![Page 1: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/1.jpg)
Project Concept &
Project Cycle
![Page 2: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/2.jpg)
Project
§ set of interrelated activities and inputs § to attain specific objectives / solve
problems § contributing to a higher goal § over a specific time-period § at specific budget § in a specific location § under responsibility of a separate
management unit
![Page 3: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/3.jpg)
What is a project?
A project is: A series of activities aimed at achieving specified objectives within a defined time period and budget
A project should also have clearly identified…. § Stakeholders and beneficiaries § Problems to be addressed and opportunities realized § Monitoring and evaluation arrangements; and § Benefits which exceed expected costs and are likely to be
sustainable
See page 8 PCM guidelines
![Page 4: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/4.jpg)
Project Cycle EU
Programming
Evaluation
Implementation Formulation
Identification
Financing
See page 16 PCM guidelines
![Page 5: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/5.jpg)
Programming
Within this framework individual projects can
be identified and carried out
Programming
Evaluation
Implementation Formulation
Identification
Financing
![Page 6: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/6.jpg)
Identification
Analysis of relevant project ideas
Programming
Evaluation
Implementation Formulation
Identification
Financing
![Page 7: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/7.jpg)
Identification
Ø Stakeholder analysis Ø Situation analysis/ Problem Tree analysis
Ø Identification of options to address the problems
Programming
Evaluation
Implementation Formulation
Identification
Financing
![Page 8: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/8.jpg)
Formulation
Feasibility Study
Ø Relevance Ø Feasibility Ø Sustainability
Programming
Evaluation
Implementation Formulation
Identification
Financing
![Page 9: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/9.jpg)
Formulation
Relevance § is the project linked to sectoral,
national and/or the agency’s objectives?
Feasibility § is the project likely to succeed? § are the objectives going to be
achieved? E.g. build a new school but have no teachers…
Programming
Evaluation
Implementation Appraisal
Identification
Financing
![Page 10: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/10.jpg)
Formulation
Sustainability § Is it likely to generate long-
term benefits? § Is the flow of benefits going to
be continued? No one-time activities
Programming
Evaluation
Implementation Appraisal
Identification
Financing
![Page 11: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/11.jpg)
Formulation
Design of a project in full operational
detail.
Programming
Evaluation
Implementation Formulation
Identification
Financing
![Page 12: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/12.jpg)
Financing
A financing proposal
is completed (financing
agreement/contract) and a decision is taken whether or not to fund the
project.
Programming
Evaluation
Implementation Formulation
Identification
Financing
![Page 13: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/13.jpg)
Implementation
Once a project has been planned and
financial support has been secured,
implementation can start.
Programming
Evaluation
Implementation Formulation
Identification
Financing
![Page 14: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/14.jpg)
Implementation
Progress is assessed (monitoring) to
adjust to changing circumstances
Programming
Evaluation
Implementation Formulation
Identification
Financing
![Page 15: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/15.jpg)
Evaluation
§ During implementation (mid –term evaluation)
§ At the end
(final evaluation) § Afterwards
(ex post evaluation)
Programming
Evaluation
Implementation Formulation
Identification
Financing
![Page 16: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/16.jpg)
PCM and “Call for proposals”
Call for Proposals (CfP’s): - usually under thematic budget lines - e.g SWITCH-Asia, EIDHR, Thematic
Programme for the Environment, food security and NSA’s
- Provide grants to e.g. NSA’s or LA’s - EU establishes the general objectives; scope
of projects; application and assessment procedures and eligibility criteria See page 17 PCM guidelines
![Page 17: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/17.jpg)
INTERNATIONAL INSTITUTE FOR GEO-INFORMATION SCIENCE AND EARTH OBSERVATION
Designing a project
Problem analysis
Problem and Objective Tree
![Page 18: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/18.jpg)
18
Problem & Objective Trees Analysis
Problem & Objective Trees Analysis is part of Objective Oriented Project Planning
![Page 19: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/19.jpg)
19
What is OOPP?
§ Discussion and analysis of relationships of causes and effects of a problematic situation
§ Visualised in a problem tree § Based on this causal picture, objectives
are formulated, visualised in an objective tree
§ Based on this objective tree, a project strategy is selected
§ Detailed project planning can follow
![Page 20: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/20.jpg)
20
Why?
Involvement of stakeholders essential: § Problems are perceived differently by different
groups in society § For ownership and commitment to the planning
process: the direct involvement of all parties at all stages
![Page 21: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/21.jpg)
21
Basic steps in OOPP
§ Analysis phase § Stakeholder analysis § Problem analysis § Objectives analysis § Strategic Alternatives analysis
§ Planning phase § Logical Framework
![Page 22: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/22.jpg)
22
Problem Analysis
§ Inventory of key problems § Define core problem § Other problems are grouped in a
hierarchical structure, reflecting causal relationships
See page 67 PCM guidelines
![Page 23: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/23.jpg)
23
Problem Analysis (2)
effects
Core Problem
causes
§ Cause and effect: developing the problem tree
![Page 24: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/24.jpg)
24
Problem Tree loss of confidence in bus company
Economic losses for passengers
Passengers are hurt or killed
People arrive too late
Frequent bus accidents
Drivers are not careful enough
Bad condition of vehicles Bad condition of roads
Vehicles are too old Insufficient maintenance
![Page 25: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/25.jpg)
25
Objective Analysis
Objective
Passenger confidence is restored
Vehicles are kept in good condition
Problem
Loss of confidence in bus company
Bad condition of vehicles
Each problem is converted into an objective: § negative problem reworded as a positive
statement
See page 68 PCM guidelines
![Page 26: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/26.jpg)
26
Objective Analysis
Describes the situation in the future once identified problems have been solved
Verify the hierarchy of objectives Illustrates the different means-ends
relationships in a diagram.
Negative situations -> solutions / positive achievements
![Page 27: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/27.jpg)
27
Objectives
§ Objectives will follow the cause and effect logic of the underlying problem tree
![Page 28: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/28.jpg)
28
Objective analysis: objective tree Passenger confidence is restored !
Passenger economic losses are reduced!
Few passengers are hurt or killed
People arrive on time !!
Frequency of bus accidents considerably reduced
Drivers drive carefully and responsibly!
Vehicles are kept in good condition
Road conditions are improved
Old vehicles are replaced
Vehicles are maintained regularly
Drivers are better trained
![Page 29: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/29.jpg)
INTERNATIONAL INSTITUTE FOR GEO-INFORMATION SCIENCE AND EARTH OBSERVATION
Logical framework
![Page 30: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/30.jpg)
30
Link between PCM and LFA
Project Cycle management
Defines different phases in the life of a project with well defined management activities and decision-making procedures
Logframe Approach A methodology for planning, managing and
evaluating projects, using tools which promote systematic analysis, stakeholder participation and structured documentation
PCM The decision-making and implementation process defined by the organization
LFA Project management method And tools
![Page 31: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/31.jpg)
31
Logical Framework Approach (LFA)
§ Can help in project design if the process steps are followed flexibly and its limitations are understood and addressed
§ The output of the LFA is the logframe matrix, which summarises the intervention logic (with assumptions) and Monitoring & Evaluation
§ The logframe matrix can be used to track progress with annual work plans and impacts.
See page 57 PCM guidelines
![Page 32: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/32.jpg)
32
Logical Framework Approach (LFA)
§ Project tool for analysis, presentation and management
§ Involves problem analysis, stakeholder analysis, developing hierarchy of objectives
§ Identifies strategic elements of a project: § Inputs § Results § Purpose § Goal
![Page 33: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/33.jpg)
33
Logical Framework
Application § preparation/design/formulation § appraisal/assessment § implementation § monitoring § evaluation
![Page 34: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/34.jpg)
34
Logical Framework (‘LogFrame’)
4-by-4 matrix that makes the logical
relationship between activities, outputs,
purpose and goal of a project, or plan
more transparent
![Page 35: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/35.jpg)
35
Logical Framework
Intervention logic
OVI MOV Assumptions
Goal Purpose Results Activities Inputs Budget Pre-conditions
![Page 36: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/36.jpg)
36
Logical Framework
Main elements
§ Intervention Logic: Hierarchy of objectives
§ OVI: Objectively Verifiable Indicators
§ MOV: Data sources (means of verification MoV)
§ Assumptions
![Page 37: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/37.jpg)
37
Logical Framework – intervention logic
§ A vertical logic
§ Clarifies “why” a project is being undertaken
§ Goal, purpose, results, activities and inputs are presented systematically as a hierarchy of objectives
![Page 38: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/38.jpg)
38
Logical Framework (10 steps)
1. Start with the intervention logic column § define the impact: purpose (ONE) § define the goal (can be one or more) § define results and activities
![Page 39: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/39.jpg)
39
Intervention Logic
§ Goal: refers to ultimate overall objective (often national or sectoral)
§ Purpose: describes the immediate project objectives (specific objectives)
§ Results: expected outputs of the activities undertaken by the project
§ Activities: define how the project is implemented to obtain the set results
§ Inputs: resources to carry out the project (means)
![Page 40: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/40.jpg)
40
Link LogFrame – Objective Tree
1
2
3
Intervention Logic
Intervention logic
Goal
Purpose
Outputs
Activities
![Page 41: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/41.jpg)
41
Logical Framework assumptions-example
Goal Reduced Unemployment Purpose Expansion of small scale shoe industries Results 1. Improved credit system 2. Increased management skills
Purpose-Goal assumption: Employment in other sectors maintained
Results-Purpose assumption Sufficient market opportunities for products of small-scale-industries
![Page 42: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/42.jpg)
42
![Page 43: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/43.jpg)
43
Assumptions
§ external factors/conditions § positively formulated § crucial for the success of the project § outside the control of the project
![Page 44: Project Concept Project Cycle - utm.my · 30 Link between PCM and LFA Project Cycle management Defines different phases in the life of a project with well defined management activities](https://reader031.vdocument.in/reader031/viewer/2022021717/5b42eba07f8b9a85708b70a5/html5/thumbnails/44.jpg)
44
Assumptions
Example Organisation keeps trained staff in jobs