project case poland, 2016 – the chańcza water...

1
Project scope Drilling drainage holes to prevent water filtration from eroding the body of the Chańcza reservoir • Number of holes: 307 • Depth/inclination: Up to 52 m (171 ft.)/vertical • Scope of drilling/total meters: 10 632 m (34 882 ft.) • Why water-propelled drilling? A high rate of penetration (ROP) and precision drilling was needed. After drilling to the projected depth, casing was used for cementation of individual zones. Project Case Poland, 2016 – The Chańcza Water Reservoir gds geo drilling solutions ab Equipment • Hammer model/sizes: WAI 40i • Drill bit/Casing system: Super Max bit Ø152 (6’’) Pump: Halliburton HT400 and T10 • Water source: From the Chańcza water reservoir • Drill rig: Two KLEMM 806 • Geologic formation: Different layers of grain sands, limestone and sandstone; each hole ended in solid sandstone. Main stakeholders • Commissioner: RZGW Kraków • Designing engineer: STAAND • Main contractor: SOLEY Sp. z o. o. Project/drilling results The earth barrier was sealed off and the length of the path of it was extended. Cross-sectional view of the reservoir Photo: https://commons.wikimedia.org

Upload: nguyenkhue

Post on 26-Aug-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

Project scopeDrilling drainage holes toprevent water filtrationfrom eroding the bodyof the Chańcza reservoir• Number of holes: 307• Depth/inclination: Up to 52 m(171 ft.)/vertical

• Scope of drilling/total meters: 10 632 m (34 882 ft.)• Why water-propelled drilling? A high rate of penetration (ROP) andprecision drilling was needed. After drilling to the projected depth,casing was used for cementation of individual zones.

Project Case Poland, 2016– The Chańcza Water Reservoir

gds geo drilling solutions ab

Equipment• Hammer model/sizes: WAI 40i• Drill bit/Casing system: Super Max bit Ø152 (6’’)•Pump: Halliburton HT400 and T10• Water source: From the Chańcza water reservoir• Drill rig: Two KLEMM 806• Geologic formation: Different layers of grain sands, limestoneand sandstone; each hole ended in solid sandstone.

Main stakeholders• Commissioner: RZGW Kraków• Designing engineer: STAAND• Main contractor: SOLEY Sp. z o. o.

Project/drilling resultsThe earth barrier was sealed off and the length of thepath of it was extended.

Cross-sectional view of the reservoir