PROJECT DELIVERYMethods and Contracts
“You can get there from here.”
![Page 2: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/2.jpg)
The Construction Specifications Institute is a Registered Provider with The American
Institute of Architects Continuing Education Systems. Credit earned on completion of
this program will be reported to CES Records for AIA members. Certificates of
Completion for non-AIA members available on request.
This program is registered with the AIA/CES for continuing professional education.
As such, it does not include content that may be deemed or construed to be an
approval or endorsement by the AIA of any material of construction or any method or
manner of handling, using, distributing, or dealing in any material or product.
Questions related to specific materials, methods, and services will be addressed at
the conclusion of this presentation.
![Page 3: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/3.jpg)
Learning Objectives
• To understand the 4 basic project delivery methods
• Learn the basic structure of AIA contracts
• Understand the benefits and limitations of each method
• Identify the challenges to A/E performance with each method
• Review recent trends in construction delivery
![Page 4: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/4.jpg)
Continuing Education Resources
• AIA "Project Delivery" search at www.AIA.org (video and articles)
• AIA Handbook of Professional Practice; Ch. 9 & 17
• CSI Project Delivery Practice Guide, 3rd Edition. Ch. 7
• Whole Building Design Guide; www.Wbdg.org
![Page 5: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/5.jpg)
What is the CDT?
• Study in the preparation and execution
of Construction Documents
• Taken from the CSI Project Delivery
Practice Guide
• An exam
• A Professional Certification
• A prerequisite for advanced CSI
Certifications
![Page 6: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/6.jpg)
Who pursues a CDT?
– Owners
– Designers (Architects/Engineers)
– Contractors (including subs)
– Suppliers
– Manufacturer’s Representatives
![Page 7: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/7.jpg)
CDT benefits?
Increases your confidence in understanding the
design and construction process
Raises the confidence of clients by
demonstrating your knowledge
Differentiates you from others by your
achievement of Certification.
Assists in preparing for the Professional Practice
A.R.E
Search "CDT" at www.csinet.org
![Page 8: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/8.jpg)
8This presentation is protected by US and International copyright laws.
Reproduction, distribution, display and use of this presentation without written
permission of the speaker and The Construction Specifications Institute is prohibited.
© CSI 2020 www.csiresources.org
PROJECT DELIVERYMethods and Contracts
“You can get there from here.”
![Page 9: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/9.jpg)
Where is “there?”
![Page 10: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/10.jpg)
...misunderstanding of
contractual obligations continue to
be a primary cause of disputes.
“Global Construction Disputes Report 2019, Arcadis
It matters how you get there.
![Page 11: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/11.jpg)
What is Project Delivery?
• AIA: “a process that allocates
roles and responsibilities...”
• AGC: “the assignment of
responsibilities, establishing
performance, building trust”
• CSI: “..sets contractual
relations in a sequential
process from project
conception to completion.”
![Page 12: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/12.jpg)
What is Project Delivery?
• the design and construction
process that
• assigns responsibilities
• sets performance requirements
and conditions
• by a sequence of procedures
• in the form of a written contract
![Page 13: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/13.jpg)
Selecting a delivery type
![Page 14: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/14.jpg)
Owner influences on selection
Experience with a type of construction
Risk assessment
Use of planning specialists:
Programming
Scheduling
Estimating
Funding
![Page 15: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/15.jpg)
Not always a choice PublicFunding from taxation
Method controlled by law
Pre-qualification
Public / Private Partnerships
PrivateFunding from capital, loans
& donors
Individuals
Private Institutions
Developers
Businesses
![Page 16: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/16.jpg)
Advance Preparations
Project Conception / Description
Owner team formation
– Owner's experts
– CM or contract advisors
– Planning Professional
Clarify program / constraints
Establish budget
Select project delivery method
Hire Design Architect
![Page 17: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/17.jpg)
Project Delivery factors affecting A/E
• Organization
– Selecting team members
– Establishing quality control /
workplan
• Execution
– Design
– Production of construction
documents
• Quality Assurance
– Communications
– Coordination of documents
– Administration during
construction
![Page 18: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/18.jpg)
– Extent (scope)
– Cost
– Time
Delivering a balance
![Page 19: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/19.jpg)
The main choices
Design – Bid - BuildB101 (Architect-Owner), A201 (Owner-Contractor), A101 (General Conditions)
Construction Manager at Risk or CM as AdvisorB133 (Architect-Owner with CM), A133 ( Owner-CM), A232 (General Conditions-CM)
Design – BuildC141 (Consultant – Owner) for concept design, bridging documents), A141 (Owner -
Design Builder), A142 (Design Builder – Contractor), A143 (Design-Builder – Architect)
*DBIA No. 535 (General Conditions)
Integrated Project Delivery IPDB195 (Multi-Party Agreement), A195 (Owner-Contractor IPD), A295 (General Cond.)
![Page 20: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/20.jpg)
Defining the elements
![Page 21: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/21.jpg)
Extent (Scope)
Defined by...
Magnitude
Form
Function
Complexity
Simple:
limited extent of work, simpler documents, fewer team members, and a more linear sequence of short duration
Complex: (small or large):
Many diverse elements, phased documents, many teams, specialties, bid packaging, scheduling challenges.
“Fee accordingly”
![Page 22: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/22.jpg)
Cost
Decided by...
– Stipulated / Lump sum (traditional)
– Cost (of the Work) plus a fee
• Fixed percentage of construction
• Service fees (Advising, multiple contracts)
• Guaranteed maximum price (GMP)
• "Soft costs" are planning, design or advisory fees.
• "Hard" cost to buy labor and materials
Cost controls
– Penalties, incentives
– Unit pricing, allowances, alternates
– Contingency funding
![Page 23: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/23.jpg)
Time
Time (duration & sequence)
“Time is of the essence”
expressed in:
Specific date(s)
Duration (calendar or working)
Sequencing of Activities:
Linear or Concurrent (overlapping)?
![Page 24: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/24.jpg)
Scheduling
"Fast –Track"
Not a delivery method, but a technique
Separates work into multiple contracts
Based upon project scheduling
Ensures completion in a condensed period of time
NOTE!
» A/E may be involved in design, construction documents,
contract packages, bidding, negotiation, and contract
administration simultaneously.
![Page 25: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/25.jpg)
Pre-Qualification
"IDIQ" Indefinite Delivery, Indefinite Quantity
For multiple projects of simpler scope
Aimed at retaining A/E services over time
Can use any delivery method to build
Allows flexibility to local Owners using public funds
"MATOC" Multiple Award Task Order Contract
Federal and Military
Aimed at retaining Contracting services
![Page 26: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/26.jpg)
The Structure of Contracts
![Page 27: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/27.jpg)
Tripartite Relationship• The essence of any Project contract is between three parties
![Page 28: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/28.jpg)
AIA Contracts
Design-Bid-Build Family
Design-Build Family
Construction Management Family
Integrated Project Delivery Family
![Page 29: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/29.jpg)
Basic provisions (AIA Contracts)
Article 1. Definitions: Basis of performance and changes
Article 2. Define the “Work”
Article 3. Time. Start and End dates
Article 4. Cost of the Work
Article 5. Forms of payments
Article 6. Dispute resolution
Article 7. Termination provisions
Article 8. Special provisions (insurance, bonds, etc.)
Article 9. Renumerate the (binding) documents
Article 10. Signatures
![Page 30: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/30.jpg)
Conditions of the Contract
• Defines basic rights,
responsibilities, and
relationships of parties
involved in performance
of Contract. Read it!
• Inherent part of (most)
Owner-Contractor
Agreements
• Follows the same order
of provisions / topics as
the Agreement.
3
0
![Page 31: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/31.jpg)
Conventional contract roles
![Page 32: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/32.jpg)
Benefits of standard contracts
Familiarity of use across A/E/C industry
Standard order and location of provisions
Standard use and definition of terms
A balance of roles, rights and responsibilities
![Page 33: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/33.jpg)
33
Important Legal ConceptsContracts are standardized, but projects are unique
• A/E obligations extend beyond their contracts:
– Professional Standard of Care
– Compliance with codes, laws and regulations
• Professionals are NOT
required to be perfect,
but contracts include “remedies.”
– Change process
– Termination
– Financial recompense (Damages)
![Page 34: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/34.jpg)
Putting it together
![Page 35: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/35.jpg)
Facility Types SimplerOne Function
Single building system
Limited services
Limited specialites
Fewer trades
Few constraints
ComplexMultiple functions
Multiple materials &
systems
Highly specialized services
Diverse trades
Cost & time controls
Parking GarageResearch &
Development
Office
Sitework
![Page 36: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/36.jpg)
Single system
SimplerConcrete frame
Lighting, drains
Elevators
Priority of constraints:
Extent (# of cars)
Cost (per stall)
Time
Parking Garage
![Page 37: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/37.jpg)
Familiar construction
ModerateConcrete foundations, Steel
frame, light gauge studs
Typical MEP + IT
Multiple Finishes
Common floor plan
Priority of constraints:
Time (relocate staff)
Extent (least s.f.)
Cost
Office Building
![Page 38: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/38.jpg)
Corporate Identity
ComplexSteel, Concrete, Curtainwall
Sustainable Design
Multiple labs and uses
Security, Data Networks
Phased build-out
Alternate energy
Specialized equipment
Extensive planning
Main constraint: Extent
Research &
Development
![Page 39: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/39.jpg)
Infrastructure
ModerateUnderground services
Earthmoving
Plantings
Site design
Priority of constraints:
Time
Cost
Extent
Sitework
![Page 40: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/40.jpg)
Tripartite Relationship• The essence of any Project contract is between three groups
![Page 41: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/41.jpg)
Project Delivery factors for the A/E
• Organization / Relations
– Selecting team members
– Establishing management
procedures
• Execution
– Project design
– Production of construction
documents
• Quality Assurance
– Meetings
– Communications
– Coordination of documents
– Administration during
construction
![Page 42: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/42.jpg)
Design-Bid-Build (D-B-B)
![Page 43: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/43.jpg)
Extent:
Limited complexity best, but all project types
Single contract
Cost:
Advance Estimating can be detailed
Competitive pricing, but less freedom to negotiate
Cost is fixed, known quantity
Lowest tolerance to changes
Time:
Linear sequence of events
Historical Familiarity, delays better understood
Design-Bid-Build (D-B-B)
Benefits
![Page 44: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/44.jpg)
Organization / Relations:
Familiarity across participants
Owner has greater control, can develop trust in A/E.
Execution:
Linear sequence of documents
Better client agreement of scope
Architect is main influence in design
Quality Assurance:
Fuller document coordination possible
Fewer cost controls needed
Architect – Contractor communications limited.
Design-Bid-Build (D-B-B)
Factors for A/E
![Page 45: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/45.jpg)
Organization / Relations:
– Inherently adversarial
– Client experience level may not match
Execution
- Document coordination & completion are critical
- Contractor entitled to rely on documents
- Redesign a real possibility to meet budget
Quality Assurance
– “Bid Day Surprise” when bids exceed budget
– Unknowns cause more changes, numerous RFIs.
– Owner has no input on quality of subs or management of work.
– A/E Duty to adminster project is higher.
Design-Bid-Build (D-B-B) Limitations
![Page 46: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/46.jpg)
Facility Types
Parking Garage
D-B-B
Research &
Development
Office
D-B-B
Sitework
![Page 47: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/47.jpg)
Construction Management, CM at
Risk (CMc)
Click to add text
![Page 48: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/48.jpg)
Extent:
– Typically used for complex projects needing cost controls
– CM’s advanced knowledge decreases Owner risks with:
• Coordination of construction / constructability
• Cost management
• Time management
• Quality controls
• Safety (I.e. Owners liability)
Execution:
– CM’s provide services beyond A/E’s basic services.
– Earlier CM involvement influences on A/E's design activities
– Documents prepared in stages, longer work plan. Some backtracking
– Greater opportunity for Owner input and agreement
– Team communications may improve to potentially lessen change orders
Construction Management (CM at
Risk) Benefits
![Page 49: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/49.jpg)
Time:
– Typically CM have expertise in Fast Tracking sequence
– Delays lest costly overall due to overlapping activities
– Long lead items taken into account earlier
– Owner's long range planning can be more effective.
Construction Management (CM at
Risk) Benefits
![Page 50: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/50.jpg)
Organization / Relations:
– Some competition with Owner's attention.
– Need additional layer of A/E leadership to coordinate with CM
Execution:
– Earlier involvement / assistance to A/E during design activities
– Documents prepared in stages, longer work plan
– Greater opportunity for Owner input and agreement
– Team communications improved to potentially lessen change
orders
Construction Management (CM at
Risk) Factors for A/E
![Page 51: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/51.jpg)
Quality Assurance
- Communications can be more open, less adversarial
- Schedules can be completed with greater accuracy
- Cost management can aid material choices, fewer surprises
- Document coordination becomes a team effort
Trends
- "Design Assist:" Earlier involvement of CM with cost / constructibility advice
- A process similar to "bridging documents" in Design-Build during project schematics
but uses Suppliers and Specialty Contractors to provide design input and pricing,
including early shop drawings.
- CM's are proposing limited General Conditions to control overhead management
expense
Construction Management (CM at
Risk) Factors
![Page 52: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/52.jpg)
Organization / Relations:
• Not typically suitable for simpler, one contract projects
• Owner surrenders some control for added expertise
• Owner often pays more in professional fees
Execution:
• Document control more challenging with multiple contracts
• Disadvantage for project no time constraints
• Additional layer of authority can reduce efficiency and communication
Quality Assurance:
• Potential exists for conflict of interest in CM cost control vs Owner needs
• CM may limit A/E communications with Owner, causing undue
compromises
Construction Management
(CM at Risk) Limitations
![Page 53: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/53.jpg)
Facility Types
Parking Garage
D-B-B
CMc
Research &
Development
CMc
D-B-B
Office
D-B-B
CMc
Sitework
CMc
![Page 54: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/54.jpg)
Owner with CM as Advisor (CMa)
CM Advisor
![Page 55: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/55.jpg)
Extent:
- Suitable for simple to moderate complexity, especially remodeling.
- Design of higher quality with tolerance for customization.
Cost:
- Negotiated pricing common.
- Use of contingencies to avoid change costs.
- Design Options used to verify best cost approach.
Time:
- Multiple overlapping Contracts. Shortened duration possible
- Contracts can be released with partial information.
Owner-CMa
Benefits
![Page 56: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/56.jpg)
Organization / Relations:
- A/E relationship with Owner may be limited.
- Owner has total control over project, and risk.
Execution
- Lengthy development phase must be carefully managed
- Documents plan should include creating alternates
- A/E risks increase the more contracts are issued on partial docs
Quality Assurance
- Early cooperation with pricing exploration is main advantage.
- Contractors get to know extent and expectations better.
Owner-CM as Advisor
Factors for A/E
![Page 57: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/57.jpg)
Organization / Relations:
– Significantly more risk to Owner, CM signs no contracts
– No recourse for errors and omissions
– A/E risks increased with customization and specialties
– Owner may limit A/E administration services
Execution:
– Document completion still critical, but heavier reliance
on delegated design
– Owners do not typically have trained staff to perform
construction or administer jobs. But use 3rd parties, not A/E.
– Owner-CMa pay CM significant fees to manage multiple
contractors.
Owner-CMa
Limitations
![Page 58: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/58.jpg)
Quality Assurance:
– Heavier than usual reliance on contingencies
– Shortened time leads to quality compromises along way.
– Conflicts arise on apparent cost overruns from incomplete
information.
– Not always clear what is included or excluded in negotiated
prices. Gaps in scope.
– Communications are compromised.
– Limiting A/E administration of contract is common.
– Financial commitment without knowing final costs
Owner-CM as Advisor
Limitations
![Page 59: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/59.jpg)
Facility Types
Parking Garage
D-B-B
CMc
CMa
Research &
Development
CMa
CMc
D-B-B
Office
D-B-B
CMc
CMa
Sitework
CMa
CMc
![Page 60: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/60.jpg)
Project Delivery
Design-Build (D-B)
Option: Owner
contracts direct with
A/E, and creates
“bridging
documents”
![Page 61: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/61.jpg)
Extent:
- "Forces" Owners to use advance planning
- Single contract with one entity
- Favors Simpler design and allows for scaling up extent
- Allows for Owner flexibility even when price is a priority
Cost:
- Cost controls as builder-designer are non-adversarial
- Bridging documents reduce risks.
- Subcontract pricing can still be competitive
Time
- Linear sequence, but may achieve overall project time reduction.
Design-Build
Benefits
![Page 62: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/62.jpg)
Organization / Relations:
- A/E role is bridging documents, limits risk.
- A/E still has influence on design and construction
- Owner has input up front, relying on DB for cost control.
Execution:
- Fast-track scheduling is an option
- Document preparation is linear, close to conventional
- Design-builders can often handle specialized services
Quality Assurance:
- Coordination is closer between Design-Builder and A/E
- DB takes responsibility for subs. Can use negotiation or other
methods to achieve results.
Design-Build
Factors for A/E
![Page 63: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/63.jpg)
Execution:
- Preparation of project description may be difficult for Owner
- Increased risk for design-builder
- Less protection for Owner by A/E since he works for Contractor
- Documents may be less detailed and material selections
made be left to design-builder
Quality Assurance:
- Owner required to administer compliance with contract.
- Contract & dispute resolution may take longer
Design-Build Limitations
![Page 64: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/64.jpg)
Facility Types
Parking Garage
D-B
D-B-B
CMc
CMa
Research &
Development
CMa
D-B-B
D-B
CMc
Office
D-B
CMc
D-B-B
CMa
Sitework
CMc
D-B
D-B-B
CMa
Campus
CMa
![Page 65: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/65.jpg)
Integrated Project Delivery (IPD)Model of an Effective Team
• Mutual respect
• Open, direct communications
• Mutual benefit and rewards
• Collaborative innovation and
decision making
• Early involvement of key
participants
• Early goal definition
• Intensified planning
• Appropriate technology
• Organization and leadership
65
![Page 66: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/66.jpg)
Project Delivery
Integrated Project Delivery (IPD)
All parties engaged, shared goals
![Page 67: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/67.jpg)
Trends
� Materials and systems are becoming
more complex and specialized
� Specialty contractors contribute earlier.
� Advance pricing becoming contractual.
� Informal (no responsibility)
� Design-Assist (may take
responsibility)
� Delegated Design (must take
responsibility)
Mixing of methods
![Page 68: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/68.jpg)
Where is “there”:
• Methods that provide mutual benefit
• Recognize and quickly resolve project difficulties
• Suppress short term self-interest for good of the project.
Contract delivery methods
that balance the influence of
the project conditions are
the basis of successful
projects.
As seen in a perfect world
![Page 69: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/69.jpg)
Questions?
6
9
![Page 70: PROJECT DELIVERY - cdn.ymaws.com](https://reader034.vdocument.in/reader034/viewer/2022042702/62655ac6985f7f6a6c130353/html5/thumbnails/70.jpg)
7
0
This presentation is protected by US and International copyright laws.
Reproduction, distribution, display and use of this presentation without written
permission of the speaker and The Construction Specifications Institute is prohibited.
© CSI 2020 www.csiresources.org
Greater St. Louis Chapter of CSI
PROJECT DELIVERYMethods and Contracts
“You can get there from here.”