project management - topics 1.warm up: which factors determine the price for an it-project? 2.ivk...
TRANSCRIPT
Project Management - topics
1. Warm Up: Which factors determine the price for an IT-project?
2. IVK – chapter 6 ‘Project Management’ discussion points
1. ‘Waterfall’ versus ‘Agile’ approach to IT application project management
2. Managing uncertainties in estimates
3. Managing problems/risks
3. IVK – chapter 7 ‘Runaway Project’ discussion points
1. Why is the IR project in difficulties?
2. What should Barton do to get the project back on track?
4. The CISCO case – discussion point
1. How do you evaluate the decisions they make?
Warm Up - a hypothetical situation
• The CIO of a Danish insurance company has hired you as an
external project manager.
• She says: “I want you to be project manager for our project ‘New
Customer System’. I urgently need a fixed price and a plan.”
• What do you need to know and why?”
• The CIO is not known for her patience and you should only
request the most important information.
Warm Up - a hypothetical situation (my own 3 minute list)
• Is the project important for the CEO? (on top 5 on the to-do list)?
• Can I get the best team?
• What is the stakeholder complexity / organizational maturity?
• What is number of interfaces to other systems?
• What is the data quality of current customer data?
• What is the functional scope?
• Any preferences regarding software vendor / technology?
IVK – ‘Project Management’ discussion points
1. ‘Waterfall’ versus ‘Agile’ approach to IT application project management.
• Pro et contra
2. Managing uncertainties in estimates / budgeting for uncertainties
• Is it a good solution to ‘overestimate’ based on estimate uncertainty?
• Is it a good solution to operate with 2 plans: An internal and an external?
3. Managing problems/risks
• How do you as a PM ensure you get ‘early warnings’ regarding problems/risks?
IVK – ‘Runaway project’ discussion points
1. Why is it ‘Infrastructure Replacement’ project in difficulties?
• Are they actually doing anything right?
2. What should Barton do to get the project back on track?
• Should he fire the system integrator?
• What else should he do?
‘CISCO case’ discussion points
1. How do you evaluate the following decisions.
• To let each division decide systems for them selves – based on common architecture.
• CISCO’s accept of doing nothing until the big break down
• The approach: Standard package, big bang, few customizations
• Fast RFP-process: 10 days to prepare – 2 weeks to respond
• Decide for duration before scope
• Budget based on ‘value’ not ‘cost’
• The Conference Room Pilot approach with CRP0 – CRP4
• Reverse decision regarding ‘few customizations’ – including selecting a package
• Deselect historic data as part of the solution
• Go live with so many problems that the first months are very painful for the business