project: act acorn feasibility study acorn...1 31/05/2018 1st issue marko maver tim dumenil steve...
TRANSCRIPT
Project: ACT Acorn Feasibility Study
Terms of Use
The ACT Acorn Consortium partners reserve all rights in this material and retain full copyright. Any reference to
this material or use of the material must include full acknowledgement of the source of the material, including
the reports full title and its authors. The material contains third party IP, used in accordance with those third
party’s terms and credited as such where appropriate. Any subsequent reference to this third party material
must also reference its original source. The material is made available in the interest of progressing CCS by
sharing this ACT work done on the Acorn project.
Pale Blue Dot Energy reserve all rights over the use of the material in connection with the development of the
Acorn Project. In the event of any questions over the use of this material please contact [email protected].
D11 Infrastructure Re-use 10196ACTC-Rep-16-01
May 2018
www.actacorn.eu
Acorn
ACT Acorn, project 271500, has received funding from BEIS (UK), RCN (NO) and RVO (NL), and is co-funded by the European Commission under the ERA-Net instrument of the Horizon 2020 programme. ACT Grant number 691712.
D11 Infrastructure Re-use Contents
ACT Acorn Consortium Page 3 of 54
Contents
Document Summary
Client Research Council of Norway & Department of Business, Energy & Industrial Strategy
Project Title Accelerating CCS Technologies: Acorn Project
Title: D11 Infrastructure Re-use
Distribution: Client & Public Domain
Date of Issue: 31st May 2018
Prepared by: Marko Maver (Bellona)
Approved by: Steve Murphy, ACT Acorn Project Director
Disclaimer:
While the authors consider that the data and opinions contained in this report are sound, all parties must rely upon their own skill and judgement when using it. The
authors do not make any representation or warranty, expressed or implied, as to the accuracy or completeness of the report. The authors assume no liability for any
loss or damage arising from decisions made on the basis of this report. The views and judgements expressed here are the opinions of the authors and do not reflect
those of the client or any of the stakeholders consulted during the course of this project.
The ACT Acorn consortium is led by Pale Blue Dot Energy and includes Bellona Foundation, Heriot-Watt University, Radboud University, Scottish Carbon Capture and
Storage (SCCS), University of Aberdeen, University of Edinburgh and University of Liverpool.
Amendment Record
Rev Date Description Issued By Checked By Approved By
1 31/05/2018 1st issue Marko Maver Tim Dumenil Steve Murphy
D11 Infrastructure Re-use Contents
ACT Acorn Consortium Page 4 of 54
Table of Contents
CONTENTS ................................................................................................................................................................................................................................................... 3
1.0 EXECUTIVE SUMMARY .................................................................................................................................................................................................................... 9
2.0 INTRODUCTION .............................................................................................................................................................................................................................. 11
3.0 SCOPE ............................................................................................................................................................................................................................................. 16
4.0 THE INFRASTRUCTURE RE-USE OPPORTUNITY ....................................................................................................................................................................... 17
5.0 ATLANTIC PIPELINE ...................................................................................................................................................................................................................... 21
6.0 GOLDENEYE PIPELINE .................................................................................................................................................................................................................. 29
7.0 MGS PIPELINE ................................................................................................................................................................................................................................ 33
8.0 GENERIC KEY RISKS ..................................................................................................................................................................................................................... 37
9.0 CONCLUSIONS ............................................................................................................................................................................................................................... 39
10.0 REFERENCES ................................................................................................................................................................................................................................. 40
11.0 ANNEX 1: CO2 PHASE CHANGE AND PRESSURE DROP .......................................................................................................................................................... 42
FACTSHEET 1: RE-USE OF NORTH SEA TOPSIDE INFRASTRUCTURE FOR CO2 STORAGE ......................................................................................................... 43
FACTSHEET 2: RE-USE OF NORTH SEA PRODUCTION OIL & GAS WELLS FOR CO2 STORAGE .................................................................................................. 47
FACTSHEET 3: RE-USE OF NORTH SEA TRANSPORT INFRASTRUCTURE ...................................................................................................................................... 51
D11 Infrastructure Re-use Contents
ACT Acorn Consortium Page 5 of 54
CONTENTS ................................................................................................................................................................................................................................................... 3
TABLE OF CONTENTS .................................................................................................................................................................................................................................... 4
FIGURES ...................................................................................................................................................................................................................................................... 8
TABLES ........................................................................................................................................................................................................................................................ 8
1.0 EXECUTIVE SUMMARY .................................................................................................................................................................................................................... 9
2.0 INTRODUCTION .............................................................................................................................................................................................................................. 11
ACT ACORN OVERVIEW................................................................................................................................................................................................................... 11
ACORN DEVELOPMENT CONCEPT ..................................................................................................................................................................................................... 14
3.0 SCOPE ............................................................................................................................................................................................................................................. 16
PURPOSE ........................................................................................................................................................................................................................................ 16
SCOPE ............................................................................................................................................................................................................................................ 16
STATEMENT OF ASSUMPTIONS ......................................................................................................................................................................................................... 16
4.0 THE INFRASTRUCTURE RE-USE OPPORTUNITY ....................................................................................................................................................................... 17
RATIONALE FOR RE-USE ................................................................................................................................................................................................................... 17
DECOMMISSIONING .......................................................................................................................................................................................................................... 17
ECONOMICS OF RE-USE ................................................................................................................................................................................................................... 18
4.3.1 Preservation ......................................................................................................................................................................................................................... 19
CASE STUDIES ................................................................................................................................................................................................................................. 20
5.0 ATLANTIC PIPELINE ...................................................................................................................................................................................................................... 21
DESCRIPTION OF ASSETS ................................................................................................................................................................................................................. 21
5.1.1 Decommissioning consideration and current status .............................................................................................................................................................. 22
5.1.2 Technical specifications and operating envelopes ................................................................................................................................................................ 22
CONVERSION AND REPURPOSING REQUIREMENTS ............................................................................................................................................................................. 24
5.2.1 Regulatory requirements ........................................................................................................................................................................................................ 25
D11 Infrastructure Re-use Contents
ACT Acorn Consortium Page 6 of 54
5.2.2 Internal and external inspection ............................................................................................................................................................................................. 25
RATIONALE FOR PRESERVATION ....................................................................................................................................................................................................... 26
5.3.1 Estimates of cost .................................................................................................................................................................................................................... 26
Re-use vs. new pipeline ....................................................................................................................................................................................................................... 27
5.3.2 Key risks ................................................................................................................................................................................................................................. 28
6.0 GOLDENEYE PIPELINE .................................................................................................................................................................................................................. 29
DESCRIPTION OF ASSETS ................................................................................................................................................................................................................. 29
6.1.1 Decommissioning consideration and current status .............................................................................................................................................................. 30
6.1.2 Technical specifications and operating envelopes ................................................................................................................................................................ 30
CONVERSION AND REPURPOSING REQUIREMENTS ............................................................................................................................................................................. 31
RATIONALE FOR PRESERVATION ....................................................................................................................................................................................................... 31
6.3.1 Estimates of costs .................................................................................................................................................................................................................. 31
6.3.2 Key risks ................................................................................................................................................................................................................................. 32
7.0 MGS PIPELINE ................................................................................................................................................................................................................................ 33
DESCRIPTION OF ASSETS ................................................................................................................................................................................................................. 33
7.1.1 Decommissioning consideration and current status .............................................................................................................................................................. 33
7.1.2 Technical specifications and operating envelopes ................................................................................................................................................................ 34
CONVERSION AND REPURPOSING REQUIREMENTS ............................................................................................................................................................................. 34
RATIONALE FOR PRESERVATION ....................................................................................................................................................................................................... 35
7.3.1 Estimates of costs .................................................................................................................................................................................................................. 35
7.3.2 Key risks ................................................................................................................................................................................................................................. 36
8.0 GENERIC KEY RISKS ..................................................................................................................................................................................................................... 37
TECHNICAL AND OPERATIONAL RISKS ................................................................................................................................................................................................ 37
LEGAL AND LIABILITY CONSIDERATIONS ............................................................................................................................................................................................. 37
9.0 CONCLUSIONS ............................................................................................................................................................................................................................... 39
D11 Infrastructure Re-use Contents
ACT Acorn Consortium Page 7 of 54
10.0 REFERENCES ................................................................................................................................................................................................................................. 40
11.0 ANNEX 1: CO2 PHASE CHANGE AND PRESSURE DROP .......................................................................................................................................................... 42
CO2 PHASE CHANGE ....................................................................................................................................................................................................................... 42
CO2 PRESSURE DROP ..................................................................................................................................................................................................................... 42
FACTSHEET 1: RE-USE OF NORTH SEA TOPSIDE INFRASTRUCTURE FOR CO2 STORAGE ......................................................................................................... 43
FACTSHEET 2: RE-USE OF NORTH SEA PRODUCTION OIL & GAS WELLS FOR CO2 STORAGE .................................................................................................. 47
FACTSHEET 3: RE-USE OF NORTH SEA TRANSPORT INFRASTRUCTURE ...................................................................................................................................... 51
D11 Infrastructure Re-use Contents
ACT Acorn Consortium Page 8 of 54
Figures
FIGURE 2-1: ACT ACORN CONSORTIUM PARTNERS .......................................................................................................................................................................................... 11
FIGURE 2-2: KEY AREAS OF INNOVATION ......................................................................................................................................................................................................... 12
FIGURE 2-3: ACT ACORN WORK BREAKDOWN STRUCTURE .............................................................................................................................................................................. 12
FIGURE 2-4: ACORN OUTLINE MINIMUM VIABLE DEVELOPMENT PLAN ............................................................................................................................................................... 14
FIGURE 2-5: ACORN BUILD OUT SCENARIO FROM THE 2017 PCI APPLICATION ................................................................................................................................................... 15
FIGURE 4-1: REUSING PIPELINES (VALUES PER KM): (BENTON, 2015). .............................................................................................................................................................. 19
FIGURE 5-1 ATLANTIC AND CROMARTY FIELD LAYOUT (BG GROUP, 2016) ....................................................................................................................................................... 22
FIGURE 5-2 AN EXAMPLE OF AN "INTELLIGENT PIG" INSPECTING PIPELINE CONDITION (INTERTEK, 2016) ........................................................................................................... 26
FIGURE 6-1 GOLDENEYE PIPELINE FROM ST FERGUS TO GOLDENEYE PLATFORM (SHELL, 2016) ...................................................................................................................... 31
FIGURE 7-1 LOCATION OF THE MILLER PLATFORM (BP, 2011) ......................................................................................................................................................................... 34
FIGURE 7-2: LOCATION OF NORTH WEST HUTTON: (JEE, 2014) ....................................................................................................................................................................... 36
FIGURE 11-1: CO2 PHASE CHANGES (GLOBAL CCS INSTITUTE, 2013) ............................................................................................................................................................. 42
Tables
TABLE 1-1 SUMMARY OF PIPELINE SPECIFICATIONS ......................................................................................................................................................................................... 10
TABLE 2-1: ACT MILESTONES AND DELIVERABLES .......................................................................................................................................................................................... 13
TABLE 5-1 ATLANTIC PIPELINE SPECIFICATIONS .............................................................................................................................................................................................. 24
TABLE 5-2: ADDITIONAL 8KM PIPELINE SPECIFICATIONS .................................................................................................................................................................................... 24
TABLE 5-3 CAPTAIN X DEVELOPMENT - TRANSPORT CAPEX (BASE CASE) ......................................................................................................................................................... 27
TABLE 5-4 CAPTAIN X DEVELOPMENT - TRANSPORT CAPEX (NEW PIPELINE SYSTEM) ....................................................................................................................................... 27
TABLE 6-1 GOLDENEYE PIPELINE SECIFICATIONS ............................................................................................................................................................................................ 30
TABLE 7-1 MGS PIPELINE SPECIFICATIONS .................................................................................................................................................................................................... 34
TABLE 11-1: ST FERGUS TO CAPTAIN NUI PIPELINE PRESSURE DROP .............................................................................................................................................................. 42
D11 Infrastructure Re-use Executive Summary
ACT Acorn Consortium Page 9 of 54
1.0 Executive Summary
The purpose of this deliverable is to consider the rationale for the preservation
of the Atlantic, Goldeneye, and Miller Gas System (MGS) pipelines, all of which
are currently under an Interim Pipeline Regime (IPR) awaiting decommissioning.
By examining the pipeline’s operating envelopes and technical specifications,
conversion/re-purposing requirements, estimated re-purposing/conversion
costs and key risks, as well as the views and needs of key stakeholders, this
report brings awareness to the infrastructure owners and relevant authorities of
the potential future value of the three pipelines.
Considering expanded decommissioning of the infrastructure in the North Sea,
including pipelines there is now a significant, low-cost opportunity to provide
additional value to these assets through their re-use. Delaying decommissioning
and re-using existing infrastructure offers lower decommissioning costs and
significant cost savings to CCS project developers. In addition, it can enable
smaller industrial players that might otherwise not be able to justify stand-alone
projects, to take up CCS. Preservation, however, will not occur without
government support and appropriate compensation given to the asset owners
for costs incurred due to prolongation of asset life (i.e. for any changes in costs,
liabilities, tax allowance, etc.).
The potential for re-use of existing pipelines as compared to building new ones
for CCS projects is determined by the cost vs. risk trade-off. While the risks
appear higher with existing pipelines, the costs are lower. The risks are believed
to be manageable, which together with the lower associated conversion/re-
purposing costs should outweigh the higher costs of building new pipelines and
infrastructure.
Overall cost estimates for the entire North Sea infrastructure
decommissioning up to year 2050 amounts to approximately
£47bn (€53bn, in today’s money), with an uncertainty of +/- 40%
(Oil & Gas Authority, 2016).
Between 2016 and 2025, the cost of planned decommissioning of
580 pipelines, in the Central and Northern North Sea, with a length
of 3,700km is estimated at £847m (€947m), which amounts to
£1.46m (€1.63m) per pipeline (including associated infrastructure
such as umbilicals & infield lines), or £225k (€251m) per km.
Pipeline decommissioning risks losing larger future value arising
from infrastructure re-use. Preservation and re-use offers a
significant opportunity and cost savings for CCS project
developers: up to 75% lower capital expenditure costs.
Currently, the three most suitable pipelines for re-use in the North
Sea include: the Atlantic pipeline, the Goldeneye pipeline, and the
MGS pipeline. All three pipelines have been preserved in-situ and
are awaiting decommissioning.
The key path to preservation of the pipelines, as identified by the
pipeline owners/operators, has been the removal or transfer of
liabilities and/or appropriate compensation for preservation.
D11 Infrastructure Re-use Executive Summary
ACT Acorn Consortium Page 10 of 54
The Atlantic pipeline is well placed for preservation given its technical and
operational specifications, particularly its large wall thickness, which gives it a
high-pressure rating and therefore a better tolerance to the pressures needed
for CO2 transport.
Previous studies on the Goldeneye pipeline, have shown the pipeline is
suitable for dense phase CO2 transportation, within its operational parameters.
The MGS pipeline, offers potential for future high-volume CO2 transport. It is in
good condition and although other infrastructure (i.e. platforms, topsides, wells)
of the Miller field are not considered for re-use, the pipeline is re-usable.
Name Length
(km) Diameter
(m)
Design Pressure
(barg)
Capacity (up to: MT/yr)
Remaining Age (years)
Atlantic 79.2 0.46 (18”) 170 3-5 ~6-10
Goldeneye 101 0.51 (20”) 125 2-4 ~8-10
Miller 240 0.76 (30”) 174 10 ~10
Table 1-1 Summary of Pipeline Specifications
D11 Infrastructure Re-use Introduction
ACT Acorn Consortium Page 11 of 54
2.0 Introduction
ACT Acorn Overview
ACT Acorn, project 271500, has received funding from BEIS (UK), RCN (NO)
and RVO (NL), and is co-funded by the European Commission under the ERA-
Net instrument of the Horizon 2020 programme. ACT grant number 691712.
ACT Acorn is a collaborative project between seven organisations across
Europe being led by Pale Blue Dot Energy in the UK, as shown in Figure 2-1.
Figure 2-1: ACT Acorn consortium partners
The research and innovation study addresses all thematic areas of the ACT Call
including ‘Chain Integration’. The project includes a mix of both technical and
non-technical innovation activities as well as leading edge scientific research.
Together these will enable the development of the technical specification for an
ultra-low cost, integrated CCS hub that can be scaled up at marginal cost. It will
move the Acorn development opportunity from proof-of-concept (TRL3) to the
pre-FEED stage (TRL5/6) including iterative engagement with relevant investors
in the private and public sectors.
Specific objectives of the project are to:
1. Produce a costed technical development plan for a full chain CCS
hub that will capture CO2 emissions from the St Fergus Gas
Terminal in north east Scotland and store the CO2 at an offshore
storage site (to be selected) under the North Sea.
2. Identify technical options to increase the storage efficiency of the
selected storage site based on scientific evidence from
geomechanical experiments and dynamic CO2 flow modelling and
through this drive scientific advancement and innovation in these
areas.
3. Explore build-out options including interconnections to the nearby
Peterhead Port, other large sources of CO2 emissions in the UK
region and CO2 utilisation plants
4. Identify other potential locations for CCS hubs around the North
Sea regions and develop policy recommendations to protect
relevant infrastructure from premature decommissioning and for
the future ownership of potential CO2 stores.
D11 Infrastructure Re-use Introduction
ACT Acorn Consortium Page 12 of 54
5. Engage with CCS and low carbon economy stakeholders in Europe
and worldwide to disseminate the lessons from the project and
encourage replication.
CCS is an emerging industry. Maturity improvements are required in the
application of technology, the commercial structure of projects, the scope of
each development and the policy framework.
The key areas of innovation in which the project will seek insights are
summarised in Figure 2-2.
Figure 2-2: Key areas of innovation
The project activity has been organised into 6 work packages as illustrated in
Figure 2-3. Specific areas being addressed include; regional CO2 emissions; St
Fergus capture plant concept; CO2 storage site assessments and development
plans; reservoir CO2 flow modelling, geomechanics; CCS policy development;
infrastructure re-use; lifecycle analysis; environmental impact; economic
modelling; FEED and development plans; and build out growth assessment.
The project will be delivered over a 19-month period, concluding on the 28th
February 2019. During that time, it will create and publish 21 items known as
Deliverables. Collectively these will provide a platform for industry, local
partnerships and government to move the project forward in subsequent
phases. It will be driven by business case logic and inform the development of
UK and European policy around infrastructure preservation. The deliverables
are listed in
Figure 2-3: ACT Acorn work breakdown structure
D11 Infrastructure Re-use Introduction
ACT Acorn Consortium Page 13 of 54
Milestone Deliverable
1) St Fergus Hub Design
D01 Kick-off Meeting Report
D02 CO2 Supply Options
D17 Feeder 10 Business Case
2) Site Screening & Selection
D03 Basis of Design for St Fergus Facilities
D04 Site Screening Methodology
D05 Site Selection Report
D13 Plan and Budget for FEED
3) Expansion Options D18 Expansion Options
4) Full Chain Business Case
D10 Policy Options Report
D11 Infrastructure Re-use Report
D14 Outline Environmental Impact Assessment
D15 Economic Model and Documentation
D16 Full Chain Development Plan and Budget
5) Geomechanics D06 Geomechanics Report
D07 Acorn Storage Site Storage Development Plan and Budget
6) Storage Development Plans D08 East Mey Storage Site Storage Development Plan and Budget
D09 Eclipse Model Files
7) Lifecycle Assessment D12 Carbon Lifecycle Analysis
8) Project Completion
D21 Societal Acceptance Report
D19 Material for Knowledge Dissemination Events
D20 Publishable Final Summary Report
Table 2-1: ACT Milestones and Deliverables
D11 Infrastructure Re-use Introduction
ACT Acorn Consortium Page 14 of 54
The Consortium includes a mix of industrial, scientific and CCS policy experts in
keeping with the multidisciplinary nature of the project. The project is led by Pale
Blue Dot Energy along with University of Aberdeen, University of Edinburgh,
University of Liverpool, Heriot Watt University, Scottish Carbon Capture &
Storage (SCCS), Radboud University and The Bellona Foundation. Pale Blue
Dot Energy affiliate CO2DeepStore are providing certain input material.
Acorn Development Concept
Many CCS projects have been burdened with achieving “economies of scale”
immediately to be deemed cost effective. This inevitably increases the initial cost
hurdle to achieve a lower lifecycle unit cost (be that £/MWh or £/T) which raises
the bar from the perspectives of initial capital requirement and overall project
risk.
The Acorn development concept use a Minimum Viable Development (MVD)
approach. This takes the view of designing a full chain CCS development of
industrial scale (which minimises or eliminates the scale up risk) but at the lowest
capital cost possible, accepting that the unit cost for the initial project may be
high for the first small tranche of sequestered emissions.
Acorn will use the unique combination of legacy circumstances in North East
Scotland to engineer a minimum viable full chain carbon capture, transport and
offshore storage project to initiate CCS in the UK. The project is illustrated in
Figure 2-4 and seeks to re-purpose an existing gas sweetening plant (or build a
new capture facility if required) with existing offshore pipeline infrastructure
connected to a well understood offshore basin, rich in storage opportunities. All
the components are in place to create an industrial CCS development in North
East Scotland, leading to offshore CO2 storage by the early 2020s.
Figure 2-4: Acorn Outline Minimum Viable Development Plan
D11 Infrastructure Re-use Introduction
ACT Acorn Consortium Page 15 of 54
A successful project will provide the platform and improve confidence for further
low-cost growth and incremental development and will provide a cost effective
practical stepping stone from which to grow a regional cluster and an
international CO2 hub.
The seed infrastructure can be developed by adding additional CO2 capture
points such as from hydrogen manufacture for transport and heat, future CO2
shipping through Peterhead Port to and from Europe and connection to UK
national onshore transport infrastructure such as the Feeder 10 pipeline which
can bring additional CO2 from emissions sites in the industrial central belt of
Scotland including the proposed Caledonia Clean Energy Project, CCEP. A build
out scenario for Acorn used in the 2017 Projects of Common Interest (PCI)
application is included as Figure 2-5.
Pale Blue Dot Energy is exploring various ways and partners to develop the
Acorn project.
Figure 2-5: Acorn build out scenario from the 2017 PCI application
D11 Infrastructure Re-use Scope
ACT Acorn Consortium Page 16 of 54
3.0 Scope
Purpose
The purpose of this deliverable is to increase awareness for owners and relevant
authorities of the infrastructure re-use potential and future value of one or more
of the three redundant oil and gas pipelines considered for CO2 transportation
from the St. Fergus Gas Terminal in northeast Scotland.
Scope
The scope of this deliverable includes:
• Literature review,
• Description of the existing assets,
• Defining operating envelopes and technical/functional specifications,
• Outlining conversion / re-purposing requirements,
• Developing, in consultation with relevant authorities and operators,
a preservation strategy for infrastructure enabling the Acorn project,
• Estimation of costs for re-use versus decommissioning,
• Assessment of key risks,
• Interview with and documentation of views/needs of key
stakeholders,
• Making a rationale for preservation.
Statement of Assumptions
The assumptions detailed in this section apply to the Acorn Project under the
ACT ERA-NET funding package. For future Acorn project development, these
assumptions may be revised.
Infrastructure
• The infrastructure re-use potential is focussed on the St. Fergus site
and three redundant oil and gas offshore pipelines: Atlantic,
Goldeneye and MGS.
Data
• The most recent data available in the public domain is considered,
including but not limited to, decommissioning programmes and
Environmental Impact Assessments (EIA’s) for the three pipelines.
• Data on cost estimates of decommissioning have been difficult to
obtain due to privacy issues. They have been provided by the
operators to BEIS in confidence. All effort was made to obtain the
most relevant and up-to-date data.
Exclusions
• The interest within this work is centred on the pipelines, and not with
any associated infrastructure (i.e. platforms, wells, umbilicals, etc.),
due to technical and commercial reasons. Wells, for example, have
either been suspended which makes them unusable, or there are
questions/issues with their design, high operating costs or limited
life.
D11 Infrastructure Re-use The Infrastructure Re-use Opportunity
ACT Acorn Consortium Page 17 of 54
4.0 The Infrastructure Re-use Opportunity
Rationale for re-use
Maturing of many major oil and gas fields, combined with the lack of significant
new discoveries and a sustained period of low oil and gas prices, has in recent
years increased interests in decommissioning of existing assets in the UK
Continental Shelf (UKCS). Furthermore, ongoing uncertainty and volatility in
commodity prices has depressed the level of new capital invested in the UKCS.
At the same time the oil and gas industry has turned towards the application of
the circular economy principles, whereby possibilities of enhancing economic
value in existing assets and reducing environmental disturbance1 generated
during decommissioning are sought. The UK’s strategy for maximising
economic recovery (MER), (Oil & Gas UK, 2016), is a formal example of the
application of such principles. Ways in which the oil and gas industry is applying
these principles, aside from recycling, includes assessing potential opportunities
for the re-use of platforms, wells and pipeline assets, including their associated
infrastructure. The re-use of platforms and wells has been part of the oil and gas
industry’s efforts for some time, re-use of pipelines, with the purpose of
transporting of CO2 for storage, is by some still considered to be in its early
development stages (Benton, 2015). Pipeline re-use in the North Sea, however,
1 Albeit it is recognized that these assets will at some point have to be decommissioned, however, the statement is based on the premise that more efficient disposal/decommissioning techniques will have been discovered/implemented by then.
2 This includes inputs provided by 34 operators for all current and proposed offshore facilities, pipelines, development wells, suspended open water exploration and appraisal wells and onshore
is still uncommon. As such, the focus of this report is on presenting the rationale
and opportunities for the re-use of pipelines for CO2 transportation and storage.
Decommissioning
Reasons for decommissioning vary: some companies delay the process due to
cash-flow constraints, while others increase field life through improvement
efficiencies, delaying decommissioning. Conversely, some companies are
expediting their decommissioning as it becomes cheaper to do so at lower
prices. In any case, decommissioning in the North Sea has been growing, with
£0.8bn (€0.9bn) in 2014, and £1.1bn (€1.4bn) spent on decommissioning in
2014 and 2015 respectively (Oil & Gas Authority, 2016). There are currently over
250 fixed installations, over 250 subsea production systems, over 3,000
pipelines and approximately 5,000 wells in the UKCS, all of which will be
required to be decommissioned.
Overall cost estimates for North Sea decommissioning up to 2050 amount to
approximately £47bn (€53bn), with an uncertainty of +/- 40% (Oil & Gas
Authority, 2016). Other studies have put these estimates at £59.7bn (€68bn) in
2016 prices2, with costs amounting to anywhere between £1.07bn (€1.2bn) and
£2.6bn (€2.9bn) per year, rising on average by 14% per year, and overall costs
terminals. The cost estimate takes into account the wide range of uncertainties of industry class 5 and 4 estimates as submitted by operators as part of the 2016 UKCS Stewardship Survey (Oil & Gas Authority, 2017). Note: The estimates made in the past, including that by CRF in 2016, have been done using different methodologies and scopes, so the results are not directly comparable.
D11 Infrastructure Re-use The Infrastructure Re-use Opportunity
ACT Acorn Consortium Page 18 of 54
potentially reaching over £17bn (€19bn) between now and 2020, and £47bn
(€52.4bn) by 2040.3
The current UK tax regime enables oil and gas companies operating in the
UKCS to reclaim a significant portion of their decommissioning expenditure as
tax refunds. 50% - 75% of total decommissioning costs in the UKCS could be
footed by the UK government and taxpayers (CRF, 2016). There is an interest
from government and industry to lower decommissioning costs., and the OGA’s
2016 Decommissioning Strategy and its 2017 UKCS Decommissioning Cost
Estimate Report set a target to reduce these costs by 35%. In this respect, a
strategic and comprehensive, rather than piece-meal and ad-hoc approach to
decommissioning is encouraged by the UK government (Oil & Gas Authority,
2017). Furthermore, the recently proposed changes to the UK’s
decommissioning tax relief regime, which will take effect from 1 November 2018,
are set to allow for the transfer of tax history4 onto the buyer of an existing asset,
who would then be able to utilise the transferred tax history to trigger a
repayment of tax paid by the previous owner. Put simply, the new owner of the
asset would, to an extent, be able to claim back the decommissioning costs. The
goal is to encourage investment into late-life assets in the North Sea and thereby
maximise economic recovery (Thomas, 2017).
Between 2016 and 2025, operators in the North Sea intend to decommission
around 17% of the total pipeline network from the UK and Norwegian
3 Over 85% of the decommissioning costs are associated with well abandonment and topside removal, while the rest being related to project management and monitoring, subsea and site remediation, and topside and substructure reuse/recycling. The latter amounts to only 1% of overall decommissioning costs. 4 The new owner would be able to utilize the transferred tax history to trigger a repayment of tax paid by the previous owner. The transferred tax history would apply only to the supplementary charge and the ring fence corporation tax, but not petroleum revenue tax.
Continental Shelves, or 850 pipelines with a total length of nearly 7,500 km.
While the central North Sea hosts the largest number of these pipelines (484)5,
the southern North Sea and Irish Sea will see the largest proportion of the total
pipeline length, 3,426km, be decommissioned (Oil & Gas Authority, 2016). Cost
of planned decommissioning of 580 pipelines with a length of 3,700km is
estimated at £847m (€947m), which amounts to £1.46m (€1.63m) per pipeline
(including associated infrastructure such as umbilicals & infield lines), or £225k
(€251m) per km.
The capital expenditure on decommissioning may result in fewer investments
into other value generating activities. Delaying decommissioning can also
provide opportunities for innovation, cost reduction and development of UK skills
and capabilities (Oil & Gas Authority, 2016). Preservation and re-use of the
infrastructure awaiting decommissioning for use in other projects, such as CCS,
is an opportunity that could reduce the costs, both for taxpayers and companies.
Taking advantage of such opportunities, which can be limited by the
repurposing/conversion costs and lifetime limitations can only be achieved
through a successful collaboration between the government and the
industry/operators.
Economics of re-use
Essentially, repurposing pipelines for CO2 transport would eliminate the cost of
removing/decommissioning them. Studies also show that the re-use of pipeline
5 Southern North Sea and Irish Sea includes 200 pipelines, while Northern North Sea has 96 pipelines set for decommissioning, which makes the total number of pipelines set for decommissioning in the UK by 2025 780, while in Norway this number is at 6 (Oil & Gas Authority, 2016).
D11 Infrastructure Re-use The Infrastructure Re-use Opportunity
ACT Acorn Consortium Page 19 of 54
could be worth five times, or more, the scrap value of the steel, if reusing the
pipelines means that new ones do not have to be built (Benton, 2015).
As an integrated transport and storage network offers a significant contribution
to cost reduction for CCS, reusing pipeline infrastructure, as part of an integrated
network would drive down costs even further. Economics of re-use also depend
on the linking up of multiple CO2 sources. In this respect, intra-industry and
government collaboration will be key (Benton, 2015).
The economics of reusing existing pipelines versus building a new one tends to
be favourable towards the former. As the Captain X CO2 storage development
(Pale Blue Dot Energy & Axis Well Technology, 2016) research has shown,
capital expenditure (Capex) for utilising the 79km 16” Atlantic and Cromarty
(Atlantic) pipeline, would amount to £37.7m (€42.8m), while construction of a
new pipeline would cost £135.4m (€152m). This included building a new 8km
pipeline from the Atlantic manifold to the Captain X NUI which were required
both in the re-use and new case scenarios (Pale Blue Dot Energy & Axis Well
Technology, 2016) (see Section 5.3.1 Estimates of cost).
It is worth noting that there is little operating cost associated with pipelines that
are currently under the IPR, apart from regular inspection. Since detailed costs
are difficult to obtain, it can be estimated that these are somewhere in the range
of £100k (€113.5k) per year. In addition, repurposing costs of an existing
pipeline only include various commissioning type duties, such as drying the
pipeline or running an intelligent pig, which could cost in ranges of £2m-3m
(€2.3m-€3.4m) and/or £2m-4m (€2.3m-€4.5m) respectively.
It is worth nothing that economics of re-use for a pipeline should be assessed
on a case-by-case basis and depends on the willingness of the pipeline owner
to transfer ownership, and the possibility of transferring tax relief on
decommissioning costs on the sale of the asset.
4.3.1 Preservation
Depending on flow rate, width, length, and material of the pipeline, as well as
other factors such as the cost of steel and current scrap value prices, re-use of
pipelines for CCS could be worth significantly more than its scrap value or re-
use for construction.
Figure 4-1: Reusing pipelines (values per km): (Benton, 2015).
Preservation is warranted if the value of preservation is greater than the value
of deferring the decommissioning of the pipeline. The cost of planned
decommissioning of 580 pipelines with a length of 3,700km in the central and
northern North Sea is estimated at £847m (€947m), which amounts to £1.46m
(€1.63m) per pipeline (including associated infrastructure such as umbilicals &
infield lines), or £225k (€251m) per km. After speaking with a number of
D11 Infrastructure Re-use The Infrastructure Re-use Opportunity
ACT Acorn Consortium Page 20 of 54
representatives from the oil and gas industry, such estimates are fairly
consistent.
If decommissioning is deferred, the operational costs of monitoring and
maintenance are low, at approximately £100k (€113.5k) per year. These costs
depend on the length and condition of each pipeline in particular. In addition,
operational expenditure (Opex) costs during deferral period are likely to be
higher in cases where the pipelines are connected to a platform. Deferral,
however, cannot be held in perpetuity, as with each passing year, the design life
of the pipeline decreases. If decommissioning (costs) can be avoided, small
Opex costs (of £100k/yr) would warrant preservation for some time (even when
taking into account inflation and discounting). Detailed assessments would have
to be performed on a case-by-case basis.
Case studies
The re-use of legacy assets such as topsides, wells and pipelines can offer
significant cost savings and an efficient approach to facilitating wider CCS
deployment, considering the initial cost hurdles faced by many CCS projects to
date. Failure to preserve this infrastructure and leave it to be decommissioned
could result both in a waste of public and private funds as well as further delay
in the deployment of CCS in the UK and Europe. Three factsheets, in Annexes
2, 3 and 4 have been produced to further promote the re-use of existing
infrastructure:
• Re-use of North Sea Transport Infrastructure for CO2 Storage
• Re-use of North Sea Topside Infrastructure for CO2 Storage
• Re-use of North Sea Production Oil & Gas Wells for CO2 Storage
This report focuses on the re-use potential of three existing and strategically
important pipelines: the Atlantic pipeline, the Goldeneye pipeline, and the Miller
Gas System (MGS) pipeline. All three are near St. Fergus gas terminal,
northeast of Aberdeen, Scotland, and are being considered for re-use as part of
project Acorn. This report is focused specifically on the re-use potential of the
three pipelines, and not the associated infrastructure (i.e. umbilicals, wells,
platforms, etc.), although this is considered and mentioned.
As such, the goal of this deliverable is not to select any one or more of the three
pipelines but to present a case for their preservation and potential re-use. In this
respect, the report provides a brief description of the assets, including their
history, design, specifications and status. It then goes on to examine any
potential conversion and re-purposing requirements, as well as key risks. Where
available, estimates of costs are provided as well the as views and needs of key
stakeholders.
D11 Infrastructure Re-use Atlantic Pipeline
ACT Acorn Consortium Page 21 of 54
5.0 Atlantic Pipeline
Description of assets
The 79.2km long Atlantic production pipeline6, installed in 2006, is connected to
the Atlantic manifold7 as part of the Atlantic and Cromarty (A&C) fields, which
comprises three wells (two at the Atlantic and one at the Cromarty field). The
Atlantic field is operated by a consortium BG Global Energy Limited (BG) and
the Cromarty field is operated by Hess Limited. In February 2016, BG Group
was acquired by Shell, making it the de facto owner and operator of the assets.
The fields are in the outer Moray Firth in the UK Continental Shelf (UKCS),
approximately 79km northeast from the St. Fergus gas terminal (see Figure 5-1
below). There are six pipeline crossings along the route from St. Fergus to the
Atlantic manifold.
The A&C fields and the infrastructure were installed in 2005, and production
started in 2006. Although the production was anticipated to last five years, it
ceased in 2009. Following another failed attempt to restart/re-use production
wells in 2010, a Cessation of Production (CoP) was agreed with the OGA in
2011. The three wells have not been abandoned, but have been suspended (i.e.
6 This includes the PL2029 production pipeline and a piggy - backed MEG pipeline (PL2031). The latter is not subject to reuse consideration as it is likely that a new control pipeline would be installed. The production pipeline is 0.46m (18”) in diameter from the landfall to 1.2km and thereafter 0.41m (16”) diameter. A large majority of the pipeline is buried in trenches of over 0.6m in depth, or by rock cover (BG Group, 2016). 7 The Atlantic manifold is a subsea manifold, through which gas was exported from two Atlantic Field and one Cromarty Field wells, via the Atlantic production export pipeline to the Scottish Area Gas Evacuation (SAGE) terminal at the St. Fergus gas plant. The MEG was supplied to the offshore wells via a 0.10m (4”) pipeline from St. Fergus and was injected into the export pipeline to inhibit the potential formation of hydrates. The Atlantic manifold is considered CO2 compatible. As
cement plugs are set, however with the completion, well head and tree still in
place) (BG Group, 2016) Most of the pipelines were flushed and cleaned of
hydrocarbons and disconnected from the wells in 2012, which were suspended
and plugged in June/July of 20148. Only the Atlantic export pipeline and the
monoethylene glycol (MEG) lines were placed under an Interim Pipeline Regime
(IPR)9 for a period of five years, to allow for potential re-use consideration.10
Although the initial five-year IPR period for the Atlantic pipeline ran out in
December 2016, Shell, who operate the pipeline, were given consent for an
additional five-year period under IPR, to 2021. This does not oblige them to
retain the pipeline until that date but provides flexibility as to when within that
period the pipeline is decommissioned.
The additional period under IPR was in part due to Project Acorn and successful
cooperation and coordination between Scottish Government, project operators
and other key stakeholders to retain the pipeline for CCS use.
part of the draft decommissioning programme it is also considered to be decommissioned and moved to shore for recycling (BG Group, 2016). 8 The plugging and abandonment of the three wells was completed as per DECC (now BEIS) requirements and in compliance with the Oil & Gas Guidelines on suspension and abandonment of wells (Oil & Gas UK, 2009). 9 Under section 29 of the Petroleum Act of 1998, an interim pipeline regime, essentially defers a full decommissioning programme until other options are explored that might extend the useful life of a field. 10 Reuse options explored included the use of the reservoirs for gas and CO2 storage, and the sale of the facilities and infrastructure to other oil and gas companies, none of which have been deemed commercially viable.
D11 Infrastructure Re-use Atlantic Pipeline
ACT Acorn Consortium Page 22 of 54
Figure 5-1 Atlantic and Cromarty Field Layout (BG Group, 2016)
5.1.1 Decommissioning consideration and current status
BG Group prepared an environmental impact assessment (EIA) and the
decommissioning programme11 for off-shore installations and pipelines at A&C
fields. In its comparative assessment, which considered environmental,
technical, societal and cost implications of the feasible decommissioning
options, it found that most of the pipeline and umbilicals associated with offshore
11 Decommissioning options compared included a “do nothing” option, a “total removal” option and “partial removal” options. The options were compared in terms of defined, weighted criteria for safety (40%), environmental impact (20%), technical feasibility (10%), societal disturbance (15%), and relative cost (15%) (BG Group, 2016).
development, which are trenched and buried at depth of 0.6m below the seabed
surface, should be left in place. The EIA also identified that following stakeholder
engagement with the Joint Nature Conservation Committee (JNCC) it was
suggested that disturbance of the habitat in the area where the pipeline is buried
would be undesirable because it would initiate a further recovery period12.
Removal of the sub-seabed infrastructure, including much of the Atlantic export
pipeline route which passes through possible marine protected area, would have
impacted the surrounding ecosystem and biodiversity.
If decommissioned, the pipelines would be disconnected from the Atlantic
manifold, cut and removed where they emerge from the seabed, with remedial
rock cover applied to the cut ends to mitigate the risk of snagging by other sea
users. This would effectively render the pipeline impossible to re-use. In
addition, the Atlantic manifold, which is connected to the two Atlantic wells and
one Cromarty well, is waiting to be decommissioned and brought onshore for
recycling.
While the A&C draft decommissioning plan explored re-use options for the
Atlantic pipeline and deemed them commercially unviable, the pipeline itself
remains by and large suitable and re-usable for CO2 transport. The pipeline
remains under IPR until the end of 2021.
5.1.2 Technical specifications and operating envelopes
The following section provides the technical specifications for the Atlantic export
pipeline from St. Fergus to the Atlantic Manifold.
12 Within the scope of the EIA, the relative impacts on the marine environment, atmospheric emissions, stakeholder concerns and legacy issues of leaving the pipelines in place were taken into account (BG Group, 2016).
D11 Infrastructure Re-use Atlantic Pipeline
ACT Acorn Consortium Page 23 of 54
The allowable design parameters depend on the mass flow rate – the amount
of CO2 per annum. In other words, the larger the mass flow rate, the larger the
pressure drop and operating pressure allowed. The pipeline was designed for a
pressure of up to 170barg, which with its 15.5mm wall thickness, including a
3mm corrosion allowance has a design life of 20 years. Such design pressure
allowance means the CO2 can be transported over the distance of the pipeline
in a dense phase. A study by Pale Blue Dot Energy (Pale Blue Dot Energy &
Axis Well Technology, 2016) on the re-use potential of the pipeline for use in the
Captain X field also looked at various mass flow rate scenarios and the impact
of pressure drop (see Annex 1: CO2 Phase Change and Pressure Drop)
throughout the length of the pipeline. It found that even in the case of an
increased mass flow rate of 5 MTpa, the pressure drop is 32bar, with the MOP
being close to 180. This would exceed the original design pressure, however,
given the pipelines wall thickness and the fact that it was in service for less than
four years before being suspended, the pipeline could be re-rated for CO2
service at such high pressure (i.e. 180bar). The study also found that the
pipeline was designed for a 20-year life and was given a 3mm corrosion
allowance for wet hydrocarbon transport. On the other hand, in the case of dry
CO2 transport, the corrosion allowance would likely be reduced to 1mm and
minimum required wall thickness to approximately 13.2mm. Consequently, the
design life for a new duty might be different. In this case, a full pipeline integrity
and life extension studies would have to be performed to confirm the suitability
of the pipeline for CO2 transport.
Worth noting is that an internal epoxy coating has been applied during its
installation in order to improve the flow and reduce commissioning works.
Although tests have shown that the coating is resistant to dense phase CO2,
long term testing may be required to ensure that no spalling or disbondment
have occurred.
A key advantage identified by a number of stakeholders for the Atlantic pipeline
for CO2 transportation is its wall thickness, which gives it a high pressure rating
and consequently a better tolerance to the pressures needed for CO2 transport.
D11 Infrastructure Re-use Atlantic Pipeline
ACT Acorn Consortium Page 24 of 54
Parameter Value
PL ID (DECC) PL-2029
Length 79km
Design Life 20years
Outer Diameter 406.4mm (16 in)
Installation S-Lay (Trenched and Buried/Rockdump)
Wall thickness 15.5mm
Crossings 7
Material X65 Carbon Steel HFW (high frequency welded)
Corrosion Allowance 3mm
External Coating Concrete weight coating 40-60mm thick
Internal Coating 0.075mm internal thin film epoxy coating
Design Pressure 170barg
Design Temperature 60 / -10°C
Operating Temperature
50°C
Table 5-1 Atlantic Pipeline Specifications
Parameter Value
Length 8km
Outer Diameter 406.4mm (16 in)
Wall thickness 14.3mm
Material X65 Carbon Steel HFW (high frequency welded)
Corrosion Allowance 1mm
Corrosion coating 3 Layer PP
Weight Coating Concrete weight Coating
Installation S-Lay (Surface Laid)
Crossings 1
Table 5-2: Additional 8km pipeline specifications
Conversion and repurposing requirements
CO2 can be transported in gaseous, dense or liquid phase, but must remain in
the same phase while in the pipeline. Phase change is not allowed to avoid
complications of operating a multiphase system and avoid higher risks and costs
(see Annex 1: CO2 Phase Change and Pressure Drop). This condition places
requirements on the choice of pumps, pipeline diameter and wall thickness,
which directly also impacts the costs. As such, the pipelines’ physical condition
and its design determine its conversion and re-purposing requirements.
D11 Infrastructure Re-use Atlantic Pipeline
ACT Acorn Consortium Page 25 of 54
Important to note also is that re-use of pipelines limits the choice of operating
conditions.
5.2.1 Regulatory requirements
Some pipelines, such as Atlantic, are important UKCS infrastructure, and
provide the means for future developments such as CO2 transport and storage.
As such their decommissioning can be deferred by being place under the Interim
Pipeline Regime (IPR). Once the owner submits a Disused Pipeline Notification
form to BEIS; the latter will then consult with other government departments and
issue a letter outlining the conditions under which decommissioning can be
deferred. If pipeline re-use is considered viable, suitable and sufficient
maintenance is required of the owner (Oil & Gas UK, 2013).
In the UK, a Pipeline Works Authorisation/variation (PWA) must be in place
before a pipeline or pipeline system construction/modification work can begin.
In this respect, a detailed EIA must be submitted and approved by BEIS.
Depending on the status of the pipeline, it takes approximately four to six months
from receipt of a satisfactory application to issuing the authorisation.
The newly repurposed pipeline would be subject to the same regulations as
before, including the Pipelines Safety Regulations 1996, Petroleum Act 1998,
and the Coast Protection Act 1949.
5.2.2 Internal and external inspection
If a pipeline has been decommissioned, it would render it useless for re-use as
it would not be cost effective to do so. As the Atlantic pipeline has not been
decommissioned, there is not a large amount of technical work required with
respect to conversion and repurposing since the pipeline remains installed from
end-to-end.
Before the pipeline could be used for CO2 transport, several steps would have
to be taken, including:
• integrity and life extension assessment,
• anode inspection,
• subsea external inspection (especially pipeline crossings or erosion
and impact on pipeline support),
• assessment of needs to support the pipeline in case of any stress
gaps across the ocean floor and the pipeline itself,
• drying of the pipeline.
Internal inspection
Integrity of the pipeline, for example, could be assessed using a so-called
“intelligent pig” (see Figure 5-2 below). This process, also referred to as
“pigging”, can also perform various maintenance operations, including cleaning
and repair. Previous study work from the Longannet and Peterhead CCS
projects suggests that the intelligent pig run would best be undertaken in the
Execute stage of a project prior to entering operations. Estimated costs for
running such an operation would be around £4million (Shell, 2016).
Further assessment of potential for ductile fracture due to rapid decompression
would also have to be performed during the Front-End Engineering Design
(FEED) study.
D11 Infrastructure Re-use Atlantic Pipeline
ACT Acorn Consortium Page 26 of 54
Figure 5-2 An Example of an "Intelligent pig" Inspecting Pipeline Condition (Intertek, 2016)
External inspection
External inspection of pipeline crossings, as well as any potential erosion or
impacts on pipeline supports, would be required. In addition, free span surveys
would have to be performed. A free span occurs where a pipeline spans
between two high points on the seabed. This can create additional stress on the
pipeline itself and must be corrected (i.e. by placing grout bags underneath and
filling them with liquid cement or grout), before the pipeline is washed and CO2
transported. Free span surveys can consist of preliminary stress and vibration
frequency checks, followed by detailed strain and fatigue life checks where
appropriate. (Kaye, Ingram, Galbraith, & Davies, 1995).
13 Opex was calculated based on a 20-year design life and a 30% contingency has been included throughout.
Rationale for preservation
The Atlantic pipeline, as technical and operating envelopes show, is well suited
for CO2 transport in light of its wall thickness and consequently a higher pressure
rating. This means the pipeline itself has a higher tolerance to the pressure
required for CO2 transport and injection. The pipeline has sufficient remaining
asset life to support the development of CCS projects in the UK. No substantial
risks were identified.
The Captain X CO2 storage development plan has previously identified using the
16” pipeline along with a new 8km 16” pipeline from the Atlantic manifold to a
newly installed Normally Unmanned Installation (NUI) at the Captain aquifer.
The 8km pipeline would be required in both re-use and new pipeline scenario
and would connect the existing pipeline with the NUI.
5.3.1 Estimates of cost
The Captain X CO2 storage development plan and budget has shown the
estimated capital (Capex), operating (Opex)13 and abandonment expenditures
(Abex) for the engineering, procurement, construction, installation,
commissioning, operation and decommissioning of the Captain X facilities.
Within the study, the following Capex estimates for utilising the existing Atlantic
and Cromarty pipeline from St Fergus to the Atlantic field were made:
The total subsea Capex (excluding wells), including pre- and post-Final
Investment Decision (FID), was estimated at £33.7million, while Abex
decommissioning costs were estimated at £4.8million. Opex costs, on the other
D11 Infrastructure Re-use Atlantic Pipeline
ACT Acorn Consortium Page 27 of 54
hand, were estimated at £8.8million for a 20-year design life. The transportation
Capex associated with laying a new pipeline was estimated as being just over
£100million (Pale Blue Dot Energy & Axis Well Technology, 2016).
Phase Category Total Captain X Development (£M)
Pre-FID Pre-FEED 0.4
FEED 0.6
Post-FID
Detailed Design 0.7
Procurement 5.1
Fabrication 4.9
Construction & Commissioning
22.0
Total Capex – Transportation (£M) 33.7
Table 5-3 Captain X Development - Transport Capex (Base case)
Phase Category Total Captain X Development (£M)
Pre-FID Pre-FEED 0.4
FEED 0.6
Post-FID
Detailed Design 0.7
Procurement 30.7
Fabrication 8.5
Construction & Commissioning
60.0
Total Capex – Transportation (£M) 101.7
Table 5-4 Captain X Development - Transport Capex (New Pipeline System)
It should be noted that the base case scenario (Table 5-3) consists of re-using
the existing 79km Atlantic pipeline (Table 5-1) from St. Fergus to the Atlantic
Manifold, and installation of an infield pipeline. Other options of acquiring the
pipeline should be considered in the future. If the acquisition of the pipeline
would not be possible (i.e. due to integrity or other issues) a new pipeline from
St. Fergus to Captain X NUI would have to be constructed (see Table 5-4).
Re-use vs. new pipeline
When considering reusing the pipeline versus constructing a new one, it should
again be pointed out that the 8km pipeline (see Table 5-2), from the Atlantic
manifold to Captain X NUI would have to be constructed in both scenarios.
As such, when making a true comparison, the costs to be considered are:
Re-use
D11 Infrastructure Re-use Atlantic Pipeline
ACT Acorn Consortium Page 28 of 54
• £33.7m (€38.3m) for the 8km pipeline from the Atlantic manifold to
the Captain X NUI;
• £4m (€4.5m) for the existing pipeline from St. Fergus to the Atlantic
manifold. This cost includes an estimated cost of running an
intelligent pig and other commissioning type duties (i.e. drying the
pipeline) to make the pipeline ready for CO2 transport.
New
• £33.7m (€38.3m) for the 8km pipeline from the Atlantic manifold to
the Captain X NUI;
• £101.7m (€113.7m) for the new pipeline from St. Fergus to the
Atlantic Manifold;
In this respect the comparison of costs between re-use and constructing a new
pipeline is £37.7m (€42.8m) and £135.4m (€152m).
5.3.2 Key risks
Key risks include corrosion and horizontal ductile fracture. The Atlantic pipeline,
however, is less susceptible to the latter due to increased wall thickness.
Nevertheless, while there is some uncertainty as to the exact level of corrosion
from the existing use, doing an “intelligent pig” assessment, as was pointed out
by several key stakeholders, would help with reducing that risk. Cost estimates
from the Peterhead CCS Project FEED Summary Report suggest that intelligent
pigging of the pipeline would cost somewhere around £4million (Shell, 2016).
Another option for reducing the risks of corrosion, as well as ductile fracture, and
providing flow assurance and system integrity would be via a so-called “pipe-in-
pipe” (PiP) solution. This, however, is rendered much more difficult in the re-use
of subsea pipelines as installations would be extremely technologically
challenging, as well as costly. Nevertheless, as it stands, we believe this to be
an unnecessary mitigation for the risks.
D11 Infrastructure Re-use Goldeneye Pipeline
ACT Acorn Consortium Page 29 of 54
6.0 Goldeneye Pipeline
Description of assets
The depleted Goldeneye gas field, whose production ran from 2004 to 2011, is
underlain by the Captain Aquifer, and is located approximately 100km offshore
from St. Fergus Gas Terminal of the northeast coast of Scotland. It is part of one
of the best studied and most suitable formations for CO2 storage in the North
Sea and is connected to St. Fergus by a 101km long and 0.508mm (20”) in
diameter carbon steel pipeline.
Shell, as the operator of the Goldeneye infrastructure (platform, wells, pipelines),
has previously said that without a CCS project all infrastructure would be
decommissioned. Because there is currently no approved decommissioning
programme for the Goldeneye field, it is believed the infrastructure could be
decommissioned within the next year without a clear case being made for the
re-use of its infrastructure.
The re-use of the platform and wells at Goldeneye offers both benefits and
certain disadvantages. One of the issues related to the Goldeneye platform is
the operating costs, which would likely be much higher if the platform was re-
used for CO2 injection. On the other hand, reusing the platform would offer the
benefit of easier re-entering/re-use of the wells. The platform is likely to require
extensive life-extension work to be done, including removal/bypassing of all
14 Storage Opex costs include: final financial mechanism payment (post-transfer obligation), lease fee, storage organization costs associated with support of the measurement, monitoring and verification activities across the full life of the project (Shell, 2016b).
production facilities and replacing them with the injection facilities required. Such
modifications tend to be quite costly.
The Peterhead CCS Project Cost Estimate and FEED Summary reports,
prepared by Shell as part of the Knowledge Deliverables for the UK CCS
Competition, provide a summary of the Capex and Opex cost estimates for the
execute phase of the project. They show, for example, that offshore Capex (i.e.
for landfall, pipeline, subsea, Goldeneye modifications, wells and subsurface)
stood at approximately £222million, of which nearly £61million was for
Goldeneye modifications, £89million for wells and surface, and £72million for
landfall, pipelines and subsurface related activities. Opex cost estimates, on the
other hand, shown that for a 15-year injection operational period, transport and
storage14 would amount to £90million and £2million respectively (Shell, 2016).
The question of equitable sharing of costs between new and future owners is an
important one in considering re-use of existing platforms. Furthermore, there are
other important technical and commercial limitations, albeit some benefits as
well, when discussing the re-use of existing wells. As mentioned, the goal of this
Report is primarily to present the necessary information and considerations for
the re-use of the Goldeneye pipeline.
The Goldeneye pipeline operated between 2006 and 2010 after which, in 2013,
it was cleaned of hydrocarbons and filled with a corrosion inhibitor and a biocide
D11 Infrastructure Re-use Goldeneye Pipeline
ACT Acorn Consortium Page 30 of 54
solution, with a protection life of seven years (Shell, 2016). It is owned by the
Goldeneye Joint Venture partners and operated by Shell.
The Goldeneye pipeline has previously been assessed for re-use potential
during the Peterhead CCS Project and the Longannet CCS Project. The FEED
study of the latter also showed that the pipeline is suitable for dense phase CO2
transportation within its operational parameters (see 6.1.2 below).
6.1.1 Decommissioning consideration and current status
There is no approved decommissioning programme for the Goldeneye field and
facilities, which include topsides, wells, and the pipeline, meaning these could
be decommissioned, and the wells abandoned, in the coming years considering
the UK oil and gas regulations, if no CCS option is progressed.
The Goldeneye pipeline operated between 2004 and 2010 after which corrosion
risk was evaluated using the Pipe RBA (Risk Based Assessment). It was flushed
free of hydrocarbons in 2013 and left mothballed with inhibited water and a
corrosion inhibitor. The pipeline has now been placed under the IPR up until
2022 and is considered suitable for dense phase CO2 transportation.
6.1.2 Technical specifications and operating envelopes
Parameter Value
PL ID (DECC) PL-1979
Length 101km
Design Life 20years
Outer Diameter 508 mm (20in)
Wall thickness 14.3mm
Material X65 Carbon Steel HFW (high frequency welded)
Corrosion Allowance 3mm
MAOP (max. allowable operating pressure)
125barg
Design Temperature +60 / 0°C
Max. CO2 flow rate 2.4MT/yr
Operating Temperature
50°C
Capacity 2-4MT/yr
Route and crossings
Direct from Goldeneye platform to Shell-Esso terminal at St. Fergus (parallel to and south of Miller / SAGE (Scottish Area Gas Evacuation) pipeline corridor)
Five pipeline crossings
Table 6-1 Goldeneye Pipeline Secifications
Previous studies have identified no significant issues and have shown that the
pipeline, which has a carrying capacity of 2-4MT/yr, is suitable for dense phase
or liquid CO2 transportation, within the defined operational parameters (i.e. max.
D11 Infrastructure Re-use Goldeneye Pipeline
ACT Acorn Consortium Page 31 of 54
and min. temperatures and CO2 water content limits). The maximum allowable
operating pressure and the pipeline diameter also govern the maximum well
injection rate (Shell, 2016).
Furthermore, when the pipeline was installed an internal epoxy coating was
applied to improve the flow and reduce commissioning works. There has been
no evidence of coating spalling or disbondment, although the Peterhead CCS
project FEED study did suggest shot blasting to remove mill scale, and special
attention to be given to dewatering the pipeline system prior to filling it with CO2,
as free water combined with high CO2 pressure could lead to extreme corrosion
rates.
Figure 6-1 Goldeneye Pipeline from St Fergus to Goldeneye Platform (Shell, 2016)
Conversion and repurposing requirements
No significant conversion/repurposing changes would need to be made to the
Goldeneye pipeline. As per the Atlantic and MGS pipelines, the conversion and
repurposing requirements are inherently related to external and anode
inspection, particularly the pipeline crossings or erosion and impact on pipeline
support. In addition to running an “intelligent pig”, an assessment of potential
needs to support the pipeline in case of any stress gaps across the ocean floor
and the pipeline itself would be performed at the FEED stage.
Rationale for preservation
The Goldeneye pipeline is considered to have sufficient remaining asset life to
support the development of CCS projects in the UK. The examination of
potential key risks and certain cost estimates indicate that preservation is
sensible.
6.3.1 Estimates of costs
Given the proprietary nature of the financial information, estimates of costs for
the preservation or decommissioning of the pipeline were not made available.
Nevertheless, the following costs considerations are associated with the
preservation of the Goldeneye pipeline:
• financial compensation as agreed-upon between the Goldeneye JV
and the government authority or a third-party entity;
• cost differential between decommissioning today versus in the
future;
• ongoing maintenance costs for the Goldeneye pipeline.
D11 Infrastructure Re-use Goldeneye Pipeline
ACT Acorn Consortium Page 32 of 54
On the other hand, preserving the Goldeneye pipeline includes, among other
things, the following benefits:
• helps retain regional CCS opportunities (i.e. network, hub);
• costs and risks are reasonably well known;
• maximizes cost efficiency from previous investments;
• no long-term government commitment to large Capex/Opex is
required;
• demonstrates to industrial emitters that government is committed to
a near-future deployment of CCS;
• creates options for future CCS business models;
• retain skills and jobs.
Providing reliable decommissioning cost estimates has proven to be extremely
difficult, with many projects experiencing between 30% to over 100% cost
overruns. Poor cost estimates are in large part the result of lack of available
performance benchmarks and forecasting models that would serve as the basis
for developing decommissioning budgets, designing decommissioning plans,
assessing the impact of changes in project scope versus actual performance,
and monitoring execution performance (BCG, 2017).
As mentioned in the introduction, pipeline decommissioning however, does not
form a large part of the overall decommissioning cost. Given the proprietary
nature of the cost estimates, the numbers are not provided in this Report.
Please also refer to Section Estimates of costs7.3.1 of this report.
6.3.2 Key risks
Some of the key risks associated with reusing the pipeline include unexpected
corrosion and ductile fracture.
Although the Goldeneye pipeline has been flushed clear of hydrocarbons and
anti-corrosion inhibitor put in place, albeit quantified as very low, there remains
a risk that excessive levels of corrosion could have made the pipeline unsuitable
for CO2 transportation. To mitigate this risk, it has been recommended that a
survey of the full length of the pipeline is made using a so-called intelligent pig,
which, at an estimated cost of £4million, would ensure maximum cost and
schedule certainty. In addition, to mitigate risk of corrosion, an anti-corrosion
coating system should be applied.
Shell has noted in its Peterhead CCS Project Basic Design and Engineering
Package report that the risk of running ductile fracture is propagated by dense
phase CO2 decompression. CO2 dense phase transport presents low
temperature risks during depressurization. Due to decompression behaviour,
uncontrolled depressurisation presents an increased risk of brittle and/or ductile
fracture. To reduce running ductile fracture risk, the composition of the CO2 must
be controlled to prevent rapid and uncontrolled depressurisation, and a running
ductile fracture propagation control is required for the pipeline design. For the
Peterhead CCS Project, Shell conducted simulations of CO2 gas composition to
model gas decompression and saturation pressure for dense phase operation
and establish a range of maximum operating temperatures for the entire length
of the Goldeneye pipeline (Shell, 2016).
In comparison to the Atlantic and MGS pipelines, the Goldeneye pipeline is of
lesser thickness, with lower tolerance to the potential pressure needed for CO2
transport. In theory this would render it more susceptible to running ductile
fracture, but this risk could be managed through effective temperature control.
D11 Infrastructure Re-use MGS Pipeline
ACT Acorn Consortium Page 33 of 54
7.0 MGS Pipeline
Description of assets
7.1.1 Decommissioning consideration and current status
The depleted Miller gas field is located 240km northeast of Aberdeen, Scotland,
in the Central North Sea, and was in operation until 2007 when the Cessation of
Production (CoP) was submitted to the OGA. The first half of the 240km and
0.762mm (30”) diameter pipeline (PL-720), which connects the St. Fergus
Terminal and the Miller field, is trenched, and the second half is surface laid.
The wells were plugged and abandoned, and the topsides are to be removed by
the end of 2018, the pipeline was flushed clear of hydrocarbons in 2009. Since
then, the pipeline has been serviced by BP, and the last service/maintenance
performed in 2013. The pipeline has been under the Interim Pipeline Regime
(IPR) for the past 10 years, which has recently been extended for a period of
further five years, until 2021.
The Miller decommissioning programme, approved in 2011, applies to the
installations (i.e. topsides, jackets) and effectively the wells, but not the pipelines
themselves. A decommissioning programme for the pipelines is yet to be
prepared. BP has taken the steps of decommissioning certain infrastructure,
including disconnecting the pipeline from the platform but the pipeline could still
be used for CO2 transport to new facilities (subsea or platform-based) at the
15 As of November 2017, given that a pipeline decommissioning program has not yet been considered, decommissioning would likely include cutting ends of the pipeline, trenching certain sections while removing others. The extent of the decommissioning also depends on the end state and what is agreed with the regulator.
Miller field. This would need to include a new oil export system, if the
development would be for EOR.
A decision as to whether the pipeline is to be decommissioned15 or preserved
for another use, would be made after the removal of other Miller field
infrastructure (i.e. platform), and after a decommissioning programme is
approved/agreed upon with the OGA and other Joint Venture partners after
2021.16 Nevertheless, the work performed thus far demonstrates the pipeline to
be in good and reusable condition, with an estimated life span into the late 2020s
or longer (Turin & Blacklaws, 2017). Furthermore, the Miller pipeline was
designed to carry gas with a high CO2 content making it well placed for CO2
transport.
While BP has identified that it is interested in finding another use of the pipeline,
it does not hold much interest in operating it, given it was installed to carry gas
from the Miller field (now being decommissioned) and as such does not provide
any value. In this respect, one of the key drivers of decommissioning is the
liability associated with the pipeline. If there was a viable business option for
reusing the MGS pipeline for something else, BP would progress the opportunity
to have the pipeline preserved and re-used. (Turin & Blacklaws, 2017).
16 The infrastructure is operated by BP (who is also the license owner for the Miller field) in partnership with ConocoPhillips and Shell. In April 2016, Petrofac was also awarded a Duty Holder contract from BP to support the late life management of the platform (BP, 2011).
D11 Infrastructure Re-use MGS Pipeline
ACT Acorn Consortium Page 34 of 54
Figure 7-1 Location of the Miller Platform (BP, 2011)
7.1.2 Technical specifications and operating envelopes
Parameter Value
PL ID (DECC) PL-720
Length 240km
Design Life 20years
Outer Diameter 762mm (30in)
Material X65 Carbon Steel HFW (high frequency welded)
Wall thickness 24mm
Corrosion Allowance 3mm
Design Pressure 174bar
Operating Temperature +75 / -10°C
Capacity 10MT/yr
Table 7-1 MGS Pipeline Specifications
Conversion and repurposing requirements
Conversion and repurposing requirements would depend on the entity looking
to re-use the pipeline, however, like the Atlantic and Goldeneye pipelines, no
significant conversion/repurposing changes would be required.
In any case, a high level of confidence would need to be obtained for anyone
looking to re-use the pipeline as it has been out of service for a long time.
Assurance on the wall thickness and robustness of the pipeline, an
understanding of the consequences of failure and what evidence is needed to
prevent any failures would have to be made prior to bringing the pipeline back
D11 Infrastructure Re-use MGS Pipeline
ACT Acorn Consortium Page 35 of 54
in to operation. A strict process of validating the integrity and potentially updating
the protection system is likely to be required ahead of re-use of the pipeline.
Rationale for preservation
The MGS pipeline is considered in good enough condition to have sufficient
remaining asset life to support the development of CCS projects in the UK. In
addition, the examination of potential key risks and certain cost estimates
indicate that preservation is sensible, given the cost of decommissioning versus
cost of constructing a new pipeline. Nevertheless, there are several important
issues to consider when making a rationale for preservation.
As mentioned, although their business strategy is focused on oil and gas, and
the pipeline itself is currently not delivering any value to BP, they are open to the
pipeline being repurposed for CO2 transport. If another organisation/entity
wanted to acquire the pipeline and its liabilities, or there was a viable business
option available for reusing the MGS pipeline, BP would be interested in
progressing the opportunity to have the pipeline preserved and re-used. An
important aspect for BP, and other JV partners, would be to not continue to own
the pipeline or retain any future liabilities associated with it. So as not to be held
liable under Section 34 of the 1988 Petroleum Act, it would be important that
sufficient due diligence is completed on the organisation/entity taking over the
ownership and liabilities, including their financial capability to operate and
manage those liabilities. In short, for BP to not proceed with their current
decommissioning plan they would require a vetted new owner to take on and
underwrite all future liabilities. (Turin & Blacklaws, 2017)
A critical issue for BP in whether to preserve or decommission the MGS pipeline
is timing. Preservation would only occur if a clear timeframe of alternative use
can be presented to them which is in line with how long BP are prepared to
retain the asset. In this respect, BP is seeking clarity on the timing and/or the
nature/level of compensation that would be provided to them to preserve the
pipeline, as opposed to decommission it.
BP has shown willingness to work with all the relevant key stakeholders,
including Bellona, Pale Blue Dot, the OGA and others, as they consider
preservation of the infrastructure important; for CCS development in the region
or other alternative uses. Nevertheless, the pipeline is currently not delivering
any value for BP, has been under IPR for the past 10 years, and no one has
presented a realisable plan to date. Time is running out. A credible plan which
relieves BP of the liabilities associated with the pipeline must be finalised and
presented before it is too late.
7.3.1 Estimates of costs
Aside from what is available in the public domain and what was provided during
consultation with BP, obtaining detailed cost estimates on the decommissioning
and/or conversion/re-purposing was difficult to obtain. Thus, lessons learned
and cost estimates are taken from a similar decommissioning project done by
BP; the North West Hutton decommissioning project. The North West Hutton
field is located approximately 130km northeast of the Shetland Islands in the
Northern North Sea (see Figure 7-2 below) and was in operation between 1983
and 2002.
D11 Infrastructure Re-use MGS Pipeline
ACT Acorn Consortium Page 36 of 54
Figure 7-2: Location of North West Hutton: (Jee, 2014)
The decommissioning project, completed in 2009, along with the removal of the
jackets and topsides included the decommissioning of two oil and gas export
pipelines, both of 13km in length. Decommissioning scope included cutting and
removal of exposed pipeline sections, removal of sub-sea isolation valves and
associated spools, umbilicals and concrete mattresses. The predicted
decommissioning costs for the 250mm (10”) PL-147 gas pipeline were £3million,
but the final costs reached £5million. Decommissioning costs of the 510mm
(20”) PL-148 oil pipeline were originally estimated at £3million, and the final cost
amounted to £10million. The £7million cost differential in estimated and actual
decommissioning cost of the PL-148 pipeline came as a result of initial cutting
technologies employed proving to be acceptable but inefficient for the large
number of cuts required. The difference came because of delays that had been
incurred due to the change of technique and equipment used (Jee, 2014).
These estimates show that the decommissioning of the 26km of the pipeline
infrastructure came at a cost of £15 million, or £0.6 million per kilometre.
7.3.2 Key risks
The risks arising from the re-use of existing pipeline are like the risks identified
with the Goldeneye and Atlantic pipelines. These include, in theory, horizontal
ductile fracture and corrosion. In order to mitigate the risks, a full-length survey
of the pipeline using the intelligent pig method could be performed.
Nevertheless, representatives from BP (Turin & Blacklaws, 2017) did suggest
that there is no concern with ductile fracture in the MGS pipeline because no
hydrocarbon is present anymore. BP is performing regular inspections through
which these risks of impacts on other users of the sea are mitigated.
At the same time, representatives from BP highlighted that running an intelligent
pig at this point in time would not make sense, as no alternative use option has
been presented yet. While an intelligent pig is quite an expensive option to run,
it is a tool that will yield the best integrity results over the totality of the length of
the pipeline.
D11 Infrastructure Re-use Generic Key Risks
ACT Acorn Consortium Page 37 of 54
8.0 Generic Key Risks
Technical and operational risks
Key risks associated with re-using the existing pipelines include corrosion and
ductile fracture, both of which are driven by the CO2 phase behaviour and
operating pressure of the pipelines. In managing operational risks, a key task is
to thoroughly clean and dry the pipelines before CO2 transportation begins. Such
risks, however, are by the current pipeline owners/operators considered to be
well understood and manageable. Running an intelligent pig is recommended
depending on the condition of the pipeline and previous history.
In addition, free spans, or where a pipeline spans between two high points on
the seabed, can create additional stress on the pipeline itself. Since dense
phase CO2 is likely to be denser than the fluids for which the pipelines were
designed, unsupported sections may not have sufficient strength. This must be
corrected (i.e. by placing grout bags underneath and filling them with liquid
cement or grout), before the pipeline is washed and CO2 transported. Free span
surveys, consisting of preliminary stress and vibration frequency checks,
followed by detailed strain and fatigue life checks where appropriate (OGJ,
1995), would help mitigate the risk of structural failures.
Legal and liability considerations
In the UK, the Offshore Petroleum Regulator for Environment and
Decommissioning (OPRED) within BEIS regulates the decommissioning of
offshore oil and gas pipelines, as well as other installations (UK Government,
17 The aim is to ensure that the new license holder can cover the decommissioning liabilities.
1988). Decommissioning obligations arise when the Secretary of State serves
the operator/owner of the pipeline a Section 29 notice under the Act (UK
Government, 1988), by which they are required to submit a decommissioning
programme by the date set by the Secretary of State. Once the programme,
including its costs, are approved by the Oil and Gas Authority (OGA), the Section
29 holder is obliged to carry out the tasks as set under the programme. Failure
to do so gives the Secretary of State the ability to take remedial action and
recover the costs from the Section 29 notice holder.
If, for example, a third party is to take over an asset (i.e. pipeline), the Secretary
of State may release a former licensee from its Section 29 obligations, if the
OGA is satisfied that adequate financial security arrangements (i.e.
Decommissioning Security Deed17) are in place in relation to the
decommissioning liabilities. Although the Secretary of State is not usually a party
in such industry led arrangements, also known as Decommissioning Security
Agreement (DSA), its presence may facilitate the withdrawal of a Section 29
notice on a departed licensee.
Nevertheless, the OGA may also in the case of an unsatisfactory
decommissioning programme, pursuant to Section 34 of the Petroleum Act,
serve a Section 29 notice to anyone, who, at any time since the issue of the first
Section 29 notice for the installation, was liable to have a Section 29 notice
served on them (i.e. former licensees).
D11 Infrastructure Re-use Generic Key Risks
ACT Acorn Consortium Page 38 of 54
Technically, although considered as a measure of last resort, until
decommissioning is complete, the Secretary of State has the right to require any
(current and former) licensee to be held liable for the decommissioning. When
assets are transferred/sold to a third party, a key component is ensuring that the
third party has all the underwriting and liability provisions so that the liabilities
are not rolled back onto the previous owner or former Section 29 notice holder.
In other words, establishing liability assurance between the parties is key.
Key considerations/issues:
• Is the pipeline under the Interim Pipeline Regime (IPR) and for how
long?
• CO2 is defined as a commodity when transported for commercial use
– such transport is legal. If CO2 is defined as waste and intended for
international transport special permits between import and export
countries are required.
• What is the extent of the (financial) liabilities associated with the
pipeline (decommissioning vs. preservation)?
D11 Infrastructure Re-use Conclusions
ACT Acorn Consortium Page 39 of 54
9.0 Conclusions
1. Between 2016 and 2025, operators in the North Sea intend to
decommission around 17% of the total pipeline network from the UK and
Norwegian Continental Shelves, or 850 pipelines with a total length of
nearly 7,500 km. The central North Sea hosts the largest number of these
pipelines (484), the southern North Sea and Irish Sea will see the largest
proportion of the total pipeline length, 3,426km, be decommissioned (Oil
& Gas Authority, 2016). Cost of planned decommissioning of 580
pipelines with a length of 3,700km is estimated at £847m (€947m), which
amounts to £1.46m (€1.63m) per pipeline (including associated
infrastructure such as umbilicals & infield lines), or £225k (€251m) per
km.
2. North Sea decommissioning has in some cases been delayed, principally
because of successful dialogue between the asset owners, the
government and other key stakeholders. These delays have been an
important short-term policy option allowing for the interim preservation of
the pipeline infrastructure.
3. The recently proposed changes to the UK’s decommissioning tax relief
regime on transfer of tax history, effective 1 November 2018, whereby
new asset owner would be able to, to some extent, claim back its
decommissioning costs, could encourage investment into late-life assets
in the North Sea and thereby maximise economic recovery (Thomas,
2017).
4. Repurposing existing legacy pipeline infrastructure offers significant cost
savings and an efficient approach to facilitating wider CCS deployment
(Brownsort, 2016) (Chandel, Pratson, & Williams, 2010) (Brunsvold,
Jakobson, Husebye, & Kalinin, 2011).
5. Initial cost estimates show that repurposing a pipeline would cost about
one fourth of the cost of building a new pipeline.
6. The best suited pipelines for re-use in the North Sea are currently:
Atlantic, Goldeneye, MGS. All are technically feasible for re-use and
under IPR until 2021.
7. Corrosion is identified as the largest potential technical risk. Any kind of
impurities in the CO2 could cause rapid corrosion and/or fracture. This
could be an issue when CO2 from multiple sources is combined. It will be
critical to ensure that capture plants meet the required CO2 purity levels,
which would be reconfirmed at the fence (before transported through the
existing pipeline).
8. Clarity on liability provisions, particularly when ownership of assets is
transferred is key. Public-private partnership has been identified as best
suited model, whereupon assets are transferred into public ownership,
with the government taking on all the associated risks and liabilities.
Investments in conversion/re-purposing and modifications would be paid
for by the private sector, with investments being incentivised (i.e. making
them tax deductible).
D11 Infrastructure Re-use References
ACT Acorn Consortium Page 40 of 54
10.0 References
BCG. (2017). The North Sea's $100 Billion Decommissioning Challenge.
Retrieved from https://www.bcg.com/en-be/publications/2017/energy-
environment-north-sea-decommissioning-challenge.aspx
BG Group. (2016). Atlantic and Cromarty Fields Draft Decommissioning
Programmes.
BP. (2011). Miller Decommissioning Programme. Retrieved from
https://www.bp.com/content/dam/bp-country/en_gb/united-
kingdom/pdf/Miller_Decomm_Programme.pdf
Brownsort, P. A. (2016). Reducing costs of carbon capture and storage by
shared re-use of existing pipeline - Case study of a CO2 capture cluster
for industry and power in Scotland. International Journal of Greenhouse
Gas Control 52, 130–138 .
Brunsvold, A., Jakobson, J. P., Husebye, A., & Kalinin, A. (2011). Case Studies
on CO2 Transport Infrastructure: Optimisation of Pipeline Network,
Effect of Ownership, and Political Incentives. Energy Procedia, 4, 3024-
3031.
Chandel, M. K., Pratson, L. F., & Williams, E. (2010). Potential Economies of
Scale in CO2 Transport Through Use of a Trunk Pipeline. Energy
Conversion and Management, 51(12), 2825-2834.
CRF. (2016). Status Capacity and Capability of North Sea Decommissioning
Facilities. Retrieved from
http://www.gmbscotland.org.uk/assets/media/documents/pressrelease
s/GMB-SCOTLAND-REPORT-Status-capacity-and-capability-North-
Sea-Decommissioning-Facilities-final-web-GMB-cover.pdf
Global CCS Institute. (2013). The Properties of CO2. Retrieved from Global
CCS Institute: https://hub.globalccsinstitute.com/publications/hazard-
analysis-offshore-carbon-capture-platforms-and-offshore-pipelines/21-
properties-co2
Intertek. (2016). Intelligent Pigging Pipeline Inspection Services. Retrieved from
https://www.youtube.com/watch?v=X5S48nytYJg&t=147s
Jee. (2014). North West Hutton Decommissioning Programme: Close-out
Report. Retrieved from https://www.bp.com/content/dam/bp-
country/en_gb/united-
kingdom/pdf/NWH_Decommissioning_Programme_Close_Out.pdf
Kaye, D., Ingram, J., Galbraith, D., & Davies, R. (1995). Freespan Analysis,
Correction method saves time on North Sea Project. Oil and Gas
Journal. Retrieved from http://www.ogj.com/articles/print/volume-
93/issue-8/in-this-issue/pipeline/freespan-analysis-correction-method-
saves-time-on-north-sea-project.html
Oil & Gas Authority. (2016). Decommissioning Strategy. Retrieved from
https://www.ogauthority.co.uk/media/1020/oga_decomm_strategy.pdf
Oil & Gas Authority. (2017). UKCS Decommissioning: 2017 Cost Estimate
Report. Retrieved from
https://www.ogauthority.co.uk/media/3815/ukcs-decommissioning-
cost-report-2.pdf
D11 Infrastructure Re-use References
ACT Acorn Consortium Page 41 of 54
Oil & Gas UK. (2009). Guidelines for the Suspension and Abandonment of
Wells.
Oil & Gas UK. (2013). Decommissioning of Pipelines in the North Sea Region.
Oil & Gas UK. (2016). UK MER Strategy.
Pale Blue Dot Energy & Axis Well Technology. (2016). D13 WP5D Report -
Captain X Storage Development Plan. Energy Technologies Institute.
Pale Blue Dot Energy and Axis Well Technologies. (2015). Captain X Storage
Development Plan and Budget. Energy Technologies Institute.
Pale Blue Dot Energy and Axis Well Technology. (2015). Strategic UK CO2
Storage Appraisal Project. Loughborough: Energy Technologies
Institute.
Shell. (2016). Peterhead CCS Project.
Turin, S., & Blacklaws, J. (2017, November 7). Information gathering
conversation for ACT Acorn project. (M. Maver, Interviewer)
UK Government. (1988). UK Petroleum Act. Retrieved from
http://www.legislation.gov.uk/ukpga/1998/17/section/19
D11 Infrastructure Re-use Annex 1: CO2 Phase Change and Pressure Drop
ACT Acorn Consortium Page 42 of 54
11.0 Annex 1: CO2 Phase Change and Pressure Drop
CO2 Phase Change
CO2 can be transported in gaseous, dense or liquid phase. To ensure single
phase flow within the pipeline and avoid a raise in risks and costs if phase
change occurred, a minimum operating pressure must be set. It is the fluid flow
regime and any pressure drop that determine the capacity of pipelines. This
capacity, however, can be increased with pressure boosting stations, located
along the pipeline, albeit their installation may increase the overall costs to a
level at which it would outweigh the benefits from re-using an existing pipeline
(Element Energy Limited, 2014).
Figure 11-1: CO2 phase changes (Global CCS Institute, 2013)
Figure 11-1 shows the points at which the CO2 exhibits phase change behaviour,
which is dependent on the temperature and the pressure. The “triple point” is
the point where CO2 can exist in three phases (gas, liquid, solid) simultaneously
in thermodynamic equilibrium. Above the so-called “critical point” (74barg and
31°C), the CO2 develops “supercritical” properties, where the liquid and gas
phases cannot exist as separate phases, but rather has some characteristics of
a gas and others of a liquid (Global CCS Institute, 2013).
CO2 Pressure Drop
The pressure drop throughout the length of the pipeline is one of the key
technical issues related to the re-use of pipelines, given that any severe changes
would not only affect the integrity of the pipeline but also its capacity.
Table 11-1 shows the St. Fergus to Captain NUI pipeline pressure drop
estimates based on different mass flow rates (Pale Blue Dot Energy & Axis Well
Technology, 2016)
Pipeline Width Mass Flow Rate
Length Fluid Phase Pressure Drop, per km
Pressure Drop
St. Fergus to Captain NUI
406mm (16”)
2MTPa
87km (79+8)
Liquid/Dense
0.062bar 5.3bar
3MTPa 0.139bar 12.0bar
4MTPa 0.244bar 20.9bar
5MTPa 0.375bar 32.3bar
Table 11-1: St Fergus to Captain NUI pipeline pressure drop
D11 Infrastructure Re-use Factsheet 1: Re-use of North Sea Topside Infrastructure for CO2 Storage
ACT Acorn Consortium Page 43 of 54
Factsheet 1: Re-use of North Sea Topside Infrastructure for CO2 Storage
D11 Infrastructure Re-use Factsheet 1: Re-use of North Sea Topside Infrastructure for CO2 Storage
ACT Acorn Consortium Page 44 of 54
D11 Infrastructure Re-use Factsheet 1: Re-use of North Sea Topside Infrastructure for CO2 Storage
ACT Acorn Consortium Page 45 of 54
D11 Infrastructure Re-use Factsheet 1: Re-use of North Sea Topside Infrastructure for CO2 Storage
ACT Acorn Consortium Page 46 of 54
D11 Infrastructure Re-use Factsheet 2: Re-use of North Sea Production Oil & Gas Wells for CO2 Storage
ACT Acorn Consortium Page 47 of 54
Factsheet 2: Re-use of North Sea Production Oil & Gas Wells for CO2 Storage
D11 Infrastructure Re-use Factsheet 2: Re-use of North Sea Production Oil & Gas Wells for CO2 Storage
ACT Acorn Consortium Page 48 of 54
D11 Infrastructure Re-use Factsheet 2: Re-use of North Sea Production Oil & Gas Wells for CO2 Storage
ACT Acorn Consortium Page 49 of 54
D11 Infrastructure Re-use Factsheet 2: Re-use of North Sea Production Oil & Gas Wells for CO2 Storage
ACT Acorn Consortium Page 50 of 54
D11 Infrastructure Re-use Factsheet 3: Re-use of North Sea Transport Infrastructure
ACT Acorn Consortium Page 51 of 54
Factsheet 3: Re-use of North Sea Transport Infrastructure
D11 Infrastructure Re-use Factsheet 3: Re-use of North Sea Transport Infrastructure
ACT Acorn Consortium Page 52 of 54
D11 Infrastructure Re-use Factsheet 3: Re-use of North Sea Transport Infrastructure
ACT Acorn Consortium Page 53 of 54
D11 Infrastructure Re-use Factsheet 3: Re-use of North Sea Transport Infrastructure
ACT Acorn Consortium Page 54 of 54