PROGRESS AND CHALLENGES IN ACHIEVING HIGH PERFORMANCE BUILDING ENVELOPES Prof. A. Janssens DEPARTMENT ARCHITECTURE AND URBAN PLANNING RESEARCH GROUP BUILDING PHYSICS, CONSTRUCTION AND SERVICES

Upload: others

Post on 16-Aug-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PROGRESS AND CHALLENGES IN ACHIEVING HIGH …qualicheck-platform.eu/wp-content/uploads/2017/01/... · ̶Priority research theme IEA-EBC programme ̶IEA-EBC Annex 58: Reliable building

PROGRESS AND CHALLENGES

IN ACHIEVING HIGH

PERFORMANCE BUILDING

ENVELOPESProf. A. Janssens

DEPARTMENT ARCHITECTURE AND URBAN PLANNINGRESEARCH GROUP BUILDING PHYSICS, CONSTRUCTION AND SERVICES

Page 2: PROGRESS AND CHALLENGES IN ACHIEVING HIGH …qualicheck-platform.eu/wp-content/uploads/2017/01/... · ̶Priority research theme IEA-EBC programme ̶IEA-EBC Annex 58: Reliable building

OVERVIEW

Actual versus theoretical energy performance

Transmission heat loss calculation

Quality of the works

Performance assessment based on in-situ

measurements

Role of dynamic analysis methods

Epilogue: what about performance of building

services?

Page 3: PROGRESS AND CHALLENGES IN ACHIEVING HIGH …qualicheck-platform.eu/wp-content/uploads/2017/01/... · ̶Priority research theme IEA-EBC programme ̶IEA-EBC Annex 58: Reliable building

STRENGTHENING REQUIREMENTS IN ENERGY PERFORMANCE LEGISLATION

Towards nearly zero

energy houses in 2021:

• Very low energy use

for heating and

cooling:‒ Thermal insulation

‒ Airtightness

‒ Energy efficient ventilation

‒ Solar shading

• On-site or nearby

renewable energy

production

E-level, Flanders, Belgium

Page 4: PROGRESS AND CHALLENGES IN ACHIEVING HIGH …qualicheck-platform.eu/wp-content/uploads/2017/01/... · ̶Priority research theme IEA-EBC programme ̶IEA-EBC Annex 58: Reliable building

THERMAL INSULATION OF BUILDING ENVELOPE: EVOLUTION OF LEGAL REQUIREMENTS IN FLANDERS

0,24 W/m²K

= 0,040 W/mK

Page 5: PROGRESS AND CHALLENGES IN ACHIEVING HIGH …qualicheck-platform.eu/wp-content/uploads/2017/01/... · ̶Priority research theme IEA-EBC programme ̶IEA-EBC Annex 58: Reliable building

ACTUAL VERSUS THEORETICAL GAS CONSUMPTION IN BUILDING STOCK

Majcen, 2016

~200 000 cases EPC label database Netherlands 2010

Energy efficiency measures have smaller impact in reality

than according to EPC-rating

Page 6: PROGRESS AND CHALLENGES IN ACHIEVING HIGH …qualicheck-platform.eu/wp-content/uploads/2017/01/... · ̶Priority research theme IEA-EBC programme ̶IEA-EBC Annex 58: Reliable building

REASONS FOR DEVIATION BETWEENTHEORETICAL ENERGY PERFORMANCE AND REALITY

Model simplifications (quasi-steady state method)

Single zone calculation

Standardised user behaviour

Not all relevant phenomena considered

Incorrect input data

Not in line with normative procedures

Not corresponding to as-built situation

Poor quality of the works

Page 7: PROGRESS AND CHALLENGES IN ACHIEVING HIGH …qualicheck-platform.eu/wp-content/uploads/2017/01/... · ̶Priority research theme IEA-EBC programme ̶IEA-EBC Annex 58: Reliable building

DATA BASED ON AS-BUILT CHARACTERISTICS?

Carrié 2016, Qualicheck booklet

Page 8: PROGRESS AND CHALLENGES IN ACHIEVING HIGH …qualicheck-platform.eu/wp-content/uploads/2017/01/... · ̶Priority research theme IEA-EBC programme ̶IEA-EBC Annex 58: Reliable building

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

8.0

9.0

10.0

Flatgebouw Rijwoning Halfopen Vrijstaand Bungalow

To

en

am

e K

-pe

il

Business as usual Standaard-details Koudebrugarm

RELEVANT PHENOMENA FOR CALCULATINGTRANSMISSION HEAT LOSS

2D- and 3D-heat transfer at building junctions and building

envelope structure (frame, ties,…) Relative share increases with better insulation

Importance of qualitative architectural detailing: Consistent avoidance of thermal bridges

Need for performance based rules and correct estimation

20%

10%

5%

K40

)2C(A

L300K

T

e

Multifamily Terraced Semi-detached Detached

Janssens et al. 2007, Buildings X

Incre

ase in K

-level

K

Page 9: PROGRESS AND CHALLENGES IN ACHIEVING HIGH …qualicheck-platform.eu/wp-content/uploads/2017/01/... · ̶Priority research theme IEA-EBC programme ̶IEA-EBC Annex 58: Reliable building

RULE 1Minimal contact length insulation

layers

EPB - accepted junction

Fulfils one of the

BASIC RULESFulfils

Ψe Ψe,lim

RULE 2Insertion of insulating element

RULE 3Long path of

minimal thermal resistance

and/or

Page 10: PROGRESS AND CHALLENGES IN ACHIEVING HIGH …qualicheck-platform.eu/wp-content/uploads/2017/01/... · ̶Priority research theme IEA-EBC programme ̶IEA-EBC Annex 58: Reliable building

INFLUENCE OF DESIGN AND WORKMANSHIP ON THERMAL TRANSMITTANCE: PITCHED ROOFS

Wood frame roof Underlay film with

unsealed overlaps

Janssens et al. 2007, Energy and Buildings

Page 11: PROGRESS AND CHALLENGES IN ACHIEVING HIGH …qualicheck-platform.eu/wp-content/uploads/2017/01/... · ̶Priority research theme IEA-EBC programme ̶IEA-EBC Annex 58: Reliable building

INFLUENCE OF WORKMANSHIP ON THERMAL TRANSMITTANCE: CAVITY WALLS

0

0.2

0.4

0.6

0.8

1

SPOUWMUREN

U-W

AA

RD

E (

W/m

2.K

)

MW +LEK XPS +LEK XPS-VENT +LEK

Hens et al. 2007, J. Building Physics

Page 12: PROGRESS AND CHALLENGES IN ACHIEVING HIGH …qualicheck-platform.eu/wp-content/uploads/2017/01/... · ̶Priority research theme IEA-EBC programme ̶IEA-EBC Annex 58: Reliable building

APPROACHES TO BETTERQUALITY OF THE WORKS

Carrié 2016, Qualicheck booklet

Page 13: PROGRESS AND CHALLENGES IN ACHIEVING HIGH …qualicheck-platform.eu/wp-content/uploads/2017/01/... · ̶Priority research theme IEA-EBC programme ̶IEA-EBC Annex 58: Reliable building

New cavity walls:

• Improved training of contractors

• Improved systems and execution

sequence allowing inspection

Page 14: PROGRESS AND CHALLENGES IN ACHIEVING HIGH …qualicheck-platform.eu/wp-content/uploads/2017/01/... · ̶Priority research theme IEA-EBC programme ̶IEA-EBC Annex 58: Reliable building

Existing cavity walls: guaranteeing

quality of installing insulation in UK

• Mass market application

• Robust Consumer Protection Arrangements– Tested certified Systems– Enforcement of technical

guidance– 1st, 2nd and 3rd party

surveillance of work– Guarantee to create

confidence in the technology

• Government policies to create demand and provide correct signals

-

100,000

200,000

300,000

400,000

500,000

600,000

700,000

800,000

1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012

An

nu

al In

stal

lati

on

s

CWI Retrofit Trends

EE C 2 C E R T ExtE E S o P EE C 1

Forecast

(G. Miller 2012)

Page 15: PROGRESS AND CHALLENGES IN ACHIEVING HIGH …qualicheck-platform.eu/wp-content/uploads/2017/01/... · ̶Priority research theme IEA-EBC programme ̶IEA-EBC Annex 58: Reliable building

OVERVIEW

Actual versus theoretical energy performance

Performance assessment based on in-situ

measurements

Role of dynamic analysis methods

Epilogue: what about performance of building

services?

Page 16: PROGRESS AND CHALLENGES IN ACHIEVING HIGH …qualicheck-platform.eu/wp-content/uploads/2017/01/... · ̶Priority research theme IEA-EBC programme ̶IEA-EBC Annex 58: Reliable building

ASSESSMENT OF ACTUAL ENERGY PERFORMANCE OF BUILDINGS

Priority research theme IEA-EBC programme

IEA-EBC Annex 58: Reliable building energy

performance characterisation based on full scale

dynamic measurements, 2011-2015

IEA-EBC Annex 71: Building energy performance

assessment based on in-situ measurements,

2016-2020

Support the development of characterisation and

quality assurance methodologies to assess the actual

energy performance of buildings

Page 17: PROGRESS AND CHALLENGES IN ACHIEVING HIGH …qualicheck-platform.eu/wp-content/uploads/2017/01/... · ̶Priority research theme IEA-EBC programme ̶IEA-EBC Annex 58: Reliable building

IEA-ANNEX 58: BUILDING ENVELOPE TEST METHODS

Disadvantages of steady-state analysis methods:

long test durations, large uncertainties

U-value of building

components based on

heat flux meters

Heat loss coefficient of

whole buildings based

on co-heating tests

Energy model

characterization of

whole buildings based

on energy monitoring

N

1kk,s,i

N

1kk,s,ok,s,i

stos,N

q

TT

R

solsolvetrH IAT·HH

Page 18: PROGRESS AND CHALLENGES IN ACHIEVING HIGH …qualicheck-platform.eu/wp-content/uploads/2017/01/... · ̶Priority research theme IEA-EBC programme ̶IEA-EBC Annex 58: Reliable building

QUALICHECK FIELD STUDY 26 HOUSES WITH RETROFIT CAVITY WALL INSULATION

• Goal of the study:

assess effectiveness

of quality control

framework for cavity

wall insulation

• In none of the cases

the measured U-value

was significantly

higher than the

theoretical value

• Wide confidence

interval (10%)

Janssens et al. 2016,

Bauphysik

Page 19: PROGRESS AND CHALLENGES IN ACHIEVING HIGH …qualicheck-platform.eu/wp-content/uploads/2017/01/... · ̶Priority research theme IEA-EBC programme ̶IEA-EBC Annex 58: Reliable building

IEA ANNEX 58: GUIDELINES FOR APPLYINGDYNAMIC ANALYSIS METHODS

Dynamic analysis of heat

flux measuring data Dynamic test conditions

System identification‒ RC-models

‒ FDE or SDE

‒ Software tools

Advantages Shorter test duration

Dynamic performance

Error estimation

Hot climates

Concerns Advanced methods

Physical meaning of parameters 32232121

22 H·TTH·TT

dt

dT·C

Measured electric power and HFS Tiles power

0

50

100

150

200

250

6

12

18 6

12

18 6

12

18 6

12

18 6

12

18 6

12

18 6

12

18 6

12

18 6

12

18

28-oct 29-oct 30-oct 31-oct 1-nov 2-nov 3-nov 4-nov 5-nov

Time [h]

Po

we

r [W

]

HFS Tiles

Electric

Page 20: PROGRESS AND CHALLENGES IN ACHIEVING HIGH …qualicheck-platform.eu/wp-content/uploads/2017/01/... · ̶Priority research theme IEA-EBC programme ̶IEA-EBC Annex 58: Reliable building

IEA ANNEX 71

Towards non-intrusive

testing:

• Smart meter readings

(short time span)

• Data driven modelling

• Estimate model

parameters

• Characterise heat

loss coefficient

eaie RR

1H

[179.0, 191.2] W/K

Bacher et al. 2011,

Energy and Buildings

Page 21: PROGRESS AND CHALLENGES IN ACHIEVING HIGH …qualicheck-platform.eu/wp-content/uploads/2017/01/... · ̶Priority research theme IEA-EBC programme ̶IEA-EBC Annex 58: Reliable building

Development and improvement of Software Tools

Updated versions of CTSM-R. Grey-box modeling. www.ctsm.info

Updated description on the DYNASTEE Web-pages

http://www.just-pm.eu/dynastee/data-analysis/software-tools/ctsm-r/

Common Exercises

FROM simple homogeneous opaque walls TO FULL SIZE BUILDINGS

ADVANCES IN DYNAMIC DATA ANALYSIS AND PERFORMANCE CHARACTERISATION

IEA-Annex 58

Page 22: PROGRESS AND CHALLENGES IN ACHIEVING HIGH …qualicheck-platform.eu/wp-content/uploads/2017/01/... · ̶Priority research theme IEA-EBC programme ̶IEA-EBC Annex 58: Reliable building

CONCLUSIONS

Environmental challenges require very high building

envelope performances

Reduce performance gap by correct calculation of

transmission heat loss and good quality of insulation

works

On-site testing is important to solve deviations between

calculated and real energy performance Applications in model development, ‘as built’ compliance

testing, commissioning,…

Data analysis methods Focus on dynamic analysis methods

‒ Shorter test duration

‒ More complete characterisation of energy performance

‒ Error estimation

Large potential, subject to further research

Page 23: PROGRESS AND CHALLENGES IN ACHIEVING HIGH …qualicheck-platform.eu/wp-content/uploads/2017/01/... · ̶Priority research theme IEA-EBC programme ̶IEA-EBC Annex 58: Reliable building

OVERVIEW

Actual versus theoretical energy performance

Performance assessment based on in-situ

measurements

Epilogue: what about performance of building

services?

Page 24: PROGRESS AND CHALLENGES IN ACHIEVING HIGH …qualicheck-platform.eu/wp-content/uploads/2017/01/... · ̶Priority research theme IEA-EBC programme ̶IEA-EBC Annex 58: Reliable building

RESULTS OF ECO-LIFE DEMONSTRATIONPROJECT: CARBON NEUTRAL DISTRICT

Energy efficiency targets:

New buildings: passive house

standard

‒ 15 kWh/m²/y heating demand

‒ Solar shading

Renovation: 50% better

compared to regulations

‒ 35 kWh/m²/y heating demand

Renewable energy production:

District heating

‒ 1MW wood chip boiler

‒ µWKK (bio-oil)

‒ Back-up gas boiler

PV-panels

Page 25: PROGRESS AND CHALLENGES IN ACHIEVING HIGH …qualicheck-platform.eu/wp-content/uploads/2017/01/... · ̶Priority research theme IEA-EBC programme ̶IEA-EBC Annex 58: Reliable building

YEARLY PRIMARY ENERGY BALANCE

Monitored energy use higher than expected: High network heat losses in district and collective heating networks

Low production efficiencies

Higher energy demand for space heating in some demonstration buildings

Page 26: PROGRESS AND CHALLENGES IN ACHIEVING HIGH …qualicheck-platform.eu/wp-content/uploads/2017/01/... · ̶Priority research theme IEA-EBC programme ̶IEA-EBC Annex 58: Reliable building

The sole responsibility for the content of this presentation lies with the authors. It does not necessarily reflect the opinion of the

European Union. Neither the EASME nor the European Commission are responsible for any use that may be made of the

information contained therein.