production and operation management2
TRANSCRIPT
-
7/27/2019 Production and Operation Management2
1/4
Amity Global Business School MUMBAI Sem II
Santosh Pathak
Material Resource Planning (MRP I)
Material Requirements Planning (MRP)
is a software based production planning
and inventory control system used
to manage manufacturing processes.
Although it is not common now-a-days, it is possible to conduct MRP
by hand as well.
An MRP system is intended to simultaneously meet three objectives:
Ensure materials and products are availablefor production and delivery to customers.
Maintain the lowest possible level of inventory. Plan manufacturing activities, delivery schedules and purchasing
activities.
When to Use
MRP I systems are usually employed when 1 or more of following
conditions exist:
-
7/27/2019 Production and Operation Management2
2/4
Amity Global Business School MUMBAI Sem II
Santosh Pathak
When usage (demand) of materials is discontinuous or highly unstable
during a firms normal operating cycle (intermittent manufacturing or job
shop operation as opposed to a continuous-processing or mass-production
operation)
MRP Processing
Gross requirements: (Forecasted)Demand period by period
Net requirements(t) =Gross requirements(t)-Projected inventory(t-1)
-Scheduled receipt(t)
If Net requirement(t) > 0set Planned order receipts(t)>=Net requirement(t)
Planned-order receipts is the production planned
Projected inventory(t)
=Projected inventory(t-1)+Scheduled receipt(t)
+Planned order receipts(t)-Gross requirements(t)
Planned order release(t-LT)=Planned-order receipts(t)
-
7/27/2019 Production and Operation Management2
3/4
Amity Global Business School MUMBAI Sem II
Santosh Pathak
MRP at Plant Level
The system adds together stocks from all of the individual storagelocations, with the exception of individual customer stock, to determine
total plant stock.
Individual storage locations can be planned separately or be excluded fromplanning.
MRP at Area Level
Only the stocks from the storage locations or subcontractor assigned to therespective MRP area are taken into account.
This enables you to plan material requirements specifically for certainareas.
MRP Planning
MRP Outputs
Planned orders - schedule indicating the amount and timing of future
orders.
-
7/27/2019 Production and Operation Management2
4/4
Amity Global Business School MUMBAI Sem II
Santosh Pathak
Order releases - Authorization for the execution of planned orders.
Changes - revisions of due dates or order quantities, or cancellations of
orders.
Performance-control reports
Planning reportsException reports
The Benefits of MRP
Inventory reduction,Reduction in production & delivery time Increased efficiency.Faster response to market changes Improved labor & equipment utilizationBetter inventory planning & schedulingReduced inventory levels without reduced customer service
SALES & OPERATIONS PLANNING OBJECTIVES
SUPPORT THE PROFIT PLANSUPPORT THE CUSTOMER INSURE REALISTIC PLANSLEAD CHANGEMANAGE INVENTORYMAKE DECISIONS -RESOLVE ISSUESMEASURE PERFORMANCEBUILD TEAM WORK!
Manufacturing Resource Planning (MRP II)Expanded MRP with and emphasis placed on integration
Financial planning
Marketing
Engineering
Purchasing