programme board – 100 day plan 10 th march 2011 working days left... 1 1
TRANSCRIPT
Programme Board – 100 Day Plan
10th March 2011
working days left...11
2Agenda
Time No. Item Owner
13:00 1 Introductions All
13:10 2 Minutes of last meeting RO
13:30 3 Update from Boards and Meetings/Commercial/ RMG Stakeholder Update
JR
13:45 4 Programme Dashboard RO
13:50 5 Project Updates All PMs
15:00 6 PMO Update RO/BM
15:25 7 Plans for next period RO
15:30 Close
3Governance Cycle
Client ReviewWith RMG and BB to act as the link between the Programme and the relevant business
strategies and stakeholders and to discuss and agree ongoing performance management requirements
Client ReviewWith RMG and BB to act as the link between the Programme and the relevant business
strategies and stakeholders and to discuss and agree ongoing performance management requirements
QuarterlyQuarterly
Board Title and PurposeBoard Title and PurposeFrequency/DurationFrequency/Duration
Programme Steering GroupProvide leadership to the programme in delivering its outputs
and benefits to time, cost, quality and stakeholder expectations
Programme Steering GroupProvide leadership to the programme in delivering its outputs
and benefits to time, cost, quality and stakeholder expectationsMonthlyMonthly
Programme Board
Provide management to the programme to deliver its outputs and benefits to time, cost, quality and stakeholder expectations
Programme Board
Provide management to the programme to deliver its outputs and benefits to time, cost, quality and stakeholder expectations
Day 1 100 Day Plan – Fortnightly
Change – Monthly
Day 1 100 Day Plan – Fortnightly
Change – Monthly
HR Working PartyTo ensure all people related issues are understood and being managed
HR Working PartyTo ensure all people related issues are understood and being managed
WeeklyWeeklyFinance Working Party
To ensure costs and benefits are identified, managed and tracked in accordance with project plans, and linked to P&L
Finance Working PartyTo ensure costs and benefits are identified, managed and tracked in accordance
with project plans, and linked to P&L
Commercials Working Party To manage interdependencies between bid work and project delivery
Commercials Working Party To manage interdependencies between bid work and project delivery
Sponsors BoardEnsure all programme
outputs are embedded as business change
Sponsors BoardEnsure all programme
outputs are embedded as business change
BB BoardBB BoardJV BoardJV Board
Romec ExecRomec Exec
23/223/23/33/3
17/217/2Cost/Phasing Workshop
10/310/3
8/38/3
15/215/2
4Programme Summary
5
6
7
8
9
10
11
12
13
14
15
16
17
18
• Plans• Process Review• SharePoint – Checking Out & Editing• Weekly Reporting• Contact List• Business Cases• Joint Mobilisation Groups• Communications
Following slides to cover:• Plans/Dependencies Status• Baseline Data (Romec & RM)• Costs• Benefits• Risks & Issues
PMO Update
19Plans/Dependencies Status
20
What RM information do we need?
Baseline Data
21Programme Costs
Year 0 (Jan 11 – Mar
11)
Year 1 (Apr 11 – Mar 12)
Year 2(Apr 12 – Mar 13)
Year 3(Apr 13 – Mar 14)
Total
Resource £0.56m £4.54m £0.74m £0.33m £6.17m
Capital £0.28m £2.07m £3.81m £0.84m £7.00m
Non-Capital £0.36m £11.73m £0.25m £0.12m £12.46m
Total £1.20m £18.34m £4.80m £1.29m £25.6m
Notes: •Latest figures provided as at 2nd March 2011. Some validation and inclusions still outstanding•Some resource working on bid but charged to change Programme included in numbers above (see below)
22Programme Benefits
23Benefits – Next Steps
• Meet remaining teams• Agree measures• Agree data and source• Define baseline• Define target and date to achieve• Validate with Finance, HR and KPIs• Link to Glide-Slope• De-duplicate• Link to milestones
24Programme Level Risks & IssuesRisk/Issue Mitigation
• Design Principles have not been agreed for the new Operating Model, particularly around Brand and People Strategies – may be unable to implement the required changes by 1st April.
• Pragmatic decision making required to phase the implementation of BBSD over 2011 and 2012. SC is raising with Exec.
• Available time to deliver shortening whilst awaiting deal signature – delays to communications, training, supplier negotiation, etc.
• Reduce by working with what is currently known.• Accept possibility that things may change.
• WSP Enforma Call logging Application / Operation need to change in order to meet Day 1 Requirements. Without correct information being fed it will not be possible to act against new performance framework
• RM to confirm by 9th March whether date will be end April /start May or end June/start July
• Timeliness of Comms across Romec, BBW and Royal Mail where all have different priorities - without effective comms buy in will suffer and this could have a knock on effect on the service.
• Working parties have been requested although timings are stretched ). Meetings to be arranged to discuss but need decisions re when comms can commence.
• Both internal and external IT teams are now at capacity – any additional requirements would need prioritisation which could lead to less effective manual workarounds
• Monitor and assess if required
• Risk that without effective closedown and cutover procedures, issues could surface with outstanding jobs and service could suffer, requiring manual intervention to rectify
• Being planned within the projects
• Possibility of strike action as part of ongoing negotiations within HR • Reduce through planning work taking place within People, Training and Communications to better understand comms/training requirements