project management unit evncpc - world bank...substation, report on environmental management plan...

83
EVNCPC NPMU EVN POWER CORPORATION CENTRAL POWER NETWORK PROJECT MANAGEMENT UNIT Add: 4 floor - 78A Duy Tan, Da Nang city Tel: 0511.2211330; Fax: 0511.3633886 RURAL DISTRIBUTION PROJECT (RD) PROJECT EA KAR-KRONG PAK 110KV LINE AND SUBSTATION IN DAKLAK PROVINCE REPORT ON ENVIRONMENTAL MANAGEMENT PLAN (EMP) Da Nang, April 2012 L .. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 21-Oct-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

  • ~ EVNCPC

    NPMU

    EVN POWER CORPORATION

    CENTRAL POWER NETWORK PROJECT MANAGEMENT UNIT

    Add: 4 floor - 78A Duy Tan, Da Nang city Tel: 0511.2211330; Fax: 0511.3633886

    RURAL DISTRIBUTION PROJECT (RD)

    PROJECT

    EA KAR-KRONG PAK 110KV LINE AND SUBSTATION IN DAKLAK PROVINCE

    REPORT ON ENVIRONMENTAL MANAGEMENT PLAN

    (EMP)

    Da Nang, April 2012

    L

    .. --------------~------.

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    wb350881Typewritten TextE1712 v69

  • ffi EVNCPC

    NPMU

    CENTRAL POWER CORPORATION

    CENTRAL POWER NETWORK PROJECT MANAGEMENT UNIT

    Add: 4 floor - 78A Duy Tan, Da Nang city Tel: 0511.2211330; Fax: 0511.3633886

    RURAL DISTRIBUTION PROJECT (RD)

    SUB - PROJECT

    EA KAR .. KRONG PAK 110KV LINE AND SUBSTATION IN DAK LAK PROVINCE

    REPORT ON ENVIRONMENTAL MANAGEMENT PLAN

    (EMP)

    / Maker by: Nguyen Trllng Tlzanlt'1)/~

    ~l Review by: Le Huy Cuong ~.

    Da Nang, April 2012

  • Sub-project: Ea Kar Krong pak 110 k V substation and branch lin

    (m2)

    TABLE OF CONTENT

    (Subproject Ea Kar-Krong Pak 11 OKV substation and Branch line is referred as project)

    ABBREVIATION EXPLAINA TIONS

    PART I: GENERAL INTRODUCTION

    1.1. Project's name

    1.2. Project's location

    1.3. Project's objectives

    104. Project's management organization

    PART II: PROJECT DESCRIPTION

    11.1. Project's location

    n.2. Project's scope

    Table 2, 1. Localities of project implementation

    Table 2.2. Description of line route

    II.3. Volume of project's main works

    Table 2.2. Volume ofproject's main works

    IIA. Fuel, machinery and tools for construction

    II.S. Activities prior and during construction stage, means for transportation of materials, equipment and machinery to project site

    II.6. Project's schedule

    II.7. Total investment capital of project

    PART III: SUMMARY OF CURRENT SITUATION OF SOCIAL - ECONOMIC AND ENVIRONMENT IN THE PROJECT AREA.

    III. I. Geographical location

    IIL2. Climate, topography and peadology

    IIL3. Natural resources

    lIlA. Population, culture, society

    III.S. Traffic system

    III.6. Natural and social-economic conditions of Ea Kar and Krong Pak

    PART IV: LEGAL FRAMEWORK

    IV.l. Vietnamese laws and regulations

    IV.2. World Bank's policies

    P ART V: GENEARAL AND ENVIRONMENTAL IMPACT SCREENING

    V.I. Overview of proj ect' s environmental impact

    - Table 5.1: Area of acquired land (temporary and permanent)

    Table 5.1.1: Area of permanently acquired land for electrical wire system

    Report on Environmental Management Plan Page 1

  • ...

    Sub-project: Ea Kar Krong pak 110 kV substation and branch lin

    Table 5.1.2: Area of temporarily acquired landfor electrical wire system. (m2)

    - Table 5.2: Number of affected household

    - Table 5.3:Communes with affected Ethnic minorities

    - Table 5.4: Number of affected vegetables and plants

    V.2. Identify the potential impact caused by the project

    - Table 5.5.·Assessment of potential impact caused by the project

    V.3. Assessment of project's impact on natural, cultural and historical conservation sites

    PART VI: PUBLIC PARTICIPATION AND CONSULTATION AND INFORMATION DISCLOSURE

    VI.l. Procedure and contents of public participation and consultation and information disclosure

    VI.2. Summary of public participation and consultation's results

    • Table 6.1: Summary of public participation and consultation

    PART VII: ENVIRONMENTAL MANAGEMENT PLAN

    VII. I. Measures to mitigate the project's negative impact

    - Table 7.1: Measures to mitigate the project's negative impact on environment

    VII.2. EMP implementation responsibilities of each party

    - Table 7.2: EMP implementation responsibilities of each party

    VII.3. EMP implementation supervision

    - Table 7.3: Supervision plan for implementation of mitigation measures ofproject's environmental impact

    - Table 7.4: Parties in duty of supervision ofEMP

    VII.4. EMP implementation reporting system

    - Table 7.5: Some reporting requests on supervision of EMP

    VII.S. Capacity building for EMP implementation

    - Table 7.6: Cost estimate for training courses on implementation of EMP.

    VII.6. Estimate cost for implementation ofEMP

    - Table 7. 7: Estimate cost for implementation of EMP

    VII.7. Urgent cases and solutions

    • Table 7.8: Urgent cases and solutions

    PART VIII: ANNEXES

    Annex 1: Sample report on monitoring of EMP implementation (applied for reports ofPMU and SIMC monitors)

    Annex 2: Sample report on monitoring of EMP implementation (applied for Contractors' reports)

    Report on Environmental Management Plan Page 2

  • Sub-project: Ea Kar Krong pak 110 kV substation and branch lin

    Annex 3: Sample for getting information (applied for communes' representatives)

    Annex 4: Map of the project area

    Annex 5: Project's environmental certificate (Registration for protecting Environment of the project) and Public participation and consultation minutes

    Annex 6: List of members making the EMP

    Report on Environmental Management Plan Page 3

  • Sub-project: Ea Kar Krong pak 110 k V substation and branch lin

    ABBREVIATION EXPLAINATIONS

    Abbreviation Full descriptions

    EMP Environmental Management Plan

    EVN Vietnam Electricity

    CPC Central Power Corporation

    Km Kilometre

    kVA Kilovolt ampere

    MVA Megavolt ampere

    PAHs Project affected households

    PPs Project affected persons

    NPMU Central power network project management unit

    sis Substation

    TL Transmission line (branch line)

    ROW Right of Way

    SEMP Site environmental management plan

    SIMC Safeguard Independent Monitoring Consultant

    WB World Bank

    . .

    Report on Environmental Management Plan Page 4

  • . ".

    Sub-project: Ea Kar /(rong pak 110 kV substation and branch lin

    PART I GENERAL INTRODUCTION

    1.1. Project's name:

    Project's name: Subproject "Ea Kar - Krong Pak llOKV substation and branch line" included in Rural distribution project -WB additional financing.

    1.2. Project's location:

    - Location: Krong Pak llOkV sIs on the area of Phuoc An town, Krong Pak district, DakLak province

    1.3. Project's objectives:

    Investment in construction of Ea Kar-Krong Pak 110KV substation and branch line to:

    - Ensure power supply for Krong Pak industrial zone, contributing in developing local economy.

    - Enlarge the market and increase the capacity of supplied electricity for customers;

    -Improve the safety in power supply -Improve the safety in power supply due to the reduction of failure frequency.

    1.4. Project's management organizations:

    - Investor: Central Power Corporation.

    - Designer and consultant: Central Power Engineering Consultant Company -(CPECC) - CPC

    - Project management Unit: Central Power network project management unit - CPC

    Report on Environmental Management Plan Page 5

  • ..

    .. ..

    Sub-project: Ea Kar Krong pak J J 0 k V substation and branch lin

    11.1. Project's location:

    PART II

    PROJECT DESCRIPTION

    Ea Kar-Krong Pak 1l0KV line runs through 2 districts: EaKar and Krong Pak, the line route is built in Ea Dar commune, Ea kar town, Cu Hue commune, Ea kar district; the Krong buk, Ea Phe and Hoa An, Phuoc An town, Krong Pak district, DakLak province.

    Starting point: Connecting from the busbar ofEa Kar 110kV substation

    Ending point: Busbar of Krong Pak 110kV substation

    The terrain that the line goes through is complex, large changes in elevation, main type of terrain is hills and mountains, main geophysics is hill land farming industrial plants like coffee, cashew nuts, and route that goes through residential area and town cut through gardening land of plentiful of perennials and fruits.

    The route almost goes along hills, avoiding residential area, sometimes there are parts cut through area with sparse households, some fields and huts. Route that goes along Highway 26 is 0.5km till 5km away from the road. On the route there are inter-communal roads, production roads, vv .. , transportation of materials for constructions could be relatively smooth.

    Table 2.1. Scope and location of the project

    Location Length of Names of route, width communes

    1. Number of of ROW that route goes sis: 01 through

    (according to districts)

    Phuoc Length - Ea Dar An town, 27.623m commune,Ea Krong Width 15m

    Kar town, Cu Pak Hue commune district, (Ea Kar Dak Lak district). province - Krong Buk

    commune, Ea Phe, commune, Hoa An commune, Phu6c An town (Krong Pak district).

    2. Land area Area of used for permanently building acquired land: substation,

    Report on Environmental Management Plan Page 6

  • Sub-project: Ea Kar Krong pak 110 k V substation and branch lin

    line route and current status of land use at the sis, in ROW

    3. Are there any substation or ROW In radius of 3km to natural conservation site or natural forest?

    4. Are there any substation or ROW In radius of 300m to historical relics, pagodas or other cultural works?

    5. Are there any substation or ROW in radius of 300m to commune centre (People's Committee, schools, markets, hospitals) or In radius of 2km to residential area?

    6. List of environmental

    Report on Environmental Management Plan

    17.103m'

    Area of temporarily acquired land: 402.840m2

    Land used for ROW is agriculture and irrigation land

    No x

    If yes, fill In (6)

    Yes, __ _

    If yes, fill In (6)

    Yes x --

    If yes, fill In (6)

    Page 7

  • Sub-project: Ea Kar Krong pak 110 kV substation and branch lin

    ly sensitive subjects has been reported from (3) to (5)

    Name of Summarizing Distance to

    slsllocation nature and slslline

    Sequence of line name of

    route sensitive subject

    From Route on

    1 starting Residential garden land

    point to G2 with many households

    From G4 to Route on

    2 Piket Residential garden land

    (20+21) with many households

    Table 2.2. Description of line route

    Sequence Districts Length (m)

    Descripton of line route

    I

    1

    2

    3

    EaKar district

    Ea Dar

    EaKar town

    CuHue commune

    10.185

    906

    From the fence of Ea Kar 110kVs/s (expanded) to Piket (09+06): From starting point of line route in the residential area, the elevation changes insignificantly, the elevation of line route running through the residential area between the road surface and garden land is quite small. Main product is coffee, there are also fruit trees and vegetables. From the starting point to G2, the line route runs along garden land with households.

    From Piket (09+06) to Piket (39+36) i.e. 09: The elevation changes insignificantly, the elevation of line route running through the residential area between the

    3.030 road surface and natural land is quite small. Main product is coffee, there are also fruit trees, wind-resisting trees and vegetables. From G4 to Piket (20:24), the line route runs along garden land with households.

    From Piket (39+36) i.e. G9 to Piket (101+85): The terrain where the route runs along is not stable. There are

    6.249 many water ponds, products are various including water rice, vegetables and coffee, cashew nut of more than 4m high is planted scatterly in coffee field.

    Report on Environmental Management Plan Page 8

  • Sub-project: Ea Kar Krong pak 110 kV substation and branch lin

    II

    4

    5

    6

    7

    Krong Pak district

    KrongBUk commune

    EaPhe commune

    HoaAn commune

    PhuacAn town

    TOTAL

    17.438

    5.858

    5.849

    3.915

    1.816

    27.623

    From Piket (101+85) to Piket (160+43): The terrain where the route runs along is quite complicated, with changing elevation, there are many water ponds, channels, main product is coffee, mixed with fruit tree, cashew nut, wind-resisting trees, there are scatterly vegetable and rice field.

    From Piket (160+43) to Piket (218+92) i.e. 025: The terrain where the route runs along is quite complicated, with changing elevation, there are many water ponds, channels, springs main product is coffee, mixed with fruit tree, cashew nut, wind-resisting trees, there are scatterly vegetable and rice field ..

    From Piket (218+92) i.e. 025 to Piket (258+07): The terrain where the route runs along is quite complicated, with changing elevation, there are many water ponds, springs, main product is coffee, mixed with fruit tree, wind-resisting trees, there are scatterly vegetable and rice field ..

    From Piket (258+07) to ending point (Krong Pdk 110kV sis fence): The terrain where the route runs along is quite complicated, with changing elevation, there are many water ponds, main product is coffee, mixed with fruit tree, wind-resisting trees, there are scatterly vegetable and rice field.

    b. Krong Pak llOkV substation:

    Krong Pak 11 Ok V sis locates on the area of Phuac An town, Krong Pak district, Dak Ulk province. (The substation is on the planned area for new residential area, at present, the whole area planned to build the sis is coffee farming land).

    - East: facing residential area + planning road.

    - West: facing Ngo Quyen street (soil road).

    - South: facing residential area + planning road.

    - North: facing residential area + planning road.

    The sis is about 1,Okm away Highway 26. The terrain is quite plain, convenient for connecting out-going and in-coming 1l0kV feeders and out-going 22kV feeders. Due to the fact that the sis is close to the planned road, it is convenient for transporting equipment and operation of the sis later.

    11.2. Scope of the project:

    Report on Environmental Management Plan Page 9

  • Sub-project: Ea Kar Krongpak 110 kV substation and branch lin

    aI Krong Pak 110kV substation:

    - Voltage level 110/22k V.

    - Expected capacity: 2x40MVA, at first, install 1 transformer of lx40MV A.

    - Foundation: At-site reinforced concrete foundation, including: transformer foundation, cable trenches, control house, shift dorm, substation gate, substation fence, etc.

    - Earthing system: Complex radius-pile poles of zinc-plated steel

    - Control and protection system: Using the computerized system.

    , - Communications system: Using optical communications system.

    - Planned area of substation: 5,516 m2 including outdoor distribution system, shift dorm, control house, yard, substation gate and substation fence, etc.

    b/llOkV bay connecting at EaKar llOkV substation:

    - Installing 01 1l0kV bay at EaKar 1l0kV sis.

    - Installing 01 control and protection cubicle for 110kV feeder.

    - Installing 01 communications panel.

    - Installing SCADA system for 110kV bay.

    c/ 110 k V branch line:

    - Connecting from Krong Pak 110kV bay to the EaKar 110kV sis

    - Voltage level: 110 kV

    - Number of circuits: 01 and 02; - From the busbar of EaKar 110kV sis to G29: 01 circuit; - from G29 to the Krong Pak 110kV busbar: 02 circuits (at first, only hanging 01 circuit).

    - Starting point: busbar of Eakar 110kV sis

    - Ending point: busbar of Krong-pak 110kV sis

    - Length of 110KV branch line: 27.623 km

    - Conductor: ACSR-185/29

    - Lightning wire: Using lightning protection WIre and optical cable of GW-50; OPGW-57

    - Insulator: glass, porcelain or polymere

    -Tower: hot dip zinc-galvanized shaped steel tower, 1 circuit and double circuit.

    - Foundation: At site mounded concrete.

    - Earthing system: Pile and radius mixed

    11.3. Volume of the project main work

    Table 2.3. Volume ojproject's main works

    Report on Environmental Management Plan Page 10

  • Sub-project: Ea Kar Krong pak 110 kV substation and branch lin

    No Items of work Unit Volume Construction

    methodologies

    I Branch line

    01 Soil excavation m3 20497.66 Manually and mechanically

    02 Soil excavation at tower foundations

    m3 21551.01 Manually and

    and leveling mechanically

    03 Concrete MI00 m3 218.43 Manually and mechanically

    04 Concrete M200 m3 1081.24 Manually and mechanically

    05 Erecting steel towers Tower 108 Manually and mechanically

    ~ Stretching conductors ACSR 185129 m 84968 Manually and mechanically

    07 Stretching OPGW57 m 28979 Manually and mechanically

    08 Earthing installation Location 108 Manually

    09 Installation of 11 Ok V insulator and

    String 566 Manually and

    accessories mechanically

    10 Zinc-galvanized steel of various types Ton 538.40 Manually and mechanically

    n Substation

    01 Level the surface of the substation m3 6954

    Manually and foundation mechanically

    02 Soil excavation m3 2964.91 Manually and mechanically

    ~ Fill the soil into the foundation m3 2304.7 Manually and mechanically

    Inner-substation road of 4m wide m2 900 Manually and mechanically

    05 Access road to the sIs of 4m wide m2 183 Manually and mechanically

    Report on Environmental Management Plan Page 11

  • Sub-project: Ea Kar Krong pak 110 k V substation and branch lin

    06 Access road to shift dorm of 3 m wide m2 72 Manually and mechanically

    07 Substation gate and substation fence m 225 Manually and mechanically

    08 Control and distribution house

    m3 1 Manually and

    (412m2) mechanically

    09 Shift dorm (248m2) m3 1 Manually and mechanically

    10 Power transformer Pcs 1 Manually and mechanically

    11 Auxiliary transformer Pcs 1 Manually and mechanically

    12 110k V disconnector Set 6 Manually and mechanically

    13 110kV circuit breaker pcs 02 Manually and mechanically

    14 123kV capacitor voltage transformer pcs 06 Manually and mechanically

    15 123kV current transformer pcs 06 Manually and mechanically

    16 96kV surge arrester set 03 Manually and mechanically

    17 21 k V surge arrester Set 03 Manually and mechanically

    18 22k V complete panels Panel 09 Manually and mechanically

    19 Control, protection, measurement Panel 08

    Manually and panel mechanically

    20 Battery and charger set 3

    21 Earthing Pcs 2135 Manually

    22 Telecom system and mini-SCADA System 1

    Manually and system mechanically

    III Fire fighting equipment and tools

    Report on Environmental Management Plan Page 12

  • Sub-project: Ea Kar Krong pak 110 kV substation and branch lin

    01 SKg C02 extinguisher pcs 10

    02 30Kg C02 extinguisher with hoI pcs 02

    03 SKg fire extinguisher pcs OS

    04 Shovel pcs 05

    OS Fire fighting ladder pcs 03

    06 12 litre bucket (tole with steel coat) pcs 04

    07 Fire-fighting orders and regulations set 02

    08 Fire-fighting tool holders Pcs 02

    09 3m3 fire fighting tank pcs 02

    10 2001 tank or sand container Pcs 06

    11 Long-handled sickle Pcs 04

    i 12 Sand m3 04

    13 Diagram of fire-fighting system Pcs 01

    11.4. Main fuel, machinery, tools for construction, and maximum number of workers at every construction site

    • Main resources for construction are: electricity and water.

    + Electricity : is supplied from diesel generators and surrounding loads (if any).

    + Water : is supplied from drill well using for the project in the substation area

    • Main machinery and tools used for the project are: 5 10 tons trucks, crane-trucks, bulldozers, excavators, concrete-mixers, diesel generators, arc welders, metal cutters, conductor spreaders, water pumps, shovels, mattocks, hammers, etc.

    Maximum number of workers at every construction site is 30 people

    11.5. Activities prior and during construction stage - Means for transportation of materials, equipment and machinery to the site:

    a/ Main works of the project prior and during construction stage:

    - Carry out compensation, site clearance.

    - Take over the construction site, set up temporary camps

    - Transport materials, equipment and human resources to the site

    - Level the surface, build access road.

    - Build substation and control house, dig foundation pits, set up towers, install transformer and power line.

    - Build substation gate and fence, etc

    Report on Environmental Management Plan Page 13

  • Sub-project: Ea Kar Krong pak 110 k V substation and branch lin

    bl Means for transportation of materials, equipment and machinery to the site:

    - Materials and equipment will be transported from freight yards and storehouses of investors to temporary storehouses of the project by specific trucks suitable with packaged format. After that, they will be transported to project's site by trucks with load capacity of 5 -7.5 tons. Roads that are used to transport materials to substation site and some tower locations are IA National highway, township roads and inter-village roads. The road must be ensured for transporting materials and equipment. The load capacity of the trucks has to be suitable with traffic load in the area. After temporarily loaded near the roads, materials and equipment will be manually carried to construction site. Because the site is near the roads, the manually carried distance is inconsiderable.

    - Building materials such as: sand, stone, cement will be supplied by local suppliers in the radius of 10 - 30 kIn.

    11.6. Project's schedule:

    The project's schedule is expected to be as follows:

    - Making investment project: June 2011.

    - Making the project technical design document: June 20 11.

    - Choosing suppliers of materials and equipment: September 20 11

    - Launch the project construction: January 2012.

    - Completion: December 2012.

    11.7. Total investment capital ofthe project:

    According to the decision on investment and construction of the project No.2826/QD-EVNCPC dated 5 July 2011, the total investment cost for the project is as follows:

    No Capital structure Investment capital (VND)

    1 Cost for construction 73 596 000 000

    2 I Cost for equipment 34802 000 000

    3 Cost for compensation and site clearance 4745 000 000

    4 Cost for the project management 1926000000

    5 Cost for consultants of investment and construction 7824000000

    6 Other costs 8842000 000

    7 Contingency 13 180 000 000

    Total 144,915,000,000

    Report on Environmental Management Plan Page 14

  • Sub-project: Ea Kar /(rong pak J J 0 kV substation and branch lin

    PART III:

    SUMMARY OF CURRENT SITUATION

    OF SOCIAL - ECONOMIC AND ENVIRONMENT IN THE PROJECT AREA

    111.1. Geographical area:

    Dak Lak province is located in the center of high land area in the longitude from 107°28'57" - 108°59'37"E and from 12°9'45" - 13°25'06" N. It is adjacent to Gia Lai to the North, to Lam Dong province to the South, to Phu Yen and Khanh Hoa province to the East and to Cambodia and Dak Nong province to the West.

    Natural area: 13,125 km2, population: 1.8 million persons including 44 ethnic groups.

    Administrative units: Buon Ma ThuQt city, Buon H6 town and districts: Ea HIeo, Easup, Krong Nang, Krong Buk, Buon Don, Cu'Mgar, Eakar, M'Ddic, Krong Pak, Krong Ana, Krong Bong, LLlk, Cu Kuin.

    111.2. Climate, topography and peadology:

    alClimate:

    Tropical highland monsoon. The average temperature is from 22.5°C, The average rainfall is from 1,956mmlyear. There are two seperate seasons. The rainy season is from May to Octorber, they dry season is from November to April of the following year. Average humidity is about 80%.

    bl Topography:

    Having the border of 70 km long with Cambodia, on which Highway 14C runs along both countries' border which is beneficial for developing border area's economy, combined with national security.

    DakLak has the biggest natural are of the whole country. High mountain area from 1000-1200m covers 35% the district's area. Highland Buon Ma Thuot is 450m high, cover 53.5% rich red land, plain and convenient for developing long-term industrial trees, raising castle and planting forests. Silt (12%) is for rice field and natural grass field. DakLak forest has a large amount of wood and many rare animals like elephants, tigers, leopards, bears, dears, roars, bulls, ...

    D~k LLlk has the main river system: Ba, Serepok rivers(branches Krong Bong, Krong Pak, Krong Ana, Krong No ... ) and some other small branches. Many high waterfall has great potential for hydropower such as Dray HLinh, Buon Ku5p. Many big lakes like LLlk, Ea Kao, Ea Sup, Dakmin ... supply farming water and aqua-products for the whole province.

    Most of the province's area is at the West of Truang Son, lower from South-East to North-West. Various terrain of mountain and hills mixed with valleys and plains.

    cI Peadology:

    The geologic system here is mainly basalt, suitable for developing long-term trees such as coffee, rubber, cashew nut, pepper and fruit trees.

    111.3. Natural resources:

    * Soil resources: The total natural land area is 13.125 km2, among which is the grayish group, red basalt and other soil groups. Soil formed from basalt has high richness (pHlH20 from neutral to sour, protein and phosphorus). Natural richness and actual richness ofthe soil groups and types are highly identical, distributed over Buon Ma Thuot high land of 90km to the direction of North-East and South-West, about 70km wide. The north of this highland is

    Report on Environmental Management Plan Page 15

  • Sub-project: Ea Kar Krong pak J J 0 kV substation and branch lin

    nearly 800m high, the south of 400m, to the west 300m, the surface of the high land is quite smooth, there are hill and mountains in few places.

    + Fuvisols:

    Formed and distributed along rivers and streams in the province. The property of this type of soil depends on the weathering products in the samples.

    + Gleysols:

    Distributed in the low area of the districts: Lak, Krong Ana and Krong bong.

    + Acrisols:

    Is the biggest group in Dak Lak, distributed in most of the districts.

    + Ferrasols, mainly basalt Is the second biggest area (after the acrisols), covering 55.6% of the basalt area of the

    whole Highland. Basalt has good mechanical and physical property, balls structure, average softness is 62-65%. High ability of saving water and absorbing nutrition ... Suitable for industrial trees with high value in term of economics like coffee, rubber, tea, pepper, etc ... and many fruit trees and other short-term industrial trees ... This is a very important advantages ofDakLak on developing agriculture.

    * Water resources: Hundreds of reservoirs and 833 streams of more than lOkm long create a dense river system for Dak Lak. Therefore, many places in the province are able to exploit the surface water, facilitating the production and living, especially the places along the Krong Ana river. Besides, the underground water gathers mainly in the basalt structure and the forth age sediments, in two forms: hole water and crack water.

    * Forest: The forest area of the province is 608,886,2 ha, in which natural forest is 594,488.9ha, planted forest is 14,397.3ha. The coverage of forest is 46.62% (2004). Dak Lak forest has a lot of rare animals, many distributed at National Park Yook Don and Nam Kar, Chu Yangsin reserves, etc. There are many rare animals in the Red Book of Vietnam and the World.

    * Mineral resources: Dak Lak has a variety of mineral resources. There are many mineml mines with different capacity and many valuable minerals such as: kaolin clay, brick clay, gold, lead, phosphor, peat coals, gems, devitrified stones, building stones and sand, etc in the province.

    111.4. Population, culture and society:

    - Population: As at 1 April 2009, the population of the province was 1,728,380 people with the density of 132 people/km2•

    - There are 44 peoples, in which Ede and M'nong are main local peoples.

    - Culture, society:

    Dak Lak is one of the origins of Gong culture of highland, being recognized by UNESCO as orally transmitted and non-physical masterpiece of the mankind.

    Noticeable when visiting Dak Lak are tmditionallong houses according to myths that can be "long as the sound of Chi eng" or the water places of the people here, a typical piece of culture of the area and the tourists will be impressed of the local made furniture like tables, chairs and even one-piece boats.

    Report on Environmental Management Plan Page 16

  • Sub-project: Ea Kar Krong pak J J 0 k V substation and branch lin

    There are festivals: elephant racing, Gong and Chieng, Coffee approved by the Government and occurred annually as a tradition.

    111.5. Traffic system:

    The province has many important traffic nodes that connect provinces in highlands and to the coastal provinces. From Buon Ma Thuot city, Highway 14 connected with Danang city through Gia Lai, Kon Tum and is 300km away from Ho Chi Minh city, Highway 26 connected with Khanh Hoa and is 200km away from Nha Trang city; Highway 27 connected with Lam Dong and is 183km away from Da Lat city; Highway 14C running along the border with Cambodia.

    111.6 Natural and Socio-economic situation of Ea Kar and Krong Pak districts.

    a. Ea Kar district:

    Ea Kar is a district of Dak Lak, its main area is Ea Kar town, 50km away from Buon Ma Thuot city, founded in December 1985. Natural area: 103.743 ha, with the total population of 143,453 people including 19 peoples. There are 58 units of Communist Party, 3,691 members, 16 administrative units (14 communes and 2 towns), 227 villages, residential groups. 4 religions: Catholicism, Buddism, Protestantism, Taodai, with 13.890 followers. Economic structure ofthe district: Agriculture, Forestry, industry, commerce and tourism. In which, agricultural production is the main activity. Living standard of part of people is still poor, low intellectual standard, obsolete customs, especially in the areas of ethnic groups and the remote areas. The poor households over the whole district is 21.39%.

    * Administrative system: There are 16 dependent units: Town: Ea Kar, Ea K N6p. Communes: Cll Hu, Ea Tih, Cll Yang, Cll Bong, Ea Dar, Cll Elang, Ea Sar, Ea So,

    Xuan Phu, Ea Pal, Cll Ni, Ea 6, Ea Kmut, Cll Prong. * Natural resource: In the province, Ea Kar is not potential on land or industrial trees.

    However, it is strong at processing industry. Noticeable here is the natural park Ea So of 27,000 ha and this is the only place

    where gray bulls still exist. * Economics: Ea kar industrial groups were formed in 2005. Up to now, there are

    many foreign investors coming.

    bl Huy~n Krong Pak:

    Krong Ptlk is a district of Dtlk Ltlk province. The centre of the district is Phuoc An town. It faces Buon Ma ThuQt in the West, Mgar to the North-West, Buon H6 to the North, EaKar to the East and Krong Bong to the South-East. This is a district which is strongly developing with 5 high schools and one Vocational training Center, one medical centre being updated with modem equipments. Ath the moment, the district is building an industrial zone to the South-East ofPhuoc An town

    *Peoples: Kinh, Ede, Tay, Nung, M'nong, Van ki~u ....... In which the Kinh people are of about 65%

    * Economy: The district has one advantage is that the area of basalt to develop coffee trees. This is one of the first places imported coffee trees with Ca Da plantation

    KrongPak district is now developing. Expanded traffic, before roads were basalt roads, now they are 90% bitumen

    * Administrative: Krong Ptlk district including Ph1l6c An town and 15 communes: Ea Hiu, Ea Kenh, Ea ~ly, Ea Knuec, Ea K~g, Ea rhe, Ea Uy, Ea Yieng, Ea Yong, Hoa An, Hoa Dong, Hoa Tien, Krong Buk, Tan Tien, Vl) Bon

    Report on Environmental Management Plan Page 17

  • Sub-project: Ea Kar Krong pak J J 0 k V substation and branch lin

    * Education: Krong Pak has a strongly developed education with 23 kindergarten, 51 primary schools, 24 secondary schools, 5 high schools and 1 Vocational training Center.

    * Tourism: Potential in tourism of the district has not yet been paid enough attention.

    Report on Environmental Management Plan Page 18

  • Sub-project: Ea Kar Krong pak 110 kV substation and branch lin

    PART IV: LEGAL FRAMEWORK

    IV.1. Vietnamese laws and regulations:

    - The Environment Law of The Socialist Republic of Vietnam issued at decision No. 52/2005/QHl1 issued on November 29th, 2005 and came into effect on July 1 sl , 2006.

    - Decree No. 80/2006/ND-CP dated August 9th, 2006 of Vietnamese Government on detail regulations and guidance on the implementation of some Articles of the Environment Law.

    - Decree No. 2112008/ND-CP dated February 28th, 2008 of Vietnamese Government on adjustment, supplement some items of the Decree No. 80/2006/ND-CP.

    - Decree No. 8112006/ND-CP dated August 9th, 2006 of Vietnamese Government on administrative fine in environmental violation.

    - Decree No. 29/2011/ND-CP dated April 18th, 2011 of Vietnamese Government on strategic environment assessment, environmental impact assessment and environmental protection commitment.

    - Circular No. 26/20111 BTNMT dated July 18th, 2011 of Ministry of Natural Resources and Environment guiding in details some articles of the Decree No. 29/20111ND-CP dated April 18th, 2011 of Vietnamese Government on strategic environment assessment, environmental impact assessment and environmental protection commitment.

    - Decree No. 106120051ND-CP dated August lih, 2005 and Decree No. 8112009/ND-CP dated October li\ 2009 of Vietnamese Government guiding the implementation of some Articles of The Power Law on safety for high voltage power network.

    - Decree No. 24/20001ND-CP of Vietnamese Government guiding the implementation of The Foreign Investment Law in Vietnam (Article 82 related to environment safeguard)

    - Implementation of safety measures for construction workers and local residents during construction: TCVN3985-1999, TCVN5308-1991, TCVN4086-1985, TCVN3254-1989, TCVN3256-1986, TCVN3146-1986, TCVN4245-1985, TCVN2293-1978, TCVN2292-1978, TCVN3147-1990, QPVN2-1975, TCVN4244-1986, QCVN:2008/BCT.

    - Performing solutions to gather and process waste water (living, construction), protect quality of water environment and life of aqua-products: QCVN 08:2008/BTNMT; QCVN 09:2008/BTNMT, QCVN 14:2008IBTNMT.

    - Performing solutions to mitigate the environmental pollutions as stipulated and closely supervising the gas emission, dust during construction of the project in order to mitigate to the minimum the impacts, meeting the norms QCVN 05:2009IBTNMT; QCVN 06:2009IBTNMT; QCVN 19:2009/BTNMT.

    - The national norms about environment: QCVN 26:2010/BTNMT - national norms about noises; QCVN 27:20101BTNMT - National norms about vibrations;

    IV.2. World Bank's policies

    - OP 4.01 Environmental Assessment

    - OP 4.12 Involuntary resettlement

    - (a) OP 4.10 Indigenous Peoples. (b) The World Bank policy on Access to Information.

    Report on Environmental Management Plan Page 19

  • Sub-project: Ea Kar Krong pak 110 k V substation and branch lin

    PART V: GENERAL AND ENVIRONMENTAL IMPACT SCREENING

    V.1. Overview of project's environmental impact

    Table 5.1: Land area required/or the project (permanent and temporary acquirement)

    Communes Permanently impacted area (m2) Temporarily impacted area (m2)

    Ea Kar district

    EaDar 1.587 26.700

    EaKartown 1.300 54.030

    CuHue 1.900 75.800

    Krong Pak district

    Krong Buk 2.600 100.800

    EaPhe 2.300 80.600

    HoaAn 600 19.000

    Phuac An town 6.816 45.910

    TOTAL 17.103 402.840

    Table 5.1.1. Land area permanently required/or power system (m2)

    Communes Agriculture land

    (m2) Irrigation land

    (m2) Residing land(m2)

    Total(m2)

    Ea Kar district 3.300 No 1.487 4.787

    EaDar 400 No 1.187 1.587

    Ea Kar town 1.100 No 200 1.300

    CuHue 1.800 No 100 1.900

    KrongPak 11.516 800 No 12.316 district

    KrongBuk 2.600 No No 2.600

    EaPhe 1.500 800 No 2.300

    HoaAn 600 No No 600

    Report on Environmental Management Plan Page 20

  • Sub-project: Ea Kar Krong pak 110 k V substation and branch lin

    Phuac An town 6.816 No No 6.816

    Total 14.816 800 1.487 17.103

    Table 5.1.2. Land area temporarily required/or power system (m2)

    Communes Agriculture land Irrigation land Residing Total

    (m2) (m2) land(m2) (m2)

    Ea Kar district 154.430 No 2.100 156.530

    EaDar 25.300 No 1.400 26.700

    Ea Kar town 53.630 No 400 54.030

    CuHue 75.500 No 300 75.800

    KrongPak 212.010 34.300 No 246.310 district

    KrongBuk 100.800 No No 100.800

    EaPhe 46.300 34.300 No 80.600

    HoaAn 19.000 No No 19.000

    Phuac An town 45.910 No No 45.910

    TOTAL 366.440 34.300 2.100 402.840

    Table 5.2. Affected households

    Communes Tang sa hQ bi anh huang sa nguOi Ea Kar district 34 152

    Ea Dar 09 44

    EaKartown 09 48

    CuHue 16 60

    Krong Pak district 50 266

    KrongBuk 22 107

    EaPhe 13 84

    Report on Environmental Management Plan Page 21

  • Sub-project: Ea Kar Krong pak 110 kV substation and branch lin

    HoaAn 06 28

    Phuac An town 09 47

    Total 84 418

    Table 5.3. Communes that have ethnic groups being affected

    Communes Affected households Number of affected persons Group

    Ea Kar district 20 109 Ede

    Ea Dar 06 35 Ede

    Ea Kar town 07 41 Ede

    CuHue 07 33 Ede

    Krong Pak district 22 135 Dao, N ilOg, Ede

    KrongBuk 09 51 Dao, Nimg, Ede

    EaPhe 13 84 Nimg, Ede

    HoaAn - - -

    Phuac An town - - -

    Total 42 244 Dao, N ilOg, tde

    • The project will impact 42 ethnic households with 244 persons. They are of E De, Nung, Dao groups and their main job is farming, few are workers for rubber and coffee firms. The project impacts to the ethnic groups are insignificant because the percentage of the areas to be acquired for foundations and substation is not high compared to their owned land. Upon consultation, all ethnic groups concur with the project and requested to receive compensation in cash at the replacement price in accordance with the regulations of the province.

    Table 5.4. Number of affected trees and plants

    Unit: tree/plant (m2)

    Commun, Jackfruit 1L0ngan Guava Butter iMang(] Peppe Bamboo Custard

    purian apple

    EaKar 35 29 34 72 district

    56 20 66 95 39

    Ea Dar 08 07 13 12 I 11 - 46 21 03

    EaKar 20 12 16 34 32 12 - 38 29

    Report on Environmental Management Plan Page 22

  • Sub-project: Ea Kar Krong pak 110 kV substation and branch lin

    CuHue 7 10 5 26 13 8 20 36 7

    Krong Pak 22 - - 79 9 11 - 42 12

    district

    Krang 9 - - 21 7 5 18 4 Buk -

    EaPhe 10 - - I ,1.1 - - - 12 -

    HoaAn 3 - - 31 2 6 - 12 8 Phu6cAn - - - - - - - - -town

    Total 57 29 34 151 65 66 137 51

    Communes Rambutan rlum Cocoa Black

    Keo Coffee

    Coffee(ROW: Plant senna (foundation)

    EaKar 40 18 73 505 690 10.306 600 district -Ea Bar 09 05 23 109 - 230 1.967 -

    EaKartown 19 9 32 202 - 220 4.172 -

    CuHue 12 4 18 194 240 4.167 600 -

    KrongPak - - - 247 400 1.820 12.336 1.800 district I

    KrangBuk - - - 98 205 360 5.957 800

    EaPhe - - - 36 15 100 1.330 1.000

    HoaAn - - - 32 59 120 1.478 -

    Phu6c An 81 121 1.240 3.571 - - - -town

    Total 40 18 73 752 400 2.510 22.642 2.400

    Statistics and surveys showed that there are 84 affected households who have trees/vegetable being cut off with 4,414 trees and 2,400m2 of vegetable. Affected trees and

    Report on Environmental Management Plan Page 23

  • Sub-project: Ea Kar Krong pak 110 kV substation and branch lin

    vegetable include: 1). Trees and vegetable in the planned sis area and foundation of towers; 2). All trees in the area of foundation of tower and high trees in the ROW. Those are trees less than 3m away from the conductors, measured from top of the tree (when the trees have developed to the maximum) to the line and the trees may tough the line upon falling down.

    For coffee in the ROW, they will not impact the operation of the power system as well as the safety on electricity. However, during construction, compensation will be made for the high trees which fall down (temporarily estimated 30%/tree).

    V.2. Identification of the potential impacts caused by the project:

    The project potential impact is described as table 5.5:

    Table 5.5. Assessment o/potential impacts caused by the project

    No Impact I V PI;/. No I-----+----+_=_=.

    Construction preparation stage

    1

    2

    Acquisition of land Yes temporarily and permanently?

    Impact households?

    on Yes

    Report on Environmental Management Plan

    Description of impact

    - Temporary land acquisition in short term on land area for ROWand construction.

    - Permanent land acquisition in long term on land area for tower foundations and substation.

    - The area of permanent land acquisition is 17,103 m2the area of temporary land acquisition is 402,840 m2

    - There are 84 households with affected crops and trees with a temporary area of 402,840 m2, permanent area of 17, 103m2;

    - There are 82 households with permanent residential land being permanently acquired for 108 foundations with total area of 10,800m2, in which:

    + 76 households with permanent agricultural land being permanently acquired with area of9,300m2

    + 6 households with permanent land being permanently acquired with area of 700m2 and 800m2 of irrigation land managed by the People's committee.

    + 2 households with permanent land being acquired for substation with total area of 6,303m2, in which:

    • 01 household being acquired for expanding Eakar substation with

    Page 24

  • Sub-project: Ea Kar Krong pak J 10 kV substation and branch lin

    3

    4

    5

    6

    7

    Construction stage

    8

    Any household needs to be relocated?

    Affected to the Yes flora due to clearance for ROW?

    Any impact on natural habitats?

    Any risk to people's health caused by explosive or chemical substances?

    Any impact on cultural and historical structures?

    Does soil erosIOn Yes cause pollution to the surface water?

    Report on Environmental Management Plan

    total area of 787m2

    • 01 household being acquired for expanding Eakar substation with total agricultural area of 5,516m2

    No No household has to be relocated.

    - Any tree higher than 4m in ROW where the transmission line runs through will be cut off. The number of trees being cut down will be as written in table 5.4.

    - When constructing the TIL, soil excavation, site clearance and other activities in ROW are unavoidable. The area of ROW (including tower foundation's area) is 402,840m2. All the damage about trees will be appropriately compensated under the regulations of the Government.

    No The transmission line and the location of installation the substation does not run through any natural forests, protected forests or nature reserve, so the clearance does not affect the flora and fauna in such areas.

    No

    No

    The sub-project does not use chemical substance and explosive.

    The TIL and sis is not in the area where there are cultural, historical and public works so it does not affect on them.

    - When excavating soil at tower foundation positions and the substation one (foundation of transformer, shift dorm, control house), the surface soil will be

    Page 25

  • Sub-project: Ea Kar Krong pak J 10 kV substation and branch lin

    9

    10

    11

    Noise vibration?

    Air pollution?

    and Yes

    Yes

    Rural traffic Yes obstruction?

    Report on Environmental Management Plan

    excavated. When it rains, this surface soil will be eroded and swept away. Materials for construction will be scattered if they are not protected. This will lead to the pollution of the surface water. However, the period of implementation at each normal tower foundation does not last long (about 1 week in maximum). Also, as to not carried out m ramy and stormy seasons, and each item is implemented completely, the soil erosion as well as the pollution of surface water IS inconsiderable.

    - Noise and vibration are caused by material transportation means and some activities of the project such as: tower erection, conductor stretching and generator. However, these means and machinery are managed by the expiration date, the construction time is also managed (in daytime), and horns should be limited when crossing residential areas.

    - For this project, its position is far from other infrastructure works so there is no impact on them.

    - Air pollution can be occurred due to the exhaust and dust of material trucks during transportation, loading materials; or dust during project implementation.

    - However, with the average number of 1 truck per week - 2 trips per day for every tower foundation and 2 trucks per month -2 trips per day for substation (implementation in 2 months) (see the main volume in item II.3).Therefore, the level of dust and exhaust by transportation affected on the environment is minor. Moreover, when transporting, materials and equipment will be covered in order to avoid scattering.

    - Materials and equipment are transported m long distance from the yard and storehouse of PMU by specific trucks with suitable packing to the temporary project areas. After that, they are transported to the construction sites by 5 tons to 7.5 tons trucks. Building materials such as: sand,

    Page 26

  • Sub-project: Ea Kar Krong pak 110 kV substation and branch lin

    12

    13

    14

    15

    Any damage or degrading to rural roads?

    Any damage to biological resources?

    Solid waste causes by soil excavation, tree cutting in ROWand constructing activities?

    Any impact on environment caused by the workers?

    Report on Environmental Management Pian

    stones, cement will be supplied by the local suppliers and transported directly to the construction sites.

    - With the average frequency of transporting as above (item 9) and constructing activities such as: soil excavating and conductor stretching, local traffic obstruction will happen. However, because the local traffic is low and the time for loading materials and equipment is short (about 1 hour), building materials (sand, stones, soil, etc) is loaded by trucks so the level of traffic jam is not high.

    No All materials and equipment are in load sharing, suitable for the load of roads. Traffic-ways here are known as highway (the 14 National highway, township roads and some other inter-village, inter-commune roads).

    No In the project construction site, there are not many wild animals and plants. The permanent acquisition land is about 130m2

    I 1 tower foundation (l08 positions) and Krong pak substation acquired about 5,516m2 and Eakar sis acquired about 787m2. These positions are located far away from each other, III a distance between two tower foundations (about 200m). Therefore, as the level of flora surface clearance as well as land acquisition for animals is not considerable, there is no loss of the biological diversity in the area.

    No Solid waste due to soil excavation (remains of soil and stones), tree cutting (body) or construction activities (junk iron, stones, sand, plastic bottles, cement wraps) will be generated during implementation.

    No It IS expected to build 01 camp III construction site of substations for workers. Local people's houses will be rented for warehouses and storehouses of material and equipment. Therefore, water and sewages of workers will affect the surrounding environment if no method to

    Page 27

  • Sub-project: Ea Kar Krong pak I 10 kV substation and branch lin

    16

    17

    18

    Operation stage

    19

    20

    Is there any Yes conflict between construction workers and local people?

    Health and safety Yes for workers and local people?

    Any landmine or Yes bomb left after war?

    Development and Yes poverty reduction?

    Causing partition of natural environment that lead to the easy invasion into wild land?

    Report on Environmental Management Plan

    protect the environment is applied.

    - There are differences between the workers and local people in income, lifestyle and custom.

    - Otherwise, the project will bring benefits to the local community so it gains lots of agreement from the local people as well as the close coordination local Authorities.

    Accidents can occur during implementation if safety regulations is not strictly followed, such as: checking tools before use, setting up danger indicators (at sites of incomplete pole foundation, at sites of generators and conductor stretching, sites near roads, sites where loading materials and equipment is being carried out, sites where there are people working high above). These accidents can happen not only to the workers but also to local people.

    In the past, this area was at war. However, over years, this area has been exploited and constructed many works, so the remained landmines or bombs after war are inconsiderable.

    - Mainly taking part in the attraction of investment and local economIC development because industrial production cannot be done without power.

    - Assisting agricultural production and other services including healthcare and education.

    No - The project does not build more temporarily access roads.

    - After the construction of tower foundation and the tower, the temporary acquired layout will be returned as it was in the past. The entire flora less than 4m in ROW will be remained so the impact to natural environment is inconsiderable. The project is not located in wild land so there

    Page 28

  • Sub-project: Ea Kar Krong pak 110 k V substation and branch lin

    21

    22

    23

    24

    25

    Health and safety Yes for operators and local people?

    Electric magnetic field?

    Any impact on planes, birds and bats?

    Any pollution by oil-wastes?

    Risks of fire and Yes explosion?

    is no impact.

    Electrical shocks and other accidents can occur.

    No The transmission line and the substation are designed, constructed according to the current regulations and standards of the Power Sector, in which, the calculation of electrical magnetic field negative effects and the standards of electrical safety and safety in operation are applied in order to avoid harm to people. Before putting the project into operation, all safe indicators have to be specified through tests, experiments and acceptance to ensure that they meet the standards and regulations set by the investors, Operational Management Unit, contractors so the operators and the local people will not be harmed by the magnetic field.

    No In the project area, there are few flying animals like bats or squirrels but a few kinds of birds and domestic animals, so there is no impact on flying animals. The tower/pole height is about 22 m to 34 m. This area has no air-route. The project will not impact planes, birds or bats.

    No The project does not remove the old transformer and does not use the equipment that contains PCB and other dangerous chemical substances. Transformer oil may be leaked in case of failure.

    Transformers and other equipment can be exploded and transformer oil can be leaked when faults occur. Therefore, fire-fighting equipment and fault oil tank must be equipped.

    V.3. Assessment of subproject impact on the natural habitats and cultural and historical structures:

    The line route does not cross and substations are not located in the natural habitats, historical and cultural structures so there is no impact on these areas.

    Report on Environmental Management Plan Page 29

  • Sub-project: Ea Kar Krong pak 110 k V substation and branch lin

    PART VI

    PUBLIC CONSULTATION AND INFORMATION DISCLOSURE

    VI.1. Procedure, process and contents of public participation and consultation and information disclosure:

    In the stage of project preparation (2011), NPMU has carried out the following activities:

    - Activity number 1: Information supply and discussion with Local Authorities about line route direction;

    - Activity number 2: Check and make inventory of the impact and number of affected households.

    - Activity number 3: Contact with sub-project affected households.

    When the investigation is completed, the NPMU will cooperate with the representatives of the communes, villages and hamlets (in project areas) to hold meeting with households whose assets are affected by the project. During these meetings, the NPMU's staff will present these following contents: Summary of the project, draft of resettlement plan (plan of compensation and resettlement), draft of EMP (Environmental management Plan), site maps, statistics and other related documents.

    The NPMU's staff announces the subproject objectives, land and crop impact by the subproject, compensative regulations and policies to P AHs and recommends the local people do not build new houses or structures in ROWs. PAHs are consulted about compensation policies and value. PAHs' questions are answered appropriately; propositions of PAHs will be recorded.

    - Activity number 4: Continue to get feedback from PAHs.

    - Activity number 5: Disseminate information;

    The project will get the decision of investment and approval of design- total cost estimate, design of construction engineering drawings after appropriate adjustment of project location, design document, capacity andlor project technologies in order to meet the demand of environmental protection and resettlement. In order to meet the requirements of OP 4.01 on information announcement, the NPMU will be:

    - Provide Vietnamese documents of resettlement plan and environmental management plan for the People's Committees of Communes and Districts in subproject areas.

    - Disseminate on local newspapers of the province for 2 months. Resettlement plan, environmental management plan and the subproject summary will be disclosed for two months at (1) Head office of District People's Committee and (2) Head office of Communal/town People's Committee.

    The EMP will be disclosed locally in local language and at InfoShop in English. VI.2. Summary of public participation and consultation's results:

    After public participation and consultation, PMU has gained these following results:

    Table 6.1: Summary of public participation and consultation

    TT Commune Location Time No. of

    Represented by Summary of

    participants opinions

    I. EaKar district,

    Report on Environmental Management Plan Page 30

  • Sub-project: Ea Kar Krong pak 110 k V substation and branch lin

    DakLak

    01 EaDar Hall of the 7h30- 9 1. Y Brenh -commune People's 11h30 ML6: Chairman Construction

    committee 16/5/2011 of the People's after crops. of Committee of Minimize -Ea Dar Ea Dar the impacts to commune commune. the view and

    2. Nguy~n Van environment. Quy~t: - Guide local Chairman of people the Farmer association of

    measures for

    Ea Dar safe use of electricity.

    commune.

    3. Nguy~n Hilu Nhi~m: Chairman of Veteran Association of Ea Dar commune

    4. Tr~n Thi LInh: Chairman of Women association of Ea Dar commune.

    5. Representatives of 05 affected HH.

    02 EaKar Hall of the 7h30- 12 l. Nguy~n -town People's llh30 Quang Chung: Construction

    committee 12/5/2011 Vice chainnan after crops. of of the People's Minimize -Ea Kar

    committee of Ea the impacts to town

    Kartown. the view and 2. Le Thanh environment. HiSu: chairman - Guide local of the Frontier people the ofEa Kar town. measures for 3. Than Thi safe use of Oanh: VIce electricity. chairman of the women association of

    Report on Environmental Management Plan Page 31

  • Sub-project: Ea Kar Krong pak 1 10k V substation and branch lin

    EaKartown.

    4. Chu Thanh Binh: chairman of the farmer association Ea Kartown.

    5. Representatives of 07 affected HH.

    03 ClIHue Hall of the 7h30- 15 l. Ph~ Huy -commune People's Ilh30 Nhm'mg: Vice Construction

    committee 17/5/2011 chairman of ClI after crops. of ClI Hue Hue commune. Minimize -commune 2. Ph~ Tian the impacts to

    Huynh: the view and Chairman of environment. Frontier of ClI - Guide local Hue commune. people the 3. Nguy~n Thi measures for Thfun: safe use of Chairman of electricity. Women association of ClI Hue commune.

    4. f)~g Quang Chinh: Chairman of farmer association of ClI Hue commune.

    5. Representatives of 11 affected HH.

    II. Krong Pak district, BakLak

    01 Krong Hall of the 7h30- 28 I. H6 Van Tam: -Buk People's Ilh30 chairman of Construction

    commune committee 14/5/2011 Krong Buk after crops. of commune - Minimize

    Report on Environmental Management Plan Page 32

  • Sub-project; Ea Kar Krong pak I/O kV substation and branch lin

    Krong Buk 2. Y SeLa Nie: the impacts to commune Secretary of the view and

    Youth Union of environment. Krong Buk - Guide local commune. people the 3. Trfut Quang measures for Vinh: Chairman safe use of of Frontier of electricity. Krong Buk commune.

    4. Ph

  • Sub-project: Ea Kar Krong pak 110 k V substation and branch lin

    commune People's 11h30 Hili: VIce Construction committee 12/5/2011 chairman of after crops. of Hoa An Minimize -HoaAn

    commune. the impacts to 3. Nguy~n the view and Phu&c Hung: environment. Chairman of - Guide local Frontier of Hoa people the An commune. measures for 4. Le Thi Tuy6t safe use of Thanh: electricity. Chairman of Women association of Hoa An commune.

    5. Representatives of 4 affected HH.

    04 Phu&cAn Hall of the 7h30- 12 L Huynh Hfru -town People's Ilh30 Dirc : chairman Construction

    committee ngay of Phu&c An after crops. of Phu&c 12/5/2011 town. Minimize -An town 2. Hoang Anh the impacts to

    Tuftil: Chairman the view and of Frontier of environment. Phu&c An town. - Guide local 3. Trinh Xmln people the B~c: Secretary measures for of Youth Union safe use of of Phu&c An electricity. town

    4. Representatives of 9 affected HH.

    Report on Environmental Management Plan Page 34

  • Sub-project: Ea Kar Krong pak 110 kV substation and branch lin

    PART VII:

    ENVIRONMENTAL MANAGEMENT PLAN

    VII.1. Measures to mitigate the suh-project's negative impacts!

    Table 7.1 Measures to mitigate the project's negative impact on environment

    No

    Pre-construction stage

    1

    2

    3

    Construction stage

    Impact Application of mitigating measures

    Permanent and - Carry out careful investigation on project area temporary land and consult local people to choose the optimal line acquisition has route that will lower the demand for land and impacts on Project resettlement to the minimum. affected households and agricultural production.

    Impact on flora and fauna due to ROW clearance.

    - Choose the optimal design about the distance between the two poles/towers and towers' height, etc to minimize the impact on affected households.

    - Carry out implementation right after the harvest and shorten the process of construction.

    - Compensate satisfactorily for damages to crops, temporary used land as well as permanent used land according to existing regulations.

    - Reinstate the construction sites after construction completion.

    - Meet with P AHs to urge them to harvest rice, crops before clearance and land used.

    - Do not allow herbicide and defoliant for tree clearance in ROW.

    - Do not allow to bum tree roots after being cut down.

    Impacts on cultural During excavation and construction, if the and historical contractors discover any objects that may be of heritage. archaeological value, any tombs or grave, they

    should cooperate with the Investors and the local museumlDepartment of Culture to take actions. In case of discovering graves, investors should cooperate with investor and local authority for solution (described in guidance Vll 7. Emergency and solutions)

    Report on Environmental Management Plan Page 35

  • Sub-project: Ea Kar Krong pak 110 k V substation and branch lin

    4

    5

    6

    7

    Soil erosion - Soil excavation and refill should be carried out in the shortest time. No excavation in heavy rain.

    -Building materials have to be stored in the storehouse to avoid rain.

    - The site to mix concrete should be far from surface water resources, do not clean concrete mixing tools directly in ponds and lakes.

    - Use unused excavated soil and stone to fill in necessary low area in the garden, or bank up floors of local people houses. These soil and stones should be loaded far from water resources.

    - During site clearance for transmission line, burning trees or using chemicals is not allowed so that the flora layer and roots can be retained and erosion risk will be lower.

    - Restore the soil surface after tower installation.

    Noise and vibration - Using construction machinery which noise level is under permitted level and which expiration date is still available.

    Air pollution dust

    - Construction should not be carried out in the evenings in sites near hospitals or residential areas.

    - For trucks that transporting materials and equipment, do not use hom when paSSIng residential areas, especially at night.

    and - Dust due to transporting materials and equipment: spraying water in areas where the frequency of transportation is high and where there is lots of dust, especially in dry and windy season.

    - Shorten to the mInImum the duration of constructing at each site. In hot and dry weather, it is necessary to spray water at soil pile and other sources that can cause dust.

    - When constructing substation or foundation that are near local people's houses, schools/ or markets, offices (with the distance less than 20m) in strong wind, the soil pile or separated building materials should be covered.

    - Do not use diesel generator until it is really necessary.

    Traffic disturbance - Reduce to the minimum the excavation and dragging line near areas with high traffic density.

    Report on Environmental Management Plan Page 36

  • Sub-project: Ea Kar Krong pak 110 k V substation and branch lin

    8

    9

    10

    Operation stage

    11

    - Set up and maintain signals at construction sites.

    - Coordinate with local Authorities to arrange the traffic control, especially when loading materials and equipment.

    Conflicts workers people

    between - Depend on the volume of work, local people can and local be employed to do simple work, avoid employing

    workers from other areas.

    Health and safety

    - Contractors must provide information accurately, fully and in time about their workers crew to local Communal People's Committee in the project affected area.

    - The workers have to follow regulations of labor and of local government.

    - In general conditions of construction contracts, it must be clearly drawn that: After the project completion, Contractors have to dismantle the camps and restore the sites as before.

    - Inform workers about safety procedures and regulations.

    - Equip safe tools for workers in order to ensure safety; Force workers to obey regulations while working.

    - Do not allow working in such conditions as lack of light, strong wind, heavy fog, etc.

    - Workers working at high positions have to obey strictly the safety regulations. Pay attention to the workers, local people and other assets on the ground.

    - Regularly check equipment, machinery and safe equipment before using.

    Landmines or bombs NPMU will make a contract with the army to clearance make sure whether there are landmines or bombs

    in the project area or not and disarm landmines before construction.

    Health and safety for workers and local people

    - Inform electric users about safety in usmg electricity.

    - Follow Decree No.106 of the Government on protecting the safety of high voltage network.

    - Routinely carry out training for the operation

    Report on Environmental Management Plan Page 37

  • Sub-project: Ea Kar Krong pak 110 kV substation and branch lin

    workers about electrical safety.

    - Routinely and always check tools for safety before using.

    - Maintain warning signals and fences at dangerous area to local people and the workers to avoid.

    - Do not burn trees after cutting down in ROW

    12 Risks due to fire and - Check routinely the precaution and fire fighting exploration tools.

    - Train the operators on precaution and fire fighting.

    VU.2. EMP implementation responsibilities of each party:

    Table 7.2: EMP implementation responsibilities of each party

    Unit

    Project investors (CPC)

    Project operation and management agency

    Environmental management unit of NPMU

    Project implementation Agency

    Subproject operating Unit

    Responsibilities

    Responsible for overall project management, including the environmental management.

    Responsible for coordination and management of project implementation, including guiding and supervising of the EMP.

    Have specific responsibility and extensive contacts with others on environmental issues

    Responsible for daily works of project implementation, including:

    i. Plan and implement environmental management activities during construction

    ii. Coordinate with other parties in environmental management activities

    iii. Carry out internal monitoring and follow independent monitoring

    iv. Follow and provide budget for

    for monitoring activities

    v. Make report on environmental information to related parties

    Responsible for operation of the project including implementation and management activities of environment during operation.

    Report on Environmental Management Plan Page 38

  • Sub-project: Ea Kar Krong pak 110 kV substation and branch lin

    EA preparation Responsible for preparing documents ofEMP consultant

    Implementation Responsible for supervision of civil works contractors during supervision unit construction, including implementation of environmental

    management activities under the EMP

    Civil works contractors Responsible for construction works and follow technical specifications outlined in the EMP, including:

    i. Apply mitigation methods during construction

    ii. Ensure safety for workers and local people during construction period.

    iii.

    Follow policies about environmental protection of Vietnam and World Bank during construction period.

    Independent monitoring Responsible for independent monitor of EMP implementation consultant

    Local community Participate in the environmental management and supervision of the project.

    DONRE Supervise the implementation ofEMP based on the environmental certificate (if necessary).

    VII.3. EMP implementation supervision:

    Table 7.3: Supervision plan/or implementation o/mitigation measures o/project's environmental impact

    No Parameters Monitoring

    Frequency methodologies

    Pre-construction stage

    1 Area of - Check the -Once before acquisition project documents construction land and on acquired land flora area and effect on clearance crops, such as:

    number of P AHs, affected land area,

    - Once before affected level In order to detect site clearance

    mistakes if any.

    - Monitor the

    Report on Environmental Management Plan Page 39

    Responsible agency

    NPMU, SIMC

  • Sub-project: Ea Kar Krong pak 110 kV substation and branch lin

    clearance whether it is carried out according to the regulations, including:

    (1) Do not burn trees after cutting down;

    (2) Do not use herbicide and defoliant to clearance;

    (3) Keep the flora m area without pole foundations.

    Construction stage

    2 Objects m Follow the When commg NPMU, doubt to information and across the SIMC, be guidance as antiques Constructors antiques written m item (during during VI!.7. excavation) foundation excavation

    3 Soil erosion (1) Observe Monthly NPMU, whether soil during SIMC (once excavation IS implementation per SIX carried out months) thoroughly and not in heavy rain.

    (2) Observe whether the excavated area and materials are covered when it rains.

    4 Noise level (1) Check the Monthly NPMU, and vibration duration of during SIMC (once

    m licence of implementation per SIX construction machinery. months) site and (2) Assess the surrounding nOise level by areas observing at the

    nearest local people's houses to

    Report on Environmental Management Plan Page 40

  • Sub-project: Ea Kar Krong pak 110 kV substation and branch lin

    the construction sites; Interview the local people living near the construction sites about noise effect. Noise level must be measured by special tools, for example: sound meter

    (3) If there is any complaint from the local people about nOise and vibration, it must be settled immediately.

    5 Dust (1) Observe Monthly NPMU, whether (i) the during SIMC (once level of dust implementation per six generated by months) construction is serious or not; (ii) Contractors have to manage the level of dust in the air or not (spray water III dusty area and in hot, windy weather)

    (2) Check the mitigating measures applied by the Contractors in order to limit the dust level in the area.

    (3) If there is any complaint and grievance from local people, it must be settled immediately.

    6 Traffic chaos Assess by Monthly NPMU, observance: during SIMC (once

    (1) The implementation per SIX

    Report on Environmental Management Plan Page 41

  • Sub-project: Ea Kar Krong pak 110 kV substation and branch lin

    7

    8

    9

    Conflicts between the workers and local people.

    Restore the construction sites

    Application of

    Report on Environmental Management Plan

    construction and other activities of the project such as: tower erection, cable dragging, conductor stretching that may cause traffic chaos In the locality;

    (2) ~ecessary methodologies to avoid traffic chaos in locality.

    (1) Assess by interviewing the local people and authorities whether there is any conflict between the workers and local people. Monitor the process, the result of conflict settlement, petition to the relevant agencies if necessary.

    (2) Check and monitor whether the workers follow the regulations set by the local Government when living temporarily in locality.

    Assess by observation whether the construction layout as well as camps are cleaned after construction or not.

    Monthly during implementation

    After every completed work of the subproject

    (1) Assess safe I Monthly

    Page 42

    months)

    ~PMU,

    SIMC (once per SIX months)

    ~PMU, SIMC (once per SIX months)

    ~PMU,

  • Sub-project: Ea Kar Krong pak 110 k V substation and branch lin

    safe measures Issues during during SIMC (once for construction implementation per six constructing whether: months) workers and - There are private local people. safe tools or not.

    -Applying safe and technical regulations III order to avoid electrical shocks and other accidents relating to electricity.

    (2) Check, assess the application of safe measures in construction for local people such as danger indicators, covenng the construction sites as well as transporting materials.

    10 Management Assess by Monthly NPMU, of building observation: during SIMC (once materials (1) the

    implementation per SIX

    management of months)

    building materials at storehouses

    (2) the management of building materials at construction sites.

    11 Landmines Assess by Monthly NPMU, and bombs checking the during SIMC (once

    documents, implementation per SIX exchange months) information to make sure that whether:

    (1) There are bombs and landmines in the

    Report on Environmental Management Plan Page 43

  • Sub-project: Ea Kar Krong pak 110 k V substation and branch lin

    project area or not;

    (2) the checking of signing the contract, executing the contract and the results of bombs and landmines and the result of disarm contract (if any).

    Operation stage

    12 ROW Observe the ROW Monthly Operation maintenance in order to define : management

    (1) Cutting the unit

    right trees or cutting the right part of trees or not, ROW clearance IS carried out according to the principles as written above ;

    (2) the maintenance of appropriate distance between the ROW and houses

    13 Safety and Check the Monthly Operation health for construction sites management operation whether: unit workers and (1) The routinely local people, healthcare for fire fighting operation workers methodologies is carried out or

    not;

    (2) The routinely checking of operation and management tools and before used or

    Report on Environmental Management Plan Page 44

  • Sub-project: Ea Kar Krong pak 110 kV substation and branch lin

    not;

    (3) the warmng signals for local people to avoid dangers are maintained or not.

    (4) There are sentry's order, preventive and fire fighting tools or not.

    (5) The preventive and fire fighting tools are checked routinely or not.

    VII.4. EMP implementation reporting system:

    - Table 7.4: Some reporting requests on supervision of EMP

    Tertiary

    Primary Secondary reporting level

    No Reported issues reporting level

    reporting (one copy level should be sent

    to DoNRE)

    Constructions stage

    1 Mitigating Sent by: Sent by: Sent by: EVN measures and Contractor NPMU Frequency: environmental Frequency: Frequency: Once every six management at Monthly Once every months construction sites

    Received by: six months Received by: NPMU Received by: WB

    Investor -EVN

    2 Environmental Sent by: NPMU Sent by: Sent by: EVN monitor technical monitor NPMU Frequency:

    Frequency: Frequency: Once every six Monthly Once every months

    Received by: six months Received by: NPMU Received by: WB

    Report on Environmental Management Plan Page 45

  • Sub-project: Ea Kar Krong pak 110 kV substation and branch lin

    Investor -EVN

    Sent by: Communal People's Committee

    Frequency: Monthly

    Received by: NPMU

    Sent by: SIMC - -

    Frequency: Once every six months

    Received by: WB

    Operation stage

    1 Environmental Sent by: Sent by: Sent by : EVN monitor including Technical staff of CPC Frequency: safety issues the Operation Frequency: Once every year

    and management Annual unit. Received by:

    Frequency: Received by: WB

    Once every six EVN

    months

    Received by: CPC

    VII.S. Capacity building for EMP implementation:

    Future training courses will be:

    1. Annual training course on implementation of environmental management plan for rural distribution project and other transmission and distribution ones will be held by EVN annually.

    2. Annual training course on share of experiences in preparation of EMP as well as implementation of EMP for rural distribution project and other transmission and distribution one will be held by EVN.

    3. Training courses on implementation of EMP for electrical project under the requirements of WB will be held by CPC.

    4. Periodically training course on safety for CPC staves will be held by CPC.

    Report on Environmental Management Plan Page 46

  • Sub-project: Ea Kar Krong pak 110 kV substation and branch lin

    5. Periodically documents on electric safety will be sent to local people.

    Table 7.5: Cost estimate for training courses on implementation of EMP

    No

    1

    2

    3

    Training contents

    Annual training course ofEVN for all Units

    Training course to share experiences in the preparation ofEMP as well as EMP report

    Training on implementation ofEMP

    Objects

    Staves of CPC,NPMU

    Staves of CPC,NPMU

    Staff of NPMU, communes and towns of the project, construction units

    Duration Holders of training

    courses

    EVN About 2 days

    (From May, 2011 to August, 2011)

    EVN, WB About 2 days

    (From May, 2011 to August, 2011)

    EVN,CPC About 2 days

    (From May, 2011 to August, 2011)

    4 CPC's rammg course on safety (hold by provincial power company periodically)

    Staves of CPC About 2 days

    TOTAL

    NPMU, Operation Management Unit

    Report on Environmental Management Plan

    (From October, 2011 to December, 2011)

    Page 47

    Cost estimate

    Included in EVN expense:

    2 persons x 2 days x 2,000,000 VND/personiday = 8,000,000VND

    Included in EVN expense:

    2 persons x 2 days x 2,000,000 VND/personiday = 8,000,000VND

    Including: 02 people of PMU, 01 person of the contractor, 02 people in the commune:

    05 people x 2 days x 2,000,000 VND/personiday 20,000,000 VND

    Including m Provincial Power company expenses: 02 people of the project, 02 people of Operation management Unit will take part in.

    04 persons x 2 days x 200,000VND/personiday

    1,600,000 VND= 1.600.000 VNf)

    37,600,000 VND

  • Sub-project: Ea Kar Krong pak 110 k V substation and branch lin

    VII.6. Estimate cost for implementation of EMP:

    Table 7.6: Estimate cost for implementation of EMP (VND)

    No Items Construction stage Operation stage

    (20 years cycle)

    1 Mitigation measures Cost is included in Cost is included in construction contract production expense of the

    operation and management unit

    2 Cost of printing electrical 10,000,000 VND

    safety guidebooks

    3 Cost of monitoring and 1 person x 13,500,000 making independent VNDx4times monitoring report of EMP 54,000,000 VND

    4 Environmental management 37,600,000 VND -capacity development

    TOTAL 101,600,000 VND (included in the production cost of operation

    management Unit)

    101,600,000 VND

    VII. 7. Emergency and solutions

    No

    Table 7.7: Emergency Responses Plan

    Chance findings and risks

    Solutions Responsibilities

    1 Antiques found during - Protect the site and inform the local Contractor, soil excavation. authority and the Quang Long NPMU

    management unit, museum or the provincial Department of natural resources and environment.

    - Hand over the antiques to the authorized agency.

    - Define the next activities (continue construction or delay for further inspection).

    2 Discover graves, bones - Protect the site and inform the local Contractor, during soil excavation authorities; NPMU

    and soil filling _ Identify people, methodologies and time

    Report on Environmental Management Plan Page 48

  • Sub-project: Ea Kar Krong pak 110 kV substation and branch lin

    3

    4

    5

    Local complaints

    people's and

    grievances about environmental pollution

    Accident at work happen to workers or the public during construction

    Accidents due to landmines, explosive materials left from war

    of relocation

    - Implement remediation actions to solve the problems as soon as possible;

    - Take note in project handbook;

    - Discuss with investors/ local authorities to fully solve complaints and grievances.

    - provide first aid to the victims immediately and take them to the nearest hospital (if necessary) as soon as possible;

    - Prepare minute at the site

    - Provide instant aid and move victims to nearest clinics and hospitals.

    - Protect the site and provide warning sites.

    - Prepare minute at site.

    6 Find explosive materials - Protect the site;

    - Inform relevant agency;

    - Contact the nearest army unit for necessary assistance.

    Report on Environmental Management Plan Page 49

    Contractor, NPMU

    Contractor, NPMU

    Contractor, NPMU

    Contractor, NPMU

  • Sub-project: Ea Kar Krong pak 110 k V substation and branch lin

    PART VIII

    ANNEX

    Annex 1: Sample report on monitoring of EMP implementation

    (appliedfor reports ofNPMU and SIMC)

    Name of project:

    Location of project: Province:

    District:

    Commune/town:

    Type of report:

    Monthly report : Yes No

    Quarterly report to EVN : Yes No

    Quarterly report to WB : Yes No

    SMIC report : Yes No

    Report date: ...... ,. ............................... .

    I Assessments 0/ i

    No Parameter Consultants' and local people's feedbacks

    During implementation stage

    1 Surface water resource pollution and land erosion

    2 Noise level in project area and neighboring residential areas.

    3 Dust

    4 Management of tree cutting and usmg temporary access roads

    5 Solid waste and remove of all materials after project completion

    6 Manage safety and sanitation conditions for workers

    7 Traffic chaos

    8 Road damages

    Report on Environmental Management Plan Page 50

    Comments/suggestions

  • , .

    Sub-project: Ea Kar Krong pak 110 kV substation and branch lin

    9 Application of safe measures

    10 Management of construction materials

    11 Management of excessive soil and stone

    12 Impact on wildlife and natural resources

    13 Proofs of damages to biological diversity (if any)

    14 Proofs of damages to historical and cultural heritage (if any)

    15 Other environmental Issues (if any)

    Operation stage

    16 ROW maintenance

    17 Impact on wildlife and natural resources

    * Main contents of a periodically monitoring report by SIMC: (1) Cover page

    (2) Contents

    (3) Introduction

    (4) Update the priority issues that defined in the previous reporting period:

    - List the priority issues that defined in the previous reporting period;

    - List the progress of Contractors in settlement every issues;

    -List the remaining issues that are not solved appropriately and recommend alternative solutions. If there is any issue that cannot be solved, explanation is required;

    (5) Results of environmental management activities in the reporting period.

    - Report on mitigating implementation defined in SEMP;

    - Whether the mitigating measures have met the targets of mitigation or not? If not, why? The explanation has to be clear and sufficient;

    (6) Conclusion of the reporting period:

    - List the priority issues defined in this reporting period. These issues will be solved in the next reporting period;

    - Explain how and when the constructors will solve each problem. If any of the problems can not be solved, explain why.

    Report on Environmental Management Plan Page 51

  • w •

    Sub-project: Ea Kar Krong pak 110 kV substation and branch lin

    (7) Annex

    (8) Already filled questionnaire and maps related to EMP

    (9) Feedback copies of infonnation exchange between PMU and contractors, etc about activities related to SEMP.

    Annex 2: Sample report on monitoring of EMP implementation

    (applied/or Contractors' reports)

    Name of the project:

    Location of the project:

    Name of implementation unit:

    Report at the beginning of the project or monthly report:

    Date of report:

    No Impacts

    Construction stage

    1 Water surface pollution

    2 Noise and vibration

    3 Soil erosion

    4 Air pollution

    5 Impact on agricultural production and temporary acquisition of production land

    6 Traffic chaos

    7 Damages on existing roads

    8 Solid waste due to soil excavation

    9 Excessive land management

    10 Impact on the environment caused by environmental workers

    11 Conflicts between project workers and local people

    12 Health and safety

    Name of report maker

    Position

    Address

    Report on Environmental Management Plan Page 52

    Applied mitigation measures

    Notes

  • Sub-project: Ea Kar Krongpak 110 kV substation and branch lin

    Phone

    Annex 3: Sample for getting information

    (appliedfor communes' representatives)

    Each commune that participates in the project will have monthly report for NPMU during implementation stage. The communal report process has to be simple and simultaneous between communes and these communes have to be responsible for their reports.

    CO~UNUALREPORT

    Project commune

    Report date

    Environnemental impact

    : .... commune, ... district, ... province

    : ... .1 •.....

    No Comments of Impact/mitigation measures communal

    representatives

    1 Dust generated by transporting means and construction activities In surrounding areas

    2 Noise generated by transporting means and construction activities in surrounding areas

    3 Project activities that pollute local rivers and lakes

    4 Tree clearance that leads to environmental impact

    5 Project activates that cause impact on agricultural land and/or residential land

    6 Project implementation that cause impact on traffic

    7 Solid waste and sewage caused by the project

    8 Social impact on workers caused by the project

    9 Accident

    10 Dust management methodologies

    11 Soil erosion and sediment management

    Report on Environmental Management Plan Page 53

    Comments of the public

  • Sub-project: Ea Kar Krong pak 110 kV substation and branch lin

    12 Gathering of materials, etc to avoid flood and chemical pollution, etc

    13 Waste management

    14 Impact on birds, endangered plants and animals caused by project activities

    15 Roads damages caused by project transportation means

    16 Other impact

    Comments

    • In the