PROGRESS REPORT APRIL 2012
Published May 20, 2012
![Page 2: PROGRESS REPORT APRIL 2012 Published May 20, 2012](https://reader036.vdocument.in/reader036/viewer/2022062314/56649f175503460f94c2e3df/html5/thumbnails/2.jpg)
The Banks Project
![Page 3: PROGRESS REPORT APRIL 2012 Published May 20, 2012](https://reader036.vdocument.in/reader036/viewer/2022062314/56649f175503460f94c2e3df/html5/thumbnails/3.jpg)
The Banks Project Master Plan
![Page 4: PROGRESS REPORT APRIL 2012 Published May 20, 2012](https://reader036.vdocument.in/reader036/viewer/2022062314/56649f175503460f94c2e3df/html5/thumbnails/4.jpg)
Riverfront Parking
![Page 5: PROGRESS REPORT APRIL 2012 Published May 20, 2012](https://reader036.vdocument.in/reader036/viewer/2022062314/56649f175503460f94c2e3df/html5/thumbnails/5.jpg)
Baseball Parking
![Page 6: PROGRESS REPORT APRIL 2012 Published May 20, 2012](https://reader036.vdocument.in/reader036/viewer/2022062314/56649f175503460f94c2e3df/html5/thumbnails/6.jpg)
Executive Summary
![Page 7: PROGRESS REPORT APRIL 2012 Published May 20, 2012](https://reader036.vdocument.in/reader036/viewer/2022062314/56649f175503460f94c2e3df/html5/thumbnails/7.jpg)
Executive SummaryOpening Day—April 5
![Page 8: PROGRESS REPORT APRIL 2012 Published May 20, 2012](https://reader036.vdocument.in/reader036/viewer/2022062314/56649f175503460f94c2e3df/html5/thumbnails/8.jpg)
Executive SummaryPete Rose Way Parking Entrance
![Page 9: PROGRESS REPORT APRIL 2012 Published May 20, 2012](https://reader036.vdocument.in/reader036/viewer/2022062314/56649f175503460f94c2e3df/html5/thumbnails/9.jpg)
Executive SummaryOngoing Construction
![Page 10: PROGRESS REPORT APRIL 2012 Published May 20, 2012](https://reader036.vdocument.in/reader036/viewer/2022062314/56649f175503460f94c2e3df/html5/thumbnails/10.jpg)
Executive SummaryOngoing Construction
![Page 11: PROGRESS REPORT APRIL 2012 Published May 20, 2012](https://reader036.vdocument.in/reader036/viewer/2022062314/56649f175503460f94c2e3df/html5/thumbnails/11.jpg)
Summary: Construction
•Public Safety Technologies•TC-28 work progress•Conduit installation 100% complete•Emergency communication panels, transformer and phones installed•Camera wiring and mounting process begun
![Page 12: PROGRESS REPORT APRIL 2012 Published May 20, 2012](https://reader036.vdocument.in/reader036/viewer/2022062314/56649f175503460f94c2e3df/html5/thumbnails/12.jpg)
Bid Package #12
Part 1 Elements• Reconstruction of
Freedom Way• Second Street
pedestrian improvements• Security cameras• Removal of Race
Street south of Freedom Way
April Progress• Project currently in
design phase• Plans will be sent to
ODOT for review end of June• Documents for
Environmental Clearance prepared, coordinated with ODOT and SHPO
![Page 13: PROGRESS REPORT APRIL 2012 Published May 20, 2012](https://reader036.vdocument.in/reader036/viewer/2022062314/56649f175503460f94c2e3df/html5/thumbnails/13.jpg)
Bid Package #12
Part 2 Elements• Roebling Bridge
pedestrian connector• River Walk along
Mehring Way• Pedestrian bridge at
Broadway & East Pete Rose Way
April Progress• Design of River Walk from
Steamboat Monument to Main Street underway; will submit to City in early June
• Broadway pedestrian bridge preliminary design presented to Urban Design Review Board on April 18
• Complete Stage 2 Plan to be submitted ODOT by June 11
![Page 14: PROGRESS REPORT APRIL 2012 Published May 20, 2012](https://reader036.vdocument.in/reader036/viewer/2022062314/56649f175503460f94c2e3df/html5/thumbnails/14.jpg)
Summary: Budget
• All public parties construction work has continuously operated within budget.
• Financial close out of Phase 1, now in process, is dependent on Developer’s Phase 1 housing subsidy payment being reconciled.
• Click the link below for corrected Phase 1 March 2012 final construction budget (due to close-out), Phase 2a construction budget, and TC-28 change order report as of April 30, 2012.
• http://www.thebankspublicpartnership.com/sites/default/files/budget-apr2012.pdf
![Page 15: PROGRESS REPORT APRIL 2012 Published May 20, 2012](https://reader036.vdocument.in/reader036/viewer/2022062314/56649f175503460f94c2e3df/html5/thumbnails/15.jpg)
Summary: Developer
Carter-Dawson• Residential 100% leased• Commercial 84% leased
![Page 16: PROGRESS REPORT APRIL 2012 Published May 20, 2012](https://reader036.vdocument.in/reader036/viewer/2022062314/56649f175503460f94c2e3df/html5/thumbnails/16.jpg)
Developer’s Leasing Activity
Legend refers to the following two slides.
![Page 17: PROGRESS REPORT APRIL 2012 Published May 20, 2012](https://reader036.vdocument.in/reader036/viewer/2022062314/56649f175503460f94c2e3df/html5/thumbnails/17.jpg)
Developer’s Leasing Activity
![Page 18: PROGRESS REPORT APRIL 2012 Published May 20, 2012](https://reader036.vdocument.in/reader036/viewer/2022062314/56649f175503460f94c2e3df/html5/thumbnails/18.jpg)
Developer’s Leasing Activity
![Page 19: PROGRESS REPORT APRIL 2012 Published May 20, 2012](https://reader036.vdocument.in/reader036/viewer/2022062314/56649f175503460f94c2e3df/html5/thumbnails/19.jpg)
Summary: Economic Inclusion
• Actual Small Business Enterprise (SBE) participation for Construction through 03/25/12 is 36.1% (goal is 30%)• Minority Business Enterprise (MBE): 15.9%• Women Business Enterprise (WBE): 2.8%
There are no MBE or WBE goals.
BidPackage
No.
ODOT DBE Goal
Contractor Commitment
Committed DBE
Amount*
Actual DBE Participation
Actual DBE
Amount*
5 8.0% 10.8% $618,354 12.0% $746,386
7 8.0% 10.7% $544,316 11.7% $676,741
6 5.0% 5.0% $536,229 5.4% $615,285
9 4% 4.9% $351,241 5.6% $412,761
11 8% 8.2% $1,828,156 7.8% $1,846,808
*Goal achieved if Actual DBE Amount equals or exceeds the Committed DBE Amount.
![Page 20: PROGRESS REPORT APRIL 2012 Published May 20, 2012](https://reader036.vdocument.in/reader036/viewer/2022062314/56649f175503460f94c2e3df/html5/thumbnails/20.jpg)
Economic Inclusion
• Workforce Data
• Combined Minority/Female Workforce participation is 17.44% as of 03/25/12
• Minority Workforce (female and male) is 16.15%
• Professional Services (SBE goal is 10%)• SBE: 12.8%• MBE: 11.3%• WBE: 2.6%There are no MBE or WBE goals.
![Page 21: PROGRESS REPORT APRIL 2012 Published May 20, 2012](https://reader036.vdocument.in/reader036/viewer/2022062314/56649f175503460f94c2e3df/html5/thumbnails/21.jpg)
• For the one-month period ending 03/25/12, a total of 100% of workers lived within the 15-County Cincinnati-Middletown Metropolitan Statistical Area (MSA)
• Local residency analysis 1,418 workers (through 03/25/12)• Tri-State
97.7%• Cincinnati-Middletown MSA 77.2%• Hamilton County 25.7%• City of Cincinnati 9.1%
There are no local residency participation goals.
Economic Inclusion
Click here for Economic Inclusion reports:http://thebankspublicpartnership.com/sites/default/files/economic-inclusion-apr2012.pdf
![Page 22: PROGRESS REPORT APRIL 2012 Published May 20, 2012](https://reader036.vdocument.in/reader036/viewer/2022062314/56649f175503460f94c2e3df/html5/thumbnails/22.jpg)
Summary: Safety
• The TC-28 Contractor, ESI, reports no lost-time accidents.
• Phase 1 and Phase 2a construction closed out with no lost-time accidents in over 416,000 hours worked.
![Page 23: PROGRESS REPORT APRIL 2012 Published May 20, 2012](https://reader036.vdocument.in/reader036/viewer/2022062314/56649f175503460f94c2e3df/html5/thumbnails/23.jpg)
Cincinnati Parks
![Page 24: PROGRESS REPORT APRIL 2012 Published May 20, 2012](https://reader036.vdocument.in/reader036/viewer/2022062314/56649f175503460f94c2e3df/html5/thumbnails/24.jpg)
Cincinnati Parks
![Page 25: PROGRESS REPORT APRIL 2012 Published May 20, 2012](https://reader036.vdocument.in/reader036/viewer/2022062314/56649f175503460f94c2e3df/html5/thumbnails/25.jpg)
Cincinnati Parks
![Page 26: PROGRESS REPORT APRIL 2012 Published May 20, 2012](https://reader036.vdocument.in/reader036/viewer/2022062314/56649f175503460f94c2e3df/html5/thumbnails/26.jpg)
Cincinnati Parks
• Schmidlapp Event Lawn and Stage• Welcomed many daily visitors in April• Was central gathering space for Cincinnati Reds Opening Day
celebration
• Bike Center • Interior build-out is complete• Bikes and Segways delivered in preparation for May opening
• The Smale Riverfront Park • Dedication and grand opening will be May 18
• Smale Riverfront Park Phase 3 (south of Mehring Way) • Construction of labyrinth and Black Brigade memorial continued
![Page 27: PROGRESS REPORT APRIL 2012 Published May 20, 2012](https://reader036.vdocument.in/reader036/viewer/2022062314/56649f175503460f94c2e3df/html5/thumbnails/27.jpg)
CommunicationsThe Banks Project in the News
• 14 articles mentioning The Banks appeared in April.
• http://www.thebankspublicpartnership.com/sites/default/files/media-summary-apr2012.pdf
![Page 28: PROGRESS REPORT APRIL 2012 Published May 20, 2012](https://reader036.vdocument.in/reader036/viewer/2022062314/56649f175503460f94c2e3df/html5/thumbnails/28.jpg)
Progress: March 2012
For more information:John F. Deatrick
The Banks Project Executive(513) 946-4434
http://www.thebankspublicpartnership.com