project development process. odot’ pdp a project management and transportation decision-making...
TRANSCRIPT
Project Development Process
ODOT’ PDP
• A project management and transportation decision-making tool.
• Developing the detail to the level necessary to make the right decision.
• PDP focus is:– Streamlining– Merger of Environmental/Design– Risk Management– Flexibility
ODOT’s Process
ODOT’s Process
• ODOT has 5 project paths (1=easy, 4/5= ODOT’s most complicated projects)
• Each path advances through five phases• Studies/engineering are “right-sized”
within each phase to better support decision-making
PDP Project Paths
ODOT’s Process
• Vast majority of ODOT projects are Path 1 and Path 2 projects– Most completed in-house
• Majority of Consultant program is Path 3 and some Path 2 projects
• ODOT has less then 20 projects that are Path 4 or 5
Planning (PL)
Planning your project…
• Planning/programming High level planning and
development Data gathering and analysis
• Statewide Transportation Plan (STIP)
Project Initiation Package
• Why “active” Scoping?• Define Study area and Logical Termini• Define PDP Path
– Discipline Specific focus areas of the PIP• Design• Traffic/safety/etc.• Geotechnical• Environmental• ROW/Utilities (start planning for…)
• Review/Approval
Purpose and Need
• Focus on an understanding of the issues that will need addressed by this project– Crash Analysis– Traffic Data– Can have secondary goals (economic
development opportunities, bike/ped accommodations, etc.)
• P&N must have supporting data!
Concept, Scope, Budget
• Ensure supporting data and analysis are in place to support a P&N
• Identify critical information needed to make a decision on the Preferred Alternative.
• Identify critical path elements• Establish schedule/budget• Getting started…scoping…
Preliminary Engineering (PE)
PE and EE
• Separate, but together!!!• Federal Authorizations…
Developing the Preferred Alt
• Goal of the PE Phase– To identify the project’s Preferred
Alternative– To ensure we have a strong understanding
of the impacts associated with this project– Considerations: design, utilities, ROW and
construct-ability. – Defined Budget/Schedule
Feasibility Studies
–First level decision document• Goal is to make a decision on the
preferred alternative or to narrow down the alternatives (or elements) that are focused in an Alternative Evaluation Report.
• Documentation of ODOT’s decision.
Feasibility Studies–Path 1 projects don’t require a FS–Format- Path 2 for projects
• Feasibility Study can take the form of:–Discipline specific study–Mtg minutes w/supporting studies–Feasibility Study- stand alone report
–Preferred Alternative• Must be based on P&N• MOTAA, TSL, Safety Studies
combined w/specific project info (environmental/PE)
Feasibility Studies• Feasibility Studies
– For Projects that are: Higher Path projects, Complex in nature, multiple alignments, public controversy, etc.…
– Preferred Alternative or reduced alternatives• MOTAA, TSL, Safety Studies are performed• Specific project info will be used to drive the decision• Feasibility Study will be a stand alone report
– Discipline specific studies– Preliminary Engineering (no Stage I)– May recommend AER
Alternative Evaluation Report
• Second Level decision document– Builds upon the Feasibility Study
• Will never have an AER without an FS in place• Will always have an AER with a Path 4/5 project
– Purpose is to make the decision of Preferred Alt. – Detail in an AER
• Higher level engineering• High level of Environmental• ROW/Utilities/Geo-tech/, etc.• Coordination
Alternative Evaluation Report
• AERs– Can focus on individual alignments as a whole
• Example: Widening project (left, right, center) as a whole project.
or
– Can focus on individual elements of a Preferred Alternative identified in the FS• Example: Intersection elements of a
widening project.
– Identify Preferred, Impacts, etc.– NEPA confirmed in EE Phase
Project Management
• PM Tips for the PE phase:– Be flexible (level of design, level of PI, level of
coordination w/other areas….) are all dependent upon the complexity and decision-making needed.
– Move tasks from other areas if you need the info to address your project…
• Cost Estimates/Project Schedule• Transition to Environmental Eng
Environmental Engineering (EE)
Environmental Engineering
• Goal of EE Phase:–Progress Stage 1 and Stage 2 Design–Complete outstanding environmental
studies–Complete NEPA and Permit approval–Begin ROW acquisition
Environmental Engineering
• Environmental Studies and Approval– Can be based on PE, Stage 1 or Stage 2– Environmental commitments
• Stage 2 Design Process• Waterway Permits• Can begin ROW/Utilities
– Title/deed, etc., – acquire w/state monies, etc.
Environmental Engineering
• Design considerations:Ensure design is buildable
Address Temp/Perm fills How will this project be built?
Ensure room for staging, de-watering, etc.
Ensure environmental commitments are addressed in the design and bid documents
Utilities are addressed…
Environmental Engineering
• ROW considerations– Can begin all pre-acquisition activities
• Deed research,• Appraisals,• Necessary coordination, etc.
– Consider Hardships or Protected Buys
Project Management
• PM Tips for the EE phase:– Monitor costs/schedule closely– Map out critical path elements
• Start waterway permits early….• Utility relocation
– Cost Estimates/Project Schedule• Transition to Final Engineering
Final Engineering/ROW (FE)
Final Engineering/ROW
• Goal of FE Phase:–Progress ROW and Utility
relocation/process–Complete Design and bid documents–Begin mitigation implementation
Final Engineering/ROW
• Considerations:–Environmental Commitments
• Ensure they are built into the design and bid documents
– Ensure design is buildable:• Staging• Stormwater details (dewatering, etc.)• Retaining wall example…
Construction (CO)
Construction
• Commitment Compliance• Mitigation implementation• Verify Design efforts
– Site visit/talk w/inspectors– Ensure Maintenance is aware of issues.
Project Development Process