progress of control system
DESCRIPTION
Progress of Control System. Presented by C.H. Wang Control Group Accelerator Center of IHEP IMAC, April 26 2006. Outline. Overview Current Status Subsystems PS,Vacuum,RF,Cryogenic Summary. Vac. local. RF Local. PS local. RF IOC. Vac.IOC. PS IOC. Ethernet. - PowerPoint PPT PresentationTRANSCRIPT
Control Group April 26, 2006
Progress of Control System
Presented by C.H. Wang
Control Group
Accelerator Center of IHEP
IMAC, April 26 2006
Control Group April 26, 2006
Outline
Overview Current Status Subsystems
PS,Vacuum,RF,Cryogenic Summary
Control Group April 26, 2006
Control System Overview
Central control room
Vac. localRF Local PS local
EthernetPS IOC RF IOC
Device or low level control system
Vac.IOC
Control Group April 26, 2006
MilestonesInsertion device 4W1 PS control (Nov.04 to July 05)
PS control in the transport line (Feb.05 to July 05)
Commissioning of the SRF Cryogenic System (Jan. 06)
New TQ PS control system running (Feb. 06)
Timing System EVG/EVR running with linac electron gun
(March,06)
Corrector PS control system installed on-site (March 06)
B 、 Q 、 S ... PS control system installed on-site (April 06)
Network devices installed on-site (March 06)
Vaccum control system installed on-site (90% )Timing System control system installed on-site (90%)
Safety Interlock system installed on-site (70% )
Control Group April 26, 2006
Subsystems
Power supply control Vacuum control RF control Cryogenic control Network Computer servers Oracle database Timing system (G.Lei) High level applications (G.Lei) New console
Control Group April 26, 2006
Requirements
Most magnet PS require 100ppm control precision and stability.
The only dipole PS require 50ppm control precision and stability.
Table 1. PS families for BEPCII rings
Name Dipolar Quadrupole Sextupole skQ Other Q
SC magnet
Kicker Correctors
Number 4 116 36 9 19 16 4 140 Stability
RII
[ppm]
50 100 100 100 100 100 100 100
Control Group April 26, 2006
Requirements
Basic functionality (setpoint, readback, control and status).
Ramping synchronously from the colliding mode to the synchrotron radiation mode.
Control Group April 26, 2006
Hardware Architecture
Ethernet
SR-PS
VME crate
PPC750
Corrector PS
Analogsetpoint/readback
Digitalcommand/
status
PSC
PSC
PSI
PSI
PSI
VME crate
VME crate
PSC
PSC
PPC750
Big PS
PSI
Analogsetpoint/readback
Digitalcommand/
status
VME crate
VSD2922
PPC750
PC/Linuxworkstation
SCC2401
SCC2401
CAMAC crate CAMAC crate
I/O
I/O
I/O
I/O
I/O
I/O
I/O
I/O
Transition modules
PS
TP-PS
•PSC/PSI is FPGA based integrated system
•Provides all functions (setpoint, readback, control and status) with a single board at the power supply.
•Not remote I/O, no communication protocol between PSC and PSI.
•Maximum response time: ~80microsecond
•PSC/PSI is FPGA based integrated system
•Provides all functions (setpoint, readback, control and status) with a single board at the power supply.
•Not remote I/O, no communication protocol between PSC and PSI.
•Maximum response time: ~80microsecond
Control Group April 26, 2006
Software Construct
UserInterface
Connectivity
IOCServices
GUI(tcl/tk)
CA
GUI(edm)
CA
GUI(Java)JCA
CA
Epics Records
SNL Device/driver
Hardware
PSC/PSI, I/O
CA
SUB
www
Oracl eDatabase
QUERY
Oracl e HW
Confi g i nfo
VDCTText editor
Generate
DbTemplate
IOC db*.db file
Macrosubstitusions+
dbload
Import/Export
data
GUI builder(edm,tcl/tk,java)
Database(VDC,text editor, Oracle JERI)
Standard applications
(Archiver/AHLStriptool,vxStats/Save&restore)
GUI builder(edm,tcl/tk,java)
Database(VDC,text editor, Oracle JERI)
Standard applications
(Archiver/AHLStriptool,vxStats/Save&restore)
Control Group April 26, 2006
60 chopper PS Testing
Control Group April 26, 2006
Ramp Principle
t
I
di1
di2
di3
t1 t2 t3 t4dt
Ramp speed:di/dt
Q3
Q2
Q1
Ramp Principle
•Calculate maximum steps for all PS
•Calculate delta setpoint of each PS under the max. steps
•IOC sends setpoint to db step by step
•All PS reach to desired setpoint at the same time
•Calculate maximum steps for all PS
•Calculate delta setpoint of each PS under the max. steps
•IOC sends setpoint to db step by step
•All PS reach to desired setpoint at the same time
Control Group April 26, 2006
Corrector VME-PSI test
Test at lab
With magnet load
Control Group April 26, 2006
PS Control System Integration
PS families
VME IOC:10, about 10,000 signals
Table 1. PS families for BEPCII rings
Name Dipolar Quadrupole Sextupole skQ Other Q
SC magnet
Kicker Correctors
Number 4 116 36 9 19 16 4 140 Stability
RII
[ppm]
50 100 100 100 100 100 100 100
Control Group April 26, 2006
PSC/PSI installation statistics
Ok+running
Chassis PSI
(Unit)
VME-PSI (unit)
PSI crates(unit)
VME crates(Unit)
Cables(pairs)
Optics(Pairs
)
PC/Linux(No.)
B 、 Q 、 S…164+17DC
198 6198*2
17digital220 1
Corrector140
140 9 2 140*2 140 2
SC magnet+QPIC
16+117 1
16*2
1digital17 3
kicker4
4 1 4*2 4 1
Insertion device4w1 2
2 1 2*2 2 1
New TQ33
33 1 33*2 2 4
Running one week In the phase of the interface test
Interface test and stability measurement
Control Group April 26, 2006
B 、 Q 、 S Control Installation
198 pcs.PSI installed
198x2 control cables installed
220 pairs of optics fiber installed
PSC 36 pcs. Installed
VME crate(IOC): 6
198 pcs.PSI installed
198x2 control cables installed
220 pairs of optics fiber installed
PSC 36 pcs. Installed
VME crate(IOC): 6
Control Group April 26, 2006
New TQ PS Control Installation
33 B Q PS PSI
1 VME-PSC crate
6 VME-PSC
33x2 analog/digital cables
33 optics fiber
33 B Q PS PSI
1 VME-PSC crate
6 VME-PSC
33x2 analog/digital cables
33 optics fiber
Control Group April 26, 2006
SC PS/QPIC Control interface test in the factory
Control Group April 26, 2006
SCPS/QPIC Control System Installation on-site
17 PSI installed
17x2 control cables(analog/digital cables)
17 pairs of optics fiber
1 VME crate(IOC)
17 PSI installed
17x2 control cables(analog/digital cables)
17 pairs of optics fiber
1 VME crate(IOC)
Control Group April 26, 2006
Corrector Control System Installation on-site
6 racks 9 VME-PSI crates 2 VME-PSC crates
140x2 analog/digital cables
140 optics fiber
6 racks 9 VME-PSI crates 2 VME-PSC crates
140x2 analog/digital cables
140 optics fiber
Control Group April 26, 2006
Summary of PS control
Hardware installation on site (~100% ) Software:~80% System testing with magnet (May to July)
Ensure I/O channels/signals ok Do calibration(AD/DA conversion) Make application software/OPI perfect
System testing with beam (Oct. )
Control Group April 26, 2006
Vacuum Control System
OPI(PC or Touch Panel)
OPI(Workststion)
Local Station Control Room
IOC(VME)
PLC(ControlLogix)
Vacuum Gauges
Ion Pump Controller
OPI
IOC
Device Controls
Local Device
Ethernet
RS-232RS-232
RS-2
32
Gate Valve
HCG or CCG
Ion Pump
Interlock Output
Alarm Output
CNETEthernet
Vacuum gauge monitoringIon pump monitoring Gate valve control/interlock/monitoringTemperature monitoring
(vacuum chamber/corrugation pipe/photon absorber)
Vacuum gauge monitoringIon pump monitoring Gate valve control/interlock/monitoringTemperature monitoring
(vacuum chamber/corrugation pipe/photon absorber)
Control Group April 26, 2006
Vacuum Control System Gate valve touchpanel
Temperature monitoring
Vacuum gauge, Ion pump monitoring
Control Group April 26, 2006
System Integration
Vacuum gauge(~200 points) Gate valve(16 points+ 48 interlock points) Temperature sensors(~1000 points) Installation(~90%)
Control cables/sensor cablesRacks/VME crates/I/O modules
System itself testing on-site (May) System testing with vacuum devices
Control Group April 26, 2006
RF Control System
The RF control system is developed by the company(THALES) based on Epics
First set of klystron has been delivered in Dec. 2004.
We have taken part in the control system acceptance test.
Second set of klystron has been delivered in Jan. 2006
We have taken part in the test of second klystron and cavity control system
Control Group April 26, 2006
Cryogenic Control
Cryogenic control system is original developed by the domestic university(HIT) using AB-PLC system.
Cryogenic is critical path in 2005. Control group took over cryogenic control starting from July, 2005.
Cryogenic control mini-workshop was held in HELP from Sept. 5 to 9 ,2005. Mr. Matthias Clausen from DESY attended and exchanged some constructive ideas with cryogenic group and control group. He also gave some crucial suggestions on control flow, control loop,control logic.
Cryogenic control adopted EPICS as development platform after that.
Control Group April 26, 2006
Structure of Cryogenic Control System
Bay Networks
iMac
00
latigid
latigid
latigid
Profi
bus
iMac
latigid
latigid
latigid
Profi
bus S7-400S7-400
iMac
latigid
latigid
latigid
Cont
rolN
et
iMac
latigid
latigid
latigid
Cont
r olN
et
Control Logi xControl Logi x
Wi ncc(ODK)
EthernetiMac
iMac
EPI CSOPI
EPI CSOPI
EPI CSfor SCQ, SSM
VME/I OC
5136-CN-VME
EPI CSfor SRFC
iMac
EPI CSOPI
Compressor Control Cryogeni c Control
CenterRoom
LocalRoom
TP
TP forSCQ, SSM
TP forSRFC
Located i ncenter room
Not Connected
compressors and turbines by S7 PLCSCQ,SSM,SRF-C by AB PLC
compressors and turbines by S7 PLCSCQ,SSM,SRF-C by AB PLC
Control Group April 26, 2006
Structure of two control layer EPICS-PLC
Control Group April 26, 2006
Cryogenic system first commissioning
Control Group April 26, 2006
Cryogenic system first commissioning
Control Group April 26, 2006
Summary of cryogenic control
The cryogenic system first commissioning with dummy load (Cavity) on January.20,2006.
The cryogenic system was put into use for testing transfer pipes and 1000L Dewar of SSM and SCQ.
Superconducting cavity will be tested with the cryogenic system and its control system in May 2006.
Cryogenic control system for SCQ has been installed on site and it will be tested in Summer of 2006.
Control Group April 26, 2006
Network
Cisco switches adopted to BEPCII control network
Hardware installation on-site (~90%) 200 cable links and 300 fiber links has been
installed in the connectors All the installed fiber links has been tested in
connectivity and power loss, everything is ok
System test on-site start in May
Control Group April 26, 2006
Network
Control Group April 26, 2006
Computer Servers
EPICS boot server two node fail-overtwo Sun Fire V880 servers and one Sun StorEdge 3310
Disk Array two-host Hot-Swap
Archiving servers: PC/Linux Oracle: PC/Linux OPI: PC/Linux and Sun thin client SunRay
Control Group April 26, 2006
Server Acceptance test
Control Group April 26, 2006
Oracle Database
Magnet measurement database(finished)
Parameter Management: the management of magnet physics and design parameters.
Upload Interface: allow to upload magnet measurement data file to application server from remote site.
Import Interface: upload magnet measurement data files to application server and import data into Oracle Database from remote site.
Control Group April 26, 2006
Oracle Database
Magnet measurement database Query and Export: anyone can query the magnet
measurement data via Web browser and results searched can produce different kinds of visual output: plots and MS Excel Spreadsheets.
System Management: the management of system basic tables and user, including insert, delete, modify and browser for records specified table. The users are specified three class with different privilege based on management function: system administrator, data operator and search user.
Data Initialization: delete specified magnet data.
Control Group April 26, 2006
System Administrator Interface
Control Group April 26, 2006
Upload and Import Interface
Control Group April 26, 2006
Query Results Average values of Multipole Erro
r Distribution for sextupole magnet 130S-01, current is 90A,135A,180A respectively
Curve of Integral Field Error Distribute for bending magnet 67B-1345-A01, 67B-1345-A02, current is about 408A
Control Group April 26, 2006
New Console
Installation
The console consists of 14 unit 14 21-inch LCDs will be installed in the console 8 32-inch LCDs and 5 42-inch PDPs will be on the display wall in next month.
The console consists of 14 unit 14 21-inch LCDs will be installed in the console 8 32-inch LCDs and 5 42-inch PDPs will be on the display wall in next month.
Control Group April 26, 2006
Summary
Hardware Installation done almost System development going well On-line test with accelerator devices
region by region May 2006
Commissioning of the control system
Oct. 2006
Control Group April 26, 2006