project management success criteria

65
THE CRITERIA OF PROJECT MANAGEMENT SUCCESS AT CHEVRON‟S CAPE TOWN REFINERY: A CASE STUDY ZENITH MOSES MITCHELL Research report presented in partial fulfilment of the requirements for the degree of Master of Business Administration at the University of Stellenbosch Supervisor: Prof C Brown Degree of confidentiality: A December 2010

Upload: matthew-phillips

Post on 14-Nov-2015

36 views

Category:

Documents


3 download

DESCRIPTION

An MS thesis describing project management success criteria from evaluating a major project at the Chevron Capetown, South Africa refinery.

TRANSCRIPT

  • THE CRITERIA OF PROJECT MANAGEMENT SUCCESS AT CHEVRONS CAPE

    TOWN REFINERY: A CASE STUDY

    ZENITH MOSES MITCHELL

    Research report presented in partial fulfilment

    of the requirements for the degree of

    Master of Business Administration

    at the University of Stellenbosch

    Supervisor: Prof C Brown

    Degree of confidentiality: A December 2010

  • ii

    Declaration

    By submitting this research report electronically, I, Zenith Moses Mitchell, declare that the entirety

    of the work contained therein is my own, original work, that I am the owner of the copyright thereof

    (unless to the extent explicitly otherwise stated) and that I have not previously in its entirety or in

    part submitted it for obtaining any qualification.

    ZM Mitchell September 2010

    Copyright 2010 Stellenbosch University All rights reserved

  • iii

    Acknowledgements

    I acknowledge God as the Almighty Father of heaven and earth. Through His wisdom and

    guidance, I managed to achieve great things and I believe that there is still more to come. I also

    want to acknowledge my late father, Norman Mitchell for bringing me into this world.

    Much appreciation goes to mother who plays a vital role in all my success stories and

    achievements.

    To my wife, no amount of words can describe my sincere appreciation for the support that you

    gave me right from the beginning. This has been three amazing years for us: getting married and

    expecting our first child. Wow, what more can a man ask for?

    Lastly, I want to share my sincere thanks for my supervisor, Prof C Brown, who supported me even

    in difficult times.

  • iv

    Abstract

    The Chevron Cape Town refinery was constructed in 1996 with a crude capacity of 100,000 barrels

    per day (bpd). The focus of the unit is production and meeting the nameplate market demand. The

    project environment for the refinery is that of maintenance and gradual upgrade. The majority of

    projects handled are small capital projects.

    The aim of this research is to identify what the success criteria for project management should be

    for projects carried out within the small capital projects department of Chevrons Cape Town

    refinery.

    An important distinction to make is that this study looks at project management success and not

    project success, although the aspects of project success will be discussed to highlight how closely

    related the two concepts are. Project success is not directly proportional to project management

    success and neither is project management success directly proportional to project success.

    In the past decades, project management success was usually indicated by the project completion

    within the time, cost and performance constraints (Kerzner, 2004:29). This has now evolved to

    understanding all the objectives of the project. Project management can still be deemed successful

    even if it did not meet all the objectives of the project and vice versa, as long as there are mutual

    trade-offs agreed to by the developer (project manager) and the client.

    White and Fortune (2002:1-11) conducted a survey to identify common criterion used for defining

    project management success. The three criteria identified for judging project success are

    completion on time, within the budget and to performance (specification).

    Project management success has been found to be a very difficult topic to define. This research

    report shown that project management success needs to be moved beyond the iron-triangle to

    other criteria like safety and meeting the objectives of the client. What was evident was that

    criteria, factors, dimensions and measures are concepts widely used by researchers and it is

    hoped that these topics. A very interesting discovery during my first interview was that project

    management success comes in three phases or parts, which are pre-delivery, delivery and post-

    delivery.

    What was evident from this research was that the criteria for project management success need to

    be established up front before the project gets to the delivery phase. There is no way that one can

    measure project management success when the success criteria one is looking for at the end of

    the project have not been established up front.

  • v

    The case study is summarised using the diagram in chapter five showing the new project

    management success criteria that needs to be adopted by the refinery.

    Future research into project management success criteria could include a survey which could go

    out the whole refinery and not just the representative sample who were interviewed for this report

    which could confirm the project management criteria found in this report.

  • vi

    Opsomming

    Die Chevron Kaapstad raffinadery is in 1996 gestig met n ruolie kapasiteit van 100,000 vate per

    dag. Die fokus van die eenheid is produksie en om aan die marknavraag te voldoen. Die

    projekomgewing van die raffinadery is instandhouding en mettertydse opgradering van die

    raffinadery. Die meerderheid van projekte wat hanteer word is klein-kapitaalprojekte.

    Die doel van hierdie navorsing is om te identifiseer wat die sukseskriteria vir projekbestuur behoort

    te wees vir projekte wat binne die klein-kapitaaldepartement van Chevron se Kaapstad raffinadery

    behartig word.

    n Belangrike onderskeid om te maak is dat hierdie studie na projekbestuursukses kyk en die

    projeksukses nie, alhoewel die aspekte van projeksukses ook bespreek sal word om uit te lig hoe

    naby verwant die twee konsepte aan mekaar is. Projeksukses is nie direk proporsioneel tot

    projekbestuursukses nie en omgekeerd.

    In die afgelope dekades was projekbestuursukses gewoonlik aangedui deur die afhandeling van

    die projek binne die tydsraamwerk, koste en prestasiebeperkinge (Kerzner, 2004:29). Hierdie

    konsep het intussen uitgebrei na n verstaan van al die doelwitte van die projek. Projekbestuur kan

    steeds as suksesvol beskou word al het dit nie aan al die doelwitte van die projek voldoen nie, en

    omgekeerd, solank as wat daar wedersydse toegewings deur beide die ontwikkelaar

    (projekbestuurder) en die klint gemaak word.

    White en Fortune (2002:1-11) het n opname gemaak om die algemene kriteria te identifiseer wat

    gebruik word om projekbestuursukses te definieer. Die drie kriteria wat uitgewys is om n projek te

    evalueer, is afhandeling van die projek binne die tydsraamwerk, koste en prestasiebeperkinge.

    Projekbestuursukes is n baie moeilike onderwerp om te definieer. Hierdie navorsingsverslag wys

    dat projekbestuursukses verby die yster-driehoek moet beweeg om ander kriteria soos veiligheid

    en die voldoening aan die klint se doelwitte, in te sluit. Wat duidelik na vore gekom het is dat

    kriteria, dimensies en metings konsepte is wat wyd deur navorsers gebruik word. n Baie

    interessante ontdekking gedurende die eerste onderhoud was dat projekbestuursukses in drie

    fases of dele voorkom, naamlik voor-lewering, lewering en na-lewering

    Wat duidelik uit die navorsing is, is dat die kriteria vir projekbestuursukses voor die aanvang van n

    projek vasgestel moet word, voordat die projek die afleweringsfase bereik. Daar is geen manier

    wat projekbestuursukes gemeet kan word wanneer die sukseskriteria wat aan die einde van n

    projek gesoek word, nie aan die begin vasgestel is nie.

  • vii

    Die gevallestudie word opgesom deur die diagram in hoofstuk vyf te gebruik wat die nuwe

    projekbestuursukseskriteria aandui wat deur die raffinadery aanvaar moet word.

    Toekomstige navorsing in projekbestuursukseskriteria kan n opname insluit wat aan die hele

    raffinadery gestuur kan word en nie net die verteenwoordigende steekproef met wie daar vir

    hierdie verslag se doeleindes onderhoud gevoer is om die projekbestuurkriteria van hierdie verslag

    te bevestig nie.

  • viii

    Table of contents

    DECLARATION ................................................................................................................... II

    ACKNOWLEDGEMENTS .................................................................................................. III

    ABSTRACT ....................................................................................................................... IV

    OPSOMMING .................................................................................................................... VI

    LIST OF TABLES .............................................................................................................. XI

    LIST OF FIGURES ........................................................................................................... XII

    LIST DEFINITIONS ......................................................................................................... XIII

    CHAPTER 1 ORIENTATION .......................................................................................... 1

    1.1 Introduction ............................................................................................................. 1

    1.2 Project environment at the refinery ......................................................................... 2

    1.3 Problem statement .................................................................................................. 5

    1.4 Research objectives ............................................................................................... 7

    1.5 Literature review ..................................................................................................... 7

    1.5.1 Project life cycle ......................................................................................................... 7

    1.5.2 Project life cycle used by the refinery ......................................................................... 9

    1.6 Research design and methodology ...................................................................... 10

    1.7 Chapter summary ................................................................................................. 10

    CHAPTER 2 LITERATURE REVIEW ........................................................................... 11

    2.1 Introduction ........................................................................................................... 11

    2.2 Project management process ............................................................................... 12

    2.2.1 Initiation ................................................................................................................... 12

    2.2.2 Planning .................................................................................................................. 12

    2.2.3 Executing ................................................................................................................. 12

    2.2.4 Monitoring and controlling ........................................................................................ 13

    2.2.5 Closing .................................................................................................................... 13

    2.3 Project management functions ............................................................................. 13

    2.3.1 Project integration management .............................................................................. 13

    2.3.2 Project scope management ..................................................................................... 14

    2.3.3 Project time management ........................................................................................ 15

    2.3.4 Project cost management ........................................................................................ 15

    2.3.5 Project performance management ........................................................................... 15

  • ix

    2.3.6 Project human resource management ..................................................................... 16

    2.3.7 Project communication management ....................................................................... 17

    2.3.8 Project risk management ......................................................................................... 18

    2.3.9 Project procurement management ........................................................................... 18

    2.4 Criteria for project management success ............................................................. 19

    2.4.1 The concept of project success ................................................................................ 19

    2.4.2 Project management success criteria ...................................................................... 20

    2.4.2.1 Indicator 1: Completion within budget ................................................................................. 21

    2.4.2.2 Indicator 2: Satisfying the project schedule ......................................................................... 21

    2.4.2.3 Indicator 3: Adequate performance standard ...................................................................... 21

    2.4.2.4 Indicator 4: Meeting project objectives. ............................................................................... 21

    2.4.3 Indicator 5: Optimising trade-offs ............................................................................. 22

    2.4.4 Project success criteria ............................................................................................ 22

    2.5 Project management success factors ................................................................... 23

    2.6 Role of the project manager towards project management success ..................... 25

    2.7 Organizational structure for projects ..................................................................... 27

    2.8 Project management tools/techniques .................................................................. 28

    2.8.1 Traditional methods (Gantt charts and wall charts) .................................................. 28

    2.8.2 Concurrent engineering/management ...................................................................... 29

    2.8.3 Project management information systems (PMIS) ................................................... 29

    CHAPTER 3 RESEARCH FINDINGS AND ANALYSIS ............................................... 30

    3.1 Introduction ........................................................................................................... 30

    3.1.1 Core effluent project background ............................................................................. 30

    3.1.2 The project management process used by the refinery ............................................ 31

    3.2 Findings from interviews and project data ............................................................ 35

    3.2.1 Interview 1: Drawing office supervisor ...................................................................... 35

    3.2.2 Interview 2: Reliability and maintenance representative ........................................... 36

    3.2.3 Interview 3: Electrical and Instrumentation stakeholder............................................ 39

    3.2.4 Interview 4: Project manager ................................................................................... 40

    3.2.5 Interview 5: Interview with customer (operations department) .................................. 42

    3.2.6 Interview 6: Interview with mechanical contractor .................................................... 44

  • x

    CHAPTER 4 SUMMARY, CONCLUSION AND RECOMMENDATIONS ..................... 46

    4.1 Introduction ........................................................................................................... 46

    4.2 Summary of main findings .................................................................................... 46

    4.2.1 Interview 1: Drawing office supervisor ...................................................................... 46

    4.2.2 Interview 2: Reliability and maintenance representative ........................................... 46

    4.2.3 Interview 3: Electrical and instrumentation stakeholder ............................................ 46

    4.2.4 Interview 4: Project manager ................................................................................... 47

    4.2.5 Interview 5: Interview with customer (operations department) .................................. 47

    4.2.6 Interview 6: Interview with mechanical contractor .................................................... 47

    4.5 Recommendations ................................................................................................ 48

    4.6 Further research ................................................................................................... 50

    REFERENCES .................................................................................................................. 51

  • xi

    List of Tables

    Table 1.1: Project management success criteria for Chevron projects ............................................ 5

    Table 2.1: Individual competency model ....................................................................................... 17

    Table 2.2: Critical factors in the project management life cycle ..................................................... 25

    Table 2.3: Organisational structure and the project characteristics ............................................... 27

    Table 3.1: Capital stewardship expectation table .......................................................................... 33

    Table 3.2: Results of interview number 1 ...................................................................................... 36

    Table 3.3: Results of interview number 2 ...................................................................................... 38

    Table 3.4: Results of interview number 3 ...................................................................................... 40

    Table 3.5: Results of interview number 4 ...................................................................................... 42

    Table 3.6: Results of interview number 5 ...................................................................................... 44

    Table 3.7: Results of interview number 6 ...................................................................................... 45

  • xii

    List of Figures

    Figure 1.1: Different types of projects undertaken at refinery (Refinery Project Data Base, 2007 -

    2010) .............................................................................................................................................. 1

    Figure 1.2: Typical structure for field projects at Chevron Refinery ................................................. 3

    Figure 1.3: Typical structure for small capital projects at Chevron Refinery..................................... 3

    Figure 1.4: Project life cycle .......................................................................................................... 8

    Figure 1.5: Basic CPDEP road map ................................................................................................ 9

    Figure 2.1: The Iron Triangle ...................................................................................................... 12

    Figure 2.2: Definition of success over time .................................................................................... 19

    Figure 4.1: Proposed project management success criteria for Chevrons Cape Town refinery

    based on this research paper ........................................................................................................ 48

  • xiii

    List definitions

    Project A project is a temporary endeavour undertaken to create a unique product or service (PMBOK GUIDE, 2000:4).

    Project management

    The application of knowledge, skills, tools and techniques to project activities to meet project requirements (PMBOK GUIDE, 2000:5). Munns and Bjeirmi defines it as the process of controlling the achievement of the project objectives (1996:81). Project Management is accomplished through the use of processes such as:

    Initiating

    Planning

    Executing

    Controlling

    Closing

    Project management success

    The successful accomplishment of a project with regards to cost, time and performance. The three dimensions indicate the degree of the efficiency of project execution (Pinkerton, 2003:337)

    Project success In the modern project management era project success is define as the accomplishment of a project within time, cost and quality and the project must be accepted by the customer.

    Field projects

    Field projects are all capital projects with a project value of less than two million rand (R2 million), regardless of the complexity of the project (Global Manufacturing Capital Stewardship Expectations, 2009)

    Small capital projects

    Small capital projects are all projects with a project value of more than two million rand (R2 million) and less than twenty five million dollars ($25 million) regardless of the complexity (Global Manufacturing Capital Stewardship Expectations, 2009).

    Project life cycle

    Project life cycle defines the phases that connect the beginning of a project to its end (Guide to the PMBOK, 2004:19). Burke (2007:273) on the other hand states that project life cycle provides and informative overview of how the level of risk changes as the project progresses through the project phases (concept, design, implement and commission).

    World class performance

    Project was within budget and schedule, meets client needs and was delivered injury and incident free (Chevrons Project Managements Handbook, 2007:203).

  • 1

    CHAPTER 1 ORIENTATION

    1.1 INTRODUCTION

    The Chevron Cape Town refinery was constructed in 1996 with a crude capacity of 100,000 barrels

    per day (bpd). The focus of the unit is production and meeting the nameplate market demand. The

    project environment for the refinery is that of maintenance and gradual upgrade. The majority of

    projects handled are small capital projects.

    The majority of the projects at the refinery are undertaken due to five reasons namely

    sustainability, replacement, growth, compliance and study. Figure 1.1 categories the different type

    of projects undertaken at the refinery.

    Figure 1.1: Different types of projects undertaken at refinery (Refinery Project Data Base, 2007 - 2010)

    Safety, which is supported at all management levels, is one of the core values of the Chevron

    Corporation ensuring the safety of all employees. There is a general feeling amongst all project

    managers that project management focuses more on safety in terms of costs and schedule and as

    a result, Chevron projects take longer and costs are slightly higher than benchmarked projects in

    other industries.

    In the early 1990s, Chevron developed and deployed the Chevron Project Development and

    Execution Process (CPDEP). Since then, additional processes and tools have been generated

    and are continuously improved upon and refined to support and complement the CPDEP. The

    CPDEP and its related processes and tools have evolved into the Chevron Project Management

    (CPM) System, which is an organised and coordinated methodology that promotes and sustains

    the successful execution of projects. Moving from a process to a system perspective is crucial to

    Chevrons sustained success with major capital projects.

    34, 35%

    6, 6% 26, 26%

    25, 25%

    8, 8%

    Category

    Compliance Growth Replacement Sustian Study

  • 2

    By moving from a process focus to a system focus, Chevron is enabling a more cohesive

    integration of the various processes and tools to manage capital projects effectively. It also

    provides an opportunity to implement continuous improvement across the entire system and

    ensures sustained organisational capability by applying the processes and tools to Chevrons

    portfolio of projects.

    The CPM System is comprised of five key components:

    Project Management Process CPDEP provides the core process and framework, which

    coordinates and aligns the other components.

    Decision Making The decision making process and behaviours that guide the project

    team and decision makers in making good quality decisions.

    Project Assurance The reviews and assurance checks that are used to assess the

    readiness of the project to proceed and help assure the project team is achieving a high

    level of decision and execution quality.

    Organisational Capability The people, processes, and practices that provide a means

    to, develop organisational plans, acquire staff, and develop and lead an effective project

    team.

    Tools and Practices - The policies, standards, procedures, best practices, supporting

    processes, and templates that enable the project team to plan and execute the project.

    Chevron became the outright owner of the Cape Town refinery in 2002 and with it came the

    expectation that the Chevron Project Development and Execution Process (CPDEP) would be

    adopted for their projects.

    The refinery has a project portfolio made up of a large number of field (short-term projects) and

    small capital projects (long term projects). Chevron has introduced a project governance model for

    projects that are linked to the CPDEP process. Projects are categorised by value and the

    expectation is that the higher the value, the more complex the project. Field projects are all

    projects with a project value (total cost) of less than R2 million and small capital projects are all

    projects with a project value of more than R2 million and less than R25 million . All projects above

    the R250 million threshold are categorised as major capital projects. Major capital projects

    normally involves stakeholders and clients outside the refinery fence, hence these projects are

    managed and monitored on a corporate level.

    1.2 PROJECT ENVIRONMENT AT THE REFINERY

    The organisation follows a matrix structure, with team members seconded to projects from different

    departments. This in itself creates challenges for project managers to ensure that project

  • 3

    alignment and project integration management are maintained at the required levels to deliver

    successful project management practices.

    Figure 1.2 illustrates the team members of a typical project in the field projects department:

    Figure 1.2: Typical structure for field projects at Chevron Refinery

    Source: Chevron Project Management Manual (2007:103)

    Within the field projects group, project managers usually fulfil a dual function - that of a project

    manager and the discipline engineer (mechanical, electrical, instrumentation, information

    technology, etc.) for most projects within the field category. This means that the field engineers are

    fulfilling a project-engineering role, instead of a pure project management role.

    Field projects are managed with a weak matrix team and the authority normally lies with the

    functional manager of the operations group. Per definition, the project manager fulfils this co-

    ordinating role. The operations department is the most important client of the field group.

    Figure 1.3 illustrates the team members of a typical project for the small capital project department:

    Figure 1.3: Typical structure for small capital projects at Chevron Refinery

    Source: Chevron Project Management Manual (2009:104)

  • 4

    Small capital projects are managed with a weak matrix team and the authority is equally spread

    amongst the technical department, operations and external stakeholders. External stakeholders

    refer to the sponsors and end users (commercial and sales department). Most of the team

    members are dedicated to a specific project on a full-time basis, but still reports to a separate line

    manager. Much better alignment between functional departments is visible within the small capital

    project department than the field project group.

    The project support office provides services for both the field and small capital project

    departments. The objectives of this department are as follows:

    Routinely compare actual performance to cost, schedule and resource baseline.

    Estimate/re-estimate cost, duration and resources needed to complete the project, by early

    identification of changes to the project scope and proactively analysing performance.

    Implement corrective actions when performance trends deviate from the baseline.

    Promote accountability for meeting business plan and project objectives.

    Develop an execution driven culture throughout the business unit.

    Provide a summary level dashboard for tracking rolled-up performance of the refinerys

    total project portfolio.

    The construction department is an independent entity that provides services to the project manager

    (field and small capital projects) concerning the execution of the project. For field projects, the

    value added by the construction department is noticeable from phase three of the project cycle and

    for small capital projects, the value added is visible from much earlier in the project cycle.

    The procurement department provides services to the project manager through the entire project

    cycle. The procurement department has has the reputation of causing bottlenecks for projects and

    has implications on delivering projects on time and to some extent, on budget.

    The refinery procurement department provides project managers with the following services:

    Procurement / buying

    Warehouse / stores management

    Contracts management / legal contracts writing

    Strategic sourcing / category management (high level strategic approach)

    Business enablement / best practices

    Starting a project is one of the key elements of a successful project. The Chevron Project

    Management System starts the process by making certain that the opportunity is aligned with the

    strategic interests of the business unit and that it creates value, as well as assuring alignment

    among the participants. A high-level project plan is develop and communicated to the

  • 5

    stakeholders, followed by a detailed project execution plan. In the early stages, project

    alternatives are analysed to select the option that provides the optimal value for the

    project.

    1.3 PROBLEM STATEMENT

    The aim of this research is to determine what the project management success criteria are for

    refinery projects and how projects should be set up for future success. The success criteria

    derived from this research should be useful to improve future projects.

    Currently, Chevrons project management success criteria are somewhat traditional in their

    expectations and are based on safety, cost, quality, and schedule. An additional criterion that is

    important to take into consideration is operability. The project management success criteria are

    mentioned in Table 1.1 below. The expectation is that each project puts up a world-class

    performance and the measures to achieve this are also mentioned in Table 1.1 below.

    Table 1.1: Project management success criteria for Chevron projects

    Performance criteria Success measure

    Cost performance Within a maximum tolerance of 10% of the authorised value.

    Scheduled performance Within a maximum tolerance of 10% of the authorised duration.

    Safety performance Zero recordable injuries and days away from work.

    Operability Within a maximum tolerance of 5% of the design requirements.

    Source: Chevrons Project Management Handbook (2009:203)

    The cost performance criteria show that all projects need to come in under budget to achieve

    world-class performance. The debate around this topic has been quite interesting at the refinery

    because it uses a P50 (50% probability) cost estimation, which means that there is a fifty percent

    chance that the project will under run and a fifty percent chance that the project will over run its

    budget. The result is that if the corporation expects projects to come in under budget, the cost

    estimate could no longer be a P50 but something a little higher and there is a chance that project

    estimators will build an additional contingency into project estimates in order to come in under

    budget. The schedule estimates are also based on the cost estimate but there is greater leniency

    regarding the schedule so it has the chance of coming in both under and over schedule, which

    seems to be it in the P50 range.

    Safety is a core value at the corporation and safety performance expects to have zero incidents

    and injuries. Project management staff is expected to introduce Chevrons safety standards for

  • 6

    every project undertaken at the refinery. These include following the incident and injury free safety

    programme, which is based on behavioural observations. This means that peers observe each

    other at the workplace and identify risky behaviour. An example of this is when a civil engineering

    contractor lifts a steel reinforcement into an excavation for a column base but the weight of the

    base is too heavy for the steel fixing team to lift. The observer would stop the job and expect a

    mobile crane to help the team complete the task. The risky behaviour in this instance would be

    damage to the teams backs if they lifted the reinforcement. Although it may not be painful in the

    near future, too much exertion could create long-term back pain.

    The operability (customer needs) criteria expects that if a plant upgrade was expected to deliver

    10,000 barrels of crude oil a day, it would be acceptable to run 9,000 barrels a day. Chevron

    expects all four criteria to be achieved to maintain a world-class performance.

    With the tight schedule and cost pressures in the small project environment, the project

    management practices and execution of small projects are accelerated or neglected. In an

    organisation where small capital projects are the main focus it is important to execute these

    projects effectively.

    For the purposes of this project, the research will look at the following problems within the small

    capital project department:

    The dual function of the project managers poses to be a career development problem for

    them because project managers for small capital projects have to fulfil both a technical and

    a project management role. This has been an issue for years at the refinery.

    The support provided by the project support office concerning cost estimates, estimate

    assurance, schedules, change control and reporting. Scheduling as a subject is not a main

    stream course at tertiary institutions, one normally comes across it by chance. The result is

    that most people have not received professional training in scheduling. At the same time,

    employing experienced planners and keeping the existing ones is proving to be a difficult

    task, especially in this industry. Various tools exist to assist the project support office.

    These tools are stand-alone systems and a certain level of expertise is required to provide

    quality reports to project managers and management.

    Scope creep has resulted in large scheduling and costs overruns in the past and major

    delays in projects.

    The procurement department has been the cause of major bottlenecks for several years.

    Several attempts have been made to improve the performance of the procurement

    department, especially regarding service provision to the small capital project department.

    Most of these attempts resulted in significant performance improvements in the

    procurement department, but a lot still needs to be done.

  • 7

    Small capital projects represent approximately 90% of the refinerys capital budget and far exceed

    the number of major capital projects. Why then is it important to execute and manage small

    projects effectively?

    The reasons are:

    that small capital projects have short schedules, and performance changes have a quick

    impact on project outcomes;

    that building competency in small projects helps to grow large project competency.

    Refinery operations are well known for tight profit margins and with the crude oil price reaching

    record high levels in 2008, effective project management processes and practices became more

    and more essential.

    1.4 RESEARCH OBJECTIVES

    The aim of this research is to identify what the project management success criteria should be for

    projects carried out within the small capital projects department of Chevrons Cape Town refinery.

    An important distinction to make is that this study looks at project management success and not

    project success, although the aspects of project success will be discussed to highlight how closely

    related the two concepts are. Project success is not directly proportional to project management

    success and neither is project management directly proportional to project success.

    Effective project management within the small capital project department is imperative for older

    refineries where growth projects form the minority of the departments project portfolio, with

    compliance and sustain projects forming the majority of the projects.

    Chevrons focus on project management is based on the drive to improve the return on capital

    employed (ROCE) and to achieve superior long-term shareholder returns. Effective project

    management will enable the refinery to:

    Select investments with a higher return more value for money spent

    Execute the same projects for less money than the competitors do.

    1.5 LITERATURE REVIEW

    1.5.1 Project life cycle

    A number of different life cycle models exist in project management. Gray and Larson (2009:6)

    state that some project managers find it useful to use the project life-cycle as the cornerstone for

    managing projects. According to Gray and Larson (2009:6) the project life cycle plays a vital role

    in:

  • 8

    recognising that any project has a limited life span;

    ensuring that there are predictable changes in the level of effort and focus over the life of

    the project.

    The starting point begins the moment the project has been given the go ahead. For most projects

    the efforts in the beginning start slowly, builds to peak, and then declines to the delivery of the

    projects (see figure 1.4 below).

    Figure 1.4: Project life cycle

    Source : Gray and Larson (2009:6-7)

    In practice, the project life-cycle is used by some project groups to estimate or re-estimate the

    timing of major tasks over the life of the project, like when the team plan a major commitment of

    resources in the defining stage.

    A driving force behind the rapid demand for project management in todays world is the shortening

    of the product life-cycle (Gray and Larson, 2009:7). Today, high-tech industries have product life

    cycles averaging 1 to 3 years, compared with 30 years ago when product life cycles averaged 10

    to 15 years. A common rule of thumb in the world of high-tech product development is that a six-

    month product delay can result in a 33 percent loss in product revenue. Emphasising how effective

    project management can provide businesses with a competitive advantage.

  • 9

    1.5.2 Project life cycle used by the refinery

    The Chevron Development and Execution Process (CPDEP) is the core process for project

    management within the Chevron Project Management System. CPDEP is a phase-gated process

    designed to improve decision-making and execution of projects by fostering better planning,

    collaboration, and communication.

    The key objectives of the CPDEP phase-gated process are to:

    Improve project decision making

    Improve project execution

    Create better alignment of team members, decision makers and shareholders

    The phase-gated process is a team-orientated process that provides overall structure and a

    sequence of work steps that are consistent across all types of projects. The most common

    representation of CPDEP is the five-phase road map shown in Figure 1.5 below.

    Figure 1.5: Basic CPDEP road map

    Source: Chevrons Project Manual Handbook (2009)

    Endorser(s) ______________Decision Executive ________Decision Review Board_____

    Endorser(s)______________Decision Executive ________Decision Review Board_____

    New Opportunities

    The process does not end here! Secondary

    opportunities and projects will loop

    back into the appropriate phase.

    Decision Makers

    The decision makers,as defined in CSOC,

    responsible for project decisions and ultimate

    project outcomes.

    Deliverables at Major Reviews

    These deliverables provide the information

    needed for decision makers to make their

    decisions. The key deliverables are collated into a

    comprehensive Decision Support

    Package (DSP) to ensure a high quality decision.

    Work Team

    The multifunctionalwork team carries out the work under the

    guidance of the project manager or

    team leader. Expectations of the decision makers are

    met through frequent communication and

    alignment checks.

    Focus Items

    Focus items can be shown on the Road Map, or simply documented in

    the PEP. These Focus Items indicate work that

    will be completed to produce deliverables necessary for effective

    decision making.

    NEW OPPORTUNITIES

    Project Manager/Team Leader____

    _____________________________

    Work Team ___________________

    _____________________________

    PHASE 5Operate and Evaluate

    PHASE 4Execute

    PHASE 2Generate and Select

    Alternative(s)To Phase 1

    DS

    P D

    ocu

    men

    t

    Update Frame Refine & add further detail

    Generate Alternatives

    Define Scope for Alternatives sufficiently to support evaluation

    Analyze Alternatives Value/Benefits Costs Schedule Uncertainties & Risks

    Narrow and Select Alternatives

    Update the Business Case

    Project Management Practices & VIPs

    Phase 2 DEQ Assessment Seek and Incorporate Lessons Learned

    Others as needed

    Develop Project Execution Plan (PEP) for Phase 3

    Road Map PEP Objectives& Strategies Detailed Plans as needed Overall Project Schedule

    Other Focus Items __________________________

    Fully Define and Freeze Scope

    Begin Detailed Design

    Project Management Practices & VIPs

    Phase 3 DEQ Assessment Seek and Incorporate Lessons Learned

    Others as needed

    Develop Project Execution Plan (PEP) for Phase 4

    Road Map PEP Objectives& Strategies Detailed Plans as needed Overall Project Schedule

    Develop Funding Request

    Other Focus Items _____________________________

    _____________________________

    Complete Detailed Design

    Consistently Execute defined Plans

    Finalize Business Plan

    Finalize Operating Plan

    Project Management Practices & VIPs

    Seek and Incorporate Lessons Learned

    Others as needed

    Other Focus Items _________________________

    _________________________

    Execute Business Plan

    Operate Asset

    Monitor and Evaluate Performance

    Identify New Opportunities

    Project Management Practices & VIPs

    Seek and Incorporate Lessons Learned

    Others as needed

    Other Focus Items ________________________ ________________________

    STOP, HOLD,

    or RECYCLE

    STOP, HOLD,

    or RECYCLE

    STOP, HOLD,

    or RECYCLE

    PHASE 1Identify and Assess

    Opportunities

    Develop Frame Discovery Definition Structure

    Preliminary Assessment

    Project Management Practices & VIPs

    Phase 1 DEQ Assessment Seek and Incorporate Lessons Learned

    CPDEP for Change Assessment

    Others as needed

    Developed the Business Case

    Develop Project Execution Plan (PEP) for Phase 2

    Road Map PEP Objectives& Strategies Detailed Plans as needed Overall Project Schedule

    Other Focus Items ______________________ ______________________

    AcceptPlan?

    PHASE 3Develop Preferred

    Alternative

    STOP, HOLD,

    or RECYCLE

    Endorser(s) ___________________Decision Executive _____________Decision Review Board__________

    Decisions

    The decision diamondrepresents key decisions and serves to

    delineate phases. The decision can be to stop,

    hold, recycle or proceed.

    OperableAssets

    Fully Defined Scope

    Proceed with Execution,

    Approve Funding

    and Phase 4 Plan?

    Execution Plan,Funding Request

    Project Manager/Team Leader

    ________________________

    Work Team ______________

    ________________________

    Project Manager/Team Leader

    ________________________

    Work Team ______________

    ________________________

    Endorser(s)______________Decision Executive ________Decision Review Board_____

    Project Manager/Team Leader

    ________________________

    Work Team ______________

    ________________________

    Endorser(s)______________Decision Executive ________Decision Review Board_____

    Project Manager/Team Leader

    ________________________

    Work Team_______________

    ________________________

    Proceed with

    Operations &

    Approve Operating

    Plan?

    Operations Metrics

    New Opportunities

    RecommendedAlternative(s)

    Proceed with

    Development of

    Preferred Alternative& Approve Phase 3

    Plan?

    Framing Document,Preliminary Assessment,

    Forward Plan

    OpportunityIdentified

    Proceed with

    Generating Alternatives

    & Approve Phase 2 Plan?

    BASIC CPDEP ROAD MAP

    Pursue New

    Opportunities?

    Rev_14-Jan-20102010 Basic CPDEP Roadmap.ppt

    Chevron Project Development and

    Execution Process (CPDEP) Principles:

    Focus on key value drivers for the opportunity

    Use of integrated multifunctional teams

    Effective input, communication and alignment between teams, decision makers, and stakeholders

    Decision driven, not activity driven - do the work necessary to support the next decision

    Consistent use of best practices and tools

    DS

    P D

    ocu

    men

    t

    DS

    P D

    ocu

    men

    t

    DS

    P D

    ocu

    men

    t

  • 10

    1.6 RESEARCH DESIGN AND METHODOLOGY

    The outcome of this research will be qualitative in nature resulting from a proposed case study.

    The mode of observation or sources of data will be participant observation, with semi-unstructured

    individual or group interviews and the use of documentary sources and other existing data. The

    unstructured interview process will be carried out with six individuals who are stakeholders in

    projects carried out at the refinery. The discussions with the participants will play a key role in

    identifying project management success criteria as projects move through the project management

    life cycle.

    The interview process will develop a table which can be used to represent project success criteria

    at the refinery. Once these criteria have been identified, the discussion will involve the importance

    that these criteria have as different categories of project are concerned.

    The semi-unstructured interviews will start by asking senior project managers what they think the

    main problems are that needs attention in this research study. The literature study will then focus

    around these problem areas, followed by an in-depth study on the documentary sources available

    and the unstructured interviews with the six participants.

    The main problem is that each project is unique and the question arises whether different category

    projects should be managed in different ways or is whether each project is so different that their

    uniqueness needs to be respected even at the project management level. Another consideration

    would be whether elapsed time has an impact on the criteria identified

    1.7 CHAPTER SUMMARY

    The velocity of change required to remain competitive or simply keep up has created an

    organization climate in which hundreds of projects are implemented concurrently. Sharing and

    prioritizing resources across a portfolio of projects in a multiproject environment like at the Cape

    Town refinery has proven to be a major challenge for senior managers at the refinery. It as to be

    highlighted that many firms has no idea of the problems involved with the inefficient management

    of small projects. A question that this research is trying to address is how to create an

    organizational environment that supports mulitproject management. The criteria developed for

    project management success in this research should assist the organization with achieving more

    accountability, flexibility, innovation, speed, and continuous improvement with regards to project

    management.

  • 11

    CHAPTER 2 LITERATURE REVIEW

    2.1 INTRODUCTION

    Kerzner (2004:1) states that for more than 35 years project management was viewed as a process

    that might be nice to have, but not one that was necessary for the survival of the firm. Project

    management was viewed as a threat to established lines of authority and, in most cases, only

    partial project management was used. In the 1950s, project management was defined as the

    application of a collection of tools and techniques to direct the use of diverse resources toward the

    accomplishment of a unique, complex, one-time task within time, cost and performance. By the

    mid-1990s companies started to change this mentality largely due to two reasons:

    Companies were under severe competitive pressure to create quality products in a shorter

    period of time.

    The importance of developing long-term relationships with the customers had come to the

    forefront, the survival of the company was now at stake.

    Each task requires a particular mix of these tools and techniques structured to fit the task

    environment and project life cycle from conception to completion of the task (Atkinson, 1999:337-

    342). The main criteria identified from what is commonly known as the iron triangle (shown in

    Figure 2.1) is still used to this day even though it is considered inadequate because of other criteria

    like safety and meeting the objectives of the client.

    Project management is a field of practice that promotes a normative approach to the management

    of projects. It is codified in standards, tools and techniques, based primarily on experiences of

    practitioners in developed Western economies and relies extensively on assumptions of economic

    rationality (Muriithi & Crawford, 2003:310). Project management applies knowledge, skills, tools

    and techniques to project activities to achieve project requirements. The art of project management

    is accomplished through the application and integration of the project management processes of

    initiating, planning, executing, monitoring, controlling and closing (PMBOK Guide, 2004:8).

    Project management varies from project to project, which makes it imperative to define what a

    project is. A project involves a single, definable purpose, end-item, result or outcome, usually

    specified in terms of cost, schedule, and performance requirements. Turner (1993:44) defines a

    project as an endeavour in which human, material and financial resources are organised in a

    novel way, to undertake a unique scope of work of given specification within constraints of cost and

    time so as to achieve beneficial change defined by quantitative and qualitative objectives.

  • 12

    Figure 2.1: The Iron Triangle

    Source: Atkinson, 1999:340

    2.2 PROJECT MANAGEMENT PROCESS

    According to Cleland and Ireland (2004:53) project management involves five processes: initiating,

    planning, executing, controlling and closing. These processes are based on the assumption that

    project managers are rational problem solvers who are able to identify and apply rational problem

    solving models to projects. These processes follow the sequence in which they are listed. In the

    event that a project goes off course, re-planning comes into play, and if a project is found to be in

    serious trouble, it may have to go all the way back to the initiating process to be re-started.

    2.2.1 Initiation

    In this stage, a project is launched after the decision has been made to undertake a project. The

    project sponsor creates a project charter that defines what needs to be done in order to meet the

    customers requirements. The charter should be used to authorise work on the project, define the

    authority, responsibility, and accountability of the project team, and establish scope boundaries for

    the job (Cleland & Ireland, 2004:53).

    2.2.2 Planning

    Planning is the most crucial part of the project, as it determines the outcome of the project. Lack of

    planning or no planning at all results in project failure. Failure to plan makes it impossible to control

    the project in cases of hiccups (Cleland & Ireland, 2004:53).

    2.2.3 Executing

    The execution stage has two aspects to it. The first is the technical aspect where the focus is on

    execution to create the product. The second aspect is implementing the project plan. This

  • 13

    facilitates easy control of the project when encountering difficulties. It is easy to take corrective

    measures to get back on track when following a well laid out plan (Cleland & Ireland, 2004:53).

    2.2.4 Monitoring and controlling

    Control is exercised by comparing where project work is to where it is supposed to be, then taking

    action to correct any deviations from the target. Controlling is done by monitoring progress. In

    monitoring, the quantity and performance are assessed with the tools available for the particular

    project. The results of the assessment are compared to the plan and if there are major deviations,

    mitigation plans are applied to put the project back in line. (Cleland & Ireland, 2004:54).

    In every project that goes well there are always minor deviations, which are usually ignored unless

    they exceed the pre-established threshold or if they could potentially drift further off course.

    2.2.5 Closing

    Cleland and Ireland (2004:53) stated the in many cases, once the product is produced to the

    customers satisfaction, the project is considered finished which should not be the case. A final

    lessons-learned review should be done before the project is considered complete. Failing to do a

    lessons-learned review means that future projects will likely suffer the same headaches

    encountered on the one just done.

    2.3 PROJECT MANAGEMENT FUNCTIONS

    In project management, there are nine broad project management functions or knowledge areas

    (Artto, Lehtonen & Saranen, 2001:255). These include the management of integration, scope, time,

    cost, risk, quality, human resources, communications and procurement. These nine functions are

    managed through the project management life cycle. Thus the knowledge, skills, tools and

    techniques are applied to manage scope, organisation, quality, cost, time and risk, from initiation

    and concept through to hand-over (termination) in a rolling, iterative process.

    2.3.1 Project integration management

    The guide to the PMBOK (2004:337) state that project integration management includes the

    processes and activities needed to identify, define, combined, unify and coordinate the various

    processes and project activities within the project management process groups. In the project

    management context, integration includes characteristics of unification, consolidation, articulation

    and integrative actions that are crucial to project completion, successfully meeting customer and

    stakeholder requirements and managing expectations. The project integration management

    processes include:

  • 14

    Develop project charter developing the project charter that formally authorises a project.

    Develop preliminary project scope statement developing the preliminary project scope

    statement that provides a high-level scope narrative .

    Develop project management plan documenting the actions necessary to define,

    integrate, and coordinate all subsidiary plans into a project management plan.

    Direct and manage project execution executing the work defined in the project

    management plan to achieve the projects requirements defined in the project scope

    statement.

    Monitor and control - monitoring and controlling the processes required to initiate, plan,

    execute, and close a project to meet the performance objectives defined in the project

    management plan.

    For the project to produce the desired outcomes, it should be well coordinated. The project

    integration management ensures that coordination by guaranteeing that the project is properly

    planned, executed and controlled.

    2.3.2 Project scope management

    The guide to the PMBOK (2004:338) states that project scope management includes the

    processes required to ensure that the project includes all the work required, and only the work

    required, to complete the project successfully. Project scope management is primarily concerned

    with defining and controlling what is and is not included in the project. The Project scope

    management processes include:

    Scope planning creating a project scope management plan that documents how the

    project scope will be defined, verified, and controlled, and how the work breakdown

    structure (WBS) will be created and defined.

    Scope definition developing a detailed project scope statement as the basis for future

    project decisions.

    Create a WBS subdividing the major project deliverables and project work into smaller,

    more manageable components.

    Scope verification formalising acceptance of the completed project deliverables.

    Scope control controlling changes to the project scope.

    Burke (2007:116) states that effective scope management as one of the key factors determining

    project success. Failure to accurately interpret the clients needs or problems will produce a

    misleading scope of work, therefore project management success could be limited.

  • 15

    2.3.3 Project time management

    The guide to the PMBOK (2004:338) states that project time management includes the processes

    required to accomplish timely completion of the project. The project time management processes

    include:

    Activity definition identifying the specific schedule activities that need to be performed to

    produce the various project deliverables.

    Activity sequencing identifying and documenting dependencies among activities.

    Activity resource estimating estimating the type and quantities of resources required to

    perform each schedule activity.

    Activity duration estimating estimating the number of work periods that will be needed to

    complete individual scheduled activities.

    Schedule development analysing activity sequences, durations, resource requirements,

    and schedule constraints to create the project schedule.

    Schedule control controlling changes to the project schedule.

    2.3.4 Project cost management

    The guide to the PMBOK (2004:338) states that project cost management involves estimating of

    project cost by covering cost of all resources such as human, material, equipment, plant, travelling

    expenses and other support details. These expenses are budgeted and tracked to ensure that the

    project is running within budget. The project cost management process include:

    Cost estimating developing an approximation of the costs of the resources needed to

    complete project activities.

    Cost budgeting aggregating the estimated costs of individual activities or work packages

    to establish a cost baseline.

    Cost control influencing the factors that create cost variances and controlling changes to

    the project budget.

    2.3.5 Project performance management

    The Guide to the PMBOK (2004:339) states that project performance management includes the

    processes and activities of the performing organisation that determine performance policies,

    objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.

    It implements the quality management system through policy and procedures, with continuous

    process improvement activities conducted throughout, as appropriate. The project performance

    management processes include:

    Performance planning identifying which quality standards are relevant to the project and

    determining how to satisfy them.

  • 16

    Performance assurance applying the planned, systematic quality activities to ensure that

    the project employs all processes needed to meet requirements.

    Performance control monitoring specific project results to determine whether they comply

    with relevant quality standards and identifying ways to eliminate causes of unsatisfactory

    performance

    Project performance management covers two aspects: performance assurance and performance

    control. Performance assurance is achieved through intensive planning to meet the performance

    requirements while performance control involves following certain steps to monitor results and

    check if they conform to the specified requirements. If performance management is overlooked, it

    can result in project failure.

    2.3.6 Project human resource management

    This refers to the identification of people required to execute the job, defining their roles and

    responsibilities and relationships. After identifying these people, they should be acquired and

    managed to execute the project.

    Cleland and Ireland (2004:11-17) states that project management competency is an essential

    building block for an organisations future growth and profitability. Competency depends on the

    personal characteristics of an individual, reflected in his or her knowledge, skills, and attitude,

    where knowledge consist of suitable familiarity, awareness and comprehension acquired by

    experience and study. Skill on the other hand is the ability of the individual to apply the knowledge,

    with attitude referring to the persons state of mind or feeling.

    The challenge that most companies have is that competency is expressed in so many ways within

    organisations, and different levels of positions within an organisation may apply different

    definitions.

    The following table indicates an individual competency model that can be used to determine the

    competency of a project manager and a method of promoting understanding and appreciation of

    top performers. It can also be used as a guideline to define job grades of project managers within

    organisations.

  • 17

    Table 2.1: Individual competency model

    Knowledge + Skills + Attitude = Competency

    Knowledge: Skills: Attitude:

    Familiarity, awareness, or comprehension acquired by study

    The ability to apply knowledge

    A state of mind or feeling

    Project Technology Interpersonal skills Maslows needs

    Strategic management Communication

    skills McGregors

    Theory X and Y

    Project management theory and practice

    Systems applications

    Authority & Responsibility

    Project management process Political sensitivity

    Emotional Intelligence

    Project management systems model

    Building conceptual models

    Source: Cleland and Ireland (2004:17)

    2.3.7 Project communication management

    The guide to the PMBOK (2004, 340) states that project communication management includes the

    processes required to ensure timely and appropriate generation, collection, distribution, storage,

    retrieval, and ultimate disposition of project information. The project communication management

    processes provide the critical links among people and information that are necessary for

    successful communication. Project managers can spend an inordinate amount of time

    communicating with the project team, stakeholders, customer, and sponsor. Everyone involved in

    the project should understand how communication effects the project as a whole. Project

    communication management processes include:

    Communication planning determining the information and communication needs of the

    project stakeholders.

    Information distribution making the needed information available to project stakeholders

    in a timely manner.

    Performance reporting collecting and distributing performance information, including

    status reporting, progress measurement, and forecasting.

    Manage stakeholders managing communication to satisfy the requirements, and resolve

    issues with project stakeholders.

    Any information that effects the project and the needs of the project stakeholders such as the

    project status, accomplishments and relevant events needs to be communicated. Communication

    management involves planning, executing and controlling the acquisition and broadcasting of all

    relevant information required by the stakeholders.

  • 18

    2.3.8 Project risk management

    The guide to the PMBOK (2004:340) states that Project risk management includes the processes

    concerned with conducting risk management planning, identification, analysis, responses,

    monitoring and the control of a project. The objectives of project risk management are to increase

    the probability and impact of positive events and decrease the probability and impact of events

    adverse to the project objectives. Project risk management processes include:

    Risk management planning deciding how to approach, plan, and execute the risky

    management activities for a project.

    Risk identification determining which risks might affect the project and documenting their

    characteristics.

    Quality risks analysis prioritising risks for subsequent further analysis or action by

    assessing and combining their probability of occurrence and impact.

    Quantitative risks analysis - numerically analysing the effect on overall project objectives of

    identified risks.

    Risk response planning developing options and actions to enhance opportunities and to

    reduce threats to project objectives.

    Risk monitoring and control tracking identified risks, monitoring residual risks, identifying

    new risks, executing risk response plans, and evaluating their effectiveness throughout the

    project life cycle.

    2.3.9 Project procurement management

    The guide to the PMBOK (2004:341) states that project procurement management includes the

    processes to purchase or acquire the products, services, or results needed from outside the project

    team to perform the work.

    Project procurement management includes the contract management and change control

    processes required to administer contracts or purchase orders issued by authorised project team

    members. Project procurement management also includes the administration of any contract

    issued by an outside organisation (the buyer) that is acquiring the project from the performing

    organisation (the seller) as well as administrating the contractual obligations placed on the project

    team by the contract. Procurement management processes include:

    Plan purchases and acquisitions determining what to purchase or acquire and

    determining when and how to do this.

    Plan contracting documenting products, services, and result requirements and identify

    potential sellers.

  • 19

    Request seller response obtaining information, quotations, bids, offers, or proposals, as

    appropriate.

    Select sellers reviewing offers, choosing from amongst potential sellers, and negotiating a

    written contract with a seller.

    Contract administration managing the contract and the relationship between the buyer

    and seller, reviewing and documenting how a seller is performing or has performed to

    establish the required corrective actions and provide a basis for future relationships with the

    seller, managing contract related changes and, when appropriate, managing the

    contractual relationship with the outside buyer of the project.

    Contract closure completing and settling each contract, including the resolution of any

    open items, and closing each contract.

    2.4 CRITERIA FOR PROJECT MANAGEMENT SUCCESS

    2.4.1 The concept of project success

    This research is conducted to determine the project management success criteria of capital

    projects at the Chevron Cape Town refinery, but the fundamentals of project management and

    project success criteria and success factors needs to be established first.

    Kerzner (2004:29-32) states that during the traditional period, project success was measured in

    technical terms only. This mainly occurred because the project objectives were also defined in

    technical terms only. During the renaissance period, cost and quality became equally important as

    technology. The definition of success changed to a project being finished in time, within cost and at

    the appropriate technical level or quality. The modern project management includes the need of

    the customer and not the manufacturer. With this definition one realises that acceptable

    performance is determined by the customer and not by the manufacturer.

    The definition of project success has changed over the years, as shown in figure 2.2.

    Figure 2.2: Definition of success over time

    Source : (Kerzner, 2004:29-33)

  • 20

    2.4.2 Project management success criteria

    In the past decades, project management success was usually indicated by the project completion

    within the time, cost and performance constraints (Kerzner, 2004:29). This has now evolved to an

    understanding of all the objectives of a project. Project management can still be deemed

    successful even if it did not meet all the objectives of the project and vice versa, as long as there

    are mutual trade-offs agreed upon by the developer (project manager) and the client.

    White and Fortune (2002:1-11) conducted a survey to identify common criteria used for defining

    project management success. The three criteria identified for measuring project success are

    completion on time, within budget and according to performance specification.

    However, these are not the sole principles by which success is determined - the fit between the

    project and the organisation and the coincidences of the project for the performance of the

    business were also reported as important criteria. Furthermore, the survey revealed that factors

    such as a realistic schedule, adequate funds and resources as well as clear objectives play a

    significant role in the project management success.

    On the other hand, project management success is also dependent on the abilities of a project

    manager. The attributes of a project manager that contributes to project management success of

    the project are his/her abilities to plan, solve problems, monitor, network, inform, motivate, solve

    conflicts, support , consult, develop, reward and delegate. According to Hyvaris (2006:216-225)

    study, it seems that planning/organising, networking and forming are the most significant

    managerial practices in the leadership behaviour of project managers.

    The overall findings of Hyvaris (2006:216-225) study implies that technical project management

    tools and methods are so developed and widely used that now that it is time to turn the focus on

    developing leadership skills. The most important factors in project management success are

    classified into three categories, namely project participants, communication and information

    exchange and the system development process.

    The common project management success indicators are completion to budget, satisfying the

    project schedule, adequate quality standard and meeting project objectives (Munns & Bjeirmi,

    2001:81-87). But the project manager (pm) cannot be held responsible if the objectives were

    incorrectly defined. In which case, the project will be a failure but the project management is still

    successful.

  • 21

    2.4.2.1 Indicator 1: Completion within budget

    The budget refers to the allocation of monetary resources to the project. Completion of a project

    within the estimated budget is a good indication of project management success. According to the

    Chevron Basic Project Management Manual (2009:3), cost estimation is the predicting or

    forecasting of the cost of constructing and equipping a facility to manufacture goods, or to provide

    a service. Cost estimation also provides the project manager and management with a realistic

    representation of the final project costs at any stage of project development to meet a specific

    project objective. Chevron expects that the actual project cost be within 10 percent of the

    authorised value for a project to be declared successful concerning cost management.

    2.4.2.2 Indicator 2: Satisfying the project schedule

    The schedule portion projects the desired completion date of the project, using the exact date for

    the day of completion. The purpose of the schedule is to create a systematic process for creating a

    project schedule, which is likely to be predictable and credible. This promotes effective

    management with specific, tactful decisions about the task, sequence and time for project

    completion.

    Chevron expects that the actual project cost be within 10 percent of the authorised value for a

    project to be declared successful concerning cost management.

    2.4.2.3 Indicator 3: Adequate performance standard

    This indicator captures the portion of the desired result relative to the (set) required standards of

    the quality of the completed work.

    2.4.2.4 Indicator 4: Meeting project objectives.

    The fourth indicator comprises of the first three. It describes what the project is to accomplish,

    when it is to be accomplished and how much it will take to accomplish it. To be able to use this

    indicator, the project objective statement is set to be clear, concise and quite effective. The

    objectives should clearly define major deliverables as the primary project outcomes as they will be

    used as the basis for judging the success of the project (Harvard Business School, 1997). Major

    deliverables serve as a primary tool that focuses managements attention on the key project

    outcomes.

  • 22

    2.4.3 Indicator 5: Optimising trade-offs

    The essence of effective optimisation is examining the entire project plan and developing creative

    means for making it more efficient (Harvard Business School, 1997). Any component of the

    project can be changed or adjusted as long as the changes are done in a systematic way, visible to

    all project stakeholders. Common trade-offs are eliminating some major deliverables, developing a

    different way to perform a task, changing dependencies, changing resources or accepting new

    parameters. Optimising means making tough decisions to make a project a success as well as the

    management thereof.

    There are several factors that can lead to a project management failure; these include an

    incompetent project manager, unsupportive top management, misuse of project management

    techniques, lack of commitment to the project and inadequate basis to the project. All these factors

    require careful consideration, but above all, the choice of the project manager is the most important

    of all. In line with the research goals the opposite of the factors for project management failure can

    also be stated as project management success indicators.

    2.4.4 Project success criteria

    What does project success mean? Should the same rule apply to all projects? Shenhar and Dvir

    (2007:26-27) suggest that a comprehensive assessment of project success in the short and long

    term can be defined by four basic measures:

    1. Internal project objectives (efficiency during the project)

    How successful was the project team in meeting its schedule?

    How successful was the project team in meeting its budget objectives?

    How successful was the project team in managing any other resource constraints?

    2. Benefit to customer (effectiveness in the short term)

    Did the product meet its specified requirements of functional performance and technical

    standards?

    What was the projects impact on the customer, and what did the customer gain?

    Does the customer actually use the product, and are they satisfied with it?

    Does the projects product fulfil the customers needs, and/or solve the problem?

    Has it created a larger market share?

  • 23

    3. Business and direct success (in the medium term)

    Has the new or modified product become an immediate business and/or commercial

    success - has it enhanced immediate revenue and profits?

    Has it created a larger market share?

    4. Preparation for the future

    Has the project created new opportunities for the future, has it contributed to positioning the

    organisation consistent with its vision, goals?

    Has it created a new market or new product potential, or assisted in developing a new

    technology?

    Has it contributed additional capabilities or competencies to the organisation?

    Project success criteria shape many aspects of the project, beginning with the functional and non-

    functional requirement specifications. This simply means that if the stakeholders understand the

    projects principal business objectives and success criteria, its easier to make decisions about

    which proposed product features and characteristics are in scope and which are not.

    2.5 PROJECT MANAGEMENT SUCCESS FACTORS

    One further clarification is required at this stage and that is the difference between success criteria

    and success factors. Lim and Mohamed (2000:98) dealt with this very question and cited the

    Concise English Dictionary to define a criterion as a principle or standard by which anything can

    be judged and a factor is any circumstance, fact or influence which contribute to a result.

    Collins and Baccarini (2004:20-25) differentiated between success criteria and success factors by

    stating that criteria are used to measure success and factors facilitate the achievement of

    success.

    According to Cooke-Davies (2002:54-56), project management researches have been trying to

    discover which factors lead to project success and have reached conclusions that have been

    widely reflected in literature for project management. Recent research shows that cost, schedule

    and quality (also called the iron-triangle) are still determining criteria when measuring project

    success. What has been debated for many years, is that even though the traditional iron triangle

    of cost, schedule and performance have stood the test of time, projects still do not meet their

    objectives as frequently as they should be doing.

    The success factors that Cooke-Davies (2002:54-56) draws from an extensive research are:

    1. Adequacy of company-wide education on the concepts of risk management,

  • 24

    2. Maturity of an organisations processes for assigning ownership of risks,

    3. Adequacy with which a visible register is maintained,

    4. Adequacy of an up-to-date risk management plan,

    5. Adequacy of documentation and organisational responsibilities on the project, and

    6. Keeping project below three years as far as possible.

    7. Allowing changes to scope of work only through a mature scope change control process.

    8. Maintaining the integrity of the performance measurement baseline.

    9. An effective benefits delivery and management process.

    10. Portfolio and management practices allow the enterprise to resource fully a suite of projects

    that match the corporate strategy and business objectives.

    11. A suite of project, programme and portfolio metrics that provide feedback on current

    projects and anticipated future success. A distinction needs to be drawn between the fact

    that project success can only be measured at the end of the project and project

    performance can be measured while the project is in progress.

    12. An effective means of learning from experience that combines explicit and tacit knowledge

    to the continuous improvement of project management processes and practices. In an

    organisation where the business is operationsbased, successful project management

    practices leads directly to the bottom line of the business

    White and Fortune (2002, 1-11) state that there are seven project success factors:

    1. Meeting clients requirements.

    2. Completion on schedule.

    3. Completion within budget.

    4. Meeting the organisations objectives.

    5. Yielding business benefits.

    6. Causing minimal business disruption.

    7. Meeting quality/safety standards.

    The project success factors identified above are relevant to project success but needs to make

    sure that a project has a handful factors and criteria to consider before the process becomes too

    cumbersome.

    Kerzner (2004:29-33) defined the critical success factors for a project over the period of the project

    life cycle. This can be seen in Table 2.2 below.

  • 25

    Table 2.2: Critical factors in the project management life cycle

    Project management life cycle Critical success factors

    Executive management acceptance phase Consider employee recommendations

    Recognise that change is necessary

    Understand the executive role in project management

    Line management acceptance phase Willing to place company interest before personal interest

    Willing to accept accountability

    Willing to see associates advance

    Growth phase Recognise the need for a corporate wide methodology

    Support uniform status monitoring/reporting

    Recognise the importance of effective planning

    Maturity phase Recognise that cost and schedule are inseparable

    Track actual costs

    Develop project management training

    Source: Kerzner (2004:42)

    2.6 ROLE OF THE PROJECT MANAGER TOWARDS PROJECT MANAGEMENT

    SUCCESS

    Gray and Larson (2009:7) states that the role of a manager is to decide and implement the ways

    and means to effectively and efficiently utilise human and non-human resources to reach

    predetermine objectives. Project managers in a small manner perform the same functions as

    functional managers since they are responsible and accountable for planning, scheduling,

    motivating, and controlling. Project managers are unique because they manage temporary, non-

    repetitive activities and frequently acts independently of the formal organisation.

    Although competency of the project manager cannot be considered as a success indicator, in

    reality the success of any project depends on the project manager. The primary responsibility of

    the project manager is to ensure that all work is completed on time, within budget and scope and at

    the correct performance levels, but this can only be done through functional knowledge which the

    project manager typically doesnt have. To achieve all the set project objectives, project managers

    must understand the mission and vision of the organisation first, then they must see how the

    project they are managing meshes with the organisations mission, and they must steer the project

    to ensure that the interests of the organisation are met.

  • 26

    To perform this big task, a project manager has to be flexible enough to wear a lot of different hats,

    many at the same time, which include the hats of an integrator, communicator, decision maker,

    motivator, evangelist, entrepreneur and change agent (Nicholas, 2004:30-40).

    This means that the project manager has to be able to integrate everything and everyone to

    achieve the project goals.

    Nicholas (2004:30-40) listed the usual responsibilities of the project manager as the following:

    Planning project activities, tasks, and end results, including doing the work breakdown,

    scheduling, budgeting, coordinating tasks, and allocating resources.

    Selecting and organising the project team.

    Interfacing with stakeholders:

    Negotiating with and integrating functional managers, contractors, consultants, users,

    and top management.

    Providing contact with the user.

    Effectively using project team and user personnel.

    Monitoring project status.

    Identifying technical and functional problems.

    Solving problems directly or knowing where to find help.

    Dealing with crises and resolving conflicts.

    Recommending termination or redirection of efforts when objectives cannot be achieved.

    In most projects, the role of the project manager is not well defined as the project managers find

    themselve