Rose Newbury
Task Expected date of completion
Date of completion Comments
Receive permission for song use
20/11/10 1/12/10 This took a long time because I had to
contact the band on facebook and they took a long time to get back to me with
permission.Research and
analyse other real media videos
22/11/10 29/11/10 This took a large amount of time
because I had to research three
videos that I thought would best fit with
the genre of my song and analyse them.
Create Storyboard 5/12/11 17/12/10 The storyboard took some time because I
draw each of the scenes out by hand
and at times changed the idea of
the video.Liaison with actors
and actresses13/12/10 13/12/10 This task was
finished on time because I could
easily contact the actresses/actors I
wanted in my video.Arrange first filming
session (book cameras)
13/12/10 13/12/10 This task was finished on time
because it was easy to arrange the
sessions and book equipment.
Organise props costumes.etc.
13/12/10 13/12/10 This task was finished on time
because the costumes were
discussed beforehand with the actors/actresses and organise the props I
only had to gain permission.
Arrange locations 13/12/10 13/12/10 This task was finished on time
because the locations were arranged in the
storyboard and just had to check that I
could use them.
Production Schedule
Rose Newbury
First filming session 15/12/10 15/12/10 The first filming session was finished on the day it began
because I had planned before hand what I was going to
film and what I needed for this
session.Upload Footage 3/1/11 3/1/11 This task was
finished on the same day as started but it
did take a large amount of time to complete because the software kept
being unresponsive and therefore
crashing which meant I had to start the upload again.
Upload Song 3/1/11 4/1/11 This task wasn’t finished on the day I wanted to because the previous task took longer than expected which
meant that uploading the song had to be put back to the next
day.Edit existing footage 4/1/11 4/1/11 This task finished on
the time expected because I just had to
edit out all of the clips that I didn’t
need for the video.Plan next filming
session8/1/11 8/1/11 This task was
finished on time because all I had to do was to plan what footage I was going
to film next.Gain permission for use of filming space
(performance Scenes)
14/1/11 14/1/11 This task was finished on the time
expected because all I had to do was gain permission from the person authorised.
Notify Actors/Actresses
14/1/11 14/1/11 This task as finished on the same day as started because I
had a way of contacting all of the
Rose Newbury
actors/actresses I wanted for this filming session.
Receive permission for props
(instruments)
14/1/11 14/1/11 This task was finished on the time expected because I
had to gain permission from the
same person I had to gain permission from for the filming space.
Second filming session
(performance element)
18/1/11 18/1/11 This filming session ended on the same
day as started because I had
planned what I need to film for the video
beforehand and there were no disruptions or
problems.Upload footage 19/1/11 20/1/11 This task wasn’t
finished on the time expected because there were problem as before with the software in that it kept freezing and
therefore disrupting to upload.
Edit 19/1/11 20/1/11 This task wasn’t finished in the time expected because the previous task took longer than expected which
mean that this task was postponed until
this date.Plan next filming
session22/1/11 22/1/11 This task was
finished in the time expected because
knew what I needed to film before hand
from my storyboard..Notify
Actors/Actresses22/1/11 22/1/11 This task again didn’t
take up lots of time because I could
easily contact the actress that I needed
or this session.Third Filming
Session25/1/11 25/1/11 This task was
finished in the time expected because
Rose Newbury
this filming session was done with one actor at the location of my house which means that it was easy to film and didn’t take long.
Upload Footage 25/1/11 26/1/11 This task took longer than expected
because again the software wasn’t
working as it should have been.
Edit 26/1/11 27/1/11 This task was postponed to this
date because of the previous task taker
longer than expected but this task in the end didn’t take up
lots of time.Create Rough Cut 5/2/11 5/3/11 This task took longer
because I had a lot of footage to edit in order to create the
rough cut and I also had problems with the software being
slow.Create Questionnaire 16/3/11 16/3/11 This task didn’t take
up a lot of time because I knew what questions I wanted to
answer so it was easy to create
Receive Feedback 20/3/11 20/3/11 This task didn’t take up a large amount of
time because I received the
feedback after the video was watched by the audience I
chose.Re-shoots 3/4/11 3/4/11 There wasn’t much
that I had to re-shoot in order to perfect my
video so this task was finished on the
date expected.Finished Video 8/4/11 9/4/11 The video was
finished a day late due to software
problems.