project: 11 braddock street, harwich port, ma distribution
TRANSCRIPT
Project Update #3 Project: 11 Braddock Street, Harwich Port, MA Date: 10.02.20 Distribution: Michael Monteiro (Client), Adam Titrington (ETA), Jason Ainsworth (CHN) Author: Zachary Miller (CHN)
Image #1- Pump truck and Concrete Delivery mobilized for placement of concrete grade beam. Image #2- Grade beam concrete placement including pumping, vibration, level control and troweling. Image #3- Reinforcing Steel inspection by Structures Workshop is covered by First Frame production crew. Image #4- Footing (Grade Beam) and Steel (reinforcing) inspection milestone by Town of Harwich Building Inspector
1 2
4 3
Project Update #3
6
Image #5- Grade beam forms stripped and ready for column reinforcing installation. Image #6- Column reinforcing underway and OSHA rebar cap protection maintained. Image #7- Phase 1 of 2 column pour ongoing. Stringlines are established during concrete placement to maintain plumb and level wall alignment.
7
5
Project Update #3
8
Image #8- Final concrete pump and placement for concrete foundation phase. Material and equipment for basement backfill and interior radon/drain piping has been delivered. Basement foundation prep to begin week of October 5th. Image #9- Concrete foundation placement complete. Basement prep and CMU wall installation to commence.
9