product process & schedule design...2018/02/03 · a product has a market estimate of 97,000...
TRANSCRIPT
-
Product Process
& Schedule Design
-
Relationship between product, process, and schedule design and facilities planning
Facilities
planner
Product designers
Process planner
Production Planner
-
Before any facility plan can be generated, the
following questions should be addressed
1. What is to be produced?
2. How are the products to be produced?
3. When are the products to be produced?
4. How much of each product will be produced?
5. For how long will the products be produced?
6. Where are the products to be produced?
-
Relationship between product, process,
and schedule design and facilities planning
Product design
Process design
Facilities design
schedule design
Figure 2.1
Relationship between product, process , and schedule (PP&S) design facilities planning.
-
Facility planning functions relationship
Links between components:
Product
Change in the design of a product.
Introducing a new product.
A significant increase in demand.
________________________________
Process:
Chang in the design of a process.
Replacement of a machine.
Adaptation of new standards.
-
Facility planning functions relationship
Links between components:
Scheduling:
Bottlenecks
Delay and idle time.
Excessive temporary storage
Obstacles to material flow.
High ratio of material handling time/production time
-
Product, Process & Scheduling Design Interaction
•Product Design 1
•Process Design 2
-
Product, Process & Scheduling Design Interaction
•Scheduling Design 3
•Facilities Design 4
-
Customer Needs
• Market Surveys, Benchmarking
• QFD, HOQ …. etc.
Product Designer
• Exploded Assembly Drawing or Photograph
• Can be prepared and analyzed by CAD
Component Design
• Detailed component part drawing
• Can be prepared and analyzed by CAD
1. Product Design Steps
-
Product Design
Product design involves
The determination of which products are to be produced
The detailed design of individual products.
Decisions regarding the products to be produced are
generally made by top management based on input from
marketing, manufacturing, and finance concerning projected
economic performance.
-
Product Design
Product must meet customer needs, this challenge can be
achieved by designers using QFD and benchmarking.
Either Exploded Assembly Drawing or Photograph can be
used to show the parts properly oriented.
Detailed component part drawing are needed for each
component part.
Drawings can be prepared and analyzed by CAD system.
-
Product Design involves:
Quality Function Deployment (QFD)
House of quality (HOQ)
Benchmarking
Design for Manufacturing and Assembly (DFMA)
Prototyping (The first testing pattern)
Exploded Assembly Drawing
Photography
CAD drawing
-
Figure 2.2 Exploded assembly drawing
-
Exploded Assembly Drawing
materials in
an airplane
-
Exploded Assembly Drawing
-
Figure 2.3 Exploded Assembly Photography
-
Figure 2.4 Component part drawing of a plunger
-
Identifying Required Processes
• Make or Buy Decision & Parts list.
• Bill of Materials (BOM) & Product Structure.
Selecting Required Processes
• Route sheet.
Sequencing Required Processes
• Assembly Chart, Operation Process chart & Precedence Diagram.
2. Process Design Steps
-
Process Design
How the product is going to be produced, on which machine, make or buy
decision, how long it will take to perform the operation.
Basically process design consists of 3 stages:
1. Identifying the required process
make-or-buy decision
part list
bill of materials
-
Process Design
2. selecting the required processes
process selection procedure
route sheet
3. sequencing the required processes
assembly chart
operation process chart
Precedence diagram
-
Process selection
& Design process
-
Make or Buy
Decision Process
Figure 3.6
The make-or-buy
decision process.
-
Process Identification
Define elemental operations Step 1
Identify alternative processes for each operation Step 2
Analyze alternative processes Step 3
Standardize processes Step 4
Evaluate alternative processes Step 5
Select processes Step 6
Computer Aided Process Planning (CAPP) - Variant
-Generative
Figure 3.10 Process selection procedure
-
After Make or Buy decision
After the make or buy decisions have been made, a list of items to be
made and the items to be purchased will be determined.
The listing often takes the form of a parts’ list or a bill of materials. A parts
list includes at least the following
1. Part numbers
2. Part name
3. Number of parts per product
4. Drawing
-
Process Design
A part list
1) part number
2) part name
3) number of parts
4) drawing number
5) material
6) size
7) quantity
8) make or buy
-
Figure 3.8 Bill of martials for an air flow regulator
Level I: subassemblies and components that feed directly into level
-
Figure 3.9 Bill of materials for an air flow regulator
-
Selecting the Required Processes
After determining “in house” parts, decisions are needed as to how the
products will be made:
- previous experiences
- related requirements
- available equipment
- production rates
- future expectations.
Outputs are processes, equipment, and raw materials required for the in-
house production of products, also called a route sheet.
-
Route sheet
The outputs from the process selection procedure are the processes,
equipment, and raw materials required for in-house production of
products. Output is generally given in the form of a rout sheet.
It lists, in addition to part information, the related operations for each
make component.
-
Figure 3.11 Route sheet for one component of the air flow regulator
-
Sequencing the Required Process
The method of assembling a product is accomplished by the
assembly chart.
Assembly chart – shows the sequence of operations in
putting the product together.
The easiest method of constructing an assembly chart is to
begin with the completed product and trace the product
disassembly back to its basic components.
-
Assembly Chart ”The easiest way of
constructing an
assembly chart is to
begin with the
completed product
and to trace the
product disassembly
back to its basic
components”
How to construct it?
Figure 3.12 Assembly chart for an air flow regulator
-
Sequencing the Required Process
Although route sheets provide information on
production methods and assembly charts indicate
how components are combined, neither provides an
overall understanding of the flow within the facility.
This is accomplished with the operation process
chart.
-
To provide an overview of
the flow within the facility
we impose the rout sheet
on the assembly chart. The
resulting chart is referred to
as an operation process
chart.
How to construct it?
Operation process chart
analog model of overall
production process
-
Sequencing the Required Process
A second viewpoint (from graph and network theory) is to
interpret the charts as network representations, or more
accurately, tree representations of a production process.
A variation of the network viewpoint is to treat the assembly
chart and the operations process chart as special cases of a
more general graphical model, the precedence diagram.
-
Precedence
diagram
A network representation of all
processes need to executed
successively. “ The diagram can be of
significant benefit to the facilities
planner. It establishes the
precedence relationships that must
be maintained in manufacturing and
assembling a product”.
Figure 3.14 Precedence diagram for an air flow regulator
-
Marketing Information
• Quantitative Information such as volume, trend, and predictability of future demand for various products
• Qualitative information
Process Requirements
• Calculation of production requirements
• Calculations with rework
• Reject allowance problem
• Estimation the number of machines required
3. Scheduling Design Steps
-
As a minimum, the market
information needed for
facilities planning is given
in the table.
Marketing
Information -
Quantitative
-
Ideally, information of the
type shown in this table
would be provided. If such
information is available, a
facilities plan can be
developed for each
demand state, and a
facility designed with
sufficient flexibility to meet
the yearly fluctuations in
product mix.
Marketing
Information -
Quantitative
-
The qualitative information
listed in this table shall be
obtained as well. This
information may provide
valuable insight to facilities
planner.
Marketing
Information -
Qualitative
-
The figure above suggests
that the facilities plan
should consist of a mass
production area for the
15% of high volume items
and a job shop
arrangement for the
remaining 85% of the
product mix.
Pareto law dose not apply
for the figure below.
Marketing Information
– Pareto’s Diagram
-
Example 2.1:
A product has a market
estimate of 97,000
components and requires
three processing steps
(turning, milling, and
drilling) having scrap
estimates of P1 = 0.04, P2
= 0.01, and P3 = 0.03
Process Requirements
105,219 101,010 100,000
0.04 0.01 0.03
97000
-
Example 2.2:
The end product
requirement is 100,000
pieces, Assume that the
defective rate in (decimal)
are d1= 0.03, d2 = 0.40,
and d3 = 0.02
Solution:
Applying this equation, The
initial input required is
103,280
Process Requirements
-
QC
Tools
• Some quality Tools such as Pareto Chart can be used
Deming
Wheel
• Deming BDCA Cycle of continuous improvement can be very useful (Plan-Do-Check-Act)
Seven Management
& Planning Tools
• Affinity diagram, Interrelation Diagraph, Tree Diagram, Matrix Diagram, Contingency Diagram, Activity Network Diagram, and Prioritization Matrix.
4. Facilities Design Steps
-
7 management and planning tools
The seven management and planning tools are
1. The affinity diagram,
2. The interrelationship digraph,
3. The tree diagram,
4. The matrix diagram,
5. The contingency diagram,
6. The activity network diagram, and
7. The prioritization matrix.
-
The affinity diagram is used to gather verbal data, such as ideas and issues, and organize it into groupings. Suppose we are interested in generating ideas for reducing manufacturing lead time. In a brainstorming session, the issues are written down on "post-it“ notes and grouped on a board or wall. Each group then receives a heading. An affinity diagram for reducing manufacturing lead time is presented in the following figure.
Affinity Diagram
-
Procedure:
1. State the issue in a full sentence.
2. Brainstorm using short sentences on
self-adhesive notes.
3. Post them for the team to see.
4. Sort ideas into logical groups.
5. Create concise descriptive headings for each group.
Affinity Diagram
-
Affinity diagram example
for reducing
manufacturing lead
time
Affinity Diagram
-
The interrelationship
digraph is used to map
the logical links among
related items, trying to
identify which items
impact others the most.
The term digraph is
employed because the
graph uses directed
arcs
Interrelation
Diagraph
-
Suppose we want to
study the relationship
between the items in
previous figure under
facilities design. The
interrelationships are
presented in this figure.
Note that this graph helps
us understand the logical
sequence of steps for the
facilities design
Interrelation
Diagraph
-
Maps out the paths and tasks necessary to complete a specific project or reach a specified goal.
Benefits:
Encourages team members to think creatively.
Makes large projects manageable.
Generates a problem-solving atmosphere.
Tree Diagram
-
Procedure:
1. Choose an action-oriented objective statement from the interrelationship diagram, affinity diagram, brainstorming, team mission statement.
2. Using brainstorming, choose the major headings.
3. Generate the next level by analyzing the major headings. Repeat this question at each level.
Tree Diagram
-
Tree diagram for the
formation of product
families
Tree Diagram
-
The matrix diagram
organizes
information such as
characteristics,
functions, and tasks
into sets of items to
be compared.
Matrix Diagram
-
The contingency diagram, formally
known as process decision program
chart, maps conceivable events and
contingencies that might occur
during implementation.It is
particularly useful when the project
being planned consists of unfamiliar
tasks. The benefit of preventing or
responding effectively to
contingencies makes it worth while
to look at these possibilities during
the planning phase.
This figure shows an example of
possible contingencies during an
earthquake.
Contingency
Diagram
-
The activity network diagram is used
to develop a work schedule for the
facilities design effort. This diagram is
synonymous to the critical path
method (CPM) graph. It can also be
replaced by a Gantt chart and if a
range is defined for the duration of
each activity, the Program
Evaluation and Review Technique
(PERT) chart can also be used. An
example of an activity network
diagram for a production line
expansion is illustrated in this figure
Activity Network
Diagram
-
The important message is that a
well thought out time table is
needed to understand the
length of the facilities design
project. This timetable can be
developed after the actions on
the tree diagram have been
evaluated with the prioritization
matrix.
Teams activities can also be
planned as shown in this typical
weekly work schedule.
Activity Network
Diagram
-
In developing facilities design
alternatives it is important to consider:
Layout characteristics
Material handling
requirements
Unit load implied
Storage strategies
Overall building impact
The figure shows prioritization
matrix for the Evaluation of Facilities Design alternatives.
Prioritization Matrix
-
The prioritization matrix can be
used to judge the relative
importance of each criterion as
compared to each other. Table
2.12 presents the prioritization of
the criteria for the facilities
design example. The criteria are
labeled to help in building a
table with weights.
This figure shows the
Prioritization Matrix for Layout
Alternatives Based on WIP
Levels
Prioritization Matrix
-
Logical application
sequence of the seven
management and
planning tools is shown
in this figure.
Summary
-
This figure shows how
the seven
management and
planning tools
facilitate the planning
of a facilities design
project
Summary