production optimization utilizing the balance-ported...
TRANSCRIPT
PRODUCTION OPTIMIZATION UTILIZING
THE BALANCE-PORTED VALVE AND
PILOT VALVE IN THE
PERMIAN BASIN
Rick D. Haydel, Donald J. Brink, Gary J.
Gassiott, Joseph Bourque - Altec, Inc.
2017 ALRDC Gas-Lift
Workshop
Houston, TX
October 23-27, 2017
Oct 23-27, 20172017 ALRDC Gas-Lift Workshop 2
Outline• Introduction
– Production Challenges, Artificial Lift Options, Why Gas-Lift
• Gas-Lift Objectives
• Industry Standard Gas-Lift Design Practices
• Balance-Ported Gas-Lift Valve Design Practices
– Example Well
• Pilot Valve Gas-Lift / Design Practices
– Example Well
• Other Design Factors to Consider
• Additional Examples, Field Plots, etc.
• Conclusion
Introduction
3
• Production Challenges in the Permian Basin
– Wide Range of Flowing Conditions (i.e. Pressures, Rate-Potential)
– Higher GOR’s
– Slug-Flow from Lateral Dynamics
– Corrosive Environments
– Determining Artificial Lift Type vs. Well Maintenance Costs
Oct 23-27, 20172017 ALRDC Gas-Lift Workshop
Gas-Lift Objectives
4
• Inject high pressure gas into the well as deep as possible
• Obtain a single point of gas injection
– Lighten gradient of fluid head above operating gas-lift valve
– Optimal GLR for maximum and most efficient production
– Lower formation pressure and maximize fluid-rate potential
Oct 23-27, 20172017 ALRDC Gas-Lift Workshop
Industry Standard Gas-Lift
Design Practices
5
• Typical valves are Injection Pressure Operated (IPO)
– Primary opening and closing force is casing or injection pressure
• Typical 3/16” port sizes are used in Permian Basin
– 3/16” works well with applicable tubing sizes, gas injection rates and
operating pressures
• 90% Casing Pressure Effect ; 10% Production Pressure Effect
• Typical design injection pressure drops of +/- 20 psi
between successive valves for closing purposes
Oct 23-27, 20172017 ALRDC Gas-Lift Workshop
IPO Valve Mechanics
6Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
Closed Open
IPO Valve Design Worksheet
7Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
Port Size & Gas
Passage
Pressure
Surface Closed
IPO Valve Design Graph
8Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
20 psi Pressure
Drops Shown
Graphically
Balance-Ported Valve Design
Practices
9
• Larger Production Pressure Effect than Typical IPO Valves
– Uniform 5/16” seat for all valve choke sizes
– 8/64”, 10/64”, 12/64”, 14/64”, 16/64” available choke sizes
– 75% Casing Pressure Effect ; 25% Production Pressure Effect
• No design injection pressure drops are required to be taken
between successive valves for closing purposes
• Bottom Valve is typically an orifice valve or “flagged back”
IPO valve
Oct 23-27, 20172017 ALRDC Gas-Lift Workshop
Balance-Ported Valve Mechanics
10Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
Closed Open
Balance-Ported Valve Design
Worksheet
11Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
Choke Size &
Gas Passage
Pressure
Surface Open &
Closed
Balance-Ported Valve Design
Graph
12Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
No Pressure
Drops Shown
Graphically
IPO vs. Balance-Ported Graphs
13Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
Balance-Ported Design Example #1(May 2016 Initial Build-Up Survey Tubing Overview Plot)
14Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
• Glasscock County, TX
• Wolfcamp B (8400’ TVD)
• 10,000’ MD Lateral
• Casing = 5-1/2” 20# ; Tubing = 2-7/8” 6.5#
• Flowing Naturally
• Well-Test Evaluation Date = May 2016
– Flowing / Build-Up Survey
– H2O = 1466 BPD
– Oil = 522 BPD
– Gas = 426 MCF
– FTP = 215 psia
– FBHP = 3086 psia
– SBHP (5 hour build-up) = +/- 3245 psia
– Simple Straight-Line PI = 12.5 BFPD/psia
Balance-Ported Design Example #1(Tubing Correlations Model Match)
15Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
Balance-Ported Design Example #1(Systems Model Match)
16Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
Balance-Ported Design Example #1(Proposed Gas-Lift Design)
17
• Balance-Ported Valve Design
– 12 Mandrels down to 7400’ MD w/ Orifice Valve on Bottom
• 500’ TVD Mandrel Spacing in Operating Envelope
– Production Packer at +/- 7500’ MD
– 1100 psi Design Operating Pressure
– +/- 500-600 MCFPD Gas Injection Rate
– 2864 Total BFPD w/ 75% Water Cut
• Based on Build-Up Survey and Projected Systems Plot
Oct 23-27, 20172017 ALRDC Gas-Lift Workshop
Balance-Ported Design Example #1(Proposed Gas-Lift Design Worksheet)
18Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
• Balance-Ported Valve Design
– 12 Mandrels to 7400’ MD w/ Orifice Valve on Bottom; 500’ Spacing
– Production Packer at +/- 7500’ MD
– 1100 psi Design Operating Pressure
– +/- 500-600 MCFPD Gas Injection Rate
– 2864 Total BFPD w/ 75% Water Cut
• Based on Build-Up Survey and Projected Systems Plot
1100 psi Pressure
Surface Open &
Closed
Balance-Ported Design Example #1(Proposed Gas-Lift Design Graph)
19Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
1100 psi Pressure
Surface Open &
Closed
Balance-Ported Design Example #1(Post Installation Kick-Off & Well-Test)
20Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
Balance-Ported Design Example #1(September 2016 Flowing Survey Results)
21
• Flowing Survey in September 2016 to evaluate well and
gas-lift design status
– 1262 Total BFPD w/ 50%Water-Cut
– 475 GOR
– 570 MCFPD Gas Injection Rate
– 158 Flowing Tubing Pressure
– 1030 psi Casing Pressure
– Injection Points 5385’ & 5911’ MD (Primary at 5385’ MD)
– Casing Fluid Level at +/- 6500’ MD
Oct 23-27, 20172017 ALRDC Gas-Lift Workshop
Balance-Ported Design Example #1(September 2016 Flowing Survey Tubing Overview Plots)
22Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
Balance-Ported Design Example #1(December 2016 Flowing Survey Results)
23
• Flowing / Build-Up Survey in December 2016 to further
evaluate well and gas-lift design status
– Well heading during flowing survey
– 967 Total BFPD w/ 50% Water-Cut
– 925 GOR
– 758 MCFPD Gas Injection Rate
– 241 psi Flowing Tubing Pressure
– 965 psi Casing Pressure
– Injection Point at 7401’ MD (Bottom Orifice Valve)
– Casing Fluid Level at 7401’ MD
Oct 23-27, 20172017 ALRDC Gas-Lift Workshop
Balance-Ported Design Example #1(December 2016 Flowing Survey Tubing Overview Plots)
24Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
Balance-Ported Design Example
#1 Summary
25
• +/- 20 psi IPO Valve Design Pressure Drops would not
have allowed the well to lift as deep during each period
surveyed
• Balance-Ported Valve Design allowed most optimal
production rates throughout the entire time frame
evaluated
• Maximized Production = Quickest Return on Investment
Oct 23-27, 20172017 ALRDC Gas-Lift Workshop
Pilot Valve Gas-Lift
26
• Pilot valves offer a way to intermittent gas-lift a well
– Intermittent lift becomes an alternative lift option when wells
approach or fall below +/- 100-150 BFPD
– Typically recommended for wells with high SBHP and low inflow
potential, or high inflow potential and low SBHP
• Pilot Valves do not require the use of a surface injection
controller
– Valve self-intermits with a continuous flow of gas injection
• Retrievable mandrel on bottom can allow for conversion to
intermittent lift without the need for a workover rig
Oct 23-27, 20172017 ALRDC Gas-Lift Workshop
Pilot Valve Gas-Lift
27Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
Pilot Valve Design Practices
28
• Upper pilot valve section that senses casing/tubing
pressure and dictates the valve spread based upon the port
size
– Valve spread allows gas volume calculation to be performed based
on tubular sizes, aimed at displacing a certain liquid slug size to
surface
• Lower power section that shifts down and uncovers a very
large flow area once the pilot section opens
– Allows high volume of casing gas to enter the tubing quickly
Oct 23-27, 20172017 ALRDC Gas-Lift Workshop
Pilot Valve Gas-Lift
29Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
Pilot Valve Design Example #1(August 2016 Initial Flowing Survey Tubing Overview Plot)
30Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
• Bone Springs (New Mexico) - 7400’ TVD
• 5,000’ MD Lateral
• Casing = 5-1/2” 17# ; Tubing = 2-7/8”
6.5#
• Flowing via Gas-Lift
• Well-Test Evaluation Date = August
2016
– Flowing Survey Only
– H2O = 98 BPD
– Oil = 130 BPD
– Gas = 491 MCF
– Injection Gas = +/- 500 MCF
– FTP = 210 psia
– FBHP = 625 psia
– Est. SBHP = 1025 psia
Pilot Valve Design Example #1(Proposed Gas-Lift Design Worksheet)
31Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
Used Full OP
for Unloading
Valves
• Combined Balance-Ported & Pilot Valve Design
– 6 Mandrels down to +/- 6800’ MD w/ Pilot Valve on Bottom
– Production Packer at +/- 6850’ MD
– 900 psi Design Full Operating Pressure w/ Balance-Ported Unloading Valves
– 3/8” Ported Pilot Valve
– +/- 180-200 MCFPD Continuous Gas Injection Rate
– Note: This well was on the edge of the Pilot Valve’s recommended window, but
the operator wanted to try the application with the primary goal being to reduce
the gas injection requirements to the well
Pilot Valve Design Example #1(Proposed Gas-Lift Design Worksheet)
32Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
Required
Continuous Gas
Injection Rate
Pilot Valve Design Example #1(Proposed Gas-Lift Design Graph)
33Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
Pilot Valve Design Example #1(Post Installation Surface Pressure Plot)
34Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
Pilot Valve Design Example #1(Surface Pressure Plot – 6 Months Later)
35Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
Pilot Valve Design Example #1
Summary
36
• Balance-Ported Valves allowed the Pilot Valve to be set at
a higher, more optimal pressure as to not open any upper
unloading valves during cyclic operation
• Pilot Valve allowed well to intermittent lift at +/- 30% of the
original continuous gas-lift design injection rate (+/- 150
MCF vs 500 MCF)
• Maintained / Increased oil production rate potential with
less gas injection
Oct 23-27, 20172017 ALRDC Gas-Lift Workshop
Other Design Factors to Consider
• Varying geothermal temperature gradients across the
Permian Basin
– Can vary significantly across the Permian Basin
• Gas Compositions
– Specific Gravities are higher in this region and need to be known
• Changing Well Conditions / Higher Equipment Expectations
– High pressure / rate-potential to low pressure / rate-potential
– Steady flow conditions to more unstable dynamic flow conditions
• Horizontal Flow Effects
– Designing for and mitigating late-life slugging conditions
• Gas-Lift Industry Knowledge & Operational Experience
– Current experience and knowledge is lower in this region
37Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
Additional Examples(Check Time)
38Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
Balance-Ported Valve Example #2
39
• Flowing Survey in December 2014 to evaluate well and
gas-lift design status / optimization potential
– 510 Total BFPD w/ 44%Water-Cut
– 465 GOR
– 277 MCFPD Gas Injection Rate
– +/- 100 psi Flowing Tubing Pressure
– 830 psi Casing Pressure
– Injection Points 6,907’ MD (Primary at 5385’ MD)
– Casing Fluid Level at +/- 8,500’ MD
Oct 23-27, 20172017 ALRDC Gas-Lift Workshop
Balance-Ported Valve Example #2
40Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
Balance-Ported Valve Example #2
41Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
Balance-Ported Valve Example #2(Tubing Correlations Match)
42Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
Balance-Ported Valve Example #2(Systems Projection)
43Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
Balance-Ported Valve Example #2(Additional Delta Pressure Plots for Illustration)
44Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
Pilot Valve Example #2
45
• Operator requested a specific field-wide Pilot Valve
project to lower field injection gas requirements in an
effort to reduce compression facilities
– Each well was receiving +/- 400 MCFPD continuous injection
before the project started
• Project included 30 wells (all requiring workover rig)
• Approximate gas injection requirements for these wells
was 10,096 MCFPD (May 2017)
Oct 23-27, 20172017 ALRDC Gas-Lift Workshop
Pilot Valve Example #2(Example Well Gas-Lift Design Worksheet)
46Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
Required
Continuous Gas
Injection Rate
Pilot Valve Example #2(Example Well Kick-Off Surface Pressure Plot)
47Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
Pilot Valve Example #2(Injection vs Production Graph)
48
+/- 10 MMCFPD Injection
+/- 5.8 MMCFPD
Injection
Gas – 10,000Oil - 1500
Gas – 3,000Oil - 300
3 Months Time Frame
Oct 23-27, 20172017 ALRDC Gas-Lift Workshop
Conclusion
• Balance-Ported Gas-Lift Valves offer production
advantages to any well that is not operating on the bottom
valve
– Deeper Gas Injection = Max Drawdown & Production Rates
• Pilot Gas-Lift Valves offer an alternative, cost-efficient
gas-lift option to artificially lift low-rate wells
• Combining the two valve types in a single-well design
plan can provide a complete gas-lift solution aimed at
production optimization for the well’s entire artificial-lift life
49Oct 23-27, 2017
2017 ALRDC Gas-Lift Workshop
References1. Petroleum Engineering Handbook, by Howard B. Bradley, et al, 3rd Printing, Society of Petroleum
Engineers, 1987.
2. Gas-Lift Theory and Practice, by K. Brown, et al, 1st Printing, The Petroleum Publishing Company,
1967.
3. The Technology of Artificial Lift Methods, by K. Brown and D. Beggs, Volume 1, Penwell Publishing
Company, 1977.
4. The Technology of Artificial Lift Methods, by K. Brown, J. Day, J. Byrd, and J. Mach, Volume 2A, The
Petroleum Publishing Company, 1980
5. Mooney, Leah (January 22, 2015). Artificial Lift Selection in the Permian. Production Point, Retrieved
from https://www.production-point.com/p4369/artificial-lift-selection-in-the-permian/
6. McEwen, Mella (February 10, 2017). Rise in horizontal drilling brings challenge of addressing slug flow.
Midland Reporter-Telegram, Retrieved from http://www.mrt.com/business/oil/article/Rise-in-horizontal-
drilling-brings-challenge-of-10921313.php
7. Rassenfoss, Stephen (November 9, 2016). Gas Lift Use Grows in Permian. Journal of Petroleum
Technology, Retrieved from http://www.spe.org/news/article/gas-lift-use-grows-in-permian
8. Rapier, Robert (November 21, 2016). The Permian Basin Keeps on Giving. Forbes, Retrieved from
https://www.forbes.com/sites/rrapier/2016/11/21/the-permian-basin-keeps-on-giving/#31f37a3a4a2a
Oct 23-27, 20172017 ALRDC Gas-Lift Workshop
Thanks to the engineering management and owners of Altec, Inc. for the permission,technical support, and financing required to support and print this paper.
- US Patent No. 4,625,941 Constant Flow ® Valve- SPE Paper No. 69402 ABBA™ Pilot Valve
Acknowledgement
Oct 23-27, 20172017 ALRDC Gas-Lift Workshop
Disclaimer
The following disclaimer shall be included as the last page of a Technical Presentation or Continuing Education Course. A similar disclaimer is included on the front page of the Gas-Lift Workshop Web Site.
The Artificial Lift Research and Development Council and its officers and trustees, and the Gas-Lift Workshop Steering Committee members, and their supporting organizations and companies (here-in-after referred to as the Sponsoring Organizations), and the author(s) of this Technical Presentation or Continuing Education Training Course and their company(ies), provide this presentation and/or training material at the Gas-Lift Workshop "as is" without any warranty of any kind, express or implied, as to the accuracy of the information or the products or services referred to by any presenter (in so far as such warranties may be excluded under any relevant law) and these members and their companies will not be liable for unlawful actions and any losses or damage that may result from use of any presentation as a consequence of any inaccuracies in, or any omission from, the information which therein may be contained.
The views, opinions, and conclusions expressed in these presentations and/or training materials are those of the author and not necessarily those of the Sponsoring Organizations. The author is solely responsible for the content of the materials.
The Sponsoring Organizations cannot and do not warrant the accuracy of these documents beyond the source documents, although we do make every attempt to work from authoritative sources. The Sponsoring Organizations provide these presentations and/or training materials as a service. The Sponsoring Organizations make no representations or warranties, express or implied, with respect to the presentations and/or training materials, or any part thereof, including any warrantees of title, non-infringement of copyright or patent rights of others, merchantability, or fitness or suitability for any purpose.