prof. williams, mbm, mpm pm 342 procurement and contract management christian gonzalez, project...
TRANSCRIPT
Project:Energy Home
Prof. Williams, MBM, MPM
PM 342 Procurement and Contract Management
Christian Gonzalez, Project Manager
Tamika Roland, Project Coordinator
Alex Torres, Quality Assurance Manager
Teria Edwards, Research & Development Manager
Table of Contents Cost of Bills Scope TQM/QFD Risk categories Risk chart Cost Breakdown WBS Breakdown EVM/S-curve Project EVM Projected Labor Efficiency Breakdown ROI(Return on Investment) Green Technology Lessons Learned Work Cited
Scope Innovative contractors will upgrade Rafael and Catalina Gonzalez house’s efficiency with a budget of $205,000, a completion time of 2 months, and a start day of April 11, 2011. Innovative techniques and technology will be utilized to reduce utility bills and certify the Gonzalez’s home a 15 rating on the LEED energy rating scale. The procured house will be systematically upgraded with energy efficient materials and appliances:
WindowsHVAC SystemSolar panelsTank less water heatersInsulatingUpgrading appliancesGeothermal unitWater heating system Water recycling systemH2O floor heatingDrip Irrigation System
Natural gas generator
The procured materials will be allocated from multiple manufacturers and experts will have to be contracted for certain instillations such as the solar panels, insulation, water heating system, and water recycling system.
This allowed for the homeowners to become more acquainted with their monitoring system.
QFDQuality Functional Deployment
Necessary to acquire the best;
-Energy efficiency
-Up-to date technology
-Communication
TQMTotal Quality Management
Risk Categories
Type of risks Description Cost
Macroeconomic Cost Inflations(Gas, Shipping) +$1,2000-2 days
Political Permits, Regulations +$1,200< 1 week
Commercial Cost and schedule completion, Performance +$2,0002-5 days
Contractual Equipment supply, Licenses, and Sales agreements
+$2,0002-5 days
Environmental Inclement weather +$1,0001-4 days
Team Resignations, Unmotivated workers +$3,0001-4 days
Risk Risk ChartWeek 3Water Recycling System install
• Malfunctioning valve
Week 5Electrical update
• Mislabeling of electrical cables
Cost: $85.00Time: 45 min.
Cost:$145Time: 3 hr 30 min
Total $ 2301 Macroeconomic 2 Political3 Commercial 4 Contractual5 Environmental 6 Team
Key
1 2 3 4 5 60
0.1
0.2
0.3
0.4
0.5
0.6
0.7
Project Risks
ActualPlanned
Cost BreakdownSolar Panels 72,000 Contract type: Cost- Reimbursable
Anderson 100 series windows 34,796 Contract type: Cost- Reimbursable
Geothermal Unit 8,339.44 Contract type: Cost- ReimbursablePermits 3,200High efficiency HVAC 6,000 Contract type: Cost- ReimbursableDemolition 2,800 Contract type: Firm FixedAppliances 16,000 Contract type: Firm FixedDumpster 500 Contract type: Firm FixedSpray Insulation 8,402.56 Contract type: Cost- ReimbursableDrywall 7,000 Contract type: Cost- Reimbursablewater recycling system Drip irrigation system
6,325.12 Contract type: Cost- Reimbursable
Natural gas generator 2,050 Contract type: Cost- ReimbursableTankless water heater 4,000H20 Floor heating System 5,000 Contract type: Cost- ReimbursableEnergy Test 3,200 Contract type: Firm Fixed
Electrician $ 3,000 Contract type: T & M
Plumber(Backup) $ 1,500 Contract type: T & M
WBS Breakdown 1.0 Research
New Energy Technology Local Sellers Building Restrictions
2.0 Preparations Bidding process Procuring
3.0 Execution
4.0 Efficiency testing Energy Test Cooling & Heating Test
5.0 Closing Contract Closing Payoff Open Accounts Document Updates
Project Start Date: April 11, 2011
Project End Date: May 26, 2011
Project Duration: 2 months
Efficiency BreakdownSolar Panels
Anderson 100 series windows
Geothermal UnitHigh efficiency HVACAppliancesMaterialsSpray InsulationDrywallwater recycling system
Drip irrigation system
propane generator connectionTankless water heaterH20 Floor heating System
Design 7
Location 8
Sustainablilty 16Water Efficiency 12Energy and Atmosphere. 38
Sustainable Sites 12Awareness and Education 3
Indoor Environmental Quality 21
Grand Total 117
Return On Investment
Return of 112% efficiency
Customer Satisfaction Return On Investment(ROI)
6 years Rebates and tax Credits
9% of completion cost
Attention to Detail:
Green TechnologyThere is $2.6 billion in grants available.
Amount of grants used in 2010, <$1 million
-U.S Dept. of Energy Feb. 2011
Recycled Roofing Wood Plastic Smog Eaters
LED Bulbs Insulation
Olive Oil Recycled Plastic Denim Paper
Thermostat radient barrier heating “Green” ammunition
Team Innovative ContractorsLessons Learned
http://687842294512203611.weebly.com/index.html
Work Cited http://www.huffingtonpost.com/2009/11/13/energy-efficient-building_n_343922.html
http://www.apowersolutions.com/
http://www.hgtvpro.com/hpro/bp_green_building/article/0,3140,HPRO_29336_5499975,00.html
http://www.geocomfort.com/products/model/gtc-two-stage-split-series
http://www.GE.com
Expert Judgment Christian Gonzalez Alex Torres