Prof. Roberto Verdone www.robertoverdone.org Project Management and Soft Skills Project Management: a Pragmatic Approach Roberto Verdone www.robertoverdone.org [email protected] +39 051 20 93817 Office Hours: Monday 4 – 6 pm, Viale Risorgimento 2 (upon agreement via email) A.Y. 2017-18 Credits: 3

Upload: others

Post on 07-Oct-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Project Management and Soft Skills Project Management: a Pragmatic Approach

Roberto Verdone www.robertoverdone.org

[email protected]

+39 051 20 93817

Office Hours: Monday 4 – 6 pm,

Viale Risorgimento 2 (upon agreement via email)

A.Y. 2017-18 Credits: 3

Page 2: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Project Management: A Pragmatic Approach

This lecture block does _not_ aim at being general and comprehensive regarding the topic of Project Management, as this would require an effort not compatible with the objectives of this course. The elementary management tools used in project activities are introduced.

Page 3: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Projects A Project is a set of activities geared towards a specific goal. A project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management is the activity aimed at planning, executing, controlling, and closing the work of a team to achieve the project goal and meet specific (measurable) success criteria.

Project Management

Page 4: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Projects Examples: -  Building a complex civil infrastructure (a skyscraper, a bridge, etc.)

-  Innovate the machinery of an industry plant. -  Design, prototype, and test a new product. -  Develop a new service to be offered by an IT company. -  Organise a complex event (a conference, a school, etc.).

-  ...

Project Management

Page 5: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Projects

Project Management

time

Goal

Page 6: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Projects

Project Management

time

Goal Kick-Off End

Project Duration

Page 7: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Projects

Project Management

time

Goal Kick-Off End

Project Duration

planning execution, control closure

Page 8: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Projects

Project Management

time

Goal Kick-Off End

Project Duration

planning execution, control closure

finances HR technical resources

Project Management

Page 9: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Projects

Project Management

time

Goal Kick-Off End

Project Duration

planning execution, control closure

finances HR technical resources

Project Management

cost

Page 10: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Projects Any Activity in (Professional) Life

Project Management

Page 11: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Work Packages (WPs), Tasks

A project is formulated as a coordinated set of activities grouped into WPs and Tasks, (possibly in a tree-based fashion, forming a WBS: Work Package Breakdown Structure). The split into smaller, more manageable activities, makes management easier.

Project Management

Task 1

Task 2

Goal

WP

Page 12: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Task 1.1 Sub-Tasks WP1 Task 1.2 …

Goal WP2 Task 2.1

WP3 Task 3.1 Task 3.2

Project Management Work Packages (WPs), Tasks

A project is formulated as a coordinated set of activities grouped into WPs and Tasks, (possibly in a tree-based fashion, forming a WBS: Work Package Breakdown Structure). The split into smaller, more manageable activities, makes management easier.

Page 13: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Project Management Work Packages (WPs), Tasks

A project is formulated as a coordinated set of activities grouped into WPs and Tasks, (possibly in a tree-based fashion, forming a WBS: Work Package Breakdown Structure). The split into smaller, more manageable activities, makes management easier. Every Task will be assigned a sub-goal and some resources (time, technical, financial, human) and a leader who will be responsible for the achievement of the goal. The same applies to WPs, as they are composed of (multiple) tasks.

Page 14: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Example: Underground soil moisture sensors for precision agriculture

Project Management

50 cm wireless transmission

terrain surface

sensor sensor

up to 6 m

collector

Cloud Server

10 m

10 m

3G

wireless transmission

area indicator

farmer

Page 15: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Example: Underground soil moisture sensors for precision agriculture Tasks:

•  T1: HW Design (sensor boards) •  T2: FW Development (sensor boards) •  T3: SW Development (cloud) •  T4: Prototyping and Lab Tests •  T5: On Field Tests •  T6: Data Analysis

Project Management

Page 16: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Example: Underground soil moisture sensors for precision agriculture Tasks: WPs:

•  T1: HW Design (sensor boards) •  T2: FW Development (sensor boards) WP1: Platform •  T3: SW Development (cloud) •  T4: Prototyping and Lab Tests WP2: Lab •  T5: On Field Tests WP3: On Field •  T6: Data Analysis WP4: Analysis

Project Management

Task 1

Task 2

Task 3

Task 4 Task 5 Task 6 Goal

WP1 WP2 WP3 WP4

Page 17: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Example: Underground soil moisture sensors for precision agriculture Resources: •  Financial: 13,1 KEUR •  Human: one student, not skilled, 150 hrs

one PhD student, skilled on Lab testing, 40 hrs one researcher, expert of (agricultural) data analysis, 40 hrs

•  Technical: collector, cloud server •  Time: four months (April-July 2018)

Project Management

Page 18: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Example: Underground soil moisture sensors for precision agriculture Resources:

WP1 WP2 WP3 WP4 Platform Lab On Field Analysis

April May June July 13,1 KEUR PhD Student Researcher Company 40 hrs 150 hrs 40 hrs

Project Management

WP1 WP2 WP3 WP4

Page 19: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Example: Organising a group week-end in Venice.

Project Management

WP1 - Travel

WP2 - Hotel

WP3 - Finances

WP4 - Cultural

Page 20: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Project Management

WP1 - Travel

WP2 - Hotel

WP3 - Finances

T1.1 - Choice from timetable T1.2 - Ticket T1.3 - Baggage

T2.1 - Choice T2.2 - Booking & Payment

T3.1 - Assessment T3.2 - Gathering of funds

WP4 - Cultural T4.1 - Choice of events

Example: Organising a group week-end in Venice.

Page 21: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Interactive Session #1 – Teams of 3 | 15 min

Organising a Summer School.

Your company X develops mechanical components, and you want to train students towards the set of competences that your company might need in the future. To this purpose, you will organise a summer school, to be offered to graduate students with an engineering degree. The school will include lectures given by University professors, and lab sessions offered by other companies belonging to the group led by company X.

Define a WBS including all activities to be planned and executed before start of the school, for its preparation (goal is KO of school).

Project Management

Page 22: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Interactive Session #1

Project Management

Any team presenting their outcome ?

Page 23: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

*** Attendance Check ***

Fill attendance form

www.robertoverdone.org Teaching

PMSS end of webpage

“Attendance March 22”

Page 24: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Short Break

Page 25: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Deliverables, Milestones Every activity of a project produces as an outcome an intermediate or final output to be used by other project activities, or delivered to the outside world.

These outputs (Deliverables) can take the form of technical reports, documents, hardware prototypes, software, video, websites, etc.

Some key points on the time axis describe moments when relevant deliverables are provided, or when something happens thet generates the start of activities. They are denoted as Milestones.

Project Management

Page 26: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Deliverables, Milestones Example: Underground soil moisture sensors for precision agriculture

WP1 WP2 WP3 WP4 Platform Lab On Field Analysis

April May June July

Project Management

WP1 WP2 WP3 WP4

D1: prototype

D2: Internal report

D3: Internal report

D4: final document for delivery

M1: milestone

Page 27: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Deliverables, Milestones Example: Underground soil moisture sensors for precision agriculture

Table of Deliverables

D# Title Type Delivery date

D1 Platform; prototype Prototype April 30 D2 Lab tests Int. report May 15 D3 On Field tests Int. report June 30 D4 Final assessment Techn. report July 31

Table of Milestones

M# Title Type Date

M1 Platform; prototype Prototype April 30

Project Management

Page 28: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Gantt, PERT A Gantt diagram is a pictorial description of the WBS that shows the duration of all activities, and when Deliverables and Milestones are expected. Useful in the planning phase, and during the course of the project for controlling purposes. A PERT (Program Evaluation and Review Technique) diagram is a pictorial description of the interrelations between the different project activities. It aims at supporting the project manager in the planning and execution phases, for the determination of the minimum project duration and the Critical Path.

Project Management

Page 29: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Project Management Gantt, PERT: Example

Organising a group week-end in Venice.

WP1 - Travel

WP2 - Hotel

WP3 - Finances

T1.1 - Choice from timetable T1.2 - Ticket T1.3 - Baggage

T2.1 - Choice T2.2 - Booking & Payment

T3.1 - Assessment T3.2 - Gathering of funds

WP4 - Cultural T4.1 - Choice of events

D1 D2 D3 D4 D5

Page 30: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Project Management Gantt, PERT: Example

Organising a group week-end in Venice.

T1.1 T2.1 T4.1

T3.1

T3.2

T1.2 T2.2

T1.3

WP1 - Travel

WP2 - Hotel

WP3 - Finances

T1.1 - Choice from timetable T1.2 - Ticket T1.3 - Baggage

T2.1 - Choice T2.2 - Booking & Payment

T3.1 - Assessment T3.2 - Gathering of funds

WP4 - Cultural T4.1 - Choice of events

START

END

Page 31: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Project Management Gantt, PERT: Example

Organising a group week-end in Venice.

WP1 - Travel

WP2 - Hotel

WP3 - Finances

T1.1 - Choice from timetable T1.2 - Ticket T1.3 - Baggage

T2.1 - Choice T2.2 - Booking & Payment

T3.1 - Assessment T3.2 - Gathering of funds

WP4 - Cultural T4.1 - Choice of events

T1.1 T2.1 T4.1

T3.1

T3.2

T1.2 T2.2

T1.3

START

END

Critical Path

Page 32: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Interactive Session #2 – Teams of 3 | 30 min

Submit a proposal for financial support to the Ministry.

Your company intends to invest on new equipment; you hear of a financing opportunity offered by the Ministry. For the proposal (you have one month of time), you need to submit: i) ten pages describing in detail the company profile, its organisation (owners, roles...) and strategy, and the equipment to buy; ii) offers from three equipment providers; iii) an excel file showing financial data and market forecasts, proving that breakeven will be reached by three years; iv) the minutes of a board meeting with approval of all documents; v) proof of payment of admission fee via bank transfer.

Prepare a WBS, Gantt and PERT. Include table of deliverables.

Project Management

Page 33: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

Interactive Session #2

Project Management

Any team presenting their outcome ?

Page 34: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

During the interactive sessions, did you feel more comfortable in: -  analysing the problem and identifying the WBS, or -  planning the activities required (Gantt and PERT), or -  both?

Project Management

www.robertoverdone.org à Teaching à PMSS à Test #3

Page 35: Project Management and Soft Skills€¦ · project has (limited) financial, human and technical resources, and is time constrained. A project is a temporary endeavour. Project Management

Prof. Roberto Verdone www.robertoverdone.org

See you next week