Project Management
Dr. Richard Jerz
© 2010 rjerz.com1
Describe or Explain:
Learning Objectives
• What are “projects”• The role of the project manager• Work breakdown structure• Project management tools (Gantt, PERT, & CPM)
• The use of software tools: MS Project
© 2010 rjerz.com2
What are Projects?
• Unique, one‐time operations designed to accomplish a specific set of objectives in limited time frame.
• Often expensive and resource intensive.
© 2010 rjerz.com5
Build A
A Done
Build B
B Done
Build C
C Done
Build D
Ship
JAN FEB MAR APR MAY JUN
On time!
Management Key Decisions
• Deciding which projects to implement• Selecting a project manager• Selecting a project team• Planning and designing the project• Managing and controlling project resources• Deciding if and when a project should be terminated
© 2010 rjerz.com6
Management of Projects
Planning ‐ goal setting, defining the project, team organization
Scheduling ‐ relates people, money, and supplies to specific activities and activities to each other
Controlling ‐monitors resources, costs, quality, and budgets; revises plans and shifts resources to meet time and cost demands
© 2010 rjerz.com7
Project Goals
• On time• On budget• Accomplish tasks with expected quality
© 2010 rjerz.com8
Project Organization
• Often temporary structure• Uses specialists from entire company• Headed by project manager• Coordinates activities • Monitors schedule and costs• Project structure is called “matrix organization”
© 2010 rjerz.com10
TestEngineer
MechanicalEngineer
Project 1 ProjectManager
Technician
Technician
Project 2 ProjectManager
ElectricalEngineer
Computer Engineer
Marketing FinanceHumanResources Design Quality
Mgt Production
President
A Sample Project Organization
11 © 2010 rjerz.com
Steps of Project Planning
• Develop statement of work• Define work breakdown structure• List resources needed• Estimate time required• Estimate the cost
12 © 2010 rjerz.com
Project Risks
• Risk: occurrence of events that have undesirable consequences• Delays• Increased costs• Inability to meet specifications• Unexpected project termination
© 2010 rjerz.com13
Risk Management
• Identify potential risks• Analyze and assess risks• Work to minimize occurrence of risk• Establish contingency plans
© 2010 rjerz.com14
Other Issues
• Temptation to understate costs• Withhold information• Misleading status reports• Falsifying records• Comprising workers’ safety• Approving substandard work
15 © 2010 rjerz.com
Project Scheduling
• Identify activities and resources needed• Identifying precedence relationships • Sequencing activities• Determining activity times & costs• Estimating material and worker requirements• Determining critical activities
© 2010 rjerz.com16
Work Breakdown Structure
Project X
Level 1
Level 2
Level 3
Level 4
18 © 2010 rjerz.com
Project Management Tools
• Project task listing• Gantt charts• Critical Path Method (CPM)• Program Evaluation and Review Technique (PERT)
19 © 2010 rjerz.com
MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Locate new facilities
Interview staff
Hire and train staff
Select and order furniture
Remodel and install phones
Move in/startup
Gantt Chart
21 © 2010 rjerz.com
Gantt Charts
• Advantages• Visual presentation• Simplicity
• Disadvantages• Updating• Doesn’t reflect costs• Doesn’t show relationships between tasks
22 © 2010 rjerz.com
PERT and CPM
• PERT: Program Evaluation and Review Technique (1958)
• CPM: Critical Path Method (1957)
• Graphically displays project activities• Estimates how long the project will take• Indicates most critical activities• Show where delays will not affect project• Can calculate slack times• Helps resource allocation
24 © 2010 rjerz.com
Precedence Diagram
1
2
3
5
6
Locatefacilities
Orderfurniture
Furnituresetup
Interview
Remodel Move in
4
Hire andtrain
7S
25 © 2010 rjerz.com
Example with Times (& AOL)
1
2
3
4
5 6
8 weeks
6 weeks
3 weeks
4 weeks9 weeks
11 weeks
1 week
Move in
26 © 2010 rjerz.com
PERT/CPM Information
• Expected completion time• Critical activities (path)• Each network activities
• Earliest (ES) & latest (LS) start• Earliest (EF) & latest (LF) finish• Slack (S): Allowable delay, = LS‐ES, or LF‐EF
• What if?
27 © 2010 rjerz.com
Critical Path Analysis
• Identifies critical path• Longest path in network• Shortest time project can be completed• Any delay on critical path activities delays project• Critical path activities have 0 slack
28 © 2010 rjerz.com
Probabilistic Estimates
Activitystart
Optimistictime
Most likelytime (mode)
Pessimistictime
o pm te
29 © 2010 rjerz.com
Advantages of PERT
• Forces managers to organize• Provides graphic display of activities• Identifies
• Critical activities• Slack activities
1
2
3
4
5 6
31 © 2010 rjerz.com
Limitations of PERT
• Important activities may be omitted• Precedence relationships may not be correct• Estimates may include a fudge factor
• Not exact science• Iterative process
1
2
3
4
5 6
142 weeks
32 © 2010 rjerz.com
It is not uncommon to face the following situations:
Shortening the duration of the project is called project crashing
Project Crashing
• The project is behind schedule• The completion time has been moved forward
33 © 2010 rjerz.com
Project Management Software
• Computer aided design (CAD)• Groupware (Lotus Notes)• CA Super Project• Harvard Total Manager• MS Project• Sure Track Project Manager• Time Line
© 2010 rjerz.com34
Software Demo: MS Project
35 © 2010 rjerz.com
Advantages of PM Software
• Imposes a methodology• Provides a logical planning structure• Enhances team communication• Flag constraint violations• Automatic report formats• Multiple levels of reports• Enables what‐if scenarios• Generates various chart types
© 2010 rjerz.com36
© 2010 rjerz.com37
Using Microsoft Project
38 © 2010 rjerz.com
Using Microsoft Project
39 © 2010 rjerz.com
Using Microsoft Project
40 © 2010 rjerz.com
Using Microsoft Project
41 © 2010 rjerz.com
Using Microsoft Project
42 © 2010 rjerz.com