production capacity application

101
INCREASING THE CAPACITY OF THE NESTEA LEMON ICED TEA FILLING SECTION OF DDC FOOD DEVELOPMENT CONTRACTING SERVICES, INC. AT SAN FERNANDO, PAMPANGA JAQUELYN MARGARET LAWAS MICIANO 2005-09921 A PRACTICUM STUDY PRESENTED TO THE FACULTY OF THE DEPARTMENT OF INDUSTRIAL ENGINEERING COLLEGE OF ENGINEERING AND AGRO- INDUSTRIAL TECHNOLOGY UNIVERSITY OF THE PHILIPPINES LOS BAÑOS IN PARTIAL FULFILLMENT OF THE REQUIREMENTS FOR THE DEGREE OF BACHELOR OF SCIENCE IN INDUSTRIAL ENGINEERING APRIL 2010

Upload: jakimlm

Post on 08-Apr-2015

717 views

Category:

Documents


0 download

DESCRIPTION

A study applying Statistical tools for improving actual production line and evaluating possibilities for optimum efficiency

TRANSCRIPT

Page 1: Production Capacity Application

INCREASING THE CAPACITY OF THE NESTEA LEMON ICED TEA FILLING

SECTION OF DDC FOOD DEVELOPMENT CONTRACTING

SERVICES, INC. AT SAN FERNANDO, PAMPANGA

JAQUELYN MARGARET LAWAS MICIANO 2005-09921

A PRACTICUM STUDY PRESENTED TO THE FACULTY OF THE DEPARTMENT OF INDUSTRIAL ENGINEERING COLLEGE OF ENGINEERING AND AGRO-

INDUSTRIAL TECHNOLOGY UNIVERSITY OF THE PHILIPPINES LOS BAÑOS IN PARTIAL FULFILLMENT OF THE

REQUIREMENTS FOR THE DEGREE OF

BACHELOR OF SCIENCE IN INDUSTRIAL ENGINEERING

APRIL 2010

Page 2: Production Capacity Application

ii

ACCEPTANCE SHEET

The practicum study, attached hereto entitled “INCREASING THE CAPACITY OF THE

NESTEA LEMON ICED TEA FILLING SECTION OF DDC FOOD DEVELOPMENT

CONTRACTING SERVICES, INC. AT SAN FERNANDO, PAMPANGA”, prepared and

submitted by JAQUELYN MARGARET LAWAS MICIANO in partial fulfillment of the

requirements for the degree of Bachelor in Industrial Engineering is hereby accepted.

___________________________ ENGR. ROMARK O. CAYUBE

Adviser and Chairman, Guidance Committee

______________ Date Signed

_______________________________ _____________________________ ENGR. DIANA MARIE R. DE SILVA ENGR. MIKEL ANGELO B. YAP Member, Guidance Committee Member, Guidance Committee ______________ ______________ Date Signed Date Signed

__________________________________

DR. AURELIO A. DELOS REYES JR. Chairman, Industrial Engineering Department

______________

Date Signed

______________________________ DR. ARSENIO N. RESURRECCION

Dean, College of Engineering and Agro-Industrial Technology

______________ Date Signed

Page 3: Production Capacity Application

iii

ABOUT THE AUTHOR

The author was born in San Fernando, Pampanga on the 19th day of November,

1988. She is the youngest among the four children of Mr. Emmanuel R. Miciano and

Mrs. Thelma L. Miciano. Her siblings are Maximillian, Kathleen, and Jose Paolo. Her

parents and brother are currently residing in San Fernando, Pampanga while her sister

now is staying in Laredo, Texas, USA.

She attended her kindergarten at Asian Montessori Center in San Fernando,

Pampanga at the age of five where she was given a chance to be accelerated to primary

education. But then she continued her primary schooling at Morning Star Montessori

School Inc in Los Baños, Laguna and graduated with academic excellence. From her

hard efforts, she was given an opportunity to finish her secondary education at Philippine

Science High School Diliman where she embarked her journey towards achieving the

vision of becoming an engineer.

In the year 2005, the University of the Philippines Los Baños keenly accepted her

to attend under the Industrial Engineering program that was newly offered by the

academe. She became a volunteer in assisting freshmen to cope up with the college

environment and workload in cooperation with the Student Organization Administrative

Division. Also, a onetime honor roll student in the College of Engineering and Agro-

Industrial Technology.

Page 4: Production Capacity Application

iv

ACKNOWLEDGEMENT

This paper would not be possible without the Lord God’s words that served

as my STRENGTH, GUIDANCE and INSPIRATION. So I’d like to thank Him firstly

for filling me with compassion, pointing me my true directions and surrounding me

with wonderful people who accompanied me throughout my journey.

From the very beginning, my parents, Manny & Thelma, have greatly

extended their support financially, emotionally and spiritually to make my whole

practicum experience be substantial and unproblematic. Thank you for all the

endless prayers, powerful words of encouragement and especially the efforts of

critically understanding my study. I’m grateful for making my heart strong enough to

face the challenges before me.

To my supportive brother, Joseph, your patience on dealing with my feelings

of resentment has helped ease and lighten my mood. For all the errands you have

made for this paper that I have persistently requested, thank you. Those little things

are part of a great accomplishment.

To my ever-loving sister, Kathleen, your comforting words sufficed our

thousand-mile distance. You know me more than I know myself and for that you’ve

been saying the exact words I wanted to hear. Thank you for giving me courage and

understanding to confront the trials with dignity. You’re my twin, no one can top that!

To my cousins and relatives, I am grateful for putting more pressure in the

thought of me having to graduate on time. It encouraged me to push even more to

relieve your anxieties.

To my adviser, Sir Omak, thank you for all your efforts in helping me

construct a substantial work, for giving me conditional chances to finish my paper

and also for endowing upon me the principles of independence.

To my panelists, Sir Mikel and Ma’am Dianne, thank you for the docile

approach in criticizing my paper. Your suggestions greatly contributed into leading

my study towards a more technical portrayal.

To other members of the IED Faculty, Sir Arvin, Ma’am Kat and Sir Marc, I’d

like to extend my gratitude for effortlessly be a factor of significant concepts through

your different outlooks that made the interpretation of the paper more profound.

To my dear friend Ara, you have greatly influenced me through your simple

yet insightful technical advises in taking my brainstorming moments into the next

level. I deeply appreciate all the efforts you have made in assisting me finish my

paper not only in the technical areas but also for helping me get through it

emotionally without holding back the tears.

Page 5: Production Capacity Application

v

To Mafei, your conniving advices on dealing with the manuscript writings

were very entertaining and helpful in a way that it refreshes my thoughts once in a

while. For all the troubles you came across just to lend me hand, I value all your

efforts.

To Yani, May, Agbu and Pii, I’m very pleased to have friends like you who did

not hold back in helping out especially at the last minute. Your support no matter

how small or great it may seem is highly regarded.

To Seph, Ronald, Marvin, Cale and Co., for suddenly reaching out and

sending your concerns through your means, thank you. I greatly appreciate all the

energy you gave out in backing me up and for lifting my spirits up in the end.

To Rie, Wewikinns, Cagayat, Daryll, Teves and others that I may have failed

to mention, I’m thankful for letting me feel your deep concerns notwithstanding the

constraints of time and distance.

To Roy, I’m thankful for willingly extending a hand in any possible way even

with your hectic schedule and tons of responsibility. You have saved me for lending

me one of the most important things that made this paper possible, Thank you!

To my ever faithful friend, Marco, I do not know where to begin thanking you

for all your devoted efforts in alleviating my endeavors in putting together this

manuscript. For all the long nights of gravelling with crucial theories (which were

later dismissed), for all the sensible instructions and advices, for imparting the

biggest of efforts throughout my manuscript writing with your prudent perspectives,

and for simply always being there for me whenever I’m in need, you are my rescuer

amidst the burdens and hardship I’ve stumbled upon. For that, my heart is filled with

deep respect, compassion and gratitude to you.

Writing this manuscript made my college experience complete with all the

knowledge, emotions and energy put into one document. Herewith, I feel that I have

arrived at the finishing point of my college education. Without this, I would not be

able to recognize my potential of independently bringing up this whole document

that serves as a symbol of one of my greatest achievements. To God be the Glory!

Page 6: Production Capacity Application

vi

EXECUTIVE SUMMARY

DDC Food Development and Contracting Services Inc. (DDC-FDCSI) is a

subcontractual company of Nestle Philippines located at Block 14 Lot 26 Lazatin Blvd.,

Villa Victoria, Dolores, City of San Fernando, Pampanga. DDC-FDCSI handles food and

beverage powder in preformed pouches for the supplies of Nestle clients and not for

retailing.

DDC-FDCSI’s Nestea Lemon Iced Tea Production line, the foremost profit

contributor among DDC-FDCSI’s major products, has been experiencing a lot of

overtime workload in its Filling Section considering it is the resource constraint in the

line. It was found out based from the capacity requested by demand and the process

capacity of the Filling Section that the Nestea Lemon Iced Tea Production Line is

subjected to 116.59% implied utilization which further signifies that the demand exceed

the current process capacity by 16.59%. The additional capacity is being covered

through scheduled overtime hours in the Filling Section.

Harnessing the scientific method and Industrial Engineering concepts for

analysis, the root causes of the low capacity of the Nestea Lemon Iced Tea (NLIT) Filling

Section were carefully identified based on its association to Man, Method, Machine and

Materials. Experimental and controllable root causes were critically assessed and

evaluated in order to provide corrective and preventive solutions to achieve the main

objective of the study which is to increase the capacity of the NLIT Filling Section.

Factors contributing to the problem identified in the study were categorized

based on the insufficiency of the manpower capacity, the manual filling operations, and

the net weight discrepancies caused by the large capacity of the scoop. A controllable

factor identified was the occasional supervision within the manufacturing line which

contributed to the lax attitude of the workers. These factors were addressed from the

formulated alternatives of providing additional workers and parallel workstations,

automating the filling and sealing operations through a machine and reallocating

workers, customization of the scoop being utilized in the line and providing systematic

and meticulous guidelines for manufacturing line monitoring.

From the evaluation of alternatives, it was recognized that purchasing a filling

and sealing machine as well as reallocating workers to the next resource constraint

would return the highest profit that was estimated to accumulate up to 38,917,832 Php

annually. Implementing this alternative would increase the capacity of the whole

production line.

Page 7: Production Capacity Application

vii

TABLE OF CONTENTS

TITLE PAGE

TITLE PAGE i

ACCEPTANCE SHEET ii

ABOUT THE AUTHOR iii

ACKNOWLEDGEMENT iv

EXECUTIVE SUMMARY vi

TABLE OF CONTENTS vii

LIST OF FIGURES ix

LIST OF TABLES xi

LIST OF APPENDICES xiii

1.0 INTRODUCTION 1

1.1 Overview of the Company 2

1.2 Background and Significance of the Study 6

1.3 Statement of the Problem 11

1.4 Objectives of the Study 11

1.5 Scope and Limitations of the Study 11

1.6 Date and Place of the Study 12

1.7 Gantt Chart 12

2.0 METHODOLOGY 13

2.1 Procedures 16

2.2 Definition of Terms and Symbols 18

3.0 SYSTEMS DOCUMENTATION 19

3.1 General Processes 23

3.2 Product Under Study 24

Page 8: Production Capacity Application

viii

TITLE PAGE

3.3 Production Capacity 25

3.4 Production System 26

3.5 Process Documentation 26

3.6 Manpower Complement 32

3.7 Machine and Equipment 33

3.8 Plant Layout 35

3.9 Workstation Under Study 36

4.0 RESULTS AND DISCUSSSIONS 37

4.1 Problem Identification 38

4.2 Problem Analysis 39

5.0 SUMMARY AND CONCLUSION 72

6.0 RECOMMENDATIONS 75

7.0 AREAS FOR FURTHER STUDY 77

REFERENCES xiv

APPENDICES xv

Page 9: Production Capacity Application

ix

LIST OF FIGURES

FIGURE NO. TITLE PAGE

1-1 Sample Finished Goods of Dehydrated Culinary Products 4

1-2 The existing Organizational Chart followed by DDC-FDCSI 5

1-3 Percentages of Volume Distribution of major product in DDC-FDCSI

7

1-4 Production Output of NLIT based on monthly demand 9

1-5 Number of Scheduled Overtime Hours in the NLIT Filling Section 9

1-6 Exact Location of DDC Food Development and Contracting Services Inc.

12

1-7 Schedule of Activities Performed during the whole study period 12

3-1 Flow Process Chart of the General Processes in DDC-FDCSI 22

3-2 Actual Dimensions of 360g NLIT pouch and 12 x 360g case 23

3-3 Production System Framework of Nestea Lemon Iced Tea 25

3-4 Flow Process Chart of Batch Preparation of NLIT Production Line 27

3-5 Flow Process Chart of Dry Mixing of NLIT Production Line 29

3-6 Flow Process Chart of Filling of NLIT Production Line 31

3-7 Nestea Lemon Iced Tea Dry Mixer 33

3-8 Digital Balance (left), Horizontal Band Sealer (right) 34

3-9 Hot Foil Coder (left), Carton Coder (right) 34

3-10 Actual Layout of the Manufacturing Plant 35

3-11 Workstations in the NLIT Filling Section 36

4-1 Flow Rate of the system with a Resource Constraint 38

4-2 Total Overtime Hours in the Filling Section for June to Nov 2009 38

4-3 Summarized Causes of Low Capacity of the Filling Section 39

Page 10: Production Capacity Application

x

FIGURE NO. TITLE PAGE

4-4 Cause Factors Associated to Man 41

4-5 Cause Factors Associated to Method 42

4-6 Cause Factors Associated to Machine 44

4-7 Cause Factors Associated to Material 44

4-8 Production Monitoring Scheme for Production Line Inspection 47

4-9 Process Flow Diagram of Manufacturing Line Checks 50

4-10 Formula for computing % Improvement 53

4-11 Additional Parallel Workstations in the NLIT Filling Section 56

Page 11: Production Capacity Application

xi

LIST OF TABLES

TABLE NO. TITLE PAGE

1-1 List of DDC-FDCSI Products and their corresponding Package Sizes

3

1-2 Process Capacities for the three major Production Lines in DDC-FDCSI

7

1-3 Calculation of Implied Utilization of NLIT Production Line 8

1-4 Comparison of the Current from Expected Implied Utilization 10

2-1 List of Technical Terms used in the research and their Meanings 16

2-2 List of Symbols used in charts and their Meanings 17

3-1 List of Documents Handled by assigned Departments 19

3-2 Production Volume in kilograms of NLIT during June to Nov 2009 24

3-3 Sample Stopwatch Data of Filling Operations 30

3-4 Number of Workers in the Sections of the NLIT Production Line 32

4-1 Average Observed Time and Standard Time of Filling Elements 41

4-2 CNX Analysis of the Root Causes of Low Capacity of Filling Section

45

4-3 First Group of Experimental Factors 47

4-4 Second Group of Experimental Factors 48

4-5 Third Group of Experimental Factors 48

4-6 Alternative Solutions for Grouped Experimental Factors 52

4-7 Standard time of Operations in the Filling Section 53

4-8 Estimating the Number of Workers per Operation 54

4-9 Determining the Output Rate of Alternative A 55

4-10 Cost of Implementing Alternative A 57

4-11 Output Rate of Alternative B 58

Page 12: Production Capacity Application

xii

TABLE NO. TITLE PAGE

4-12 Cost of Implementing Alternative B 59

4-13 Output Rate for Alternative C 60

4-14 Cost of Implementing Alternative C 61

4-15 Comparison of Cost of Implementing Alternatives 62

4-16 Annual Cost of Alternative A 63

4-17 Annual Benefit of Alternative A 64

4-18 Annual Cost of Alternative B 65

4-19 Annual Benefit of Alternative B 66

4-20 Annual Cost of Alternative C 67

4-21 Annual Benefit of Alternative C 68

4-22 Weighted Rating of Importance 69

4-23 Rating for Net Benefit 69

4-24 Rating for Ease of Implementation 70

4-25 Rating of Alternatives 71

Page 13: Production Capacity Application

xiii

LIST OF APPENDICES

APPENDIX TITLE PAGE

A Computation for the Goal Improvement

xv

B Nestea Lemon Iced Tea Conversion Units

xvi

C Time Study xvii

D Westinghouse System Ratings xxi

E Net Present Value of Alternative B xxii

F Certificate of Completion xxiii

Page 14: Production Capacity Application

1.0 INTRODUCTION

Page 15: Production Capacity Application

2

1.1 Overview of the Company

1.1.1 Company Profile

The DDC Food Development and Contracting Services, Inc. (DDC-

FDCSI)) was founded on March 1, 2004 by its General Manager, Danilo Dizon

Canlas, whose initials appear on the official business name of the company. He

was formerly committed with Nestle Philippines Employee who started as

Assistant Vice President– Technical Division, Service Department for culinary,

Products Specialist, Head of Food Application Group until becoming one of the

Vice Presidents. As a licensed Chemical Engineering who finished a Bachelor of

Science in Chemical Engineering in the Mapúa Institute of Technology, Engr.

Danilo D. Canlas broadened his knowledge on the food industry and attended

international seminars on food processing as well as management. After retiring

from Nestle Philippines, he decided to establish his own company. The first

commercial run of DDC FDCSI occurred on the March 6, 2004, five days after it

was established. The company was developed out of the need for contractual

services as anticipated by the founder. Originally, the company intended to be a

food development facility where new flavors of products and testing would be

handled. But their client, Nestle Philippines, decided to offer a bigger

responsibility in handling supplies for different products.

The major services offered by the company are Preparation of Flavor

Premixes, Batch Preparation, Dry Mixing and Filling of Powdered Products and

Keeping Quality Time Management for selected Powdered Products. The DDC

FDCSI serves as a third party subcontractor involved in the manufacturing and

packaging of designated products from their sole client, Nestle.

Page 16: Production Capacity Application

3

1.1.2 Products

The main products handled by DDC-FDCSI are classified into two family

groups: Dehydrated Culinary Products and Beverage Products. All the products

processed in their plant are powdered products. The list of the specific products

handled by the company is shown in Table 1-1.

DDC-FDCSI is entrusted by Nestlé to carry out the whole operation of

dehydrated culinary products as well as beverage products with the raw

materials provided by the Nestlé accredited suppliers. The dehydrated culinary

products consist of subfamily groups of Stocks and Gravies and Cream Soups

while the beverage service products comprise Milo Vending Mix and Nestea

lemon Iced Tea. These products are not available in retail stores but are provided

to other clients of Nestle such as fast food restaurants and malls.

Table 1-1 List of DDC-FDCSI Products and their corresponding Package Sizes

PRODUCTS Number of pouches per case

x net weight per pouch

Dehydrated Culinary

Stocks and Gravies

Chicken Stock 8x1kg Beef Stock 8x1kg Pork Stock 8x1kg Seafood Stock 8x1kg Chicken Gravy 8x1kg Basic Brown Sauce 8x1kg

Cream Soups

Cream of Chicken 8x1kg Cream of Corn 8x1kg Cream of Mushroom 8x1kg Cream of Asparagus 8x1kg Cream Soup Base 8x1kg

Beverage

Milo Vending Mix 8x1kg Nestea Lemon Iced Tea 12x360g *Source: DDC-FDCSI, 2009

Page 17: Production Capacity Application

4

Figure 1-1 Sample Finished Goods of Dehydrated Culinary Products

Individual sizes of products are indicated in Table 1-1 where large net

weights of the products are packed. This specification is primarily set by Nestle to

be distributed to their respective clients. Delivery of finished goods directly to the

clients of Nestle is not part of DDC-FDCSI services. Instead, finished goods are

primarily delivered straight to Nestle North Distribution Center in Bulacan.

Page 18: Production Capacity Application

5

1.1.3 Organizational Chart

The organizational chart of the company is shown in Figure 1-2 below

where the level of department involved in the study is indicated. Nestea Lemon

Iced Tea (NLIT) Production Line is the main focus as emphasized in the figure.

Three set of crews for every process are involved in the NLIT Production Line.

Figure 1-2 The existing Organizational Chart followed by DDC-FDCSI

Page 19: Production Capacity Application

6

1.2 Background and Significance of the Study

The food and beverage industry is composed of companies involved in

processing raw food materials and manufacturing, packaging, or distributing food or

drink. The exponential population growth brings about the continuous increases in

demand in the food and beverage industry. High levels of demand require high

volumes of production. Associated production costs become the critical factor that

determines the ability of the company to meet seasonal demands. It now appears

more practical and appropriate for a large company to decide to subcontract services

to third party companies in order to meet the level of seasonal demands.

DDC-FDCSI is considered a significant contributor in the food and beverage

industry as it handles the supply for Nestle. The services subcontracted by Nestle to

DDC-FDCSI are batch preparation, dry mixing and filling. Demand forecasts by

Nestle are not controlled by the company since they only offer services and not the

sales. Production volumes of DDC-FDSCI rely on the weekly supply outlook received

from Nestle. The goal of the company is to maximize their profit through cost-efficient

operations within the given factors that caused the problem identified in the study.

Recommendations for increasing the capacity of the Filling Section provide more

beneficial options instead of forcing them to increase their capacity through overtime.

From the list of products being handled by the company in Table 1-1, DDC-

FDCSI provided three separate production lines for the three major groups of

products being processed in the plant. These major production lines are manifested

in the organizational chart in Figure 1-2 and they are identified as the Dehydrated

Production Line, Milo Vending Mix Production Line and the Nestea Lemon Iced Tea

Production Line. Volume contribution of each product group is presented in Figure 1-

3 where the Nestea Lemon Iced Tea has the largest percentage of share compared

to the Dehydrated Culinary products and Milo Vending Mix. Focusing on cost-

efficient recommendations for Nestea Lemon Iced Tea would significantly have an

effect on the benefits gained by the company.

Page 20: Production Capacity Application

7

Figure 1-3 Percentages of Volume Distribution of major products in DDC-FDCSI

Major Product Families are designated to distinct production lines. Every

production line comprises of three sections, the Batch Preparation, Dry Mixing and

Filling which correspond to the services offered by the company. Process Capacities

of each section shown in Table 1-2 were provided by the Production Assistant based

on the historical records of actual performances. The highlighted values in Table 1-2

are the slowest production rates that incidentally determine the production rate of the

whole production line and the maximum capacity of the processes in series. The Dry

Mixing Section, Batch Preparation Section and Filling Section are the resource

constraints in the Dehydrated Culinary Products, Milo Vending Mix and Nestea Lemon

Iced Tea respectively. Capacity for Dehydrated Culinary Products and Milo Vending

Mix is one batch per hour determined by their corresponding resource constraints.

Table 1-2 Process Capacities for the three major Production Lines in DDC-FDCSI

Section Dehydrated

Culinary (batches/hour)

Milo Vending Mix (batches/hour)

Nestea Lemon Iced Tea (batches/hour)

Batch Preparation

1.25 1 1.125

Dry Mixing 1 1.5 1.5

Filling 1.875 1.875 0.625

*Source: DDC-FDCSI, 2009

20.27%

26.93%52.80%

Volume in kilogram Distribution of the Major Product Families in DDC-FDSCI

Dehydrated Culinary

Milo Vending Mix

Nestea Lemon Iced Tea

Page 21: Production Capacity Application

8

Based on the comparison of volume distribution, Nestea Lemon Iced Tea was

resolved as the product focus of the study. From the processes involved in Nestea

Lemon Iced Tea Production Line, the Filling Section has the lowest capacity of 0.625

batches per hour that determines the process capacity of the whole line. This further

narrows down the extent of the research to be mainly engaged in the NLIT Filling

Section. The low capacity of the Filling Section creates a predicament with the large

volume levels of Nestea Lemon Iced Tea handled by the company.

To further evaluate the demand levels and the process capacity of the NLIT

Production line, it would be necessary to calculate the implied utilization. In computing

for the implied utilization, the capacity requested by the demand is to be divided by the

available capacity of the production line. Capacity requested by demand is equivalent

to the total production output per month since DDC-FDCSI completes the monthly

demand received. The available process capacity was obtained from the rate of the

NLIT Filling Section and the actual production hours from June to November in the

year 2009. Table 1-3 shows the computed values of implied utilization. This

performance measure conveys how much demand exceeds the capacity of the

process where values exceeding 100% entails the deficiency in the capacity of the

production line. The recurrence of this scenario is apparent in the monthly production

of Nestea Lemon Iced Tea which verifies an imperative matter needed to be

addressed.

Table 1-3 Calculation of Implied Utilization of NLIT Production Line

NESTEA LEMON ICED TEA

June July Aug Sept Oct Nov

Capacity Requested by Demand

Batch per

month 144.755 124.485 129.842 121.392 140.037 143.960

Process Capacities

Batch per

month 120 115 120 115 125 115

Implied Utilization 120.63% 108.25% 108.20% 105.56% 112.03% 125.18%

Page 22: Production Capacity Application

9

Figure 1-4 shows the NLIT Production Line has a low capacity with respect to

the level of output being handled. DDC-FDCSI copes with the high levels of demand

by increasing the capacity through allowing scheduled overtime for the resource

constraint process.

Figure 1-4 Production Output of NLIT based on monthly demand

The actual number of overtime hours accumulated in meeting the high levels of

demand for the six-month data obtained is shown in Figure 1-5 below.

Figure 1-5 Number of Scheduled Overtime Hours in the NLIT Filling Section

June July Aug Sept Oct Nov

Actual Output 8377 7204 7514 7025 8104 8331

Actual Capacity 6944.44 6655.09 6944.44 6655.09 7233.80 6655.09

6000

6500

7000

7500

8000

8500

Pro

du

cti

on

Ou

tpu

t (i

n c

as

es

)

Production Output of NLIT for June to November 2009

June July Aug Sept Oct Nov

Overtime hours 115.80 99.59 103.87 97.11 112.03 115.17

85.00

90.00

95.00

100.00

105.00

110.00

115.00

120.00

Nu

mb

er

of

Ho

urs

Scheduled Overtime Hours in the NLIT Filling Section for the month of June to November 2009

Page 23: Production Capacity Application

10

The number of scheduled overtime hours shown in Figure 1-5 represents the

production hours of the Filling Crew which consists of seven workers. The standard

labor cost for contractual workers is 325.00 Php. Workers in the Production

Department are all contractual. Using the overtime rate of 130% primarily set by wage

policies of DDC-FDCSI incurs additional cost during scheduled overtime of seven

workers of the Filling Crew which is computed from the actual overtime hours. The

total additional overtime cost is equal to 475,832.18 Php for the period of June to

November 2009.

The length of the overtime hours is correlated with the increase of demand.

Overtime hours represent the amount of work required to accomplish demand above

the maximum capacity of the NLIT production line. The General Manager has

established average demand projections in the year 2010. The level of demand is

expected to increase up to 15,000 cases per month which is equivalent to 1.35

batches per hour.

Table 1-4 Comparison of the Current from Expected Implied Utilization

Parameter YEAR 2009 YEAR 2010

CAPACITY REQUESTED BY DEMAND

Batch per hour

0.72869 1.35

AVERAGE PROCESS CAPACITY

Batch per hour

0.625 0.625

IMPLIED UTILIZATION Percentage 116.59% 216%

The percentage of Implied Utilization calculated exceeded 100% as it signifies

the demand will further surpass the current process capacity of the NLIT Production

line by 16.59%. Continuing the scheduled overtime to cope with the capacity

requested by demand would double the monthly overtime cost. Thus, the need to

increase the capacity of the NLIT Production line is apparent.

Page 24: Production Capacity Application

11

1.3 Statement of the Problem

The capacity of Nestea Lemon Iced Tea Production Line cannot keep up with

the level of demand DDC-FDCSI is accepting. Having the lowest capacity, NLIT

Filling Section determines the production output rate. Relative to the 6-month

average capacity requested by demand, the process capacity is deficient by 16.59%.

As a result, it experienced a total of 4505 scheduled overtime hours of the Filling

Crew that incurred a total cost of 475,832.18 Php for the six-month period.

1.4 Objectives of the Study

The general objective of the study is to increase the capacity of the Nestea

Lemon Iced Tea Production Line by at least 44 % (see Appendix A for

computations).

The specific objectives of the study are to:

• illustrate the current flow of processes in the NLIT Production Line through

diagrams and flow process charts,

• identify the resource constraint that hinders the capacity of the system in

meeting the demand for NLIT Production through capacity profiles,

• determine the factors that caused the limitations of the lowest capacity,

• elevate the capacity of the resource constraint and generate alternatives,

• evaluate the associated costs and benefits of the alternative solutions, and

• Recommend the most cost-efficient alternative.

1.5 Scope and Limitations of the Study

The study opted for one product that contributes the largest percentage of the

total production volume of DDC-FDCSI which is Nestea Lemon Iced Tea. The focus

of the study is on the Filling Section of the NLIT Production Line since it has the

lowest capacity in the series of processes involved.

Page 25: Production Capacity Application

12

1.6 Date and Place of the Study

The plant and business office of DDC Foods Development and Contracting

Services, Inc. is currently situated at Block 14 Lot 26 Lazatin Blvd., Villa Victoria,

Dolores, City of San Fernando, Pampanga, Philippines. Figure 1-6 shows the road

map that indicates the exact location of the plant from the Jose Abad Santos Avenue

to Lazatin Blvd. The study began on April 13 and ended on June, year 2009.

Figure 1-6 Exact Location of DDC Food Development and Contracting Services Inc.

1.7 Gantt Chart

In laying out the activities throughout the study, Figure 1-7 shows the

procedures conducted and the duration of the completion of the tasks.

Figure 1-7 Schedule of Activities Performed during the whole study period

Page 26: Production Capacity Application

2.0 METHODOLOGY

Page 27: Production Capacity Application

14

2.1 Procedures

The identification of the possible areas of study was conducted during the

orientation of the basic processes being performed in the company. After the

comprehensive discussion and briefings regarding the policies, practices,

documentations, tests and responsibilities, the production facilities were observed.

The production supervisor provided indications of the possible areas where DDC-

FDCSI encountered problems. One of the possible areas that hold a critical

predicament was the Filling Section of the Nestea Lemon Iced Tea Production Line

since it has a lower production rate compared to the Batch Preparation and Dry

Mixing Section. In examining the weekly production schedule and the daily schedule

monitoring of production personnel, the filling process crew constantly experienced

scheduled overtime shifts to increase the capacity and keep up with the amount of

workload accepted. From this scenario, the need of increasing the capacity of the

NLIT production line was manifested. Data were gathered during the days when the

Filling Section was operating.

The seven processes in the filling process were thoroughly observed in the

succeeding days of production. Time Study was conducted during the Actual

Observation and Preliminary Data Gathering task in the schedule of activities as

shown in Figure 1-7. Snapback method was used to record the pace of the individual

processes. Stopwatch data is available in Appendix C where the recorded time is in

seconds. Rating factors of each observed time based on the current conditions

during the time of observation of the researcher which is supported by the

Westinghouse Rating System in Appendix D. Normal time was computed from the

observed time and performance rating where its average was used to obtain the

standard time of the system. Allowance Factors were included in the computation in

order to make the data more realistic. No outliers from the raw data were found thus

all recorded readings were used as samples for computations. From the statistical

data, the required number of samples was computed. All the computations are

shown in Appendix C according to the sequence of the time study procedure.

Page 28: Production Capacity Application

15

Further continuing the computations would bring about the actual number of

workers required for the whole operation in order to meet the target production rate

which was primarily set to the next resource constraint which is the Batch

Preparation Section with a rate of 1.085 cases per minute. Increasing the capacity

was limited to this rate to avoid formation of another bottleneck problem outside the

scope of the study.

From the initial data, analysis and documentation was made while

brainstorming for the main predicament. To further support the strength of the

problem identified, root causes were evaluated that contributed to the real problem.

Significantly knowing the source and generating solutions to small factors of cause

would in turn result to a greater improvement. Related production concepts were

deliberated to further illustrate the alternatives to be proposed. External research is

part of the evaluation where the applicable production concepts are selected to

appropriately quantify and exhibit the actual occurrences in the NLIT Filling Section

of DDC-FDCSI.

Generated alternatives were based on the root cause analysis and the

controllable, noise, and experimental analysis. Related causes were grouped

accordingly and each group has their corresponding alternatives based on the

identified root causes. Evaluating the alternatives was performed based on the

criteria relevant for the selection. At any alternative chosen, the other experimental

factors of the eliminated groups were as well solved with the chosen alternative. This

is true since the experimental factors are correlated relative to the main problem.

Cost-Benefit Analysis was conducted to assess the net benefits of the alternatives

using Factor Rating. The best alternative having the highest rating was to be

recommended. A summary and conclusion of the study was included and the areas

for further study are discussed in the latter part.

Page 29: Production Capacity Application

16

2.2 Definition of Terms and Symbols

The following tables serve as guide for technical terms used within the

company as well as the symbols used to describe certain processes.

Table 2-1 List of Technical Terms used in the research and their Meanings

Capacity Constraint Resource Any resource that is a potential bottleneck

if not addressed carefully.

Cycle Time

The amount of time each workstation has

to complete its set of tasks before the

product moves to the next station.

Fence 1 The lower limit for the acceptable range

Fence 3 The upper limit for the acceptable range

Flow Rate or Throughput Rate It is the average rate at which units flow

past a specific point in the process.

Implied Utilization Capacity requested by Demand divided

by the Available Capacity

Inter Quartile Range

Represents the length of the interval that

contains roughly the middle 50% of the

data.

NLIT Nestea Lemon Iced Tea

Non-bottleneck Any resource whose capacity is greater

than the demand placed on it.

North DC Distribution Center of Nestle in the

Northern part of Luzon

Polybags Polyethylene Bags with a maximum

capacity of 20 kilograms

Process Capacity the maximum output rate per unit time

Resource Constraint or Bottleneck

It is a resource that is so heavily loaded

that it cannot perform its entire assigned

task. It is the maximum process capacity.

Weekly Supply Outlook The weekly forecast of Nestle demand.

Page 30: Production Capacity Application

17

Table 2-2 List of Symbols used in charts and their Meanings

Symbol Meaning

Involve basic process and specific operations

Inspection of specified task and also used in specific

processes

Storage

Document involve in the process

Transport

Delay

Symbols were used to illustrate the flow of the processes involved in the

general procedure of the company as well as the detailed tasks in the production line

of Nestea Lemon Iced Tea which is further discussed in the next chapter.

Page 31: Production Capacity Application

3.0 SYSTEM DOCUMENTATION

Page 32: Production Capacity Application

19

3.1 General Processes

The three departments involved in the manufacturing process at DDC-FDCSI

are the Logistics, Production, and Quality Assurance. The specific tasks of each

department are illustrated in Figure 3-1 that serves as an overview of the whole

process. Manufacturing process starts with the procurement of raw materials based

from and packaging materials based from the weekly supply outlook up to the

dispatch of finished goods. Every operation in the process undergoes a standard

procedure and documentation. Checklists and forms are filled-out for the purpose of

recording the inventory and at the same time monitoring the every operation involved

in manufacturing for traceability purposes. The documents within the processes are

listed in Table 3-1 corresponding to the designated departments.

Table 3-1 List of Documents Handled by assigned Departments Department Document

Production

Start-up and Shutdown Checklist

Daily Schedule Monitoring of Personnel

Dehydrated Culinary Production Monitoring

Weekly Production Schedule

Checklist of recipe

Input/Output Net Weight Control

Production Report

Quality Assurance

Sensory Evaluation Tests

Truck Inspection Checklist (inbound/outbound)

Physico-chemical testing

Moisture Content Analysis

Input/Output Net Weight Control

Release Documents

Logistics

Weekly Supply Outlook

Requisition Slip

Sales Invoice

Inventory List

Packing Report

Production Output

Page 33: Production Capacity Application

20

The Logistics Department uses the SAP software of Nestle from the encoding

of raw materials to releasing them into their system. This software exclusively

ensures the safe transfer of significant data from DDC-FDCSI to Nestle. In acquiring

supplies from the warehouse, a requisition slip is sent containing the list of raw

materials and packaging materials needed in the manufacturing plant. Inventory

levels of raw materials are manually recorded through backward tracing of the

logistics from the acquired production reports. From the standard procedures,

inventory level monitoring is performed on a monthly basis.

The three main processes involve in Production of dry products are Batch

Preparation, Dry Mixing and Filling. Each process is further discussed in the

following sections of the paper. Furthermore, the track of production is carefully

monitored every step through a Production Monitoring Scheme followed as a

standard basis for operations. Monitoring between the manufacturing lines is

specifically performed by the production assistant.

The QA Department is responsible for the quality of the supplies received in

the plant and the finished goods. Release documents are taken by an authorized

person after comparing all relevant test results and process parameters with the

release criteria. This is both applicable for raw materials and finished goods. Raw

Materials have to undergo the internal release system before utilizing it for

production. A release of a finished product means that a given lot becomes free to be

handed over without restriction to a customer, for distribution or use. For that reason,

it is mandatory that each batch that is released meets all the release criteria before

being dispatched to Nestlé’s North Distribution Center. The Release System includes

all procedures related to release, from the way the release decision is taken, by

whom, on which basis, where the decision is recorded, as well as the consequences

of the release decision on the status and movement of the finished goods. DDC-

FDCSI is responsible for defining manufacturing parameters and criteria given in the

Product Specifications would be relevant as release criteria. Sensory evaluation, net

contents, and critical control points must all be included. Release criteria must be

met consistently during the whole production of a lot and evaluated accordingly.

Page 34: Production Capacity Application

21

Sensory evaluation holds an essential role in product development and

quality assurance. The taste, smell, texture and appearance of food and beverage

products are important when defining the final quality and product standard. Sensory

is a significant aspect of the over-all characteristics of the product. The sensory

characteristics are noticeable to the consumer and can either give them pleasure or

displeasure. It is of utmost importance to know what the sensory characteristics are

of a given product and be able to maintain these consistently. For this reason, DDC-

FDCSI regards sensory evaluation as an important release criterion for the Nestea

Lemon Iced Tea.

Nestle Quality System (NQS) requires sensory evaluation to be carried out

throughout the production, from raw materials to the products supplied to the

customer. The In/Out test has been chosen as the sensory quality control method for

Nestle Factories to guarantee consistent quality. A trained panel evaluates samples

as either “In” or “Out” of sensory specifications. For each product the sensory

specifications must comprise the list of key attributes, most of which should derive

from 60/40 consumer tests, and their acceptable range. Assessors are trained to

recognize what is “In” and what is “Out” by means of reference samples, pictures or,

in exceptional cases, descriptions illustrating the various “In”, “Borderline” and “Out”

cases for key attributes. The result of the evaluation is the percentage of assessor

rating the sample as “In”. This percentage determines which batches pass or fail,

based on a set of decision rules defined by Management. Product Standard is a

product which meets all analytical and sensory specifications and produced using

prescribed process parameters. The product sample must have been selected

approved and maintained using a standard procedure.

Page 35: Production Capacity Application

22

Figure 3-1 Flow Process Chart of the General Processes in DDC-FDCSI

Page 36: Production Capacity Application

23

3.2 Product under Study

From the products being handled in the company, the study chose to focus

on Nestea Lemon Iced Tea based from its large production volume contribution. As

seen previously in Figure 1-3, 52.80 % of the total production volume is contributed

by the Nestea Lemon Iced Tea Product alone.

Figure 3-2 Actual Dimensions of 360g NLIT pouch and 12 x 360g case

The actual image of the product is seen in Figure 3-2 above. The net weight

of the product is 360 grams per pouch. Conversion of units used within the

production is based from the batch size of the production line. For the NLIT, the

batch size is 250 kilograms per batch. Every case contains 12 pouches of NLI.

Further conversion of units is indicated in Appendix B. The product unit size of NLIT

is relatively lower than the other products having a standard weight of 1 kilogram.

Despite of this, Nestea Lemon Iced Tea produces the largest production volume.

The raw materials used in the production of NLIT are citric acid, tea extract,

gum Arabic, flavor lemon, sugar, sweetener aspartame, Vit C ascorbic acid, and

sweetener acesulfame. The raw materials are weighed according to their

specifications during batch preparation and are homogenously mixed in the Dry

Mixing Section before being filled into pre-formed pouches in the Filling Section.

Page 37: Production Capacity Application

24

3.3 Production Capacity

From the six-month data of production volumes shown in Table 3-2 below,

the Nestea Lemon Iced Tea has an average of 32186.16 kg per month. High

demands have been constantly met by the production capacity with scheduled

overtime of workers. The amount of scheduled overtime workload is relative to the

difference between the Production Volume and the Actual Capacity per month.

Overtime hours rely on the actual production hours available in the Filling Section.

The actual capacity is determined by the Filling Section having the lowest capacity in

the series of processes involved. Master Production Schedule dictates the allocation

of workload in a weekly basis. Filling Section only starts production as the preceding

Sections provide a complete set of mixed batches.

Table 3-2 Production Volume in kilograms of NLIT during June to Nov 2009 Month Production Volume (in kg) Actual Capacity (in kg)

June 36188.64 30000.00

July 31121.28 28750.00

August 32460.48 30000.00

September 30348.00 28750.00

October 35009.28 31250.00

November 35989.92 28750.00

Page 38: Production Capacity Application

25

3.4 Production System

The general production system of Nestea Lemon Iced Tea is illustrated in

Figure 3-3. The inputs to the system are the raw materials and packaging materials.

Raw materials for NLIT are sugar, tea extract, gum Arabic, flavor lemon, sweetener

aspartame, ascorbic acid, and sweetener acesulfame. Packaging materials would

include the pre-formed pouches, label paper adhesive, and case corrugated. In

undergoing the production process, the outputs of the process are NLIT cases with

the corresponding lot codes for traceability and the date of expiry. These labels are

relevant information required by food authorities.

Figure 3-3 Production System Framework of Nestea Lemon Iced Tea

Tracing a physical object is necessary when a need to retrieve information

about its history, application or location exists. Its usefulness is for tracking possible

defects if detected outside of the DDC-FDCSI system. Information regarding the

Date conducted, Personnel involved, Quantity produced, Batch Code, Analysis

(Passed or Failed), Manufacturing Date, Usage Decision Date, Usage Decision By,

Batch Code of bulk used, Inspection Lot Number of Finished Product, List of all raw

and packaging materials used with corresponding batch code, inspection lot number

and usage decision date, CCP monitoring, Date dispatched, and Destination plant

(North DC).

Page 39: Production Capacity Application

26

3.5 Process Documentation

3.5.1 Batch Preparation Section

In the Batch Preparation Section, the raw materials are obtained from the

storage area by pallets which are transferred with the use of a manual pallet jack.

Each raw material has its corresponding lot code which is used to monitor

material usage and inventory level. Lot codes used are exclusive only in the

DDC-FDCSI system which is manually recorded. This becomes relevant for

products having similar raw materials being used. Material usage recording uses

lot codes to hold information that would be relevant for tracing the raw materials

used for a specific batch in the NLIT production.

Weight specifications of raw materials in the Actual Production Area are

indicated on the NLIT Batch Preparation Checklist document as well as on

readable signs near the digital balance for referencing during the weighing

process. Workers assigned to weigh raw materials refer mostly on the signs

posted near them. Amounts are fixed based on the actual batch size used within

the production line which is 250 kilograms. Figure 3-4 shows the detailed

activities in the Batch Preparation Section with no significant delays occurring in

the process. Raw Materials are separately placed in polybags with their

corresponding weight specification and the capacity of the polybag upon

transferring to the Dry Mixing Section. Labeling format is based on the assigned

batch number indicated in the Master Production Schedule. Each Raw Material

occupy only one polybag except for the Sugar ingredient which requires ten

polybags. The labeling format for the sugar ingredients is as follows: “Raw

Material Symbol – Batch Number – A to J”. The remaining raw materials such as

the tea extract, citric acid, and other small components occupy only one polybag.

Labeling for the other raw materials would comprise of the raw material symbol

and batch number.

Page 40: Production Capacity Application

27

FLOW PROCESS CHART OPERATION: Batch Preparation of Beverage Production Line

LOCATION: DDC Plant

COMPANY: DDC Food Development and Contracting Services, Inc

SECTION: Beverage Line – Batch Preparation Process

ANALYST: Jaquelyn Margaret L. Miciano TYPE: Summarized METHOD: Present

ST

EP

DESCRIPTION

SYMBOL

REMARKS

OP

ER

AT

ION

TR

AN

SP

OR

T

DE

LA

Y

INS

PE

CT

ION

ST

OR

AG

E

1 Transport Raw Materials

to Batch Preparation Process

2 Scouring of dirt from bags of raw materials

Check presence of wood splinters

3 Labeling of Polyethylene

Bag

Uses marking

pen

4 Dragging the Raw

Material near the digital balance

5 Sieving of Sugar

Check presence

of foreign objects

6 Transferring Sugar to empty PE Bags

7 Weighing of Raw

Material according to recipe

Uses checklists for each recipe

8 Tying of Polyethylene

bag

9 Transferring weighed raw materials to pallet

10 Recording of Material

Usage

11 Stacking of Prepared

Batches on pallets

Figure 3-4 Flow Process Chart of Batch Preparation of NLIT Production Line

Page 41: Production Capacity Application

28

3.5.2 Dry Mixing Section

Prepared batches are transferred by plastic pallets using a manual pallet

jack to the Dry Mixing Section with batch numbers indicated on the polybags.

The labeled polybags are placed on pallets according to the sequence of

batches. One batch of sugar ingredient occupies one pallet. The remaining raw

materials are grouped according to ingredients and not by batch numbers. This is

to automatically distinguish the different ingredients. Tipping and loading the raw

materials to the dry mixer is done in a particular order for a preliminary mixing.

The order of placement in the dry mixer is five polybags of sugar, one polybag of

tea extract, citric acid and the small components and then the remaining five

polybags of sugar. Figure 3-5 demonstrates the operations concerning the Dry

Mixing Section of the production line.

From the conducted trials and tests, eight minutes is enough for the dry

mixer to attain the homogeneity of the bulk mixture. Sensory Evaluation tests are

carried out as part of the standard quality protocols of the QA Department where

sampling is made per batch as exemplified in the General Processes Section of

the chapter. Labeling format depends on the batch number being handled. There

would be a resulting 10 polybags of mixed powder for every batch and are

labeled as follows: “Batch Number – A to J”. A new set of polybags is used to

transfer the batches to the Filling section.

Page 42: Production Capacity Application

29

FLOW PROCESS CHART OPERATION: Dry Mixing of Beverage Production Line LOCATION: DDC Plant COMPANY: DDC Food Development and Contracting Services, Inc

SECTION: Dry Mixing Process

ANALYST: Jaquelyn Margaret L. Miciano TYPE: Machine METHOD: Present

ST

EP

DESCRIPTION

SYMBOL

REMARKS O

PE

RA

TIO

N

TR

AN

SP

OR

T

DE

LA

Y

INS

PE

CT

ION

ST

OR

AG

E

1 Setup of Machine

2 Transport Prepared

Batches to Dry Mixing Process

3 Label Polyethylene

Bags

according to

batch numbers

4 Pour raw materials

inside Dry Mixer

5 Run Dry Mixer

Set to 8 minutes for homogeneity

6 Pour bulk mixture into bins with labeled PE

Bags

7 Recording of Batch

Completion

8 Stacking of Prepared

bulk mixture on pallets

Figure 3-5 Flow Process Chart of Dry Mixing of NLIT Production Line

Page 43: Production Capacity Application

30

3.5.3 Filling Section

The batches handled in the Dry Mixing Section are transferred to the

Filling Section and are processed in sequence according to their batch numbers.

Operations involve are labeling, coding, scooping, weighing, sealing, wiping,

stacking and lot coding. A better illustration of the flow of the operations is

presented through a Flow Process Chart in Figure 3-6. The standard time was

calculated from the time study conducted within the NLIT Filling Section as

presented in Appendix C. Inspection is done every 15 minutes in the weighing

operation as part of the standard procedure for the net weight control. It is

determined whether the net weight of the particular pouch is within the allowable

weight range set by the company. The allowable range is ± 0.5 % of the 360-

gram net weight.

Time study was conducted to establish the standard time of the

operations in the Filling Section. This work measurement technique represents

an impartial production standard. Stopwatch data samples obtained are

presented in Table 9. Complete raw data samples are exhibited in Appendix C.

Elements chosen are the operations involved in the Filling Section as indicated

also in the Flow Process Chart in Figure 13. Standard time computations are also

located in Appendix C.

Table 3-3 Sample Stopwatch Data of Filling Operations Element

No. Process Name

Trial No. (Actual time in seconds) Ave

1 2 3 4 5 6 7 8

1 Labeling

of Pouches

72.34 56.04 47.86 59.73 74.85 83.91 60.32 83.16 67.38

2 Coding

of Pouches

35.77 47.72 64.07 84.42 59.75 60.28 54.27 76.34 60.3

3 Scoop Nestea Mixture

37.26 59.84 47.60 45.73 48.33 51.84 47.18 52.30 47.61

4 Weigh

Pouches 108.19 127.08 138.27 72.31 151.89 155.84 168.17 191.59 134.1

5 Seal

Pouches 123.57 160.72 126.78 106.94 145.06 113.87 157.28 175.17 134.8

6 Wipe off powder residue

59.67 71.54 55.78 57.85 72.36 59.89 89.24 62.74 65.75

7 Stack

and Lot coding

31.43 43.10 41.85 44.69 46.72 41.38 35.07 52.18 41.68

Page 44: Production Capacity Application

31

FLOW PROCESS CHART OPERATION: Filling of Beverage Production Line LOCATION: DDC Plant COMPANY: DDC Food Development and Contracting Services, Inc

SECTION: Filling Process

ANALYST: Jaquelyn Margaret L. Miciano TYPE: Summarized METHOD: Present

ST

EP

Tim

e (m

in)

DESCRIPTION

SYMBOL

REMARKS

OP

ER

AT

ION

TR

AN

SP

OR

T

DE

LA

Y

INS

PE

CT

ION

ST

OR

AG

E

1 Transport Packaging Materials to Labeling

Process

2 Transfer prepared bulk

mixture in filling process

3 0.9 Label Preformed

Pouches with stickers

4 0.7 Punch codes in

pouches

5 Place bulk mixture into

bin

6 0.6 Scoop bulk mixture into

pouches

7 1.7 Weigh pouches

According to specification

8 Input Output Weight

Content

Every 15 minutes

9 1.7 Seal pouches

10 0.9 Wipe off powder residues outside

pouches

11 0.5 Fill, Stack, Code Cases

and tag pallets

13 Transport pallets in

dispatch area

14

Dispatch

Figure 3-6 Flow Process Chart of Filling of NLIT Production Line

Page 45: Production Capacity Application

32

3.6 Manpower Complement

The three main processes in the company have their own designated crews.

Four workers are assigned to accomplish the tasks in the Batch Preparation Section

while the Dry Mixing Section requires only three. Presence of a dry mixer made tasks

under the Dry Mixing Section to become more inclined on the standard operating

procedure of the machine. Table 3-4 shows the tasks and the number of workers

assigned to it.

Table 3-4 Number of Workers in the Sections of the NLIT Production Line

SECTIONS TASKS NUMBER OF WORKERS

Batch Preparation

Siever 2

Weigher 2

TOTAL 4

Dry Mixing

Operator 2

Helper 1

TOTAL 3

Filling

Labeller 1

Coder 1

Scooper 1

Weigher 1

Sealer 1

Wiper 1

Stacker 1

TOTAL 7

*Source: DDC-FDCSI, 2009

Focusing on the Filling Section, its crew consists of seven operators in the

production line that includes the labeler, coder, scooper, weigher, sealer, wiper, and

stacker. Each operator is assigned to a single task within the production line. In

comparing the number of workers of each section, the Filling Section has the highest

number of workers involved in its operations.

Page 46: Production Capacity Application

33

3.7 Machine and Equipment

The Batch Preparation process has two equipments being used which is the

digital balance for the in acquiring the specifications of the raw materials. The 100-

kilogram capacity of the digital balance for Batch Preparation is larger than the one

used in the Filling Section.

The machine present in the production of Nestea Lemon is the dry mixer that

has a maximum capacity of 250 kilograms. The batch size in the production is

equivalent to the maximum capacity of the mixer. During operation, the whole cone

of the mixer rotates 360 degrees at the rate of 6 revolutions per minute. The

cylinders inside the cone rotate simultaneously with the cone ensuring the

homogeneity of the mixture.

Figure 3-7 Nestea Lemon Iced Tea Dry Mixer

In the Filling Section, there are four equipments being used within the

production line. These are the digital balance, horizontal band sealer, hot foil coder

and carton coder. Figure 3-8 shows the images of the digital balance and the

horizontal band sealer. Capacities of the two equipments are based from their

function. The digital balance has a capacity of 1200 grams. Transmission speed of

the horizontal band sealer is 3 feet per minute. Figure 3-9 displays the images for the

hot foil coder and carton coder. Its capacities are based on the maximum speed of

printing onto packaging materials. Printing speed of the hot foil coder is 20 to 50

prints per minute while the carton coder has a speed of 300 imprints per minute.

Page 47: Production Capacity Application

34

Figure 3-8 Digital Balance (left), Horizontal Band Sealer (right)

Figure 3-9 Hot Foil Coder (left), Carton Coder (right)

Given the capacities of the equipments used within the Filling Section, the

actual capacity is still determined by the production rate of the worker since these

equipments are manually used.

Page 48: Production Capacity Application

35

3.8 Plant Layout

An illustration of the actual floor layout of the plant is shown in Figure 3-10.

The three distinct production lines have their own area for Batch Preparation, Dry

Mixing and Filling. NLIT Filling Section is the focus of the study as stressed in the

figure.

Figure 3-10 Actual Layout of the Manufacturing Plant

Page 49: Production Capacity Application

36

3.9 Workstation under Study

Inside the NLIT Filling Production Area are the stations of the processes

executed in the whole Filling Section. The arrangement is presented in sequence

with the red arrows corresponding to its flow from the labeling to the stacking and lot

coding. Referring to the plant layout as basis, the bottom part of the workstation is

the partitioning wall from the NLIT Dry Mixing Area. Squares represent tables used

within the production line as processes are performed in standing position. Every

operation consists of only one worker to accomplish the task. The pallet at the side of

the scooper holds the mixed batches from the Dry Mixing Section while the pallet at

the end of the process would consist of the prepared NLIT cases in the Filling

Section. Proper palletizing is followed based on the required arrangement indicated

in the cases to ensure the locked position of the whole batch.

Figure 3-11 Workstations in the NLIT Filling Section

Page 50: Production Capacity Application

4.0 RESULTS AND DISCUSSIONS

Page 51: Production Capacity Application

38

4.1 Problem Identification

A resource constraint exists in the Nestea Lemon Iced Tea Production Line.

The actual capacity of each Section is based from their performances and production

output records. In comparing the capacities of the three production lines, the Filling

section has the lowest capacity indicating that it is the bottleneck of the system. The

production output rate is established by the bottleneck operation. As seen in Figure

4-1, the Filling Section limits the total production capacity to 0.625 batches per hour.

Figure 4-1 Flow Rate of the system with a Resource Constraint

In the effort of attaining the capacity requested by demand, the filling process

increases its capacity by regularly extending work hours of the Filling Crew. The

overall overtime hours accumulated to 4505 hours from the seven workers involved

in the filling process. Figure 4-2 shows the overtime production hours in the Filling

Section alone for the given monthly period as illustrated below.

Figure 4-2 Total Overtime Hours in the Filling Section for June to Nov 2009

Since the NLIT make up for 52.8 % of the total production volume, it would be

important to address capacity problems occurring in the NLIT Production Line. With

the high volumes of production, it is necessary to increase the capacity of the Filling

production line by dealing with the resource constraint.

June July Aug Sept Oct Nov

Overtime hours 115.80 99.59 103.87 97.11 112.03 115.17

50.00

70.00

90.00

110.00

130.00

Nu

mb

er

of

Ho

urs

Total Overtime Hours in the NLIT Filling Section for the month of June to November 2009

Page 52: Production Capacity Application

39

4.2 Problem Analysis

4.2.1 Identification of Root Causes of the Problem

From the three main processes in the NLIT Production Line, The Filling

section determines the average production rate since it has the lowest actual

capacity compared to the Batch Preparation and Dry Mixing Process. In

analyzing the factors that caused its low capacity, the factors were classified into

Man, Method, Machine and Material. The summarized first level factors of the

problem are presented through the fishbone diagram in Figure 4-3.

Figure 4-3 Summarized Causes of Low Capacity of the Filling Section

Each factors under of Man, Method, Machine and Material contributes to

the main predicament of having low capacity of the NLIT Filling Section. There

are no environmental conditions that significantly affect the capacity of the

process. Temperature, lighting and humidity in the production area are

maintained at constant levels without abrupt changes.

Page 53: Production Capacity Application

40

4.2.1.1 Man

The current production rate of the Filling Section with a crew

consisting of seven workers is 0.625 batches per hour. Insufficiency in the

number of workers was recognized from comparing the amount of

workload to the actual capacity of the process. Workload arrives from the

Dry Mixing Section with a rate of 1.5 batches per hour which is faster than

the process capacity of the Filling section thus workload is accumulated

through time. Part of the fast rate of the Dry Mixing Section is the

presence of a machine relative to the manual operations of the filling

process. The Filling Section lags in production by 0.875 batches per hour

which in turn is handled through allowing scheduled overtime of the Filling

Crew for every production. Production Department does not acknowledge

the need to increase the manpower capacity of the Filling Section and

instead chooses to tolerate overtime of the Filling Crew.

Workers of the Filling Crew are designated to distinct processes

involved in the production line which was illustrated in the layout of the

Filling Workstations in Figure 3-11. One of the processes involved is the

weighing of 360-gram pouches of Nestea Lemon Iced Tea powder. From

the time study conducted, the weighing operation takes the longest time

to execute. Referring to the average observed time and standard time of

the Filling operations in Table 4-1, the weighing of pouches has shown its

consistent time-consuming operation as it holds the longest time

recorded. Although the sealing operation does not linger far from the

values of the weighing operation, no problems contributed by the sealer

occur during this operation. For the weighing operation, adjustments have

to be made to ensure the 0.5 % allowable net weight difference of the

pouches. This has been caused by a factor associated to Man where the

scooper creates net weight discrepancies because of the scoop’s volume

capacity of 450 grams that exceeds the required amount of 360 grams

per pouch. For that, the weighing operation requires net weight

adjustments.

Page 54: Production Capacity Application

41

Table 4-1 Average Observed Time and Standard Time of Filling Elements

Element No. And Description

Average Observed Time (min/case)

Standard Time (min/case)

1. Labeling of Pouches 1.150 1.261

2. Coding of Pouches 0.957 1.049

3. Scoop Nestea mixture 0.818 0.896

4. Weigh pouches 2.274 2.493

5. Seal Pouches 2.252 2.469

6. Wipe off powder residue 1.146 1.257

7. Stack and Lot Coding 0.641 0.702

Another factor associated to Man is the occasional lax attitude of

workers which happens when there is no supervision. The production

assistant is responsible for supervising and overseeing the current status

of the production line. Part of this responsibility is ensuring the proper

execution of the tasks within the line with accordance to the expected

pace of production. This is compulsory to guarantee that the master

production schedule is followed. Failing to execute inspection between

shifts occur despite the existing production policy which contributes to the

further slowing down of the operations in the production line.

Figure 4-4 Cause Factors Associated to Man

Page 55: Production Capacity Application

42

4.2.1.2 Method

The factor associated with the Method used is the high processing

time of the Filling Section relative to the other processes in the NLIT

Production Line. Manual processes performed within the Filling

production line rely on the manpower capacity of the Seven-worker Crew.

The absence of a filling machine forces the Filling section to maximize

manpower capacity that is detrimental to the length of processing time. Its

significance is relative to the presence of a dry mixing machine in the

preceding process which is the Dry Mixing Section. Existence of a dry

mixer significantly increases the rate of production in the Dry Mixing

Section resulting to bottleneck processes within the NLIT production line

particularly the Filling process being next in line. Unbalanced capacities

within the line significantly contribute to additional production costs.

Manual net weight control is a contributing factor to the high

processing time. Adjustments have to be made during the weighing

process because of the high volume capacity of the scoop compared to

the required net weight of individual pouches. A smaller scoop is used to

make these adjustments. Since the NLIT product is the only product

handled at 360 grams per pouch and all the other products have a unit

size of one kilogram, the available 450-gram standard size of the scoop

within the plant has caused the weighing process of the NLIT Filling

Section to be a factor in the high process time. This is further supported

through the average observed time of the weighing operation as

presented in Table 4-1.

Figure 4-5 Cause Factors Associated to Method

Page 56: Production Capacity Application

43

4.2.1.3 Machine

Machine performances in the Filling section have not caused the

lowering of capacity of the production line. Manual operation of machines

causes it to depend on the worker’s handling speed. Efficiency of the

machines is relative to the performance of the worker as the equipments

used are semi-automated. Performance of the machines utilized in the

production line solely relies on the quality of the output being produced in

accordance to their functions. Sealing ability of the Horizontal Band

Sealer is measured through appropriate quality test for leaking of

pouches. Separate standard procedures are performed to measure these

performances. No significant defects have been recorded based on the

performance of the machines. Preventive Maintenance for these

machines that were illustrated in the previous chapter is regularly

performed upon start of production. This avoids considerable delays

during production resulting to no machine downtimes.

Initial number of machines was determined from the expected

level of production volume as well as from the existing Production lines of

the Dehydrated Culinary and Milo Vending Mix products. The Dehydrated

Culinary Production Line was design for small volumes of production with

respect to the levels of demand received for products under this group.

From the workstation designs of established production lines within the

plant, the design for the NLIT Production line originated on the existing

designs used by the company. Underestimation of the volumes of orders

has limited the capacity of the NLIT Filling Section to a single set of

machines. Quantity of the machines that were purchased by the company

for the NLIT Filling Section was based on the initial design of the

workstation that only has a single set for one production line. Decision on

the workstation design by the Management was resolved upon launching

the production of NLIT. Increase in the production volume of NLIT through

time was underestimated by Management that causes the low capacity of

the Filling Section.

Page 57: Production Capacity Application

44

Machines involved in the Filling section include the digital balance,

horizontal band sealer, hot foil coder and carton coder. One of each

machine is available in the NLIT Filling section. The number of machines

restricts the capacity of the process since increasing manpower is not

viable without additional machines. The layout of the workstation in Figure

3-11 supports the design of having a single operator for each machine.

Primary investment for the NLIT Filling Section was constricted to a single

set of machines. This further restricts the capacity of the Filling section as

the number of workers is relative to the number of machines available.

Additional manpower entails additional machines.

Figure 4-6 Cause Factors Associated to Machine

4.2.1.4 Material

The only contributing factor associated with the Material is the

small net weight of the product. Processing time is further lengthened by

the small breakdown of the large batch sizes. From the batch size of 250

kilograms, the process is required to break the large volume into 360

grams. The Filling Section performs this task to satisfy the requirements

of the client which is out of the control of the company.

Figure 4-7 Cause Factors Associated to Material

Page 58: Production Capacity Application

45

4.2.2 CNX Analysis

The associated root causes are further classified into C’s, N’s and X’s

which are controllable, noise and experimental factors respectively. Table 4-2

shows the summary of the root causes recognized and their corresponding

classification. Referring to Table 4-2, two noise factors, one controllable factor

and five experimental factors were identified. Factors classified under noise

entails that these causes would not be addressed by the study. Tackling the

controllable factor contributes to resolving the problem through adhering to the

standard practices within the manufacturing plant. Resolving experimental factors

by means of utilizing appropriate concepts related to the causes would in turn

result to determining alternative solutions to address the main problem.

Table 4-2 CNX Analysis of the Root Causes of Low Capacity of Filling Section

Root Causes Controllable

(C)

Noise

(N)

Experimental

(X)

Amount of work load exceeds the manpower capacity.

The scooper creates large net weight discrepancies.

The production assistant forgets to inspect the Filling Section. �

There is an absence of a filling machine.

The volume capacity of the scoop is 450 grams.

The workstation is initially designed for small volumes of production

There is a single set of machines available.

The net weight of the NLIT mixture to be filled is small.

Page 59: Production Capacity Application

46

Noises are root causes that are beyond the control of the company and

beyond the scope of the study. These are the problems that the study would not

be able to handle as the limitation of the scope applies. Noise is identified in the

Material cause factors where the net weight of the product was observed to be

small. Required weight specifications are provided by the client. DDC-FDCSI is

not involved in determining the appropriate net weight of the product that makes

the cause to be out of scope. This requires versatility in the production of DDC-

FDCSI to handle difference in weights of products. Another noise factor is

associated with Machine causes. Expecting small volumes of production has

limited the availability of machines to a single series. The General Manager and

the Project Engineer are the ones responsible for determining the number of

machines required. Demand levels for the product were underestimated thus

leading to a low capacity of the NLIT Filling Section relative to the capacity

requested by demand. These are the factors excluded in the scope of the study

because it is difficult to control.

Controllable root causes are merely problems due to lack of compliance

in the policies and standards set by DDC-FDCSI. To deal with this problem, strict

implementation of the rules should be manifested to the operators and

employees that directly affect the root cause of the problem. One controllable

factor associated with Man is identified through the CNX analysis which is

summarized in Table 4-2. Inspection of the Filling Section is a critical

responsibility of the production assistant as it affects the attitude and effort of

workers during production. Irregular production line monitoring occurs despite the

small facilities of the manufacturing plant. Recommended number of inspections

is at the minimum of twice per production shift based on the standard

procedures. The schedule of inspection has no fixed time slot to avoid the

workers’ anticipation of the production assistant’s arrival. A Production Monitoring

Scheme is currently followed by the production department. Details regarding the

standard procedure are presented in Figure 4-8. Examination process is

conducted by the production assistant during the first and last quarter of the

production shifts. Production output rate is to be checked by visually inspecting

the status of the production line.

Page 60: Production Capacity Application

47

DDCDDCDDCDDC Food Development Contracting Services,

Inc. San Fernando, Pampanga PRODUCTION

MONITORING SCHEME

ITEM: NESTEA LEMON ICED TEA

CHAPTER 3: MANUFACTURING LINE CHECKS

Area: FILLING

OBJECT PURPOSE

EXAMINATION

WHAT HOW WHEN BY WHOM

FILLING CREW

PRODUCTION LINE STATUS

CHECK

OUTPUT RATE

VISUAL INSPECTION

DURING THE FIRST AND LAST

QUARTER OF THE SHIFT

PRODUCTION ASSISTANT

Figure 4-8 Production Monitoring Scheme for Production Line Inspection

The experimental causes are the problems that can be altered in such a

way of achieving the objectives of the study. These are the ones that can have

quantitative solutions in order to improve the current system. To further address

each experimental factor, the initially identified experimental factors are to be

grouped.

Correlation exists between experimental cause factors and it would be

more comprehensive to further group the experimental factors according to their

causes. There are seven experimental causes identified. Cause factors

emphasizing the insufficient capacity are selected among the classifications of

Man, Machine and Method to determine the Experimental Factor Group A shown

in Table 4-3. The first would be the amount of workload exceeds the manpower

capacity. The workload entering the filling process is determined by the amount

of workload the Dry Mixing Section finishes. The last factors selected is

concerned with Machines that there is a single set of machines available in the

NLIT Filling Production Line. Machines identified in the series of processes

involved in the Filling Section are described in detail in the previous chapter. The

grouped factors are associated with the actual capacity of the NLIT Filling

Section in terms of the availability of the resources used in production.

Table 4-3 First Group of Experimental Factors

Group Experimental Factors

A

1. Amount of workload exceeds manpower capacity.

2. There is a single set of machines available.

Page 61: Production Capacity Application

48

The Experimental Factor Group B consists of only one cause factor as

shown in Table 4-4. Absence of a filling machine is recognized to have caused

the manual handling of the filling process. Because of this, the production output

rate is controlled and limited by the manpower capacity. Moreover, the

identification of this factor is as well relative to the preceding process in the Dry

Mixing Section where a dry mixer is present in the operation. This group

concerns the automation of the processes involved in the Filling Section through

introducing a filling machine. The need for a machine was developed from the

current rate of the preceding process. Attending to this need intends to resolve

the main problem as well as the other cause factors identified in the study.

Table 4-4 Second Group of Experimental Factors

Group Experimental Factors

B 1. There is an absence of a filling machine.

Lastly, Experimental Factor Group C involves the factor causes related to

the use of the inappropriate tool in the scooping area. From Table 4-5, the root

causes include the large volume capacity of the scoop and the necessity to make

weight adjustments. The following factors were identified in the cause factors

associated to Man and Method respectively. Group C particularly deals with the

high processing time contributed by the weighing operation in the filling process

which in turn is caused by the large capacity of the scoop.

Table 4-5 Third Group of Experimental Factors

Group Experimental Factors

C

1. The scooper creates large net weight discrepancies.

2. The volume capacity of the scoop is 450 grams.

The three experimental factor groups distinguished caused the main

problem of the Filling Section having a low capacity. Resolving any group of

factors would successively provide solutions for the other group of factors since

the causes are interrelated in such a way that they all address to the need to

increase in capacity of the Filling Section.

Page 62: Production Capacity Application

49

4.2.3 Presentation of Alternatives

4.2.3.1 Controllable Factor

From the CNX Analysis conducted in the previous section, the

single controllable factor identified is the inspection of the filling

production line by the production assistant. In attending to this cause,

proper regulation for controlling the cause is necessary to assure the

action to be consistently performed. The objective is to provide a

systematic procedure of inspecting production line status in order to avoid

the occasional lax attitude of the workers in between shifts. Illustration of

the flow of tasks for the procedure is presented in Figure 4-9.

The responsibility of the Manufacturing Line checks is designated

to the Production Assistant where production line monitoring would be

documented. From Figure 4-9, the Daily Production Schedule of the NLIT

Filling Section is to be checked whether the production line is scheduled

to operate on the specific day or not. The exact dates of production are as

well reflected on the Master Production Schedule of the Production

Department. Record keeping of inspection is to be made mandatory to

every scheduled production where the status and rate of production is

consistently monitored. During the days of operation, inspection is

conducted on the first four hours of the shift. Random Sampling for the

specific hour of inspection is carried out through the following steps:

i. Determine the current day of the month (1st to 31st).

ii. Divide the date to four, which is the duration of the initial

and final inspection.

iii. Get the remainder of the previous operation.

iv. Add the remainder to the start of the first four hours and

the last four hours of the shift.

v. Conduct the inspection within the computed hour.

Page 63: Production Capacity Application

50

Figure 4-9 Process Flow Diagram of Manufacturing Line Checks

Page 64: Production Capacity Application

51

The production area for the Filling Section is visited during the

hour of inspection as calculated from the random sampling method

outlined earlier. Specific minutes of the computed hour of inspection on

the production line would be subjectively determined by the Production

Assistant given that other responsibilities within the manufacturing plant

are still performed as well. The duration of the inspection estimated to last

20 minutes given that each processes in the Filling Section is overseen.

The Production Monitoring Scheme logbook is filled up with the

recorded relevant information. Exact time of inspection must be indicated

as well as the Batch Number being processed. Aside from the batch

numbers labeled on the polybags from the Dry Mixing Section, “A” to “J”

is labeled beside the corresponding batch number with respect to the ten

polybags of Nestea Lemon Iced Tea mixture. Similar format is to be used

in addressing the current batches being handled in the Filling Section

during the time of inspection. Recording these information would aid in

establishing the Master Production Schedule with the obtained actual

capacities of the Filling Section.

In any case of deviation of the current rate of production, the

assessment of the Production Assistant must be deliberated with the

Production Manager or any higher authority present in the manufacturing

plant. This is to ensure the proper plan of action before addressing it to

the problem. No fixed plan of action could readily address the problems

encountered in the manufacturing plant. Further analyzing the existing

problems would be required in any given scenario. The action to be

performed would be based on the strict product specifications and the

current target production rate. Existing plan of action being regularly

followed in the Filling Section is allowing scheduled overtime of workers

this is to address the slow production rate of the Filling Section relative to

the previous process. Other decisions made by the Production

Department are relative to the crisis being dealt with.

Page 65: Production Capacity Application

52

4.2.3.2 Experimental Factors

Experimental factors were initially grouped according to the

correlation of the causes. In generating possible alternatives,

corresponding solutions that specifically addressed each group of

experimental factors were established.

Table 4-6 Alternative Solutions for Grouped Experimental Factors

Experimental

Factor Alternative

A Additional workers and Parallel workstations

B Purchase Filling and Sealing Machine and

Reallocation of workers

C Customized scoop, Additional workers and

Parallel workstations

The objective is to elevate the capacity by 44% from the computed

Goal in Appendix A. Basis for this quantitative measure of improvement is

supported by the Six sigma concept. This percentage is acknowledged to

be the least possible % improvement that the study can accomplish.

Alternatives presented are expected to reach the 44 % increase in

capacity of the Filling Section.

Time study is the work measurement tool used to establish the

standard time of each operation. The standard times would become the

basis for identifying the filling operations that require increase in capacity.

As previously stated, the increase in capacity is further restricted by the

next resource constraint in the NLIT Production Line which is the Batch

Preparation Section. The rate of the Batch Preparation Process becomes

the target rate for improvement of the capacity of the Filling Section.

Computations for the standard time are indicated in Appendix C. Table 4-

7 shows the result of the computed standard times.

Page 66: Production Capacity Application

53

Table 4-7 Standard time of Operations in the Filling Section

Element No. And Description

Standard Time (min/case)

1. Labeling of Pouches 1.261

2. Coding of Pouches 1.049

3. Scoop Nestea mixture 0.896

4. Weigh pouches 2.493

5. Seal Pouches 2.469

6. Wipe off powder residue 1.257

7. Stack and Lot Coding 0.702

Total 10.127

To determine the adequacy of the new production rate of the

proposed alternatives, a comparison between the rates should be made

using the formula from Figure 4-10. The current output rate of the Filling

Section to be used in the formula would be entirely fixed for all

alternatives which is equivalent to 0.625 batches per hour. From the

longest standard time to be computed from the proposed alternatives, the

unit measurement of minutes per case would be translated into batches

per hour based on the conversion of units in Appendix B. This would

result to the new output rate of the proposed alternative to be entered in

the formula. Consistent unit measurement between elements is required

upon applying the formula presented in Figure 4-10. The calculated %

improvement would be applied to all the alternatives as a tool for

evaluation. (Bautista,2008)

Figure 4-10 Formula for computing % Improvement

Page 67: Production Capacity Application

54

Alternative A: Additional workers and Parallel workstations

Alternative A would deal with the Group A experimental factors by

determining the required number of additional workers and their

corresponding workstations. Estimation of the required number of workers

is shown in Table 4-8. Standard minutes values is derived from the ideal

target output rate of 1.125 batches per hour which is equivalent to 0.9216

minutes per case and setting this as the divisor for the established

standard times. Values in the standard minutes’ column were rounded off

to estimate the number of operators required in the production line.

Table 4-8 Estimating the Number of Workers per Operation

Element No. And Description

Standard Time

(min/case)

Standard minutes

(min/case)

Number of operators

1. Labeling of Pouches 1.261 1.368 2

2. Coding of Pouches 1.049 1.138 1

3. Scoop Nestea mixture 0.896 0.973 1

4. Weigh pouches 2.493 2.705 3

5. Seal Pouches 2.469 2.679 3

6. Wipe off powder residue 1.257 1.364 2

7. Stack and Lot Coding 0.702 0.762 1

Total 10.127

13

To identify the slowest operation, the estimated number of

operators is to be divided into the standard minutes for each of the seven

workers. This would be necessary in order to determine the new flow rate

of production of the filling process. The slowest operation would entail the

production rate of the line with the additional workers allocated

accordingly to the operations with the longest standard times as done

earlier. Table 4-8 shows the result of identifying the new output rate of the

production line as proposed by Alternative A.

Page 68: Production Capacity Application

55

Table 4-9 Determining the Output Rate of Alternative A

Element No.

And Description

Standard Time

(min/case)

Number of Workers

Standard Time/

Number of Workers

1. Labeling of Pouches 1.26 2 0.631

2. Coding of Pouches 1.05 1 1.049

3. Scoop Nestea mixture 0.90 1 0.896

4. Weigh pouches 2.49 3 0.831

5. Seal Pouches 2.47 3 0.823

6. Wipe off powder residue 1.26 2 0.629

7. Stack and Lot Coding 0.70 1 0.702

Total 10.13 13 6.191

From the computations done in Table 18 above, the longest

operation is the coding of pouches. This operation determines the output

from the line which is, 1.049 minutes per case or 0.988 batches per hour.

The output rate of Alternative A is expected to increase by 0.363 batches

per hour which is equivalent to the additional capacity offered by the

proposed alternative.

Parallel workstations are to be added relative to the estimated

number of workers for each operation. The proposed layout of the added

weighing and sealing workstations is shown in Figure 28. Flow of

operations is indicated by the arrows. For the labeling and wiping of

pouches, no additional workstations were introduced since the operation

does not require any machines to be added. Extra workers for these

operations maximize the space of the workstations and double the

amount of work that can be performed in the operation.

Page 69: Production Capacity Application

56

STACKING AND

LOT CODING

Figure 4-11 Additional Parallel Workstations in the NLIT Filling Section

In comparing the output rate of alternative A to the current rate,

the formula in Figure 4-10 was utilized to determine the percent

improvement of the proposed alternative. From the new output rate of

alternative A, the current output rate was improved by 58.08% which

exceeded the goal primarily set in the study. The intention of additional

workers is to level with the current rate of production and not exceed it.

The initial cost of hiring additional workers is 400 Php each. Additional six

workers would result to a total of 2,400 Php hiring cost. Parallel

workstations are to be established relative to the additional workers

required. Referring to Table 4-9, an additional of two workers is to be

added in the weighing and sealing operations. The cost of digital balance

is 6,500 Php each thus an additional of two units would add up to 13,000

Php. Horizontal band sealers cost 13,000 Php each. Adding two

additional sealers costs 26,000 Php. The total cost of the additional

parallel workstations is 41,000 Php. Table 4-10 shows the breakdown of

the costs of implementing Alternative A from the unit cost of every

additional resource proposed in the alternative.

Page 70: Production Capacity Application

57

Table 4-10 Cost of Implementing Alternative A

Additional Resources Cost Total

People 6 Hiring cost

per worker

400 Php 2,400 Php

Horizontal Band

Sealer

2 Unit Price 13,000 Php 26,000 Php

Digital Balance 2 Unit Price 6,500 Php 13,000 Php

TOTAL 41,400 Php

Alternative B: Purchase Filling and Sealing machine and

Reallocation of workers

Alternative B requires the company to invest on an Automated

Filling and Sealing machine. The machine is expected to perform the

labeling, coding, filling and sealing operations involved in the Filling

Section. An automated filling and sealing machine has an estimated cost

of 300,000 Php given by the accredited machine suppliers. These

suppliers located in the country usually obtain assembly parts from other

countries as well. Further customizing the filling and sealing machine to

completely cover the whole operation for the Filling Section would entail

additional cost. Availability of the machine was considered as a factor in

determining the viable option to pursue. The filling and sealing machine

appropriate for the filling operations has a capacity of 30 pouches per

minute which is equivalent to 2.5 cases per minute. The rate was

obtained from the maximum weight capacity the machine can fill and the

design capacity of the machine. The filling machine is expected to run at

a rate of 0.4 minutes per case. Presence of the machine does not entirely

hold the output rate of the entire filling operation.

Page 71: Production Capacity Application

58

Based on Table 4-11, the output rate of Alternative B is

determined by the longest operation which is the stack and lot coding.

Introducing a Filling and Sealing Machine increases the capacity of the

Filling Section to 0.702 minutes per case which is equivalent to 1.477

batches per hour. An additional capacity of 0.852 batches per hour is

made available by Alternative B.

Table 4-11 Output Rate of Alternative B

Element No. And Description

Standard Time (min)

Number of

Workers

Machine Capacity

(min)

Standard Time/ Number of Workers or

Machines

1. Labeling of Pouches

1.26 0

0.4 0.4

2. Coding of Pouches

1.05 0

3. Scoop NLIT mixture

0.90 0

4. Weigh pouches 2.49 0

5. Seal Pouches 2.47 0

6. Wipe off powder residue

1.26 2 - 0.628

7. Stack and Lot

Coding 0.70 1 - 0.702

Total 10.13 3 - 1.73

Referring again to Table 4-11, the number of workers required for

the whole operation is reduced to three. The remaining four workers is to

be reallocated to the NLIT Batch Preparation Section. The NLIT Batch

Preparation Section currently has four workers in the production area and

adding the four workers from the Filling Section would double its current

capacity of 1.125 batches per hour to 1.6875 batches per hour. In doing

so, the longest process in the NLIT Production Line would still be the

Filling Section having the capacity of 1.477 batches per hour.

Page 72: Production Capacity Application

59

Reallocation of the workers from the Filling Section to the Batch

Preparation Section would require one day training on the procedures

performed. Tasks of the four workers to be reallocated are sieving and

weighing. The Production Assistant will be the one responsible for training

the workers. A day’s training is sufficient enough since the task follows a

standard procedure. Breakdown of costs for Alternative B is presented in

Table 4-12.

Table 4-12 Cost of Implementing Alternative B

Modification of

Resources

Cost Total

Worker

Retraining

4 Cost per

worker

325 Php 1,300 Php

Trainer 1 Cost per

trainer

400 Php 400 Php

Filling and

Sealing Machine

1 Unit Price 300,000 Php 300,000 Php

TOTAL 301,700 Php

The % improvement of Alternative B relative to the current output

rate of the system is equivalent to 136.32% based on the formula shown

in Figure 4-10 using the increased capacity of 1.477 batches per hour.

Alternative B increased the capacity of the whole NLIT Production Line by

also addressing the capacity constraint resource which is the Batch

Preparation Section. Although the total cost of implementing Alternative B

is higher, it is paid back by the high percentage of improvement. Further

evaluation is made in the succeeding section to compare improvement

results among the alternatives.

Page 73: Production Capacity Application

60

Alternative C: Customized scoop, Additional workers and Parallel

workstations

Alternative C focuses on the customizing a failsafe scoop to

reduce weight adjustments in the production line. The 450-gram scoop is

to be replaced with a 360-gram scoop. Customization of the scoop from a

supplier would cost the company 1,500 Php each. Introducing the

customized scoop is expected to contribute at least 44% improvement

based from the computation of the goal thus the weighing process is

expected to reduce processing time by 44%. Computing for the improved

rate of the weighing operation is as follows:

Improved rate of weighing process = 44% of 2.4925 minutes per case

= 1.0967 minutes per case

Processing time of the weighing of pouches is expected to reduce

by 1.0967 minutes per case which would result to the expected standard

time of the process to be 1.3958 minutes per case. This was reflected on

the standard time used for the weighing operation in Table 4-13 below.

Table 4-13 Output Rate for Alternative C

Element No. And Description

Standard Time (min)

Number of

Workers

Standard Time/ Number of Workers

1. Labeling of Pouches 1.26 2 0.631

2. Coding of Pouches 1.05 1 1.049

3. Scoop NLIT mixture 0.90 1 0.896

4. Weigh pouches 1.40 2 0.698

5. Seal Pouches 2.47 3 0.823

6. Wipe off powder residue 1.26 2 0.628

7. Stack and Lot Coding 0.70 1 0.702

Total 10.13 12 5.427

Page 74: Production Capacity Application

61

Output Rate of Alternative C is dictated by the longest operations

in its series of processes which is the coding of pouches. This can be

compared with the output rate of Alternative A since the same operation

turned out to be the longest. Thus, the output rate of Alternative C is

similar to that of Alternative A which is 1.049 minutes per case or 0.988

batches per hour. Conveying the % improvement of its increase in

capacity, it is also 58.08% relative to the current output rate. Five workers

are added as estimated in Table 4-13 with their respective tasks. Since

additional workers are placed to operations requiring machines, additional

parallel workstations are as well needed to implement this modification.

Corresponding costs of additional resources is presented in Table 4-14.

Table 4-14 Cost of Implementing Alternative C

Additional Resources Cost Total

People 5 Hiring cost

per worker

400 Php 2,000 Php

Horizontal Band

Sealer

2 Unit Price 13,000 Php 26,000 Php

Digital Balance 1 Unit Price 6,500 Php 6,500 Php

Customized Scoop 1 Unit Price 1,500 Php 1,500 Php

TOTAL 36,000 Php

The alternatives presented addresses to each of the group of

experimental factors identified in the root cause analysis. Although the

alternatives do not deal with all the experimental factors, each is expected

to resolve the root causes through directly providing a solution to the main

problem. The uniform objective of the three alternatives of increasing the

capacity of the Filling Section supports this approach.

Page 75: Production Capacity Application

62

4.2.4 Cost-Benefit Analysis

Costs and Benefits from the maintenance, opportunity and additional

capacity can be translated to its monetary value to determine the Net Benefit

of the three alternatives. This would be used as criteria in the evaluation in

the next subchapter. Table 4-15 suggests the cost of implementing each of

the alternatives to be chosen. From Table 4-15 below, Alternative B requires

the largest investment compared to the other alternatives.

Table 4-15 Comparison of Cost of Implementing Alternatives

Alternative Total Cost of Implementation

A 41,400 Php

B 301,700 Php

C 36,000 Php

Costs of maintenance as well as the opportunity loss for each

alternative is accounted and translated in a yearly basis. Benefits from the

additional capacity and overtime savings were also projected annually in

order to obtain the Net Benefit of the alternatives. Formulas used were

obtained from Park 2002.

Alternative A: Additional workers and Parallel workstations

Parameters used were projected annually based from the average

production and overtime hours per year as well as the annual frequency of

repairs for the machines. The frequency of repairs is based from the

maintenance performed by the company in its current system. Cost of

maintenance for the machines involved was provided by the Production

Assistant.

Page 76: Production Capacity Application

63

Table 4-16 Annual Cost of Alternative A

Maintenance Cost Php Time Total

Manpower 6 Regular rate per

hour

40.625

Average production hours per

year

2304 561,600

Manpower 6 Overtime rate per

hour

52.8125

Average expected OT hours per year

1287.12

407,856.15

Horizontal Band Sealer

2

Replace-ment of Sealing Belt and Cleaning

750

Frequency of replace-ment per

year

12 18,000

Digital Balance

2 Repairs 500 Frequency of repair per year

2 2,000

Opportunity Cases per

hour

Cost

per

case

Time

Opportunity loss in capacity

7.928 450

Average production hours per

year

2304

8,220,000

TOTAL 9,209,456.15 Php

Opportunity cost was computed relative to the ideal rate which is the

capacity of the next resource constraint, the Batch Preparation Section. This

was set as the Capacity Resource Constraint provided that it is the next

bottleneck in the system and exceeding this capacity would create further

problems in balancing the NLIT Production Line. Batch Preparation Section

has a capacity of 1.125 batches per hour. Comparing this to the proposed

rate of 0.988 batches per hour, the difference is 0.137 batches per hour

which is equivalent to 7.928 cases per hour. Refer to Appendix A for

conversion of parameters. The cost per case is equivalent to the net profit per

case given by the company.

Page 77: Production Capacity Application

64

Table 4-17 Annual Benefit of Alternative A

% Improvement Overtime Benefit

58.08%

Average overtime

man-hours per year

OT Cost per

hour (Php) Savings

9009.84 52.8125 276,363.33

Increased Capacity

Additional cases per

year

Service Rate

Per case (Php) Additional Profit

48,400 450 21,780,000

TOTAL 22,056,363.33 Php

Computing for the Net Benefit of Alternative A is as follows:

Net Annual Benefit = Annual Benefits – Annual Cost

= 22,056,363.33 – 9,209,456.15

= 12,846,907.18 Php

Page 78: Production Capacity Application

65

Alternative B: Purchase Filling and Sealing Machine and Reallocation of

workers

Table 4-18 Annual Cost of Alternative B

Maintenance Cost Php Time Total

Filling and Sealing Machine

1

Repair and

Mainte-nance

1,500 Frequency of repair per year

12 18,000

Miscella-neous (Parts

replace-ment and others)

7,500 Frequency of repair per year

4 30,000

Opportunity Cases

per hour

Cost

per

case

Time

Opportunity loss in capacity

12.182 450

Average production hours per

year

2304 12,630,000

TOTAL 12,678,000 Php

Cost of maintaining the filling and sealing machine was estimated by

the Project Engineer of the company as well as the occurrence of repairs per

year. These estimations were as well based from the expected number of

repairs based on the projected levels of production and the cost of obtaining

parts from the supplier of the machine. The costs were projected annually

based on the frequency provided. Opportunity costs were computed relative

to the doubled capacity of the Batch Preparation after reallocating workers

from the Filling Section which is 1.6875 batches per hour. From these, the

Annual Cost of Alternative B was computed to have accumulated to

12,678,000 Php.

Page 79: Production Capacity Application

66

Table 4-19 Annual Benefit of Alternative B % Improvement Benefit

136.32%

Overtime

Average

overtime man-

hours per year

OT Cost per

hour Savings

9009.84 52.8125 475,832.18

Increased Capacity

Additional

Capacity in

cases

Service Rate

Per case Additional Profit

113,600 450 51,120,000

TOTAL 51,595,832.18 Php

Computing for the Net Benefit of Alternative B is as follows:

Net Annual Benefit = Annual Benefits – Annual Cost

= 51,159,652.68 – 12,678,000

= 38,917,832.18 Php

Net Present Value at 13% bank interest rate = Php70,134,756.49

Page 80: Production Capacity Application

67

Alternative C: Customized scoop, Additional workers and Parallel

workstations

Parameters used were projected annually based from the average

production and overtime hours per year as well as the annual frequency of

repairs for the machines. The frequency of repairs is based from the

maintenance performed by the company in its current system. Cost of

maintenance for the machines involved was provided by the Production

Assistant. The unit costs used for this alternative are similar to the costs used

in alternative A since the resources added were the same. Resources differ in

terms of quantity as compared to Alternative A.

Table 4-20 Annual Cost of Alternative C

Maintenance Cost Php Time Total

Manpower 5 Regular rate per

hour

40.625

Average production hours per

year

2304 468,600

Manpower 5 Overtime rate per

hour

52.8125

Average expected OT hours per year

1287.12 339,880.13

Horizontal

Band

Sealer

2

Replace-

ment of

Sealing

Belt and

Cleaning

750

Frequency

of replace-

ment per

year

12 18,000

Digital Ba-lance

1 Repairs 500 Frequency of repair per year

2 1000

Opportunity Cases

per hour

Cost

per

case

Time

Opportunity loss in capacity

7.928 450

Average production hours per

year

2304 8,220,000

TOTAL 9,047,480.13 Php

Page 81: Production Capacity Application

68

Loss in opportunity was derived from the ideal rate which is the Batch

Preparation. The ideal rate was set to avoid creation of new problems in the

system. Increase in capacity is limited by the Batch Preparation Section since

it is the next bottleneck in the production line. Batch Preparation Section has

a capacity of 1.125 batches per hour. Comparing this to the proposed rate of

0.988 batches per hour, the difference is 0.137 batches per hour which is

equivalent to 7.928 cases per hour. Refer to Appendix A for conversion of

parameters. The cost per case is equivalent to the net profit per case given

by the company.

Table 4-21 Annual Benefit of Alternative C

% Improvement Benefit

58.08%

Overtime

Average overtime hours per year

OT Cost per hour (Php)

Savings

9009.84 52.8125 276,363.33

Increased Capacity

Additional cases per year

Service Rate Per case (Php)

Additional Profit

48,400 450 21,780,000

TOTAL 22,056,363.33 Php

Computing for the Net Benefit of Alternative C is as follows:

Net Annual Benefit = Annual Benefits – Annual Cost

= 22,056,363.33 – 8,707,600

= 13,008,883.18.20 Php

Page 82: Production Capacity Application

69

4.2.5 Evaluation of Alternatives

Alternatives are evaluated according to the ease of implementation as

well as their corresponding net benefits. Criteria selected are further weighed

based on its importance. The level of importance is assessed relative to the

measure of the criteria with respect to the given objective of the study.

Table 4-22 Weighted Rating of Importance

Description Rating

Very Important 5

Important 4

Fairly Important 3

Not That Important 2

Irrelevant 1

Assessing the net benefits includes the consideration of additional

investment the company needs to pursue the given alternative. The rating of

importance of this criterion is very important. Net benefits define the

projected payback of investments entered in the proposed alternatives which

is very useful for long-term strategy. Using this as a measure for evaluation

clearly helps on the degree of the return on investments.

Table 4-23 Rating for Net Benefit

Description (values are in Php) Rating

32,000,000 – 40,000,000 5

24,000,000 – 32,000,000 4

16,000,000 – 24,000,000 3

8,000,000 – 16,000,000 2

0 – 8,000,000 1

Page 83: Production Capacity Application

70

The importance for ease of implementation is weighed based on the

ability of the company to execute and handle new developments. This

measure is considered important given the existing constraints in the

company that could cause additional problems. From the established rating

factors, each alternative were individually assessed based on the selected

criteria.

Table 4-24 Rating for Ease of Implementation

Description Detailed Description Rating

Very Easy to Implement

Technology of resources used is already acknowledged and available.

5

Easy to Implement Technology of new resources used is already acknowledged.

4

Moderately Easy to Implement

Technology of new resources used is recognizable

3

Difficult to Implement Technology of new resources used is advanced.

2

Very Difficult to Implement

Advance technology of new resources used requires expertise.

1

Alternative A received a rating of “2” under the Net Benefit factor

based on the range of values presented in Table 4-25. Its ease of

implementation is relatively easy to pursue since similar worker tasks and

machines would only be added to the existing work design. No new

technology is introduced for this alternative.

Alternative B was given a rating of “5” and “3” for the net benefit and

ease of implementation factor respectively. High returns were projected

through the cost-benefit analysis which entered the highest range for the net

benefit factor giving the alternative rate of “5”. Introducing a new machine

comes with necessary trainings for the new technology and the

implementation of a different set of standard procedures for the proper

handling of the Filling and Sealing Machine.

Page 84: Production Capacity Application

71

Alternative C has the same range of annual benefits as of the first

alternative for the reason that the two alternatives resulted to the same %

improvement as well as having close costs of implementation. Rating for this

alternative was affected by the computed Net Benefit value relative to the

high payback of Alternative B. Introduction of a customized design of the

scoop does not entail a new level of technology since the tasks were not

drastically altered in this alternative. Because of this, Alternative C is

considered easy to implement since only additional workers and machines

were modified with similar operations performed.

Table 4-25 Rating of Alternatives

Alternative

Rating Factor

Rating Net Benefits

(5)

Ease of Implementation

(4)

A 2 4 36

B 5 3 37

C 2 4 36

Do Nothing 1 5 25

The alternatives are evaluated based on the criteria chosen. The

ratings are shown in Table 4-25. Alternative B has the highest rating which is

to purchase a filling and sealing machine and reallocate workers.

Page 85: Production Capacity Application

5.0 SUMMARY AND CONCLUSION

Page 86: Production Capacity Application

73

DDC Food Development and Contracting Services, Inc manufactures food and

beverage powdered products of Nestle Philippines. The Production Department consists

of three major production lines: Dehydrated Culinary Products, Milo Vending Mix and the

Nestea Lemon Iced Tea. The study dealt with the Nestea Lemon Iced Tea Production

Line which comprises of three processes: Batch Preparation, Dry Mixing and Filling.

Further focus was given to the Nestea Lemon Iced Tea Filling Section through the

recognition of its low capacity relative to the other processes.

From the concepts and tools for analysis used throughout the study, the results

pointed to the problem of the Filling Section having low capacity. It was determined that

the capacity of the current system lags 16.59% from the capacity requested by demand.

Analyzing the problems presented a number of root causes classified into Man,

Machine, Method and Material. These were further examined through CNX Analysis

where the experimental factors were identified as follows: 1. Amount of workload

exceeds manpower capacity, 2. The number of machines is insufficient, 3. There is an

absence of a filling machine, 4. The scooper creates large net weight discrepancies and

5. The volume capacity of the scoop is 450 grams. These factors were grouped

according to the aspect being addressed as well as the alternatives to be provided.

A set of alternatives were proposed to address the root causes identified in the

analysis. Alternative A provided solutions of additional workers and parallel workstations.

Alternative B deals with the absence of a filling machine through recommending an

investment on acquiring a filling machine and reallocating existing workers to the next

resource constraint of the production line. Alternative C concentrated on the remaining

the cause factors through customizing the volume capacity of the scoop. The %

improvements of the alternatives were determined from the increase in capacity

presented relative to the current production rate of the NLIT Filling Section. Calculations

resulted to 58.08 % increase in capacity for Alternative A and C while an increase in

capacity of 136.32 % is expected in the implementation of Alternative B. Large

differences in % improvement is apparent given that Alternative B automates the whole

process. To further filter the alternatives, a cost-benefit analysis was conducted to

project the net benefits of each alternative.

Page 87: Production Capacity Application

74

Costs of opportunity loss, modification of resources proposed, and maintenance

were considered upon implementing each alternative. Estimated costs of implementation

were 41,400 Php, 301,700 Php and 36,000 Php for Alternatives A, B and C respectively.

To further assess how the % improvement of the alternatives would reflect on monetary

terms, savings from overtime and expected additional profit from the increased capacity

were accounted and translated as annual benefits for each alternative. Projected annual

benefits were 12,846,907.18 Php, 38,917,832.18 Php and 22,056,363.33 Php for

Alternative A, B and C respectively.

The alternatives were evaluated with the selected criteria for assessment, net

benefits and the ease of implementation. Weighted rating was provided for each

criterion. Rates for each alternative were outlined from the given description of every

level presented in the criteria. Costs were determined from the additional investment

required by the alternatives presented. The ease of implementation was weighed

according to how the company is expected to acknowledge the alternatives presented.

Based from the evaluation, Alternative B has the highest rating.

Initial investment is required for the implementation of the chosen alternative

which amounts to 301,700 Php that is reflected from the purchase of a brand new filling

and sealing machine as well as the cost of retraining reallocated workers of the Filling

Section to the Batch Preparation Section of the NLIT Production Line. This investment is

paid back with an annual net benefit of 38,917,832.18 Php accounting the overtime

savings and opportunity costs.

Page 88: Production Capacity Application

6.0 RECOMMENDATIONS

Page 89: Production Capacity Application

76

Analyzing the operations of the company resulted to addressing major problems

encountered in the manufacturing line such as having a low capacity of the Nestea

Lemon Iced Tea Filling Section. Through comprehensively scrutinizing the predicaments

recognized, the study has provided recommendations.

The selected recommendation for increasing the capacity of the Filling Section is

to purchase an automated filling and sealing machine and reallocate workers in the

production line. This option would result to higher gains as compared to the other

alternatives. Automating the filling operation increases the capacity by 136.32 % relative

to the existing output rate of the Filling Section. Benefits corresponding to the increase in

capacity cover the initial investment required to implement this recommendations.

Addressing the causes of the factors classified to Machine, the other root causes is

expected to be solved at the same time given that all root causes attends to the main

problem identified in the study.

Providing a systematic and meticulous Production Monitoring Scheme for

manufacturing line checking is recommended in addressing the controllable factor

identified in the study. Inspection of the production lines is necessary to avoid the lax

attitude of workers during production. Random sampling of the specific time of inspection

prevents the workers from anticipating the arrival of the inspector. Documentation is

made from the inspection as monthly reports are filed and necessary actions are

executed to possible problems in production. It is mandatory that the inspection is to be

regularly imposed to stabilize the performance of the production line.

Page 90: Production Capacity Application

7.0 AREAS FOR FURTHER STUDY

Page 91: Production Capacity Application

78

The study focused on addressing the capacities of the Nestea Lemon Iced Tea

Production Line and particularly dealing with the Filling Section. Attending to the basis of

the master production schedule is a main interest for future studies as it can provide

great opportunities for improvement. Design of the production lines is currently in series

which creates problems of transfer and buffer batch sizes. Tackling this problem is a

different perspective where inventory system would be involved.

Two other main product groups, Milo Vending Mix and the Dehydrated Culinary

Products, can be further examined through individual studies. From the capacities

presented by the three production lines, the Dry Mixer of Milo Vending Mix is observed

to be underutilized. Since Milo contributes 27% of the total production volume, further

examining its status can contribute to the company as well.

The usage of polyethylene bags within the production line is not restricted as

seen in the Flow Process Charts of the NLIT Production Line. This is apparent in all the

three production lines. No control is imposed on the use of polyethylene bags and the

scraps are not accounted by the company. Further investigating this scenario would

promote green manufacturing in the company.

Lastly, the cleaning procedure of the tools and equipments used in all production

lines require the use of Oxonia solution. This is to keep all products pathogen-free by

constantly monitoring the area and the equipment being used. All the equipments are

cleaned with the Oxonia solution and its use is not regulated by the company. Effects of

the oxonia solution when released to the environment are not concerned by the

company. DENR has already questioned this issue of release of the chemical. Further

analyzing this and the possibility of introducing a water treatment facility within the

manufacturing plant would assure the company’s compliance to the environmental

standards.

Page 92: Production Capacity Application

xiv

REFERENCES

ANUPINDI R., S. CHOPRA, S. DESHMUKH, J.A. VAN MIEGHEM & E. ZEMEL. 2008.

Managing Business Process Flows: Principles of Operations Management.

International Edition. New Jersey: Pearson Education Inc.

ARNOLD, J.C. & J.S. MILTON. 2004. Introduction to Probability and Statistics: Principles

and Applications for Engineering and the Computing Sciences. 4th edition. New

York: McGraw-Hill Inc.

BAUTISTA, J.L.A. 2008. Minimizing Idle Times at the Powder Condiments Line of

Consolidated Packaging Enterprises, San Francisco Del Monte, Quezon City.

Undergraduate manuscript. UP Los Baños.

HEIZER, J. & B. RENDER. 2005. General principles in operations management. 7th

edition. New Jersey: Pearson Education South Asia

NIEBEL, B.W. 1993. Motion and time study. 9th ed. USA: Richard Irwin, Inc.

PARK, C.S. 2002. Contemporary engineering economics 3rd edition. New Jersey:

Pearson Education, Inc.

STEVENSON W.J. 2007. Operations Management. 9th edition. New York: McGraw-

Hill/Irwin Education Inc.

Page 93: Production Capacity Application

xv

Appendix A: Computation for the Goal Improvement

For the purpose of having a definite objective of the study, the Six sigma concept

on Goal computation is used. (Bautista, 2008) The formula below was used to determine

the Goal.

GOAL = Baseline – 0.7(Baseline – Entitlement)

Baseline = Lowest Process Capacity in the NLIT Production Line (Filling Section)

= 0.625 batches per hour

Entitlement = Capacity Constraint Resource (CCR) in the NLIT Production Line

(Batch Preparation Section)

= 1.125 batches per hour

GOAL = 0.625 – 0.7(1.125-0.625)

= 0.275

% IMPROVEMENT = 0.275/ 0.625

= 44 %

The quantitative goal of the study is to increase the current process capacity of

the NLIT Production Line by 44 %.

The capacity of the Filling Section is the current baseline as it establishes the

average performance of the process. Using the capacity of the Batch Preparation as the

entitlement and the target performance, the difference in the capacities multiplied by

0.70 and subtracting this from the baseline would lead to the percentage of improvement

that the study aims to achieve.

Page 94: Production Capacity Application

xvi

Appendix B: Nestea Lemon Iced Tea Conversion of Units

1 pouch = 360 grams

1 case = 12 pouches

1 pallet = 96 cases

1 batch = 250 kilograms

NLIT Parameters June July Aug Sept Oct Nov

In Cases 8377 7204 7514 7025 8104 8331 In Kilograms 36188.64 31121.28 32460.48 30348 35009.28 35989.92 IN Batches 144.7546 124.4851 129.8419 121.392 140.0371 143.9597

Page 95: Production Capacity Application

xvii

Appendix C: Time Study

The time study conducted was based from Niebel, 1993 as well as all formulas

used. The table below shows the observed time recorded with 10 initial samples:

No. Process Name

Trial No. (Actual time in seconds)

1 2 3 4 5 6 7 8 9 10

1 Labeling

of Pouches

72.34 56.04 47.86 59.73 74.85 83.91 60.32 83.16 63.72 71.85

2 Coding

of Pouches

35.77 47.72 64.07 84.42 59.75 60.28 54.27 76.34 71.93 48.43

3 Scoop Nestea Mixture

37.26 59.84 47.60 45.73 48.33 51.84 47.18 52.30 36.75 49.26

4 Weigh

Pouches 108.19 127.08 138.27 72.31 151.89 155.84 168.17 191.59 119.79 107.91

5 Seal

Pouches 123.57 160.72 126.78 106.94 145.06 113.87 157.28 175.17 133.79 104.86

6 Wipe off powder residue

59.67 71.54 55.78 57.85 72.36 59.89 89.24 62.74 68.09 60.37

7 Stack

and Lot coding

31.43 43.10 41.85 44.69 46.72 41.38 35.07 52.18 47.13 33.26

In computing for outliers within the observed data, the next table below shows

the computed range of acceptance using IQR.

Observation Trial No.

Process No. And Description

1. Labelling of Pouches

2. Coding of Pouches

3. Scoop Nestea mixture

4. Weigh pouches

5. Seal Pouches

6. Wipe off powder residue

7. Stack and Lot Coding

1 47.86 35.77 36.75 72.31 104.86 55.78 31.43

2 56.04 47.72 37.26 107.91 106.94 57.85 33.26

3 59.73 48.43 45.73 108.19 113.87 59.67 35.07

4 60.32 54.27 47.18 119.79 123.57 59.89 41.38

5 63.72 59.75 47.6 127.08 126.78 60.37 41.85

6 71.85 60.28 48.33 138.27 133.79 62.74 43.1

7 72.34 64.07 49.26 151.89 145.06 68.09 44.69

8 74.85 71.93 51.84 155.84 157.28 71.54 46.72

9 83.16 76.34 52.3 168.17 160.72 72.36 47.13

10 83.91 84.42 59.84 191.59 175.17 89.24 52.18

AVERAGE 67.38 60.30 47.61 134.10 134.80 65.75 41.68

STD. DEV. 11.80 14.63 6.84 34.48 24.07 10.03 6.63

MEDIAN 59.73 48.43 45.73 108.19 113.87 59.67 35.07

Q1 74.85 71.93 51.84 155.84 157.28 71.54 46.72

Q3 15.12 23.50 6.11 47.65 43.41 11.87 11.65

1.5IQR 22.68 35.25 9.17 71.48 65.12 17.81 17.48

FENCE1 37.05 13.18 36.57 36.72 48.76 41.87 17.60

FENCE3 97.53 107.18 61.01 227.32 222.40 89.35 64.20

NUMBER OF

SAMPLES 5.87 11.26 3.95 12.65 6.10 4.45 4.85

Page 96: Production Capacity Application

xviii

Comparing the range from fence 1 to fence 3 of each operation, the observed

times in the first table have fallen within the range. There are no significant outliers in the

observations made. The number of samples made was also enough to support the

establishment of standard times.

Additional Trials were conducted to meet required number of samples. In the

computations made, an additional of at least three samples was needed to make the

observations significant. The table below presents the additional five observations:

Process No.

Process Name

Trial No. (Actual time in seconds) Average

Standard Deviation 11 12 13 14 15

1 Labeling

of Pouches

77.54 84.12 59.78 68.50 71.64 72.32 9.20

2 Coding

of Pouches

59.16 36.15 47.88 72.01 43.06 51.65 14.13

3 Scoop Nestea Mixture

53.25 47.54 59.72 51.09 48.29 51.98 4.89

4 Weigh

Pouches 133.68 152.63 107.72 131.79 179.75 141.11 26.85

5 Seal

Pouches 159.30 164.28 105.43 104.26 145.78 135.81 29.07

6 Wipe off powder residue

75.27 93.25 58.13 83.91 63.74 74.86 14.35

7 Stack

and Lot coding

33.87 30.32 29.16 31.79 34.59 31.95 2.30

The performance factor to be utilized in calculating the standard time was

obtained in accordance with the Westinghouse rating system. Appendix D holds the

complete ratings for each category. Ratings for the whole observation of each operation

are presented below. The sum of the ratings is subtracted from the perfect performance

factor leaving a 97% performance factor for the whole production line relative to its

actual execution of operations.

Skill C2 +0.03

Effort E1 - 0.04

Conditions D +0.00

Consistency E - 0.02

Algebraic Sum - 0.03

Performance Factor 0.97

Page 97: Production Capacity Application

xix

In computing for the Normal Time, the following formula is used:

NORMAL TIME = OBSERVED TIME * PERFORMANCE FACTOR (Neibel,1993)

The table below shows the computed Normal times based from the observed time:

Element No. And Description

Normal Time (min/case)

1. Labeling of Pouches 1.116

2. Coding of Pouches 0.928

3. Scoop Nestea mixture 0.793

4. Weigh pouches 2.206

5. Seal Pouches 2.185

6. Wipe off powder residue 1.112

7. Stack and Lot Coding 0.621

Total 8.962

Allowance factors were derived from the observations of the researcher during

production. These allowances are presented in the table below.

ALLOWANCE FACTORS

PERSONAL NEEDS 5 0.05

BASIC FATIGUE 4 0.04

STANDING 2 0.02

MONOTONY 2 0.02

0.13

Page 98: Production Capacity Application

xx

Using total of the allowances identified, the value is used in computing for the standard time of the operations in the Filling Section with the formula below:

STANDARD TIME = NORMAL TIME * (1 + ALLOWANCE FACTOR) (Neibel,1993)

The table below shows the computed Standard times based from the observed time:

Element No. And Description

Standard Time (min/case)

1. Labeling of Pouches 1.261

2. Coding of Pouches 1.049

3. Scoop Nestea mixture 0.896

4. Weigh pouches 2.493

5. Seal Pouches 2.469

6. Wipe off powder residue 1.257

7. Stack and Lot Coding 0.702

Total 10.127

Page 99: Production Capacity Application

xxi

Appendix D: Westinghouse System Ratings

Westinghouse System Skill Ratings +0.15 A1 Super skill +0.13 A2 Super skill +0.11 B1 Excellent +0.08 B2 Excellent +0.06 C1 Good +0.03 C2 Good 0.00 D Average - 0.05 E1 Fair - 0.10 E2 Fair - 0.16 F1 Poor - 0.22 F2 Poor Westinghouse System Effort Ratings +0.13 A1 Excessive +0.12 A2 Excessive +0.10 B1 Excellent +0.08 B2 Excellent +0.05 C1 Good +0.02 C2 Good 0.00 D Average - 0.04 E1 Fair - 0.08 E2 Fair - 0.12 F1 Poor - 0.17 F2 Poor Westinghouse System Condition Ratings +0.06 A Ideal +0.04 B Excellent +0.02 C Good 0.00 D Average - 0.03 E Fair - 0.07 F Poor Westinghouse System Consistency Ratings +0.04 A Perfect +0.03 B Excellent +0.01 C Good 0.00 D Average - 0.02 E Fair - 0.04 F Poor

Page 100: Production Capacity Application

xxii

Appendix E: Net Present Value of Alternative B

The Net Present Value of Alternative B would determine the equivalent worth of inflows to outflows based from the costs and benefits identified in the alternative. Assumptions were made upon projecting the net present worth of the annual cash flows. Service life used was based on the useful life of the Filling and Sealing Machine which is 10 years. The interest rate was obtained from the current bank interest available, 13%. The net cash flow was determined from the costs and benefits of the alternative for each year. Present values for every year of the given useful life of the machine were computed. Formulas from Park, 2004 were used to project those values by dividing the net cash flow by 1 plus the bank interest rate raised to the equivalent service life.

Year Costs Benefits Net Cash flow Present Value at

year 2010

2010 -301,700

-301,700 -301,700

2011 12,678,000 51,159,652.68 38,917,832.18 11,487,348.04

2012 12,678,000 51,159,652.68 38,917,832.18 10,165,794.72

2013 12,678,000 51,159,652.68 38,917,832.18 8,996,278.515

2014 12,678,000 51,159,652.68 38,917,832.18 7,961,308.42

2015 12,678,000 51,159,652.68 38,917,832.18 7,045,405.681

2016 12,678,000 51,159,652.68 38,917,832.18 6,234,872.284

2017 12,678,000 51,159,652.68 38,917,832.18 5,517,586.092

2018 12,678,000 51,159,652.68 38,917,832.18 4,882,819.551

2019 12,678,000 51,159,652.68 38,917,832.18 4,321,079.249

2020 12,678,000 51,159,652.68 38,917,832.18 3,823,963.937

Net Present Value 70,134,756.49 Php

The recommended solution is expected to return a positive Net Present Value and return profit as the worth of inflows is greater than the equivalent worth of outflows.

Page 101: Production Capacity Application

DDC DDC DDC DDC 14-26 Lazatin Blvd.,Villa Victoria, Dolores, City of San Fernando, Pampanga

20 March 2010

To whom it may concern:

This is to certify that

Engineering Student of the University of the Philippines Los Baños underwent on

training (OJT) at DDC Food Development Contracting Services, Inc., from 20 April 2009

to 30 May 2009. She successfully completed the two hun

requirement of the academic program by observing processes, methods and operations,

and doing hands-

Materials Warehouse.

This certification is being iss

whatever lawful intent it may serve.

Issued this 20th day of March 2010 at City of San Fernando, Pampanga, Philippines

DANILO D. CANLAS

General Manager

Appendix F: Certificate of Completion

DDC DDC DDC DDC FOOD DEVELOPMENT AND CONTRACTING SERVICES, INC

26 Lazatin Blvd.,Villa Victoria, Dolores, City of San Fernando, PampangaTel No. (045) 961-8220; Telefax No. (045) 961-4636

To whom it may concern:

This is to certify that MS. JAQUELYN MARGARET L. MICIANO

Engineering Student of the University of the Philippines Los Baños underwent on

training (OJT) at DDC Food Development Contracting Services, Inc., from 20 April 2009

to 30 May 2009. She successfully completed the two hundred (200) hours of actual work

requirement of the academic program by observing processes, methods and operations,

-on work in the Production Department, Logistics, Quality Assurance, and

Materials Warehouse.

This certification is being issued upon request of Ms. Jaquelyn Margaret L. Miciano for

whatever lawful intent it may serve.

day of March 2010 at City of San Fernando, Pampanga, Philippines

DANILO D. CANLAS

General Manager

xxiii

DEVELOPMENT AND CONTRACTING SERVICES, INC

26 Lazatin Blvd.,Villa Victoria, Dolores, City of San Fernando, Pampanga

L. MICIANO, a BS Industrial

Engineering Student of the University of the Philippines Los Baños underwent on-the-job

training (OJT) at DDC Food Development Contracting Services, Inc., from 20 April 2009

dred (200) hours of actual work

requirement of the academic program by observing processes, methods and operations,

on work in the Production Department, Logistics, Quality Assurance, and

ued upon request of Ms. Jaquelyn Margaret L. Miciano for

day of March 2010 at City of San Fernando, Pampanga, Philippines