Labour packages:
1.Construction packages:
Jet groundingTimber frameStaircases
2. Services packagesarchimedes screw water filters Boiler
3.Community Packages:Rammed earth wallsrammed earth floorstimberal vaulting roofs
water system
1A. Jet grounding foundations below ground surface
(ommited from next drawings to avoid confusion)
1B. Timber plat-form frames con-structed on top of foundations.
2A. Timber con-struction acts as shuttering sup-port for rammed earth walls built between the tim-ber frame con-struction by the community
3A. building grows as a when the community needs it. they define their own communal space adding roofs us-ing timberal vaulting and ce-ramic bricks and fast setting con-crete.
[Academic use only]
jet grouting
timber frame
high strengthmortar
formwork attached
rammed earth from timber platform
timber construction-rammed earth construction
![Page 2: project development](https://reader036.vdocument.in/reader036/viewer/2022070504/568c4b961a28ab49169cc21e/html5/thumbnails/2.jpg)
[Academic use only]
Black- timber construction by contractororange- rammed earth by communitypink- community additional shelters and covers
[Academic use only]
1:100
1:200
plans and sections in progress
early plan- different construc-tion packages not yet shown
![Page 3: project development](https://reader036.vdocument.in/reader036/viewer/2022070504/568c4b961a28ab49169cc21e/html5/thumbnails/3.jpg)
1:100
1:200
T+0 Jet grounding
T+1 removing ground
T+2 filling in with rammed earth
T+3 fixing timber columns
T+5 timber platform framing and bracing
1:200 Iso to show sequence of foun-dations and timber structure through two parts of the scheme
natural ground
retaining wall
BUILD SEQUENCE DRAWINGS close up