project lima eia traffic impact study v2 - eskom · d:\documents and settings\reddyl\desktop\prash...

24
D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc ENVIRONMENTAL IMPACT ASSESSMENT: TRAFFIC/TRANSPORTATION STUDY FOR PROJECT LIMA for BOHLWEKI ENVIRONMENTAL January 2007 Prepared by: Adrian Brislin Goba Pty Ltd Belvedere Place 5 Eglin Road Sunninghill Tel. (011) 236-3300 Fax. (011) 236-3303

Upload: dinhbao

Post on 01-Oct-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Project LIMA EIA Traffic Impact Study v2 - Eskom · D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 3 The

D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study

v2.doc

ENVIRONMENTAL IMPACT

ASSESSMENT:

TRAFFIC/TRANSPORTATION STUDY

FOR

PROJECT LIMA

for

BOHLWEKI ENVIRONMENTAL

January 2007

Prepared by:

Adrian Brislin

Goba Pty Ltd

Belvedere Place

5 Eglin Road

Sunninghill

Tel. (011) 236-3300

Fax. (011) 236-3303

Page 2: Project LIMA EIA Traffic Impact Study v2 - Eskom · D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 3 The

D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study

v2.doc

Page 3: Project LIMA EIA Traffic Impact Study v2 - Eskom · D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 3 The

i

TABLE OF CONTENTS

PAGE NO.

1 INTRODUCTION ....................................................................................................... 1

2 STATUS QUO CONDITIONS ....................................................................................... 1

2.1 Description of Road Infrastructure........................................................................... 1

2.2 Description of Present Travel Patterns ..................................................................... 1

2.3 Location of Employee Residences ............................................................................ 2

2.4 Other Transport Infrastructure................................................................................ 2

3 TRAFFIC/TRANSPORT IMPACTS.................................................................................. 2

3.1 Transport of Components during Construction .......................................................... 2

3.2 Construction Traffic ............................................................................................... 3

3.3 Transport of Employees (Operational Traffic) ............................................................ 5

4 SUMMARY OF TRAFFIC IMPACTS ................................................................................ 5

5 CONCLUSIONS ........................................................................................................ 7

6 RECOMMENDATIONS ................................................................................................ 7

ANNEXURES

Annexure A Locality Map and Road Infrastructure

Annexure B Existing 2007 Traffic Conditions

Annexure C Impact of Construction Traffic 2012

Page 4: Project LIMA EIA Traffic Impact Study v2 - Eskom · D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 3 The

D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 1

1 INTRODUCTION

Goba Pty Ltd was appointed by Bohlweki Environmental to undertake a

traffic/transportation impact study as part of the Environmental Impact Assessment for

the proposed Project LIMA(Steelpoort Pump Storage scheme) to be located near

Roossenekal in the Mpumalanga Province. A study area locality plan is shown in

Annexure A, Figure 1. Site A has been established as the preferred site for the

construction of the Steelpoort Pumped Storage scheme.

This report contains a description of the Status Quo transport infrastructure and the

transport/traffic impact for the construction period and operational period of the

proposed Steelpoort Pumped storage scheme.

The De Hoop Dam will be completed in 2010 and construction on the Pumped storage

scheme will commence in mid 2009 and be completed within 5 years by 2014.

2 STATUS QUO CONDITIONS

The following section summarises the present conditions related to transportation for the

proposed development of the Steelpoort Pumped Storage Scheme.

2.1 Description of Road Infrastructure

The Steelpoort River Valley under consideration is located between the Stoffberg to

Phokwane provincial road (R579) and the Roossenekal to Steelpoort provincial road

(R555). A map highlighting these roads is shown in Figure 2, Annexure A.

The proposed De Hoop Dam is located some 20km further north along the Roossenekal

to Steelpoort Road (R555) near the Limpopo Province border at the tributary of the

Steelpoort and Klip rivers.

The proposed pumped storage scheme site A is shown in Figure 2 together with the

proposed access roads from the main provincial roads to the sites.

2.2 Description of Present Travel Patterns

The R579 (Road P62-2), R555 (Road 169-1) and R577 provincial routes are not highly

trafficked with daily volumes ranging between 600 and 2000 vehicles per day.

Detailed 12 hour classified traffic counts were undertaken in January 2007 at the

following locations:

Page 5: Project LIMA EIA Traffic Impact Study v2 - Eskom · D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 3 The

D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 2

i) R579 (Road P62-2) in Sehlakwane at the junction to the Upper Reservoir site

ii) R579 (Road P62-2)at the junction with the local access road across to R555

iii) R555 (P169-1) at the junction with the access road from R579

iv) R555 (P169-1) and R577 junction outside Roossenekal

A summary of the counts is shown in Figure B1, B2 and B3, Annexure B for the morning

peak , afternoon peak and 12 hour time periods respectively. A Provincial traffic count

was also obtained for the section of the R555 (P169-1)north of Kennedy’s Vale. The

count was 1500 vehicles per day with 30% heavies. Using the 12 hour to daily factors of

this provincial count the Average daily traffic for the four counting stations was

estimated and is contained in Figure B4, Annexure B.

2.3 Location of Employee Residences

The most likely dwelling location of employees to the pumped storage scheme is the

Nebo Plateau (near sehlakwane) and Roossenekal , however the number of permanent

staff to operate the scheme once online is minimal (only 40 staff). The location of the

construction camp for both the De Hoop Dam and the Pumped Storage scheme will also

be near Roossenekal.

2.4 Other Transport Infrastructure

There is a railway line from Middelburg to Roossenekal, but this is the nearest rail

terminal to the site.

3 TRAFFIC/TRANSPORT IMPACTS

3.1 Transport of Components during Construction

Several very large 250ton component parts would need to be transported to the Site

from either Durban harbour or Richards Bay. The frequency of delivery would be no

more than 1 every six months. This would require abnormal load transport and the

application for the permit to do so is a lengthy and costly process which is outlined

below.

The most likely route from Durban harbour or Richards Bay follows National Route N2

along the Kwazulu-Natal coast via Pongola and Piet Retief. From there the R33 via

Amsterdam, Warburton, Carolina, Belfast and on to Stoffberg. The route then deviates to

via the R555 towards Roossenekal and via the access road to the Valley site.

Page 6: Project LIMA EIA Traffic Impact Study v2 - Eskom · D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 3 The

D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 3

The critical part of the Abnormal Load Route Permit application is the survey of the

prospective route by a qualified structural Engineer who needs to examine all the

bridges/overpasses/underpasses and issue a certificate of compliance for the particular

vehicle type/width/length and height.

It is estimated that the whole survey and Application procedure may take three to four

months to complete, and this would have to be scheduled in the construction programme

of the Steelpoort Pumped storage scheme. Although the tonnage is significant the low

frequency of the trips means that the traffic loading impact is negligible. Close to the

Construction site turning radii of 50m are required for the large superlink loads.

The transport of components impact extent is regional, the duration is very short-term,

its intensity is low, and the degree of certainty is highly probable.

3.2 Construction Traffic

This traffic relates directly to the traffic expected during the construction of the

Steelpoort Pumped storage scheme itself, which is expected to take place over a period

of 5 years. It is anticipated and estimated that the number of construction employees

to/from the construction site will peak at 1500 per day. 67% of these workers would be

unskilled and semi-skilled living in the Nebo Plateau (surrounding Sehlakwane). The

balance is assumed to live near Roossenekal. The split of workers between the two

construction sites is expected to be 80% : 20% to the Valley site and Upper Reservoir

site respectively. In vehicular terms, assuming 50 workers per bus, 30 buses are

required to transport workers daily from there dwellings to the two sites. Of this daily

construction employee traffic 100% is conservatively assumed to arrive in the a.m. peak

hour and depart in the p.m. peak hour. This traffic is over and above the envisaged

construction camp workers which may amount to 70 near the Upper Reservoir site and

2500 near the Valley site.

The revised number of construction workers housed at both the upper and lower

reservoir sites would result in an increase in the number of buses transporting workers

to the upper reservoir by 3 buses per direction during peak hour. The effect of locating

the 2500 workers on site at the lower reservoir will reduce the number of buses to/from

the site to zero. This change in accomodation, therefore, has a beneficial effect by

reducing the traffic impact of transporting workers to a very small amount during peak

hours and the day. The transporatation for food and supplies for the workforce although

higher is considered to be low in magnitude and infrequent.

The magnitude and exact nature of heavy vehicle construction traffic is very difficult to

determine. The sources of construction materials, supply of material components and the

construction programme all influence the nature and frequency of road-based vehicle

transport to/from the site. The source of construction material would mainly be Gauteng.

Page 7: Project LIMA EIA Traffic Impact Study v2 - Eskom · D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 3 The

D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 4

The raw materials for the on-site Cement plant can arrive by rail. Obviously the cement

would have to be transported from Roossenekal station to the Valley site.

The heavy vehicle construction traffic is assumed to amount to 20 trucks per day to the

Valley site and 5 trucks per day to the Upper Reservoir site. 50% of the trucks are

expected to arrive during the A.M peak hour and depart in the P.M. peak. The cumulative

vehicular traffic impact of construction employees and heavy construction vehicles is

shown in Figures C1 to C4, Annexure C, for the a.m. peak, p.m. peak, 12 hour and daily

periods respectively.

A traffic evaluation was performed at the key intersections under consideration. A mid-

time period of 2012 was chosen to represent the construction traffic scenario. The

results show that the 2012 construction traffic impact on peak hour traffic operations at

the key intersections surrounding the Steelpoort Pumped storage scheme is not

significant.

The impact on pavement loading to the surrounding roads may, however, be more

significant. Assuming the 20 truckloads per day which are fully loaded inbound (3.5

E80s per truck) and empty outbound (2.0 E80s per truck) as well as 24 buses (2.5 E80s

fully loaded and 1.8 E80s empty) translates to 213 E80s per day along Route R555

which presently carries an estimated 1647 E80s per day. This represents a proportion of

13%. The accumulative additional axle loading over a sustained 60 month period is

268 380 E80s which is only a contibution of an additional 8% over the five year period.

The overall impact of the construction traffic during the construction period translates to

advancing the need for pavement rehabilitation by 8%. This situation is the worst-case

for the Provincial road R555 (P169-1). As the traffic dissipates along the R555 (Road

P69-1) and R577 the proportional impact becomes reduced. The additional daily E80 axle

load for each section of the study area is shown in Figure C5, Annexure C.

The additional impact on the pavement of the section of road R579 (P62-2) is 105 E80s

per day. This represents a proportion of 42% of the present daily E80 axle loading of

249 E80s. If this is accumulated over the 60 month construction period the impact will

be 132 174 E80s compared to the present cumulative 499 868 E80s (a proportion of

26%). If the roads were planned to be rehabilitated in 7 years time then the impact of

the bus and construction traffic would mean that rehabilitation would have to be

undertaken in 5 years and 10 months time, an advance of 1.85 years.

The effect on pavement loading and subsequent advance of any rehabilitation

programme should be mitigated after completion of construction by the possible

contribution to the roads rehabilitation programme by Eskom. It should however be

acknowledged that the Pumped Storage scheme has so many other economic benefits

Page 8: Project LIMA EIA Traffic Impact Study v2 - Eskom · D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 3 The

D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 5

such as employment creation, electricity provision and irrigation benefits of incalculable

magnitude that this suggestion of contribution could easily be waived.

The construction traffic impact extent is regional, the duration is short-term, it’s intensity

is low and it will definitely occur.

3.3 Transport of Employees (Operational Traffic)

The additional traffic generated in transporting employees from their residences to work

at the new Steelpoort Pumped storage scheme is small. There is only envisaged to be a

staff complement of 40 for the Control Centre of the Valley site who would most likely

stay in Roossenekal.

This assumed passsenger car traffic was evaluated at the key intersections along the

present Roosenekal to Valley site road. The results of the traffic evaluation indicate that

the impact of the 2014 operational traffic is small as there is presently sufficient spare

capacity at all key junctions to accommodate this peak period traffic increase.( an

increase of approxamitely 15%)

The operational traffic impact extent is localised, the duration is long-term, it’s intensity

is low and it will definitely occur.

4 SUMMARY OF TRAFFIC IMPACTS

4.1 Rating Matrix for Transport of Components

Criteria Rating

Extent 3

Duration 1

Intensity 1

Probability of occurrence 3

Total 8

This is rated as a Medium Negative Impact before the

implementation of mitigation and management measures

Mitigation and Management measures

- No of trips kept to a minimum

- Use approved route

Page 9: Project LIMA EIA Traffic Impact Study v2 - Eskom · D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 3 The

D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 6

- Transport ouside peak hours on busy sections

Criteria Rating

Extent 3

Duration 1

Intensity 1

Probability of occurrence 3

Total 8

This is rated as a Medium Negative Impact after the

implementation of mitigation and management measures

4.2 Rating Matrix for Construction Traffic

Criteria Rating

Extent 3

Duration 1

Intensity 1

Probability of occurrence 4

Total 9

This is rated as a Medium Negative Impact before the

implementation of mitigation and management measures

Mitigation and Management measures

- Road rehabilitation after construction

-

Criteria Rating

Extent 3

Duration 1

Intensity 1

Probability of occurrence 4

Total 9

This is rated as a Medium Negative Impact after the

implementation of mitigation and management measures

4.3 Rating Matrix for Operational Traffic

Criteria Rating

Extent 2

Duration 3

Intensity 1

Probability of occurrence 2

Total 8

This is rated as a Medium Negative Impact before the

implementation of mitigation and management measures

Mitigation and Management measures

Page 10: Project LIMA EIA Traffic Impact Study v2 - Eskom · D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 3 The

D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 7

- Travel between sites is minimised(electronic control)

- Only 40 staff at Valley control centre

Criteria Rating

Extent 2

Duration 3

Intensity 1

Probability of occurrence 2

Total 8

This is rated as a Medium Negative Impact after the

implementation of mitigation and management measures

5 CONCLUSIONS

1. The transport of components has a Medium Negative impact as the extent is

regional, the duration is very short-term and it is highly probable to occur.

2. The construction traffic has a Medium Negative impact as the extent is regional,

the duration is short-term and it will definitely occur.

3. The operational traffic has a Medium Negative impact as the extent is localised,

the duration is long-term and it will definitely occur.

6 RECOMMENDATIONS

It is recommended that the medium negative impact determined using the matrix rating

system be given a low weighting when compared to other environmental factors as the

Steelpoort Pumped storage scheme benefits far outweigh the considered LOW impact of

the transport/traffic.

Page 11: Project LIMA EIA Traffic Impact Study v2 - Eskom · D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 3 The

D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc

ANNEXURE A

___________________________________

Figure 1 Study Area Locality Map

Figure 2 Road Infrastructure

Page 12: Project LIMA EIA Traffic Impact Study v2 - Eskom · D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 3 The

Fig. 1

Proj. No. 16103GTAPROJECT LIMA PUMPED STORAGE SCHEME

LOCALITY PLAN

PROJECT LIMA

Page 13: Project LIMA EIA Traffic Impact Study v2 - Eskom · D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 3 The

Fig. 2

Proj. No. 16103GTA

ROAD INFRASTRUCTURE

or

To

Ste

elp

ot

Tf

e

o S

tofb

rgoto

ffberg

T S

ROOSSENEKAL

SEHLAKWANE

Tin

do

Dela

Page 14: Project LIMA EIA Traffic Impact Study v2 - Eskom · D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 3 The

D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc

ANNEXURE B

___________________________________

Figure B1 2007 existing a.m. peak volumes

Figure B2 2007 existing p.m. peak volumes

Figure B3 2007 existing 12 hour traffic

Figure B4 2007 existing Daily traffic

Page 15: Project LIMA EIA Traffic Impact Study v2 - Eskom · D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 3 The

4 1 62 202

11 0

63

1

223

56 5

90

106 20

17

17

R:\16103GTA\Design\400_Roads\[Processed Counts.xls]C2

Project:

16103GTA

STEELPOORT PUMPED STORAGE SCHEMEFigure B1

2007 EXISTING AM PEAK VOLUMES ( 06:30 - 07:30)

751

702

65 1715

32

Sehlakwane

Roossenekal

R555

R555

R577

R10

R5

R6

R579

R579

R8

R579

2

1

3

4

R1

To

Ken

ned

y's

Vale

Upper Reservoir

site

To

Sto

ffberg

To

Sto

ffberg

To Dindela

Valley site

(37%)

(21%)

(3%)

(3%)

(2%)(16%)

(16%)

(1%)

(2%)N

eb

o

Pla

teau

Total 106% Heavy (2%)

Page 16: Project LIMA EIA Traffic Impact Study v2 - Eskom · D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 3 The

2 4 108 101

11 0

0

2783

800

65 2132

21

R:\16103GTA\Design\400_Roads\[Processed Counts.xls]C2

Project:

16103GTA

STEELPOORT PUMPED STORAGE SCHEMEFigure B2

2007 EXISTING PM PEAK VOLUMES ( 16:00 - 17:00)

61 2

3

7

57 11

301

1

0

021

Sehlakwane

Roossenekal

R555

R555

R577

R10

R5

R6

R579

R579

R8

R579

2

1

3

4

R1

To

Ken

ned

y's

Vale

To

Sto

ffberg

To

Sto

ffberg

To Dindela

Upper Reservoir

site

Valley site

(1%)

(12%)

(13%)(1%)

(21%)

(21%)

(5%)

(7%)

(2%)

Neb

o

Pla

teau

Total 108

% Heavy (21%)

Page 17: Project LIMA EIA Traffic Impact Study v2 - Eskom · D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 3 The

26 872 113

1216 2

2224

14

13271

621 85

26818

674 80

94

94

R:\16103GTA\Design\400_Roads\[Processed Counts.xls]C2

Project:

16103GTA

STEELPOORT PUMPED STORAGE SCHEMEFigure B3

2007 EXISTING 12 HOUR VOLUMES

176

83222

727240

188274

32

23

Sehlakwane

Roossenekal

R555

R555

R577

R10

R5

R6

R579

R579

R8

R579

2

1

3

4

R1

To

Ken

ned

y's

Vale

To

Sto

ffberg

To

Sto

ffberg

To Dindela

774

Upper Reservoir

site

Valley site

Neb

o

Pla

teau

(23%)

Total 674% Heavy (5%)

(21%)

(9%)

(9%)

(18%)

(19%)

(2%)

(5%)

(5%)

Page 18: Project LIMA EIA Traffic Impact Study v2 - Eskom · D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 3 The

85

138

1880

R:\16103GTA\Design\400_Roads\[Processed Counts.xls]C2

Project:

16103GTA

STEELPOORT PUMPED STORAGE SCHEMEFigure B4

2007 EXISTING DAILY TRAFFIC

744

452

724

1887

1124

2285

2287

88

2580

Sehlakwane

Roossenekal

R555

R555

R577

R10

R5

R6

R579

R579

R8

R579

2

1

3

4

R1

To

Ken

ned

y's

Vale

To

Sto

ffberg

To Dindela

Upper Reservoir

site

Valley site

Neb

o

Pla

teau

(5%)

(5%)

(1%)

249

1647

2387( 23%)

( 2%)(22%)

1714

(25%)

(1%) (25%)

(1%)

(10%)

(10%)

6

(0%)

Total 2285% Heavy (25%)

E80's/ day

14

Page 19: Project LIMA EIA Traffic Impact Study v2 - Eskom · D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 3 The

D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc

ANNEXURE C

___________________________________

Figure C1 2012 a.m. peak volumes

Figure C2 2012 p.m. peak volumes

Figure C3 2012 12 hour traffic

Figure C4 2012 Daily traffic

Figure C5 E80 Daily Axle volumes plus

Construction traffic

Page 20: Project LIMA EIA Traffic Impact Study v2 - Eskom · D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 3 The

34

34

19 73 202

11 0

0

2077

822

93 2119

48

22

R:\16103GTA\Design\400_Roads\[Processed Counts.xls]C2

Project:

16103GTA

STEELPOORT PUMPED STORAGE SCHEMEFigure C1

2012 AM PEAK VOLUMES ( 06:30 - 07:30)

117 23

19

26

62 16

130

3

19

2028

Sehlakwane

Roossenekal

R555

R555

R577

R10

R5

R6

R579

R579

R8

R579

2

1

3

4

R1

To

Ken

ned

y's

Vale

Upper Reservoir

site

To

Sto

ffberg

To

Sto

ffberg

To Dindela

Valley site

Neb

o

Pla

teau

Page 21: Project LIMA EIA Traffic Impact Study v2 - Eskom · D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 3 The

34

34

22 124 101

11 0

01

18

1826

63 20

361

67 3

4

15

R:\16103GTA\Design\400_Roads\[Processed Counts.xls]C2

Project:

16103GTA

STEELPOORT PUMPED STORAGE SCHEMEFigure C2

2012 PM PEAK VOLUMES ( 16:00 - 17:00)

43112

930

92 2537

36

20

Sehlakwane

Roossenekal

R555

R555

R577

R10

R5

R6

R579

R579

R8

R579

2

1

3

4

R1

To

Ken

ned

y's

Vale

Upper Reservoir

site

To

Sto

ffberg

To

Sto

ffberg

To Dindela

Valley site

Neb

o

Pla

teau

Page 22: Project LIMA EIA Traffic Impact Study v2 - Eskom · D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 3 The

68

68

65 973 123

1318 2

24

220896

92924

845 307240

236

71

R:\16103GTA\Design\400_Roads\[Processed Counts.xls]C2

Project:

16103GTA

STEELPOORT PUMPED STORAGE SCHEMEFigure C3

2012 12 HOUR VOLUMES

744 90

105

118

686 109

30120

26

51

50304

Sehlakwane

Roossenekal

R555

R555

R577

R10

R5

R6

R579

R579

R8

R579

2

1

3

4

R1

To

Ken

ned

y's

Vale

Upper Reservoir

site

To

Sto

ffberg

To

Sto

ffberg

To Dindela

Valley site

Neb

o

Pla

teau

25

Page 23: Project LIMA EIA Traffic Impact Study v2 - Eskom · D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 3 The

932545

133

831

509

845

2103

188

2079

R:\16103GTA\Design\400_Roads\[Processed Counts.xls]C2

Project:

16103GTA

STEELPOORT PUMPED STORAGE SCHEMEFigure C4

2012 DAILY TRAFFIC

Sehlakwane

Roossenekal

R555

R555

R577

R10

R5

R6

R579

R579

R8

R579

2

1

3

4

R1

To

Ken

ned

y's

Vale

To

Sto

ffberg

To Dindela

Upper Reservoir

site

Valley site

Neb

o

Pla

teau

(5%)

(6%)

(1%)

2238

2714( 25%)

( 6.5% )

(23.

5%)

458

(25%)

(20%)(26%)

(28%)

(10%)

(14%)

161

(1%)

Total 2285% Heavy (25%)

E80's/ day

140(98%)

426

1297

2905

2150

2579

Page 24: Project LIMA EIA Traffic Impact Study v2 - Eskom · D:\Documents and Settings\ReddyL\Desktop\Prash - SPSS\PDF - Appendices\Traffic\Project LIMA EIA Traffic Impact Study v2.doc 3 The

53

R:\16103GTA\Design\400_Roads\[Processed Counts.xls]C2

Project:

16103GTA

STEELPOORT PUMPED STORAGE SCHEMEFigure C5

E 80 DAILY AXLE VOLUMES PLUS CONSTRUCTION TRAFFIC

IMPACT

105 Sehlakwane

Roossenekal

R555

R555

R577

R10

R5

R6

R579

R579

R8

R579

2

1

3

4

R1

To

Ken

ned

y's

Vale

To

Sto

ffberg

To Dindela

Upper Reservoir

site

Valley site

Neb

o

Pla

teau

(42% )

249

213

1714

6

213 Construction( % ) Proportional contribution% Heavy (25%)

1647

213

132

(7

,7%

)

28

14

77

Daily E80

( 13

% )

E 80s /day extra