Construction of Stage II of the Student center Name of the Project Original / Amended TCE Cumulative Expenditure as at Financial Progress (%) Physical Progress (%) Construction of (Stage II) of the Student Centre building %65%TRANSCRIPT
![Page 1: Progress of the ongoing Construction Projects as at 31-07-2015 Gampaha Wickramarachchi Ayurveda Institute University of Kelaniya](https://reader036.vdocument.in/reader036/viewer/2022062504/5a4d1bb77f8b9ab0599cefee/html5/thumbnails/1.jpg)
Progress of the ongoing Construction Projects as at 31-07-2015
Gampaha Wickramarachchi Ayurveda Institute University of Kelaniya
![Page 2: Progress of the ongoing Construction Projects as at 31-07-2015 Gampaha Wickramarachchi Ayurveda Institute University of Kelaniya](https://reader036.vdocument.in/reader036/viewer/2022062504/5a4d1bb77f8b9ab0599cefee/html5/thumbnails/2.jpg)
Construction of Administration Building (AC4)
Name of the ProjectOriginal /
Amended TCE
Cumulative Expenditure as at 31.07.2015
Financial Progress (%)
Physical Progress (%)
Construction of four storied Administration building (AC4) 79.0 36.0 63% 65%
![Page 3: Progress of the ongoing Construction Projects as at 31-07-2015 Gampaha Wickramarachchi Ayurveda Institute University of Kelaniya](https://reader036.vdocument.in/reader036/viewer/2022062504/5a4d1bb77f8b9ab0599cefee/html5/thumbnails/3.jpg)
Construction of Stage II of the Student center
Name of the Project Original / Amended TCE
Cumulative Expenditure as at 31.07.2015
Financial Progress (%)
Physical Progress (%)
Construction of (Stage II) of the Student Centre building 46.0 18.0 40% 65%
![Page 4: Progress of the ongoing Construction Projects as at 31-07-2015 Gampaha Wickramarachchi Ayurveda Institute University of Kelaniya](https://reader036.vdocument.in/reader036/viewer/2022062504/5a4d1bb77f8b9ab0599cefee/html5/thumbnails/4.jpg)
Construction of Academic Building (AC2)Construction of Academic Building (AC2)
Name of the ProjectOriginal /
Amended TCE
Cumulative Expenditure as at
31.07.2015
Financial Progress (%)
Physical Progress (%)
Construction of four storied Academic building (AC2) 134.4 26.0 26% 20%