project b warranty

Upload: superb-heart

Post on 08-Jul-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/19/2019 Project B Warranty

    1/20

     

    t - ~ ~ . 1 1 ~ 1

    a s ~ t

    Saudi Electricity Company

    SCHEDULE A CONTRACT

    NO.

    30621090/00

    Title

    Page

    15.5

    Appoint

    COMP NY

    REPRESENT TNE

    A-19

    15.6 Provide Bench Marks and Survey Points A-19

    16.

    Changes

    A-20

    16.1

    CH NGE ORDER

    A-20

    16.2 Basis

    for

    Determining Compensation

    for

    Changes A-20

    16.3

    CH NGE ORDER Signature A-21

    16.4 No Compensation for performing Changes without a

    CH NGE

    A-21

    ORDER

    16.5

    Changes Required by Poor Design and Specifications

    A-21

    16.6 Failure by CONTR CTOR and COMP NY to Agree on a Change A-21

    16.7 Failure

    by

    CONTR CTOR

    &

    COMP NY

    to

    Agree on A-21

    Compensation for Change

    16.8

    Changes In Saudi Laws of Income Tax and Custom Duties

    A-22

    17.

    Completion and

    Acceptance

    A-22

    17.1 Substant ial Breach

    of CONTR CT

    A-22

    17.2 Design Completion A-22

    17.3

    Technical Complet ion of the

    PROJECT

    PORTIONS A-22

    17.3.1

    Power Plant Units

    A-22

    17.3.2 Non-Power Plant Facilities

    A-23

    17.4

    Notice of Technical Completion and Corrective

    WORK

    A-23

    17.5

    CONTRACTOR's Failure to Perform Corrective WORK

    A-25

    17.6 CONTR CTOR

    shall perform

    start-up

    and

    trial

    operation

    of

    A-25

    Power Plant Units

    17.7

    Preliminary Acceptance of

    the PROJECT

    PORTIONS A-25

    17.7.1

    Power Plant Units

    A-25

    17.7.2

    Non-Power Plant Facilities

    A-25

    17.7.3

    Preliminary Acceptance Date A-26

    17.8

    Final Acceptance of

    the PROJECT

    PORTIONS and the

    WORK

    A-26

    17.8.1 Final Acceptance of the Power Plant Units

    A-26

    17.8.2

    Final Acceptance

    of the

    Non-Power Plant Facilities

    A-26

    17.8.3

    Final Acceptance

    of the WORK

    A-27

    17.9

    Adjustment

    to Final Acceptance Date

    A-27

    17.10

    Readiness

    for

    Commercial Operation

    of

    Power Plant

    Unit

    A-27

    17.11 Running

    the

    Unit(s)

    after

    Readiness

    for

    Commercial A-28

    Operation

    18.

    Warranties and Remedy Of

    Defects

    A-28

    18.1

    Warranty Coverage

    A-28

    18.2

    Warranty

    Duration

    A-29

    18.2.1

    For Power Plant Units

    A-29

    18.2.2 For Non-Power Plant Facilities

    A-31

    18.3

    Other

    Special Warranty Items

    A-32

    18.4

    Submission

    of

    Warranty Certificates

    A-33

    18.5

    Rights and Remedies Provided

    by

    Law

    A-33

    18.6

    Repair Latent Defects

    A-33

    TC 4

    Construction of Qurayyah Open Cycle Power Plant Schedule A

  • 8/19/2019 Project B Warranty

    2/20

    · · · ·

    ~ . . 4 S l t ~ . 1 ~ · :a.s.. .Mt

    Saudi Electricity Company

    SCHEDULE A

    CONTRACT NO. 30621090/00

    17.7.3

    Preliminary

    Acceptance Date

    The date on which all of the conditions in Paragraphs 17.7.1 and

    17.7.2 of this Schedule A have been fulfi lled shall be deemed

    as

    Preliminary Acceptance Date , even if the Preliminary Acceptance

    Certificate is issued

    at

    a later date. Within two (2) weeks after the

    Preliminary Acceptance Date,

    COMPANY

    shall issue

    the

    Preliminary

    Acceptance Certificate to CONTRACTOR. However, Preliminary

    Acceptance Certificate can be issued with minor punch list items

    which do

    not

    hinder safe and reliable operation of the PROJECT as

    determined by the COMPANY.

    17.8 Final Acceptance of the PROJECT PORTIONS and

    the WORK

    17.8.1 Final Acceptance

    of

    the Power Plant Units

    Final Acceptance

    of

    each Power Plant

    Unit

    (Power Plant

    Unit

    Final

    Acceptance) shall be achieved when:

    17.8.1.1 Technical Completion for the Power Plant Unit has been

    achieved, and

    17.8.1.2 Preliminary Acceptance for the Power Plant Unit has been

    achieved, and

    the

    CONTRACTOR has completed all the

    remaining punch list items, and

    17.8.1.3 The Performance Testing is complete, and

    17.8.1.4 All defects found during the warranty period have been

    repaired, replaced

    or

    as otherwise have been taken care

    of to the satisfaction of COMPANY and

    17.8.1.5 All final as-built drawings and the Operation and

    Maintenance Manuals for the Power Plant Unit have been

    received by COMPANY and

    17.8.1.6 In the case of Power Plant Unit No. 01, the

    COMPANY

    personnel have completed training on operation and

    maintenance of the PROJECT as described in the Scope of

    Work and Technical Specifications, PTS No. 06EG902.

    17.8.2 Final Acceptance of the Non-Power Plant Facilities

    Final Acceptance

    of

    each Non-Power Plant Facility (Non-Power Plant

    Facility Final Acceptance) shall be achieved when:

    17 8.2.1 Technical Completion

    for the

    Non-Power Plant Facility has

    been achieved, and

    17.8.2.2 Preliminary Acceptance for the Non-Power Plant Facility

    has been achieved, and the CONTRACTOR has completed

    all the remaining punch list items, and

    17.8.2.3 All defects found during the warranty period have been

    repaired, replaced

    or

    as otherwise have been taken care

    of to the satisfaction of COMPANY and

    A-26

    Construction

    of

    Qurayyah Open Cycle Power

    Plant

    Schedule

  • 8/19/2019 Project B Warranty

    3/20

     

    SCHEDULE A

    i -I.;1J453t

    ~ : ~ 1

    :a.S _;..it,tl

    Saudi Electricity

    Company

    CONTRACT NO.

    30621090/00

    17.11

    Running

    the Unit(s) after

    Readiness

    for

    Commercial Operation

    I f COMPANY,

    after

    the Readiness for Commercial Operation of any Power

    Plant Unit(s), runs

    the

    Power Plant Unit(s)

    for

    Commercial Use prior

    to

    or

    during carrying out

    the

    Performance Test or Reliability Run,

    the

    following

    conditions shall govern:

    17.11.1 COMPANY shall issue the Preliminary Acceptance Certificate (PAC) for

    this particular Power Plant Unit(s)

    after

    successful operation for a

    period of fourteen

    (14)

    days from the Readiness

    of

    Commercial

    Operation Date.

    17.11.2 In case there is a shut down due

    to

    failure which is attributed to

    CONTRACTOR

    during the fourteen

    (14)

    days period of Commercial

    Use mentioned in Paragraph 17.11.1 above, the date

    of

    the issuance

    of Preliminary Acceptance Certificate shall be postponed by the

    number

    of

    days the Power Plant Unit remains shutdown

    for

    repair.

    17.11.3

    I f

    the Performance Test could not be performed within the first 600

    operating hours after the Readiness for Commercial Operation Date,

    for

    reasons attributed

    to

    COMPANY only, then the degradation curve

    shall be applied based on

    the

    actual fired hours achieved

    at

    the time

    of the test exceeding 600 hours as per Paragraph 8.4.3

    of

    Schedule

    C

    of the

    PURCHASE CONTRACT. The Reliability Test run for the

    particular Power Plant Unit(s) shall be carried out after the Power

    Plant Unit(s) is no longer used for Commercial operation.

    17.11.4 Warranty period shall commence in accordance with Paragraph 18

    of

    Schedule A unless the Power Plant Unit(s) is used for Commercial

    Operation, in which case the warranty period shall commence from

    the Readiness

    for

    Commercial Operation date

    of

    the Power Plant

    Unit.

    18. Warranties and Remedy

    of

    Defects

    The SELLER's warranties and remedy of defects

    for the

    EQUIPMENT i t shall provide and

    which

    CONTRACTOR

    shall install,

    test

    and commission under this CONTRACT are set

    forth in

    the

    PURCHASE CONTRACT. This Paragraph

    18

    of Schedule A describes the

    CONTRACTOR's warranty obligations with respect to the materials and equipment i t

    shall provide and the WORK it shall perform under this

    CONTRACT.

    18.1

    Warrantv

    Coverage

    CONTRACTOR warrants:

    18.1.1 that it shall perform the WORK in a competent, diligent and

    workmanlike manner; and in accordance with prudent industry

    practices, CONTRACT specifications, and SELLER's officially provided

    manuals, guidance and acceptance criteria;

    18.1.2 that the PROJECT shall be engineered and designed in accordance

    with good quality, efficiency, design and engineering practices

    as

    agreed in the specifications; shall meet the design criteria described

    in the Scope

    of

    Work and Technical Specifications,

    PTS

    No. 06EG902

    and any additional design criteria agreed to by COMPANY; and as

    engineered and designed, shall be

    fit

    for the

    purposes intended;

    18.1.3 that the materials for the PROJECT shall be merchantable,

    fit

    for the

    purposes

    of

    generating electric

    power when

    operated in

    A-28

    Construction of Qurayyah Open Cycle Power Plant Schedule A

  • 8/19/2019 Project B Warranty

    4/20

    SCHEDULE A

    ~ ~ · · i

    ; · · ~ ·

    .

    t - l ; 1 ~ a 5 ~

    Saudi Electricity Company

    CONTRACT

    NO. 30621090/00

    accordance with CONTRACTOR's and manufacturer's specific

    operating instructions, free of defects in design, material or

    workmanship, and conform

    to the

    standards and specifications

    contained or referred to in

    the

    Scope of Work and Technical

    Specifications,

    PTS

    No. 06EG902 and any additional standards and

    specificatioQs

    contained

    or

    referred

    to

    in

    Schedule B ; and

    18.1.4

    that the fabrication of all parts, systems and units of

    the

    PROJECT

    shall be free of defects in workmanship and

    in

    accordance

    with the

    designs, drawings, and specifications prepared by

    CONTRACTOR

    and

    with good and efficient fabrication and craft practices, and

    18.1.5 that

    all materials and

    equipment

    provided

    by CONTRACTOR

    under

    this CONTRACT

    are compatible

    with

    the

    International

    Standards, and

    that

    test certificates are provided where requested by

    the

    Specifications.

    18.2 Warranty Duration

    18.2.1

    For Power Plant

    Units

    18.2.1 .1 The warranties described in Paragraph 18.1 of this

    Schedule A shall become effective

    for

    each Power Plant

    Unit upon the issuance

    of

    Preliminary Acceptance

    Certificate by COMPANY for that Power Plant Unit

    indicating that the Power Plant Unit has complied with the

    commissioning and performance acceptance test and is

    taken over

    by the COMPANY for

    Commercial Use.

    18.2.1.2 As

    soon as the warranty period starts,

    CONTRACTOR

    shall

    establish special coordination and liaison

    with

    the

    COMPANY s

    operators and maintenance crew on matters

    of

    operation and maintenance.

    18.2.1.3 CONTRACTOR

    agrees that the warranties shall survive

    acceptance of any payment for equipment and any other

    parts of the Power Plant Units, whether any defect shall

    be patent or latent, for twelve-thousand (12,000)

    operating service hours or

    twenty-four (24)

    Gregorian

    months excluding time

    out

    of service for modification,

    design, erection

    or

    breakdown problems, whichever shall

    occur first, after issuance of Preliminary Acceptance

    Certificate and

    for

    a similar period with equipment

    repaired

    or

    replaced pursuant

    to the

    provisions

    of

    Paragraph 18.2.1.6 below.

    However, these warranties shall expire in any case after

    the

    lapse of

    forty-eight

    (

    48)

    Gregorian months from the

    date

    of issuance

    of the

    applicable Preliminary Acceptance

    Certificate. ·

    18.2.1.4

    The

    CONTRACTOR s

    entire obligation

    with

    respect to

    these warranties shall be to repair', i.e. to remove, to

    repair

    and reinstall, or to replace , i.e. to remove and to

    reinstall with new element, any

    part/system of

    the

    equipment

    which, under the specified use and proper

    maintenance by COMPANY, proved defective during the

    warranty period, provided

    COMPANY

    gives

    CONTRACTOR

    A-29

    Construction

    of

    Qurayyab Open Cycle

    ower lant

    - Schedule A

    ..

    g

    .

  • 8/19/2019 Project B Warranty

    5/20

    /::_:;.J

    SCHEDULE A

    l;t_. oSSlt a s ~ t

    Saudi

    Electricity

    Company

    CONTR CT

    NO 30621090/00

    prompt written notice and satisfactory

    proof

    of such

    defect.

    18.2.1.5 f any

    equipment

    part

    or

    system is proved upon

    examination to be defective, COMPANY and CONTRACfOR

    will mutually agree that CONTRACfOR shall either repair

    such defective

    part or

    system or replace it and in such

    case

    CONTRACTOR

    shall

    bear

    all of

    the

    repair and

    replacement costs including sh ipping, packing and ·

    handling costs up to

    WORK

    SITE.

    18.2.1.6 The same warranties shall cover any part or system of

    the Power Plant Unit that shall be replaced or repaired by

    the

    CONTRACfOR under

    the

    above conditions and shall

    be in effect

    for

    a period

    of

    twelve-thousand

    12,000)

    operating hours or

    twenty-four

    24) calendar months

    whichever occurs first, except as otherwise specified,

    effective as from the day when said replaced or repaired

    parts

    or

    systems are reinstalled.

    If the

    said replaced

    or

    repaired part

    or

    system fails

    to

    meet the warranty period for a second time,

    CONTRACfOR shall

    either modify the

    said

    part or

    system

    or replace the

    part/system

    with a new one, free of any

    charge

    to

    COMPANY However, the

    total

    warranty period

    shall in no case extend beyond forty-eight

    48)

    Gregorian

    months

    from the

    date of Preliminary Acceptance

    of the

    Power Plant Unit.

    In

    order to assure and give maximum obtainable

    availability

    of

    the Power Plant Units and to speed up the

    permanent

    repair

    on any defective

    part/system,

    CONTRACfOR shall keep the defective

    part/system

    temporarily

    repaired and available

    for

    Commercial Use

    of

    COMPANY until a permanent

    remedy

    is made.

    For the permanent remedy of

    the

    problem, CONTRACfOR

    shall arrange immediate services

    of the

    specialist

    engineers and required material.

    18.2.1.7 f the defect is determined to be due to improper design

    or manufacture and

    i t

    can be reasonably determined that

    such a defect exists in other elements of the equipment,

    CONTRACTOR

    shall replace or modify such elements as

    mutually agreed, even if such elements have not yet

    failed. CONTRACfOR shall

    bear

    all costs associated

    with

    such repair

    or

    replacement.

    18.2.1.8 CONTRACfOR disclaims any respons ibility and liab ifity for

    defects or deficiencies during

    the

    warranty period

    for the

    relevant Power Plant Unit, which are due

    to

    faulty

    operation and maintenance, as well as major repair

    works carried

    through by the COMPANY not

    in accordance

    with the operation and maintenance manual and

    recommendations or any recognized method.

    18.2.1.9

    During the Commercial Use in which

    the

    Power Plant

    Units have been operating, from Preliminary Acceptance

    Date up to

    the

    end

    of Warranty

    Period for the· relevant

    Power Plant Unit, the warranty engineer shall also be

    A 30

    Construction

    of

    Qurayyah Open Cycle Power Plant Schedule A

    ·

    v

  • 8/19/2019 Project B Warranty

    6/20

    /

    SCHEDULE

    A

    1.:1 >P ~ . : l ~ l ' a ~ 1

    Saudi Electricity Company

    CONTRACT NO.

    30621090/00

    responsible for supervision of any routine inspection,

    trouble shooting, scheduled maintenance, overhauls

    (minor

    and major) which has been recommended by any

    of

    the equipment manufacturers which will be carried

    out

    by COMPANY personnel. CONTRACTOR acknowledges that

    a warranty engineer shall be provided by both

    the

    CONTRACTOR

    for the complete WORK and by the SELLER

    for the EQUIPMENT supplied under

    the

    PURCHASE

    CONTRACT. The warranty engineers shall be available

    during the Warranty Period to provide advice and counsel

    only and not to supervise or manage the work of Other

    Contractors.

    18.2.1.10 To meet spare parts requirements during the Warranty

    Period,

    CONTRACTOR

    shall be fully responsible and shall

    not depend on COMPANY s stock in any way.

    CONTRACTOR shall make

    the

    spare

    part(s)

    required

    to

    return

    the

    Power Plant Unit/equipment

    to

    service

    available

    at the WORK

    SITE within

    a

    reasonable period of

    time dependent on

    the

    circumstance

    of

    the repair or

    replacement required.

    18.2.1.11 During the Warranty Period,

    CONTRACTOR

    shall provide

    all and any consumable material and parts related its to

    warrantv obligations such as but

    not

    limited to all fuel

    filters, air intake filters, lubricants, insulation oils, C0

    2

     

    halon, foam concentrate water and sewage

    treatment

    chemicals, laboratory chemicals, etc ... all in addition

    to

    first fills but excluding fuel and fuel additives.

    18.2.2 For Non-Power Plant Facilities

    18.2.2.1 The warranties described in Paragraph 18.1 of this

    Schedule

    A

    shall become effective for each Non-Power

    Plant Facility upon the issuance of Preliminary Acceptance

    Certificate by COMPANY for that Non-Power Plant Facility

    indicating that it has complied with the

    CONTRACT

    requirements and is taken over by the COMPANY

    for

    occupancy or use or operation.

    18.2.2.2 CONTRACTOR

    agrees that the warranties shafl survive

    acceptance

    of

    any payment for equipment and any

    other

    parts of the

    Non-Power Plant Facilities

    1

    whether any

    defect shall be patent

    or

    latent

    1

    for twelve 12) Gregorian

    months

    after Issuance of Preliminary Acceptance

    Certificate and

    for

    a similar period with the

    equipment/material/structure repaired or replaced

    pursuant to the provisions

    of

    Paragraph 18.2.2.5 below.

    However, these warranties shall expire in any case

    after

    the lapse of twenty-four

    (24)

    Gregorian months from the

    date

    of

    issuance

    of the

    applicable Preliminary Acceptance

    Certificate; except for the silencing equipment and

    building roofs as described in Paragraph 18.3

    of

    this

    Schedule A .

    18.2.2.3

    The CONTRACTOR s entire obligation wlth respect to

    these warranties shall be

    to

    repair'. i.e.

    to

    remove, to

    repair and reinstall, or to replace , i.e. to remove and to

    A-31

    Construction

    of Qurayyah

    Open Cycle Power

    Plant-

    Schedule A

  • 8/19/2019 Project B Warranty

    7/20

    SCHEDULE

    A

    9 - ~ ~ ~ ~ ~ ~ ; a s ~

    Saudi

    Electricity Company

    CONTRACT

    NO.

    30621090/00

    reinstall with new element

    any

    part/system

    of

    the Non

    Power Plant Facility which under

    the

    specified use and

    proper maintenance by

    COMPANY

    proved defective

    during the

    warranty

    period provided COMPANY gives

    CONTRACTOR prompt

    written

    notice and satisfactory

    proof of such defect.

    18.2.2.4

    I f

    any

    part or system of

    the

    Non-Power Plant Facility is

    proved upon examination to be defective

    COMPANY

    and

    CONTRACTOR will

    mutually

    agree that CONTRACTOR

    shall either repair such defective part or system or

    replace i t and in such case CONTRACTOR shall bear all of

    the repair and replacement costs including shipping

    packing and handling costs up

    to

    WORK SITE.

    18.2.2.5 The same warranties shall cover any part or system of

    the Power Plant

    Unit that

    shall be replaced

    or

    repaired by

    CONTRACTOR

    under

    the above conditions and shall be in

    effect for a period

    of

    twelve

    (12)

    Gregorian months

    effective as from the day when said replaced or repaired

    parts or systems

    are

    reinstalled.

    I f

    the

    said replaced or repaired part or system fails

    to

    meet the

    warranty

    period for a second time,

    CONTRACTOR shall

    either modify

    the said

    part/system

    or

    replace the part/system with a new one free

    of

    any

    charge

    to

    COMPANY. However the.total

    warranty

    period

    shall in no case extend beyond twenty-four (24)

    Gregorian months from

    the

    date

    of

    Preliminary

    Acceptance

    of

    the Non-Power Plant Facility.

    18.2.2.6

    I f

    the defect is determined to be due to improper design

    or manufacture and it can be reasonably determined that

    such a defect exists in

    other

    elements

    of

    the equipment

    CONTRACTOR shall replace or modify such elements as

    mutually agreed even

    if

    such elements have not yet

    failed. CONTRACTOR shall bear all costs associated with

    such repair or replacement.

    18.2.2.7 CONTRACTOR disclaims any responsibility and liability for

    defects or deficiencies during the warranty period for the

    relevant Non-Power Plant Facility which are due to

    faulty

    operation and maintenance as well as major repair

    works carried

    through

    by the COMPANY not in accordance

    with the operation and maintenance manual and

    recommendations or any recognized method.

    18.2.2.8 During the Warranty Period CONTRACTOR shall provide

    all and any consumable material and parts related

    to its

    warrantv obligations.

    18.3 Other Special Warranty

    I tems

    18.3.1

    Not Used

    18.3.2

    All building roofs shall have guarantee against water leakage for

    ten

    (10) years after the Preliminary Acceptance of each building.

    18.3.2

    Notwithstanding Paragraph

    17.8.2

    of

    this Schedule A , COMPANY

    shall issue the applicable Final Acceptance Certificate after one (1)

    A-32

    Construction of Qurayyah Open Cycle Power Plant Schedule A

    :.::

    .

    ; _·

    ;·:

  • 8/19/2019 Project B Warranty

    8/20

    SCHEDULE A

    9 l : 1 ~ ~ ~ ~ · ; a s ~

    Saudi Electricity Company

    r . - ~ :

    .:·:.:·:.·:.:

    CONTRACT

    NO. 30621090/00

    Gregorian

    year

    from Preliminary Acceptance Date

    of the

    Non-Power

    Plant Facility If

    there

    are no warranty defects but in no case beyond

    two 2) Gregorian years from the date of issuance of the applicable

    Preliminary Acceptance Certificate.

    18.4 Submission of

    Warranty

    Certificate

    All · warranties obtained by CONTRACTOR for materials

    or

    equipment

    purchased

    by CONTRACTOR for

    installation

    in the

    PROJECT shall be deemed

    to be for the benefit of COMPANY and shall on Preliminary Acceptance of the

    PROJECT

    be made available to COMPANY.

    18.5

    Rights & Remedies Provided

    by law

    The rights and remedies of COMPANY provided by this CONTRACT are in

    addition to any

    other

    rights and remedies provided by

    law or

    in Sharia

    or

    otherwise.

    18.6

    Repair Latent Defects

    CONTRACTOR

    is obliged

    at

    any given

    time

    to

    repair

    Latent Defects for a

    period of

    three

    3) Gregorian years from the

    expiry

    date

    of

    the Warranty

    Period of the respective Power Plant Unit and Non-Power Plant Facility. Latent

    Defects means a substantial defect in the equipment/WORK that

    materially

    affects the operation/ use or performance of the equipment/WORK, or any

    part thereof, which appears after expiry of the Warranty Period and would not

    have been disclosed by normal inspection procedures by COMPANY and was

    caused by or arises from the

    CONTRACTOR s

    Gross Negligence.

    19. Subcontracts

    19.1 COMPANY

    Authorization

    and

    Subcontracting

    Plan

    Any subcontract for the performance of any portion of the

    WORK

    shall be

    procured only

    after CONTRACTOR

    has received

    written

    authorization from

    COMPANY to subcontract

    that

    portion of the WORK.

    I f not

    already

    accomplished

    prior

    to the effective

    date

    of

    the CONTRACT,

    then promptly

    thereafter, CONTRACTOR

    shaH

    submit to COMPANY REPRESENTATIVE for

    COMPANY s

    approval, the CONTRACTOR s subcontracting plan. This

    subcontracting plan shall specifically identify those

    portions

    of

    the WORK

    that

    CONTRACTOR

    proposes to subcontract. In procuring subcontracts/

    CONTRACTOR

    shall select

    SUBCONTRACTOR

    solely on

    the

    basis of financial and

    technical considerations.

    This Paragraph shall be

    limited

    to

    major

    subcontracts and

    SUBCONTRACTORS

    included in CONTRACTOR s list of major subcontractors which shall be deemed

    approved

    by the

    COMPANY

    with the

    effectiveness

    of the

    CONTRACT.

    19.2 Subcontracting

    Notice to

    COMPANY

    19.2.1

    After receiving COMPANY s written authorization that a portion of the

    WORK may

    be subcontracted/

    CONTRACTOR

    shall, before procuring

    any subcontract, submit a notification to COMPANY containing the

    following

    information

    (This Paragraph shall only apply to

    major

    equipment

    and such

    SUBCONTRACTORS

    who are present on site.):

    a] I f the proposed SUBCONTRACTOR is a sole proprietorship or

    partnership

    1

    the name and address of the proprietor or each

    member of

    the partnership, as

    the

    case

    may

    be. ·

    A-33

    Construction

    of Qurayyah

    Open Cycle Power Plant Schedule A

    ~ : ;

    } . ~

    - - - - - - - - - - - ~

  • 8/19/2019 Project B Warranty

    9/20

    SCHEDULE

    A

    4 1 \ . ; 1 ~

    ~ ~ ~ ~ : a s ~

    Saudi

    Electricity

    Company

    CONTRACT NO. 30621090/00

    20.9 Consequential Damages

    CONTRACTOR,

    its agents and SUBCONTRACTORS, shall not be liable in any

    event to COMPANY nor

    shall

    COMPANY

    be liable

    to CONTRACTOR,

    Its agents

    and

    SUBCONTRACTORS,

    for any indirect, special, consequential losses or

    damages including,

    but not

    limited

    to,

    loss of

    profit or

    products, whether such

    liability is based, or claimed to be based upon any breach of either party's

    obligations

    under the CONTRACT, or whether

    such liability is based,

    or

    claimed

    to be based, upon any negligent act

    or

    omission of a party,

    its

    personnel,

    agents, appointed representatives or SUBCONTRACTOR.

    20.10 Maxjmum l iabi l i ty

    Except as provided in Paragraph 20.7 and notwithstanding anything contained

    elsewhere in this CONTRACT to

    the contrary,

    the total

    liability

    of CONTRACTOR

    and his

    SUBCONTRACTORS

    to

    COMPANY under this CONTRACT

    shall

    not

    exceed the amount

    of

    the

    CONTRACT

    Price set forth in Paragraph 1.1 of

    Schedule C

    as

    may be modified

    from

    time to time. All liabilities under

    this

    CONTRACT shall

    terminate

    four (4) years from Final Acceptance of the WORK

    except for

    the

    warranty liabilities contained in Paragraphs

    18.3

    and

    18.6

    of

    Schedule A .

    21.

    Insurance

    21.1 Carrv and Maintain Insurance at all Times

    CONTRACTOR shall, at

    its

    own expense, carry and maintain in force at all

    times

    the

    following insurance policies:

    21.1.1 Comprehensive General Liabil ity Insurance CCGLl

    a) Coverage

    Comprehensive General

    Uability

    Insurance coverage with

    limits

    of no less than twenty mil l ion Saudi Riyals (SR 20,000,000)

    per occurrence for

    bodily

    injury, death or property damage

    during the performance of the WORK. CONTRACTOR represents

    and warrants that the aforesaid insurance covers,

    without

    limitation,

    loss of,

    or

    damage

    to

    COMPANY's

    other

    property

    for

    which CONTRACTOR is responsible

    pursuant

    to Paragraph 20.5 of

    this

    Schedule

    A .

    b) Term

    CONTRACTOR shall carry and maintain this insurance in full force

    at

    all times from

    the

    effective date

    of

    the

    CONTRACT

    through the

    Preliminary Acceptance of all the PROJECT

    PORTIONS

    and

    thereafter during the Warranty Period, and until CONTRACTOR has

    fully demobilized from the

    WORK

    SITE.

    c)

    Designation

    of SELLER and

    COMPANY

    as Additional

    Insured

    in

    CGL

    Comprehensive General Uability Insurance shall designate

    SELLER and COMPANY as additional insured as regards SELLER's

    and COMPANY s liabilities for WORK performed by CONTRACTOR

    pursuant to

    the CONTRACT.

    A 37

    Construction of Qurayyah Open Cycle Power Plant Schedule A

  • 8/19/2019 Project B Warranty

    10/20

    SCHEDULE A

    ; . 1 . ; 1 ~ ~ . 1 ~ 1

    : a s ~ t

    Saudi

    Electricity Company

    CONTRACT NO. 30621090/00

    Such policy shall contain a cross-liability clause so that SELLER,

    COMPANY

    and

    CONTRACTOR

    are regarded as

    third

    parties to

    each

    other.

    21.1.2

    CONTRACTOR s

    All Risk Insurance

    a)

    Coverage

    CONTRACTOR's

    All Risk Insurance (CAR) coverage for

    the

    entire

    PROJECT. The sum insured

    per

    occurrence shall be no less

    than

    the

    total

    CONTRACT

    Price or replacement cost of the PROJECT

    and the cost of removing debris following an insured loss.

    b) CAR - Policy to be extended

    to

    cover In-Land Transit with a

    sub-limit of estimated value of items carried at any one

    time.

    c) Term

    CONTRACTOR shall carry and maintain this. insurance in full force

    ·at all times from the effective date of the

    CONTRACT

    through the

    Preliminary Acceptance of all the

    PROJECT

    PORTIONS and

    thereafter during

    the

    Warranty Period, and until

    CONTRACTOR

    has

    fully demobilized from the WORK SITE.

    d) Designation

    of SELLER

    and

    COMPANY as Additional

    Insured

    in CAR

    CONTRACTOR's

    All Risk Insurance shall designate

    SELLER

    and

    COMPANY as additional insured as regards

    SELLER's

    and

    COMPANY's liabilities for WORK performed by CONTRACTOR

    pursuant

    to

    the

    CONTRACT.

    Such policy shall contain a cross-liability clause so that SELLER,

    COMPANY and

    CONTRACTOR

    are regarded as

    third

    parties to

    each other.

    21.1.3 Professionallndemnitv Insurance

    21.1.4

    CONTRACTOR shall effect and maintain [a single

    project]

    Professional

    Indemnity insurance from the effective date of this CONTRACT until the

    date three (3) years from Final Acceptance

    of

    the

    WORK

    in the names

    of

    the

    CONTRACTOR,

    its

    SUBCONTRACTORS

    and consultants to

    indemnify

    them

    in respect

    of

    their legal liability for claims made against

    them during

    the

    period

    of

    insurance for any negligent act,

    error or

    omission by the CONTRACTOR, its SUBCONTRACTORS and consultants

    in the conduct and execution

    of

    their

    professional activities and duties

    relating the design and/or supervision

    of

    installation and/or testing and

    commissioning

    of the WORK.

    This insurance shall be in

    the amount

    of

    SR: 2 000 000 in respect of each claim and SR: 20 000 000 in the

    aggregate for all claims during

    the

    period

    of

    insurance, and shall be

    subject to worldwide jurisdiction. The deductible shall

    not

    exceed SR:

    25 000

    in respect of each claim

    or

    such other amount, which

    the

    COMPANY, acting reasonably, may approve in writing.

    Completed Operations

    Third

    Party Liabil ity

    Insurance

    CONTRACTOR shall effect and maintain in the joint names of the

    COMPANY,

    the CONTRACTOR, its

    SUBCONTRACTORS, and

    S - Ch

    other

    persons

    or

    parties

    as the COMPANY may

    choose Completed

    A 38

    Construction

    of

    Qurayyah Open Cycle Power Plant- Schedule A

  • 8/19/2019 Project B Warranty

    11/20

      · · · ·

    ·----------- · · - - · - - - ~ - ~ = · ' - : ' * . ~ , , f :

    ~ ~ ~ ~ j j ~ ~ ~ ·

    Saudi Electricity

    Company

    SCHEDULE A

    CONTRACT

    NO.

    30621090/00

    31. Taxes

    final certificates from

    the

    Directorate

    of

    Zakah and Income Tax

    as

    well

    as

    the

    General Organization

    of

    Social Insurance (GOSI) which confirm

    that

    all

    applicable Zakah and CONTRACTOR income

    tax

    obligations have been paid by

    CONTRACTOR through the previous Hijra year period.

    These certificates shalt be delivered to:

    The Manager

    Controller's Department

    Eastern Operating Area

    Saudi Electricity Company

    Room 2-215E,

    SEC-EOA

    Headquarters

    P.

    0. Box 5190, Dammam 31422

    Kingdom of Saudi Arabia

    31.1 Payment

    of

    Taxes

    CONTRACTOR, or CONTRACTOR s

    personnel, shall pay all taxes, penalties,

    customs duties, fees, levies, assessments and charges required or levied by

    the

    Government

    of the

    Kingdom

    of

    Saudi Arabia and

    the

    government

    of

    any

    country, or any political subdivision thereof, arising out of or relating to the

    performance

    of the

    WORK, without claim

    for

    reimbursement from COMPANY.

    31.2

    Withholding

    Tax

    Pursuant to pertinent provisions of the Income Tax Law of the Kingdom of

    Saudi Arabia issued under Royal Decree No. M/1 dated

    15/1/1425,

    an

    income

    tax

    will be deducted if the CONTRACTOR is considered as a Non-Resident in the

    Kingdom

    of

    Saudi Arabia (as defined

    in

    Article 3 of the Income Tax Law), in

    accordance with Paragraph 4.11 of Schedule C of this CONTRACT.

    32. Bank

    Guarantee

    32.1

    Amount and Validity

    Jo¢ z¢:?;r ~

    CON?;CTOR has presente,d Bank Guarantee

    ,

    dated / :1 « «

    2

    t : X ~ 7

    ~ . i # e . s - ~ / ~ t ; 9 ' ~

    issue by ~ a s . F ~ a n k , for Saudi Riyals, representing five

    percent '(5%) of the

    CONTRACT

    Price, as guarantee

    for

    CONTRACTOR s

    performance

    of

    the WORK. CONTRACTOR undertakes to keep the bank

    guarantee valid throughout the CONTRACT Term and

    for

    twenty-four (24)

    Gregorian months following

    the

    actual Preliminary Acceptance of all PROJECT

    PORTIONS. Upon

    written

    request

    of

    the

    CONTRACTOR,

    the

    value

    of the

    Bank

    Guarantee may be reduced at

    the

    end of the Warranty Period

    of

    relevant

    PROJECT PORTION(S) by an amount equal to five percent

    (5%)

    of the

    CONTRACT PRICE

    of the relevant PROJECT PORTION{S) or

    to

    an amount

    judged by COMPANY to be adequate to cover the value

    of

    any uncompleted

    portion

    of the WORK or the

    corrected/rectified WORK as mentioned in

    Paragraphs 18.2 and 18.6 of this Schedule A .

    32.2 Extension

    of

    Bank Guarantee

    In

    the event

    that the CONTRACTOR s

    Bank Guarantee needs

    to

    be extended,

    as a result of delayed Preliminary Acceptance due to any reason whatsoever,

    CONTRACTOR shall, no later than seven (7) days after the actual Preliminary

    A-49

    Construction

    of

    Qurayyah Open Cycle PowerPlant Schedule A

    ~ ]

    f.

    '

  • 8/19/2019 Project B Warranty

    12/20

    . f ) ; ( ~ : : ~ ~ ; ; ; f f : g ~ g :

    fSC)

    f:_,\ ;.}l

    ~ ~ K

    SCHEDULE A

    ~ ~ ~ 4 S ~ I

    Saudi

    Electricity Company

    CONTRACT

    NO.

    30621090/00

    Acceptance,

    submit

    to

    COMPANY

    an extension

    of

    the

    Bank Guarantee covering

    the entire

    warranty period.

    32.3 Failure by CONTRACTOR

    to Extend

    i ts Bank Guarantee

    Should

    CONTRACTOR

    fail to extend the validity of its Bank u a r a n t ~ e as

    required, COMPANY shall

    draw

    down

    the

    full amount

    of the

    Bank Guarantee.

    The CONTRACTOR shall be provided in any event, thirty (30) calendar days

    advance

    written

    notice during which time

    the

    CONTRACTOR must commence to

    cure the default to avoid the COMPANY drawing down on the Bank Guarantee.

    After

    expiration

    of the warranty

    period specified

    in

    Paragraph 18, Schedule A

    of the CONTRACT and if the COMPANY has

    drawn

    down the Bank Guarantee,

    then COMPANY shall refund to

    CONTRACTOR

    that

    amount

    of the Bank

    Guarantee which was drawn down, less that amount which COMPANY, in

    its

    full

    and absolute discretion, deems necessary to retain In

    order

    to

    meet the

    CONTRACTOR s

    warranty

    obligations.

    33. Validitv of

    Commercial Registration

    CONTRACTOR shall ensure

    that

    Its Commercial Registration (CR) or License is valid

    throughout the entire duration of the

    CONTRACT

    and any extension(s) thereof. In the

    event

    that its CR

    or

    License expires during the duration of

    the CONTRACT

    and any

    extenslon(s) thereof,

    CONTRACTOR

    shafl

    submit

    to COMPANY a copy

    of its

    application

    form or

    proof for

    renewal

    prior

    to

    the

    expiration of

    its

    CR or License and shall submit

    its new or renewed

    CR

    or License

    within forty-five (45)

    days

    after the

    expiration

    of its

    previous CR or License. Failure

    by CONTRACTOR

    to submit such

    document

    may cause

    COMPANY to withhold

    its

    invoices until its new or renewed

    CR

    or License is submitted

    to COMPANY.

    34.

    CONTBACT

    language

    This Schedule A has

    not

    been translated

    into

    Arabic.

    CONTRACTOR

    and COMPANY

    agree to be bound by the English text.

    35. General

    Provisions

    The CONTRACT supersedes all previous agreements, correspondence and

    understandings between the parties concerning

    the WORK,

    and constitutes

    their

    entire

    agreement concerning the

    WORK

    to be performed hereunder. No promise, agreement,

    representation

    or

    modification

    to the CONTRACT

    shall be of any force

    or

    effect

    between the parties, unless set forth or provided for in the

    CONTRACT,

    a CHANGE

    ORDER

    or an

    AMENDMENT.

    36.

    Packing and Deliverv

    Afl

    equipment

    must be packed in accordance

    with COMPANY

    general packing

    specification No. IO No. 0011 (6/82) which by this reference is

    made

    part of this

    CONTRACT.

    All shipments and deliveries shall be

    in strict

    accordance with the

    requirements of the CONTRACT.

    37. Protection Against

    Infringement

    CONTRACTOR warrants that the WORK does not infringe any patent rights, copyrights,

    trademarks, or

    trade

    secrets owned or controlled by

    any

    Third Party, either in the

    country

    of

    manufacture

    or

    use.

    CONTRACTOR

    agrees

    to

    defend,

    indemnify

    and hold

    COMPANY harmless against any and all liability, loss

    or

    expense arising out of patent,

    copyright, trademark infringement or trade secret misappropriation claim relating to

    the

    WORK.

    A 50

    Construction of Qurayyah Open Cycle Power Plant Schedule A

    .;

    *

    _________

    I

  • 8/19/2019 Project B Warranty

    13/20

     

    2. PLANT DESIGN CRITERIA

    2.1 General

    This Specification calls for the erection of gas turbine power plant and associated

    equipment and the design and supply of supporting services which shall initially be installed in open

    cycle configuration with the intention to convert to combined cycle at a later date. The design shall be

    modern, well proven, safe, economically attractive both in capital cost and running cost and offering a

    high availability with low forced outage rate. The plant shall be fully automated and require minimum

    operator intervention for normal operation. Contractor B shall comply with the Specification unless

    compliance would for any reason put at risk safety, reliability and economy due to deviation from

    standard practice of Contractor B. However, the intent of the Specification shall always be complied

    with.

     Any deviations from the Specification shall be clearly identified in Schedule FF, which shall

    be completed and returned as part of the Tender.

     Any new and additional equipment supplied under this Contract shall be designed and

    selected to ensure high reliability and availability of the complete plant with low forced outage rates and

    minimal maintenance over the lifetime of the power station, which shall be defined as 40 years.

     An appropriate level of redundancy shall be included in each new system; the Works shall

    be designed so that no single auxiliary plant failure shall result in the total loss of the unit generating

    capability. In this context, it is required that with agreed exceptions, all unit auxiliaries will be provided

    with at least one installed spare (N+1). For the station auxiliaries, no single equipment failure shall

    result in any loss of station generating capability.

    Prototype plant will not be acceptable, and plant that is offered with limited operating

    experience must be fully supported by manufacturer’s warranties and indemnities.

    2.2 Unit rating

    The gas turbine units, rated at the site ambient condition given in Schedule AA, shall meet

    the nominal power requirement range of 1900 MW ±  80 MW open cycle and shall be installed to

    provide 500 MW available generation by 1 June 2008 and further 350/400 MW available by 1 August

    2008, and with a further 1016 MW, ± 40 MW open cycle plant to be available for generation by 1 June

    2009. The CIF delivery dates for the gas turbine units, generator transformers, unit transformers and

    IPBs shall be as stated in Schedule BB.

    The gas turbine generators shall be suitable for outdoor installation and conversion to

    combined cycle operation 3+1 configuration at a later date.

    The guarantee and warranty for the gas turbines and associated equipment shall be the

    responsibility of the gas turbine generator supplier Contractor A without exception. The guarantee and

    warranty for any new and additional equipment supplied under this Contract shall be the responsibility

    of Contractor B and in the event that any other requirements of this Specification are in conflict with

    Contractor B’s ability to meet the performance requirements contained in Schedule CC1, such

    exceptions shall be identified. It is the intent that the gas turbine supplier supplies his standardmodular gas turbine design to the maximum extent possible.

    Page 3 of 330  PTS # 06EG902  - PROJECT-B, VOL-2CONSTRUCTION OF QURAYYAH OPEN CYCLE POWER PLANT

  • 8/19/2019 Project B Warranty

    14/20

     

    4.9 Spare parts

    Contractor B shall provide with his tender, for the equipment in Contract B, a complete

    priced list of spare parts, in Schedule HH. The list shall be developed on an estimated usage basis and

    supporting data from existing plants shall be provided to substantiate the spares holding and usage

    proposed.

    The priced list of spares shall include a recommended stockholding to cover all initial

    inventory, planned maintenance and strategic reserves up to and including the first 2 years of operation

    from plant takeover.

    Contractor B shall provide all the commissioning consumables and spares up to take over

    of the works.

    4.10 Special tools and lif ting devices

    Contractor B shall supply, for the equipment in Contract B, a complete set of any specialtools and other equipment necessary for the dismantling, work storage, re-erection and adjustment of

    any part of the plant. Tools shall be provided in new condition, adequately labelled to their use and

    contained in stout and suitable padlocked boxes.

     Any special lifting devices/slings required shall be provided and clearly marked by

    embossed labels which show safe working loads. Test Certificates shall be provided where applicable.

    Suitable lifting equipment shall be provided to facilitate removal and maintenance of plant

    and equipment. Lifting devices shall be designed in accordance with the latest editions of the relevant

    ISO standard or equivalent. All electrical and mechanical functions shall be tested before despatchfrom the manufacturer’s works. Operational and overload tests shall be carried out on site.

    Suitable lay down areas and methods of retrieving the equipment should be included to

    support the integrated approach to the crane facilities.

    4.11 Warranty engineer

     A warranty engineer shall be located on site for a period of one (1) year following the date

    of Takeover to cover the equipment in Contract B. The warranty engineer shall have not less than eight

    years experience of power plants similar to the Facility and shall act proactively to ensure the best

    performance and availability of the plant is achieved. A CV for the proposed engineer shall be

    submitted for approval prior to him taking up the appointment.

    The Contract shall include for all travelling, accommodation and subsistence costs of the

    engineer and for his replacement by a similarly experienced engineer during periods of leave or long-

    term sickness. The replacement engineer shall be to approval. Such approval shall not be

    unreasonably withheld.

    The warranty engineer shall be available on site between 0800 – 1700 hours Saturday to

    Thursday, and available for callout duty outside of these hours.

    Page 39 of 330  PTS # 06EG902  - PROJECT-B, VOL-2CONSTRUCTION OF QURAYYAH OPEN CYCLE POWER PLANT

  • 8/19/2019 Project B Warranty

    15/20

     

    The warranty engineering shall be responsible for the following throughout the warranty

    period:

    i. Ensuring that the O&M operator is operating and maintaining the entire plant in

    accordance with the manufacturers’ instructions, and notifying the Owner (SEC)

    and the O&M operator of any shortcomings.

    ii. Providing technical advice and support to the O&M operator.

    iii. Monitoring the performance and availability of the plant.

    iv. Assisting with troubleshooting.

    v. Acting as liaison with Contractor B’s head office for the clearance of any defects

    existing on Takeover or occurring during the warranty period, to ensure that they

    are cleared promptly.

    The Owner (SEC) will monitor the performance of the warranty engineer. Should his

    performance be unsatisfactory, Contractor B shall provide a replacement engineer to the satisfaction of

    the Owner (SEC).

    Page 40 of 330  PTS # 06EG902  - PROJECT-B, VOL-2CONSTRUCTION OF QURAYYAH OPEN CYCLE POWER PLANT

  • 8/19/2019 Project B Warranty

    16/20

     

    s. Assorted glass “T” and “Y” pieces.

    t. Separating funnels.

    u. Volumetric flasks.

    v. Reagent bottle.

    w. Funnels.

    x. Gas sample tubes.

    y. Dissolved oxygen sample tubes.

    6.4.8.5 Reagents

     A complete listing of all reagents required for the analytical equipment, reagents for manual

    analysis, standard reference solutions, and others required for a complete functioning laboratory shallbe provided for Owner (SEC) review. The reagents shall be of the required purity for the instruments

    and as required by ASTM test methods. The listing shall include the reagent name, and quantity

    recommended. Sufficient reagents shall be furnished for 2 years of operation after the warranty period.

    Contractor B shall advise the Owner (SEC) of reagents with shelf lives shorter than the warranty period

    plus 2 year period.

    6.4.8.6 Ancillary equipment

    The following ancillary equipment represents the minimum to be furnished. Ancillary

    equipment needed to provide a complete and functioning laboratory shall be furnished. A complete

    listing of this equipment shall be provided for Owner (SEC) review and acceptance. The listing shall

    provide a brief description, type, size, model number and quantity of each item:

    a) Analytical balance

    b) Electronic balance

    c) Calibration masses

    d) Westfall type specific gravity balance

    e) Camel’s hair balance brushes

    f) Balance desiccators

    g) Centrifuge, oil

    h) Muffle furnace

    i) Gas pressure regulator for oxygen cylinders

     j) Three-beam balance

    k) Portable sample cooler

    Page 118 of 330  PTS # 06EG902  - PROJECT-B, VOL-2CONSTRUCTION OF QURAYYAH OPEN CYCLE POWER PLANT

  • 8/19/2019 Project B Warranty

    17/20

     

    6.4.8.8 Accessories and spare parts

    Equipment furnished shall be provided with all required accessories and spare parts

    sufficient for 2 years of operation after the warranty period.

    6.4.9 Waste water systems

     A site effluent disposal system for 15 gas turbine open cycle configuration is required to

    ensure that all potentially contaminated wastes generated by the construction, operation and

    maintenance of the power station shall be controlled in accordance with World Bank guidelines and

    local legislation. This layout and arrangement of the waste water system shall take into account the

    requirement to extend the system for combined cycle conversion.

    Effluent from the drains of the laboratory, battery room, plant and chemical dosing drains

    shall also be suitably treated.

    Surface water with the potential of oil contamination shall be directed to an oil/waterseparator prior to discharge. All waste oil shall be collected for off-site disposal.

    Gas turbine compressor wash effluent shall be segregated and stored at a suitable location

    for off-site disposal.

    Sampling and instrumentation shall be included in the final discharge to ensure compliance

    with the requirements of relevant legislation. As a minimum, this shall include equipment to measure

    flow, temperature and pH. Provision to take a manual sample shall be provided. Discharge of

    wastewater outside agreed limits shall be prevented by the control system.

    For Qurayyah OCGT plant no discharge sewer is available, the final effluent disposal shall

    be routed to an evaporation pond. Two 100 per cent evaporation ponds shall be provided for the

    OCGT plant installation and the proposed site layout should take into account the requirement to

    construction additional evaporation pond(s) for the combined cycle plant conversion. Details of the

    proposed discharge system shall be provided within the Tender.

    For further details of the site waste water systems, refer to Section 9 of this Specification.

    6.4.9.1 Packaged sewage treatment plant

     A packaged sewage treatment plant shall be provided to cater for the total foul watertreatment requirements of the station, with adequate margins, under all conditions of operation. The

    plant shall be complete with sanitary drainage piping, manholes and grease traps required for

    conveying sewage, comminutor and bar screen, pre-engineered activated sludge modules, chlorination

    equipment, treated sewage holding facility, treated sewage transfer pump sets, interconnecting piping

    valves and supports, associated instruments and controls, associated electrical work, associated civil

    work and all tanks shall be fitted with access ladders, platforms, vents and access ports. Level and

    contents gauges shall be located for operational convenience.

    The plant shall be capable of treating 300 litres per day of raw sewage per person during

    normal operation together with a provision for peak demand at 2.5 times normal operational flow.

    Page 123 of 330  PTS # 06EG902  - PROJECT-B, VOL-2CONSTRUCTION OF QURAYYAH OPEN CYCLE POWER PLANT

  • 8/19/2019 Project B Warranty

    18/20

     

    8. INSTRUMENTATION AND CONTROL

    8.1 Introduction

    This Section describes the technical requirements for the supply and installation of

    instrumentation and control (I&C) for the open cycle power plant. All I&C equipment necessary to allow

    the safe and efficient operation of the power plant shall be supplied, installed, commissioned and

    tested.

    Gas turbine generators (GTGs) and ancillary equipment, a hydrogen plant and ancillary

    equipment and a CEMS system together with all associated I&C equipment and systems will be

    supplied under a separate contact by Contractor A. Contractor B will be responsible for interfacing to

    and/or integrating these I&C systems into the DCS and other control/monitoring systems being supplied

    to provide an integrated system for the control and monitoring of the power plant.

    The DCS will provide control, monitoring, alarming, trending, logging, archiving and data

    acquisition and storage for the gas turbines and associated equipment for each combined cycle block.

     A consistent control, instrumentation and data acquisition philosophy shall be applied

    throughout the power plant. The objective shall be to standardize all equipment, wherever possible,

    throughout the power plant in order to rationalize operation, maintenance and reduce spare parts. In

    general, all equipment shall be of modern compact design, incorporating proven technology and

    supplied from one composite range as marketed by a reputable international manufacturer. The DCS

    Vendor shall be from a short list of reputed manufacturers approved by SEC.

    The hardware and software for DCS shall be the latest available at the time of system

    installation. The latest system software version shall be made available for all units prior to the

    completion of warranty period so as to have an identical and latest software version for all systems of

    the plant.

    Contractor B shall be responsible for liaising with Contractor A and Owner (SEC) to obtain

    all data and information necessary to allow for the design, build and commission of his I&C systems,

    DCS and interfaces required to connect to Contractor A’s equipment and SEC existing equipment.

    8.2 Scope of supply

    The extent of supply described shall be the minimum necessary to achieve the required

    objectives and shall consist of, as a minimum, the following:

    a. Complete control, protection and monitoring systems for the plant being provided

    including the fuel systems, gas detection, fire detection, common services and

    auxiliary equipment.

    b. Interfaces to and integration into the DCS and other control and monitoring systems

    of equipment provided by Contractor A.

    Page 189 of 330  PTS # 06EG902  - PROJECT-B, VOL-2CONSTRUCTION OF QURAYYAH OPEN CYCLE POWER PLANT

  • 8/19/2019 Project B Warranty

    19/20

     

    h. Packing for shipment including check for completeness of shipment, handling

    requirements, and case markings and identification.

    Contractor B shall keep the Engineer/Owner (SEC) informed in advance of the time of

    starting and of the progress of the work in its various stages so that arrangements can be made for

    inspection and for test. Contractor B shall plan the performance of inspection and tests so as to avoid

    the delaying of the work.

     All of the required inspections and tests shall be made at Contractor B's expense.

    Contractor B shall include for all travel and accommodation costs incurred by the Owner (SEC) in

    attending inspection visits and including the cost of all samples used. Contractor B shall be responsible

    for any additional costs incurred by the Engineer/Owner (SEC) arising from the postponement, re-

    inspection or additional inspections or visits attributable to Contractor B, subcontractors or suppliers’

    performance as deemed necessary by the Engineer/Owner (SEC). Contractor B shall also provide,

    without charge, all reasonable facilities and assistance for the safety and convenience of the

    Engineer/Owner (SEC) in the performance of his duties.

    If the plant or any portion thereof fails under test to give the required performance, such

    further tests which are considered necessary by the Engineer/Owner (SEC) shall be carried out by

    Contractor B and the whole cost of the repeated tests shall be borne by Contractor B. This also applies

    to tests carried out at subcontractor’s works.

    10.6 Non-conformances

    Non-conformances identified by the Engineer/Owner (SEC) shall be notified to Contractor B

    by issue of the Engineer’s Non-Conformance Report. Contractor B shall receive and action all non-

    conformance reports and re-inspection shall not be notified until the completed non-conformancereport, together with any applicable re-work or concession application, have been accepted by the

    Engineer/Owner (SEC)

    Where applicable, rejection of materials, equipment and/or components will be made as

    promptly as practicable following any inspection or test involvement by the Engineer/Owner (SEC)

    Failure to inspect and or reject materials, equipment and/or components shall neither relieve

    Contractor B from responsibility for such items which may not be in accordance with the specified

    requirements, nor impose liability for them on the Engineer/Owner (SEC)

    Contractor B and subcontractors quality assurance programme shall identify and isolate

    raw materials and components not conforming to the Design Book. All such items shall be reported to

    the Owner (SEC) via a non-conformance report.

     Approval of a concession application is the prerogative of the Engineer/Owner (SEC) and

    approval of a particular case shall not set precedent.

    The Engineer/Owner (SEC) shall have complete authority to accept or reject any

    equipment or part thereof considered unsatisfactory and/or not in accordance with the contract

    requirements.

    Page 318 of 330  PTS # 06EG902  - PROJECT-B, VOL-2CONSTRUCTION OF QURAYYAH OPEN CYCLE POWER PLANT

  • 8/19/2019 Project B Warranty

    20/20

     

    The witness of any inspection and tests by the Engineer/Owner (SEC) of any components

    or lots thereof does not relieve Contractor B of any responsibility whatever regarding defects or other

    failures which may be found before the end of the warranty period.

    10.7 Quality control records, certificates and certificates of conformance

     At the end of each visit to a manufacturer to carry out quality control activity, the Engineer’s

    Representative will complete a Quality Control Record and hand one copy to a responsible

    representative of the Manufacturer.

    The Quality Control Record (QCR) will identify the item inspected, the stage of

    manufacture, and the nature of the QC carried out, and will list all points which require remedial action

    by the manufacturer, before the subject item can be released.

    When each item of equipment is ready for despatch from the place of manufacture and the

    Engineer/Owner (SEC) has verified compliance with specified requirements up to that point, a Quality

    Control Certificate will be issued to Contractor B.

    The Quality Control Certificate (QCC) will identify the item to which it applies and will

    release that item from the Engineer’s control only. The QCC does not constitute any form of

    acceptance of the item by either the Engineer or the Owner (SEC).

    Contractor B shall provide a Certificate of Conformance confirming compliance with the

    Contract requirements and as detailed in the manufacturing record data book.

    Sets of all test records, test certificates and performance curves, whether or not they have

    been witnessed by the Engineer, shall be supplied for all tests carried out in accordance with theprovisions of this Contract.

    Sets of all test certificates shall be endorsed with sufficient information to identify the

    material or equipment to which the certificates refer, and shall carry in the top right hand corner the

    following reference:

    Owner’s name

    Project title

    Engineer’s reference number.

     All test documentation shall be in the English language.

    No materials or equipment shall be shipped to the site until all tests, analysis and

    inspections have been made and Contractor B's Certificate of Conformance has been reviewed and

    released by the Engineer/Owner (SEC) or unless otherwise agreed by the Engineer/Owner (SEC)

    10.8 Specif ic tests and inspections

    Refer to Schedule GG for details of specific tests and inspections.

    Page 319 of 330 S # G O C O