production and operation management2

Upload: nandn

Post on 14-Apr-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 Production and Operation Management2

    1/4

    Amity Global Business School MUMBAI Sem II

    Santosh Pathak

    Material Resource Planning (MRP I)

    Material Requirements Planning (MRP)

    is a software based production planning

    and inventory control system used

    to manage manufacturing processes.

    Although it is not common now-a-days, it is possible to conduct MRP

    by hand as well.

    An MRP system is intended to simultaneously meet three objectives:

    Ensure materials and products are availablefor production and delivery to customers.

    Maintain the lowest possible level of inventory. Plan manufacturing activities, delivery schedules and purchasing

    activities.

    When to Use

    MRP I systems are usually employed when 1 or more of following

    conditions exist:

  • 7/27/2019 Production and Operation Management2

    2/4

    Amity Global Business School MUMBAI Sem II

    Santosh Pathak

    When usage (demand) of materials is discontinuous or highly unstable

    during a firms normal operating cycle (intermittent manufacturing or job

    shop operation as opposed to a continuous-processing or mass-production

    operation)

    MRP Processing

    Gross requirements: (Forecasted)Demand period by period

    Net requirements(t) =Gross requirements(t)-Projected inventory(t-1)

    -Scheduled receipt(t)

    If Net requirement(t) > 0set Planned order receipts(t)>=Net requirement(t)

    Planned-order receipts is the production planned

    Projected inventory(t)

    =Projected inventory(t-1)+Scheduled receipt(t)

    +Planned order receipts(t)-Gross requirements(t)

    Planned order release(t-LT)=Planned-order receipts(t)

  • 7/27/2019 Production and Operation Management2

    3/4

    Amity Global Business School MUMBAI Sem II

    Santosh Pathak

    MRP at Plant Level

    The system adds together stocks from all of the individual storagelocations, with the exception of individual customer stock, to determine

    total plant stock.

    Individual storage locations can be planned separately or be excluded fromplanning.

    MRP at Area Level

    Only the stocks from the storage locations or subcontractor assigned to therespective MRP area are taken into account.

    This enables you to plan material requirements specifically for certainareas.

    MRP Planning

    MRP Outputs

    Planned orders - schedule indicating the amount and timing of future

    orders.

  • 7/27/2019 Production and Operation Management2

    4/4

    Amity Global Business School MUMBAI Sem II

    Santosh Pathak

    Order releases - Authorization for the execution of planned orders.

    Changes - revisions of due dates or order quantities, or cancellations of

    orders.

    Performance-control reports

    Planning reportsException reports

    The Benefits of MRP

    Inventory reduction,Reduction in production & delivery time Increased efficiency.Faster response to market changes Improved labor & equipment utilizationBetter inventory planning & schedulingReduced inventory levels without reduced customer service

    SALES & OPERATIONS PLANNING OBJECTIVES

    SUPPORT THE PROFIT PLANSUPPORT THE CUSTOMER INSURE REALISTIC PLANSLEAD CHANGEMANAGE INVENTORYMAKE DECISIONS -RESOLVE ISSUESMEASURE PERFORMANCEBUILD TEAM WORK!

    Manufacturing Resource Planning (MRP II)Expanded MRP with and emphasis placed on integration

    Financial planning

    Marketing

    Engineering

    Purchasing