product process & schedule design...2018/02/03  · a product has a market estimate of 97,000...

61
Product Process & Schedule Design

Upload: others

Post on 25-Jan-2021

16 views

Category:

Documents


0 download

TRANSCRIPT

  • Product Process

    & Schedule Design

  • Relationship between product, process, and schedule design and facilities planning

    Facilities

    planner

    Product designers

    Process planner

    Production Planner

  • Before any facility plan can be generated, the

    following questions should be addressed

    1. What is to be produced?

    2. How are the products to be produced?

    3. When are the products to be produced?

    4. How much of each product will be produced?

    5. For how long will the products be produced?

    6. Where are the products to be produced?

  • Relationship between product, process,

    and schedule design and facilities planning

    Product design

    Process design

    Facilities design

    schedule design

    Figure 2.1

    Relationship between product, process , and schedule (PP&S) design facilities planning.

  • Facility planning functions relationship

    Links between components:

    Product

    Change in the design of a product.

    Introducing a new product.

    A significant increase in demand.

    ________________________________

    Process:

    Chang in the design of a process.

    Replacement of a machine.

    Adaptation of new standards.

  • Facility planning functions relationship

    Links between components:

    Scheduling:

    Bottlenecks

    Delay and idle time.

    Excessive temporary storage

    Obstacles to material flow.

    High ratio of material handling time/production time

  • Product, Process & Scheduling Design Interaction

    •Product Design 1

    •Process Design 2

  • Product, Process & Scheduling Design Interaction

    •Scheduling Design 3

    •Facilities Design 4

  • Customer Needs

    • Market Surveys, Benchmarking

    • QFD, HOQ …. etc.

    Product Designer

    • Exploded Assembly Drawing or Photograph

    • Can be prepared and analyzed by CAD

    Component Design

    • Detailed component part drawing

    • Can be prepared and analyzed by CAD

    1. Product Design Steps

  • Product Design

    Product design involves

    The determination of which products are to be produced

    The detailed design of individual products.

    Decisions regarding the products to be produced are

    generally made by top management based on input from

    marketing, manufacturing, and finance concerning projected

    economic performance.

  • Product Design

    Product must meet customer needs, this challenge can be

    achieved by designers using QFD and benchmarking.

    Either Exploded Assembly Drawing or Photograph can be

    used to show the parts properly oriented.

    Detailed component part drawing are needed for each

    component part.

    Drawings can be prepared and analyzed by CAD system.

  • Product Design involves:

    Quality Function Deployment (QFD)

    House of quality (HOQ)

    Benchmarking

    Design for Manufacturing and Assembly (DFMA)

    Prototyping (The first testing pattern)

    Exploded Assembly Drawing

    Photography

    CAD drawing

  • Figure 2.2 Exploded assembly drawing

  • Exploded Assembly Drawing

    materials in

    an airplane

  • Exploded Assembly Drawing

  • Figure 2.3 Exploded Assembly Photography

  • Figure 2.4 Component part drawing of a plunger

  • Identifying Required Processes

    • Make or Buy Decision & Parts list.

    • Bill of Materials (BOM) & Product Structure.

    Selecting Required Processes

    • Route sheet.

    Sequencing Required Processes

    • Assembly Chart, Operation Process chart & Precedence Diagram.

    2. Process Design Steps

  • Process Design

    How the product is going to be produced, on which machine, make or buy

    decision, how long it will take to perform the operation.

    Basically process design consists of 3 stages:

    1. Identifying the required process

    make-or-buy decision

    part list

    bill of materials

  • Process Design

    2. selecting the required processes

    process selection procedure

    route sheet

    3. sequencing the required processes

    assembly chart

    operation process chart

    Precedence diagram

  • Process selection

    & Design process

  • Make or Buy

    Decision Process

    Figure 3.6

    The make-or-buy

    decision process.

  • Process Identification

    Define elemental operations Step 1

    Identify alternative processes for each operation Step 2

    Analyze alternative processes Step 3

    Standardize processes Step 4

    Evaluate alternative processes Step 5

    Select processes Step 6

    Computer Aided Process Planning (CAPP) - Variant

    -Generative

    Figure 3.10 Process selection procedure

  • After Make or Buy decision

    After the make or buy decisions have been made, a list of items to be

    made and the items to be purchased will be determined.

    The listing often takes the form of a parts’ list or a bill of materials. A parts

    list includes at least the following

    1. Part numbers

    2. Part name

    3. Number of parts per product

    4. Drawing

  • Process Design

    A part list

    1) part number

    2) part name

    3) number of parts

    4) drawing number

    5) material

    6) size

    7) quantity

    8) make or buy

  • Figure 3.8 Bill of martials for an air flow regulator

    Level I: subassemblies and components that feed directly into level

  • Figure 3.9 Bill of materials for an air flow regulator

  • Selecting the Required Processes

    After determining “in house” parts, decisions are needed as to how the

    products will be made:

    - previous experiences

    - related requirements

    - available equipment

    - production rates

    - future expectations.

    Outputs are processes, equipment, and raw materials required for the in-

    house production of products, also called a route sheet.

  • Route sheet

    The outputs from the process selection procedure are the processes,

    equipment, and raw materials required for in-house production of

    products. Output is generally given in the form of a rout sheet.

    It lists, in addition to part information, the related operations for each

    make component.

  • Figure 3.11 Route sheet for one component of the air flow regulator

  • Sequencing the Required Process

    The method of assembling a product is accomplished by the

    assembly chart.

    Assembly chart – shows the sequence of operations in

    putting the product together.

    The easiest method of constructing an assembly chart is to

    begin with the completed product and trace the product

    disassembly back to its basic components.

  • Assembly Chart ”The easiest way of

    constructing an

    assembly chart is to

    begin with the

    completed product

    and to trace the

    product disassembly

    back to its basic

    components”

    How to construct it?

    Figure 3.12 Assembly chart for an air flow regulator

  • Sequencing the Required Process

    Although route sheets provide information on

    production methods and assembly charts indicate

    how components are combined, neither provides an

    overall understanding of the flow within the facility.

    This is accomplished with the operation process

    chart.

  • To provide an overview of

    the flow within the facility

    we impose the rout sheet

    on the assembly chart. The

    resulting chart is referred to

    as an operation process

    chart.

    How to construct it?

    Operation process chart

    analog model of overall

    production process

  • Sequencing the Required Process

    A second viewpoint (from graph and network theory) is to

    interpret the charts as network representations, or more

    accurately, tree representations of a production process.

    A variation of the network viewpoint is to treat the assembly

    chart and the operations process chart as special cases of a

    more general graphical model, the precedence diagram.

  • Precedence

    diagram

    A network representation of all

    processes need to executed

    successively. “ The diagram can be of

    significant benefit to the facilities

    planner. It establishes the

    precedence relationships that must

    be maintained in manufacturing and

    assembling a product”.

    Figure 3.14 Precedence diagram for an air flow regulator

  • Marketing Information

    • Quantitative Information such as volume, trend, and predictability of future demand for various products

    • Qualitative information

    Process Requirements

    • Calculation of production requirements

    • Calculations with rework

    • Reject allowance problem

    • Estimation the number of machines required

    3. Scheduling Design Steps

  • As a minimum, the market

    information needed for

    facilities planning is given

    in the table.

    Marketing

    Information -

    Quantitative

  • Ideally, information of the

    type shown in this table

    would be provided. If such

    information is available, a

    facilities plan can be

    developed for each

    demand state, and a

    facility designed with

    sufficient flexibility to meet

    the yearly fluctuations in

    product mix.

    Marketing

    Information -

    Quantitative

  • The qualitative information

    listed in this table shall be

    obtained as well. This

    information may provide

    valuable insight to facilities

    planner.

    Marketing

    Information -

    Qualitative

  • The figure above suggests

    that the facilities plan

    should consist of a mass

    production area for the

    15% of high volume items

    and a job shop

    arrangement for the

    remaining 85% of the

    product mix.

    Pareto law dose not apply

    for the figure below.

    Marketing Information

    – Pareto’s Diagram

  • Example 2.1:

    A product has a market

    estimate of 97,000

    components and requires

    three processing steps

    (turning, milling, and

    drilling) having scrap

    estimates of P1 = 0.04, P2

    = 0.01, and P3 = 0.03

    Process Requirements

    105,219 101,010 100,000

    0.04 0.01 0.03

    97000

  • Example 2.2:

    The end product

    requirement is 100,000

    pieces, Assume that the

    defective rate in (decimal)

    are d1= 0.03, d2 = 0.40,

    and d3 = 0.02

    Solution:

    Applying this equation, The

    initial input required is

    103,280

    Process Requirements

  • QC

    Tools

    • Some quality Tools such as Pareto Chart can be used

    Deming

    Wheel

    • Deming BDCA Cycle of continuous improvement can be very useful (Plan-Do-Check-Act)

    Seven Management

    & Planning Tools

    • Affinity diagram, Interrelation Diagraph, Tree Diagram, Matrix Diagram, Contingency Diagram, Activity Network Diagram, and Prioritization Matrix.

    4. Facilities Design Steps

  • 7 management and planning tools

    The seven management and planning tools are

    1. The affinity diagram,

    2. The interrelationship digraph,

    3. The tree diagram,

    4. The matrix diagram,

    5. The contingency diagram,

    6. The activity network diagram, and

    7. The prioritization matrix.

  • The affinity diagram is used to gather verbal data, such as ideas and issues, and organize it into groupings. Suppose we are interested in generating ideas for reducing manufacturing lead time. In a brainstorming session, the issues are written down on "post-it“ notes and grouped on a board or wall. Each group then receives a heading. An affinity diagram for reducing manufacturing lead time is presented in the following figure.

    Affinity Diagram

  • Procedure:

    1. State the issue in a full sentence.

    2. Brainstorm using short sentences on

    self-adhesive notes.

    3. Post them for the team to see.

    4. Sort ideas into logical groups.

    5. Create concise descriptive headings for each group.

    Affinity Diagram

  • Affinity diagram example

    for reducing

    manufacturing lead

    time

    Affinity Diagram

  • The interrelationship

    digraph is used to map

    the logical links among

    related items, trying to

    identify which items

    impact others the most.

    The term digraph is

    employed because the

    graph uses directed

    arcs

    Interrelation

    Diagraph

  • Suppose we want to

    study the relationship

    between the items in

    previous figure under

    facilities design. The

    interrelationships are

    presented in this figure.

    Note that this graph helps

    us understand the logical

    sequence of steps for the

    facilities design

    Interrelation

    Diagraph

  • Maps out the paths and tasks necessary to complete a specific project or reach a specified goal.

    Benefits:

    Encourages team members to think creatively.

    Makes large projects manageable.

    Generates a problem-solving atmosphere.

    Tree Diagram

  • Procedure:

    1. Choose an action-oriented objective statement from the interrelationship diagram, affinity diagram, brainstorming, team mission statement.

    2. Using brainstorming, choose the major headings.

    3. Generate the next level by analyzing the major headings. Repeat this question at each level.

    Tree Diagram

  • Tree diagram for the

    formation of product

    families

    Tree Diagram

  • The matrix diagram

    organizes

    information such as

    characteristics,

    functions, and tasks

    into sets of items to

    be compared.

    Matrix Diagram

  • The contingency diagram, formally

    known as process decision program

    chart, maps conceivable events and

    contingencies that might occur

    during implementation.It is

    particularly useful when the project

    being planned consists of unfamiliar

    tasks. The benefit of preventing or

    responding effectively to

    contingencies makes it worth while

    to look at these possibilities during

    the planning phase.

    This figure shows an example of

    possible contingencies during an

    earthquake.

    Contingency

    Diagram

  • The activity network diagram is used

    to develop a work schedule for the

    facilities design effort. This diagram is

    synonymous to the critical path

    method (CPM) graph. It can also be

    replaced by a Gantt chart and if a

    range is defined for the duration of

    each activity, the Program

    Evaluation and Review Technique

    (PERT) chart can also be used. An

    example of an activity network

    diagram for a production line

    expansion is illustrated in this figure

    Activity Network

    Diagram

  • The important message is that a

    well thought out time table is

    needed to understand the

    length of the facilities design

    project. This timetable can be

    developed after the actions on

    the tree diagram have been

    evaluated with the prioritization

    matrix.

    Teams activities can also be

    planned as shown in this typical

    weekly work schedule.

    Activity Network

    Diagram

  • In developing facilities design

    alternatives it is important to consider:

    Layout characteristics

    Material handling

    requirements

    Unit load implied

    Storage strategies

    Overall building impact

    The figure shows prioritization

    matrix for the Evaluation of Facilities Design alternatives.

    Prioritization Matrix

  • The prioritization matrix can be

    used to judge the relative

    importance of each criterion as

    compared to each other. Table

    2.12 presents the prioritization of

    the criteria for the facilities

    design example. The criteria are

    labeled to help in building a

    table with weights.

    This figure shows the

    Prioritization Matrix for Layout

    Alternatives Based on WIP

    Levels

    Prioritization Matrix

  • Logical application

    sequence of the seven

    management and

    planning tools is shown

    in this figure.

    Summary

  • This figure shows how

    the seven

    management and

    planning tools

    facilitate the planning

    of a facilities design

    project

    Summary