Familiarise themselves with the key LEAN sourcing principles that will be applied to all procurements
– Work with the procurement team to identify what policy initiatives will result in a potential future procurement
• The Procurement team will:
– Become knowledgeable (and trained) in operating the new LEAN approach using the standard operating procedures
– Be ready and prepared to work with Business stakeholders to plan procurements in good time
– Support business stakeholders in planning and delivering procurements within 120 days
– Ensure that as a department we are complying with these policy requirements
Training
• The Government Procurement Service (GPS) is rolling out training across central government which will comprise:
– 1 day LEAN Sourcing Awareness course
– 3 day LEAN Sourcing Simulation workshop
• Initially the both course types will be classroom based but an e-learning package is being developed to replace the 1 day course. This should be available by May 2012
• Further information will be available from GPS by phoning the service desk on 0345 4102222 or by emailing [email protected]